Claim handling and repairs following fire damage claim, including roof waterproofing and electrical supply issues
Text of the determination
Determination
Case number 732975
Financial firm SURA Pty Ltd
Determination | Case number: 732975 Page 1 of 28
Case number: 732975 13 December 2021
1 Determination overview
1.1 Complaint
The complainant held a Commercial Building Insurance policy (the policy) underwritten by the
financial firm (insurer). The complainant lodged a claim under the policy after the insured
building suffered fire damage in October 2017.
The insurer accepted the claim and appointed loss adjustors (PC) to assess and coordinate
reinstatement works.
This complaint is about the handling of the claim by PC as well as the work completed and
conduct of the appointed builder (DW) and other trades.
The complainant was represented by his broker and his wife during the claim. For the sake of
brevity and convenience, any reference to the complainant in this determination includes his
representatives.
1.2 Issues and key findings
Is the insurer liable for additional loss, damage, or rectification?
The available information shows the insurer completed some repairs in line with the agreed
scope of works and does not establish additional damage/rectification needs to be covered.
The insurer is liable to waterproof the roof and pay for damage caused by water ingress in the
storm on 7 September 2018 as set out in section 2.1 below.
The costs which are required to be paid by the insurer are set out in section 2.1 below.
Is the insurer required to make any other payments?
Save that the insurer is to reimburse the complainant for report costs ($1,941.50) plus interest
on $1,941.50 from the date the reports were paid until settlement pursuant to section 57 of
the Insurance Contracts Act (the Act), the insurer is not required to make any other payments
as set out in section 2.2 below.
Is the complainant entitled to compensation?
The available information shows that mostly the insurer did not unreasonably delay or
mishandle the claim. Issues which arose in relation to electrical power supply and the steps
the insurer took to address it were unsatisfactory and likely caused stress and inconvenience.
As such, the insurer is to pay the complainant $2,500 non-financial loss compensation for
stress and inconvenience and $5,000 financial loss compensation for loss of rent.
Was the insurer required to offer renewal of the policy?
The insurer exercised its right not to offer renewal of the complainant‟s policy and notified the
complainant of its decision more than 14 days prior to the renewal as required under the Act.
Determination | Case number: 732975 Page 2 of 28
In the circumstances, it has not breached an obligation owed to the complainant under the
policy or the Act.
1.3 Determination
This determination is partly in favour of the complainant.
Should the complainant accept this determination then within seven days of notification of
acceptance, the insurer is to:
pay to the complainant the amounts awarded by the panel as detailed in section 2.1 of this
determination
act as set out in the heading “insurer liable to waterproof roof and to pay for damage
caused by water ingress ” in section 2.1
pay the complainant $1,941.50 (plus interest) for report costs and
pay the complainant $2,500 non-financial loss compensation and $5,000 financial loss
compensation.
As for amounts awarded by the panel as addressed in section 2.1 of this determination, if the
complainant has made and paid for repairs, the insurer is to pay interest pursuant to section
57 of the Act on those amounts from the date of the final decision (7 July 2020) or from the
date of payment (whichever is the earlier) until settlement.
Otherwise, the insurer is not required to make any other payment or take any further action in
relation to the claim or the complaint.
Determination | Case number: 732975 Page 3 of 28
2 Reasons for determination
2.1 Is the insurer liable for additional loss, damage or
rectification?
Circumstances of the complaint
The complainant took out the policy with the insurer in or around April 2017 for the year
commencing 30 May 2017.
In October 2017, the complainant lodged a claim for fire damage under the policy. There is no
dispute the complainant suffered loss covered under the policy in relation to a fire which
occurred on 8 October 2017.
The insurer engaged a loss adjuster (PC).
As part of its assessment of the claim, PC obtained information on which it concluded the
premises could be repaired/reinstated. This included building and engineering reports as well
as scope of works (SOW) from the engineer (SW).
The complainant says the insured property has not been reinstated to pre-incident condition
and the insurer has not ensured like for like replacement as required under the policy. The
complainant has made lengthy submissions detailing complaints about the management of
the claim.
Among other things, the complainant says:
PC/DW failed to obtain appropriate approval for roof replacement and only obtained a
building certificate from the local Council after he raised this issue. He considers a
Development Application (DA) rather than a certificate should have been obtained and the
latter leaves him worse off
the insurer has not accepted responsibility for roof leak which occurred after roof
replacement and due to failures in works completed by DW
DW did not complete some works provided for in the SOW and applicable variations
appropriately and there are issues with the quality of work done which the complainant
says he has incurred additional costs to address
the insurer has refused to provide warranty documents for specific items installed by DW,
despite his requests
the electricity infrastructure was not installed to the pre-fire capacity
the insurer‟s handling of the claim was poor which resulted in his wife spending a lot of
time managing the claim and trying to address errors by the insurer‟s contractors/sub -
contractors
delays experienced caused d isruption to the „new incoming tenant that necessitated the
need to offer a 4- month rent free period for the period 1 April to 1 August 2018‟.
The complainant seeks a review of the above issues as well as other matters including the
insurer‟s decision not to offer renewal of the policy for the period commencing in May 2018.
Broker acting as complainant ’s agent when policy commenced
The insurer is liable to settle at the cost to reinstate the damaged property.
Determination | Case number: 732975 Page 4 of 28
The terms under which cover is provided under the complainant‟s policy are contained in the
applicable policy documents. These are the Certificate of Insurance (COI) and a Product
Disclosure Statement (PDS).
The COI shows the complainant took out asset protection cover with a building sum insured
of $240,000 with an uplift because of the insured location to $288,000.
The complainant complains he was not made aware of the full extent of the policy cover and
that the full limit of the insurance cover has not been used.
The complainant confirmed the policy was arranged through his broker and that he has no
issue with the broker‟s conduct.
The broker was acting as the complainant‟s agent, not the insurer‟s agent. In these
circumstances, the responsibility lies with the broker to ensure the complainant is aware of
the policy terms. There is no dispute the broker was provided with the policy documents for
the period of cover.
In these circumstances, the panel is satisfied the insurer is entitled to rely on the policy terms
and conditions in its assessment and settlement of the claim.
Insurer is not liable to settle for the full limit of cover
Further, the insurer is not obliged to pay the full limit of the insurance cover. The panel is
satisfied the policy terms require the insurer to indemnify the complainant for the damage
caused by the fire only. The insurer is required to settle the cost to reinstate the damaged
property only up to the building sum insured.
Insurer appointed experts to prepare SOW
The insurer appointed a loss adjustor (PC), a builder (DW) and an engineer (SW) to
determine the cause and extent of damage, as well as what was required to reinstate the
property.
The complainant mainly dealt with PC throughout the claim as it managed the claim and
liaised with the complainant on the insurer‟s behalf.
PC‟s initial report dated 16 October 2017 includes photographs and a list of observed
damage. In the report PC notes some make safe had been conducted by a builder (WW) and
that an engineer (SW) had attended the premises to provide advice and prepare a scope of
works (SOW).
PC reports there was significant fire damage in the rear of the building which spread into the
ceiling. The report notes:
plasterboard walls were severely burnt exposing the brick walls
the footings and brick wall, shopfront façade and awning appeared „largely unaffected‟
the interior and roof structure will likely need to be gutted and rebuilt which may require
council planning permission and delay rectification works into the new year.
PC provided numerous other reports throughout the claim process, some of which will be
discussed in this determination.
SW subsequently provided a SOW to PC. PC referred the scope of works to DW and another
builder who provided quotations for the cost of repairs. PC reviewed the quotations and
recommended the building contract go to DW.
Determination | Case number: 732975 Page 5 of 28
PC continued liaison with the complainant, the broker and the builder regarding the refined
scope of works. Updated quotations were obtained. Both builders estimated construction time
would take 10 weeks. The complainant indicated he would contact the council to confirm
certification requirements. The complainant also indicated he may seek a further independent
repair quotation.
On 22 December 2017 the complainant accepted the SOW and agreed to DW carrying out
repairs as evidenced by the payment of the policy excess.
Having considered all the available information, the time frame in which the above took place
and the broker‟s role, the panel does not accept the complainant‟s position was compromised
before the complainant accepted the scope of works.
Variations totalled $46,231.43
The available information also shows once repairs commenced several issues were included
in variations (totalling $46,231.43).
I n PC‟s 11th report dated 13 July 2018 PC noted all reinstatement works required under the
policy were completed. The report notes the final invoice from DW for the works completed
was $178,525.58 being the original contract price plus variations less the policy excess of
$1,000.
In its 12 th report dated 28 August 2018 PC noted DW completed cleaning the driveway and
patching plaster to the shopfront following installation of the glass frontage. DW was paid a
further $683.10.
Complainant has the onus to establish his contentions
The complainant has many complaints about the building cost variations, work the builder did
not perform, work done badly and the conduct of DW and PC. The complainant says some of
the works completed did not comply with the SOW and/or were not done correctly and require
rectification. For ease of reference, these items will be considered under several headings
below.
The panel notes the complainant must establish on the balance of probabilities that he has
suffered a loss caused by an event to which the policy responds. This is known as a valid
claim. For all his complaints, the onus is on the complainant to establish on the balance of
probabilities the claimed damage was caused by the fire, by the repairs, or that repairs were
inadequate or not completed in accordance with policy terms and conditions.
Council application/approval for the roof
The complainant says DW should have obtained a DA approval prior to replacement of the
roof. He says such application/approval was allowed fo r in PC‟s scope of work (SOW) as well
as in DW‟s quotation, but it was not obtained. The complainant says the Building Information
Certificate obtained post work is not the same as a DA and states it only lasts for 7 years. He
questions what happens after the 7-year period.
The complainant also says the insurer used a different material (KL) for the roof replacement
and this material itself is not certified by the council‟s certificate which only deals with the roof
structure.
Determination | Case number: 732975 Page 6 of 28
The complainant asserts an application for a building certificate was only made after the roof
repairs had commenced and raises issues about the lack of DA approval.
In response the insurer says:
DW submitted the Development Application (DA) to the relevant council on 1 May 2018 for
replacement work to the existing roof and a reference number and link was provided
DA is a development application, which is defined as a formal application to council for
carrying out various types of development
DW did not make a mistake in submitting the DA for approval
DW received approval and a Building Certificate for the roof replacement which is available
at the council‟s website
All repairs were scoped and checked by an engineer and the assessor (PC)
The insurer provided a link to the relevant information in the exchanged response to the
complainant on or about 2 September 2020.
The panel reviewed the link to the council website. The panel notes an application was made
for „replacement work to existing roof‟ at the insured address on 1 May 2018. T he council
records show status as „Building Certificate Issued‟.
The complainant maintains the building certificate (BC) is not the same as a DA and the latter
should have been obtained.
The panel has carefully considered the parties‟ submissions about BC versus DA.
The complainant is adamant an error has been made, not only because a BC was obtained,
but also because it was obtained after roof replacement had occurred. He says BC‟s are
obtained after the fact from councils where illegally constructed building works have occurred,
last for only seven years after which the council can require repair, demolition, alteration or a
rebuild.
DW‟s quote shows the work was to be done in accordance with Australian Standards and
council requirements.
The SOW includes item 15 which allowed for all necessary costs to provide plans and
specifications required to submit DA (if applicable) and receive a construction certificate.
The available information, including the scope of works and PC‟s reports indicate plannin g
permission or approval may be required in the context of discussing possible duration of
repairs.
The panel has carefully reviewed information provided about the requirement (or otherwise)
for council permit/authorisation in the form of a DA or a BC.
The panel is not satisfied on the available information that authorisation obtained in the form
of a BC is incorrect or in breach of relevant law/regulation.
A review of the BC shows the council inspection occurred on 16 May 2018 and that:
1. the certificate operates to prevent council from taking certain actions in relation to the
building (or part thereof), „making an order under the Environmental Planning &
Assessment Act 1979 or the Local Government Act 1993 requiring the building to be
repaired, demolished , altered, added to or rebuilt‟
2. states the certificate operates to prevent the council from making an order under the
legislation listed in 1 above, for a seven- year period but this is specified as being „in
Determination | Case number: 732975 Page 7 of 28
relation to matters arising only from the deterioration of the building because of wear
and tear‟
The complainant provided extracts from an email from what appears to be a council worker
(CM) dated 26 March 2018 in support of his position that a DA is required.
In the email CM says:
he had looked thro ugh „SEPP Exempt & Complying Development 2008‟ (presumably
legislation/regulation) and provides excerpt from subdivision 27 which deals with minor
building alterations (external) and paragraph 2.53, and
was unable to identify any exemption for external st ructural work including „new
replacement roof‟
roof replacement works „could fall within the provisions of Complying Development
Certificate for the remaining works (not yet completed) and a Building Certificate
application for works already undertaken‟
In the panel‟s view, it is not sufficiently clear as to the capacity in which CM made this
statement and what question(s) he was responding to. The statement itself does not include
sufficient information on which the panel can be satisfied an error was made by the insurer in
obtaining a BC. Rather as stated above, the wording of the BC and information on the council
link confirms a BC is satisfactory for „replacement work to existing roof‟ as noted on the
council website.
Further, the panel notes CM appears to confirm BC applications can be made for works
already undertaken.
Finally, the SOW does not mandate a DA.
In any case, even if the panel accepted a DA should have been made prior to roof works
commencing (and it does not), AFCA cannot award any remedy as the complainant is
seeking an acknowledgement of liability for possible future loss. AFCA cannot provide a
remedy for loss which has yet to occur or has not crystallised.
Insurer liable to waterproof roof and to pay for damage caused by water ingress
Repairs were completed in August 2018. The building was tenanted. In early September
2018, the tenant reported water ingress from the roof in a storm on 7 September 2018.
The complainant says the tenant showed him photos/video of water ingress during heavy rain
and that he observed wetness to the floor, watermarks and dampness on the ceiling/ceiling
join.
He notes the ceiling cavity was contaminated and that there was damage to areas of
electrical infrastructure which needed to be assessed for cover.
The complainant considered the water ingress was a result of KL roofing used, incorrect
installation/construction and overall failures in work carried out by DW when the roof was
replaced which according to his expert input was “not a perfect build”.
The complainant considers the insurer has not met its obligation to replace the roofing like for
like as different materials to the original was used by DW (including the KL roofing).
Determination | Case number: 732975 Page 8 of 28
Additionally, he considers the warranty for the roofing should be extended because of the
issues with water ingress not being satisfactorily addressed (because the overflow
workaround was being figured out).
He seeks:
the plumber‟s work for the overflow work
the cost of the roofing reports ($726.00 and $1,215.50), and
review of warranty issues and extension of warranty
cost of time involved in attending to these matters
These last 3 matters will be dealt with separately later in this determination.
The insurer says the water ingress was not related to claimed incident and building works.
Rather, it says the damage was caused when the complainant‟s tenant installed roof vents
and other works for its dry-cleaning equipment.
The complainant does not accept the tenant‟s work is the cause of water ingress. The
complainant also says the tenant advised him DW undertook more (unauthorised) work, but
he does not know if the roof is watertight.
PC says the roof was constructed/installed correctly by DW and signed off by civil engineer
(SW), local council and the builder with a warranty.
The complainant says SW is not independent and DW is not able to independently provide an
opinion about DW‟s work.
The panel notes SW provided a construction certification for roof and ceiling structure at the
insured premises in which it certif ies and confirms „that the completed roof and ceiling
structures are in accordance with the above- mentioned structural drawings and details‟.
In support of its position, the insurer has provided a report DW completed after the reported
water leak as well a s PC‟s report (number 13) which addresses the issue.
PC says after DW assessed the premises (two days after a storm); it did not find any storm
related damage. It says from discussions with DW and the subcontracted roofer (AL) about
the reports provided by the complainant, there is no evidence of incorrect installation and any
water ingress.
Relying on these conversations and photographs which are attached to the report it says:
the step design in roof installation is within amount specified by roofing sheet manufacturer
whirly- birds were installed at an appropriate location with „more than enough distance
(500mm+) for water to make its way around the shaft and not back up‟
flashings were not fixed or sealed to neighbouring property as the complainant informed
the builder/roofer this was not allowed
gutters installed were the same and at the same location they were in prior to the fire and
made appropriate overflow provisions
water could not flow back into the building because the gutter is slotted
the mesh under the roof sheeting has nothing to do with the leak and was not installed
because during installation a platform scaffold was used
several modifications had been done to the roof by the complainant‟s tenant which means
the roof warranty is likely to have been voided and the modification and/or installations are
likely the cause of ingress reported
Determination | Case number: 732975 Page 9 of 28
photographs provided show the modifications to the roof and roof sheeting by the tenant
during the installation of vents and stacks which has changed the roof structure since
DW‟s construction
the insurer may want to appoint its own engineer to assess allegations re water ingress.
The insurer did not appoint an engineer.
Reports relied on by the parties are set out in supporting section 3.3 of this determination.
DW said the cause of water ingress reported is hail build-up during a storm which allowed
water to back-flow over flashing entering the roof void.
DW noted minor paint damage to the centre ceiling inspection joint
DW said some damage had been caused by the tenant‟s roofer during installation of content
fit out for which it is not liable. In reaching its conclusion DW points out:
the tenant reported that water came „out of the dry -cleaning system exhaust, power cable
next to exhaust, centre ceil ing expansion joint and mains power supply”
there was visible damage to paint work at the expansion joint only
prior to inspection, the tenant had engaged other roofers for installation of contents fit out
the tenant‟s work damaged the roof including roof clips which have been pulled apart and
sheets which are damaged
In response, the complainant says:
DW incorrectly assumed the tenant had installed „whirly birds‟ on the roof as the whirly
birds and stepped sheeting identified were installed by DW
DW made errors regarding the location of water entry reported by the tenant. While DW
suggests water came in from dry cleaning system exhaust or power cable next to it, based
on the tenant‟s report to the complainant, the water came through the conduit on the
northside rear wall, through the bathroom area on the north side of the property, through
the middle ceiling joint (which he believes is below the step in the roof) and through the
electrical cables at the northside shop front
DW is not independent, and the report is biased
water did not come through the tenant‟s flues and vents which are on the south rear of the
building.
The complainant relies on 3 reports which are summarised in supporting section 3.3 of this
determination.
The builder (DS) identifies several problems with the roof including the way the barge
cappings have been installed and the inadequacy of flashing and capping and pressure seals
on the northern and southern sides of the building.
Relevant to the paint damage identified by DK, DS says the roof has been laid in two
separate pieces and the join flashing is not big enough.
The engineer (TY) identified the same issue. TY also refers to lack of apron flashings at the
north side wall.
TY specifically exonerates the tenant‟s work. He says:
4.5 Flashings around flue penetrations and vents in the new roof sheeting were
found to be installed in a proper workmanlike manner and there was no evidence
of water penetration into the interior of the occupancy from these roof
penetrations.
Determination | Case number: 732975 Page 10 of 28
The roof report obtained in September 2018 from AL refers to the same issues identified by
DS and TY. That is, that the step in the middle of the roof is inadequate and the flashings to
both sides are not sealed.
AL also identifies that the whirlybird roof vents were installed in the wrong place, the gutter at
the back is too small to cope and metal mesh should have been installed under the
installation.
The panel has carefully reviewed the reports and information provided in relation to the
claimed water ingress and the installation of the roof.
In the context of this claim, the complainant must establish the claimed damage was caused
by the September storm and/or because the insurer‟s work to the roof was inadequate.
The panel notes the complainant‟s assertions are rebu tted by PC after consultation with DW
and the roofer as set out in PC‟s 13 th report.
The panel also notes the claimed water ingress occurred around 5 months after the roof was
replaced by the insurer and following modification and/or installation of equipment which
required vents/shafts in the roof by the complainant‟s tenant.
The complainant says DW is not independent. The panel acknowledges this statement but
also notes the photographs provided by DW showing the roof before and after the tenant‟s
installations.
The panel accepts TY is independent and his report is clear and unambiguous. TY says the
tenant‟s fit out has not compromised the roof.
Having carefully reviewed the three reports provided by the complainant, the panel accepts
that assertion.
Th e panel notes the installation of the roof was approved by the insurer‟s engineer, and the
local council. However, the panel is persuaded that the preponderance of expert evidence is
that the roof is not waterproof for the reasons stated by DS and TY. Both reports refer to the
same issues with the roof – that the two separate pieces of the roof are not properly sealed,
and the apron flashings are not properly sealed.
AL identifies the same issues. Only AL identified the issue regarding the mesh. The panel
does not accept this is responsible for water ingress.
AL also identifies that the whirlybird roof vents have been installed in the wrong place but in
the absence of comment by DS and TY, and in view of PC‟s assertion on this issue, the panel
does not accept this issue means the roof is not waterproof.
AL says the gutters at the back are too small. DS and TY do not criticise the gutters. In view
of the material provided by PC in relation to the gutters, the panel does not accept the gutters
were inadequate or responsible for water ingress.
The panel notes the re is no expert opinion which supports the complainant‟s contention the
roof is faulty or leaked because of the KL roofing used. Based on the available information,
the panel does not accept this assertion.
Should the complainant accept this determination then within seven days of notification of
acceptance, the insurer is to repair the roof, so it is waterproof.
The waterproofing work required is identified by DS and TY in their reports.
Determination | Case number: 732975 Page 11 of 28
Alternatively, the insurer may opt to obtain a quotation to cash settle the cost of waterproofing
the roof. The cash settlement must include a 20% uplift to take into account any
contingencies or variations which may occur once repairs commence.
The insurer is also responsible to indemnify the complainant for the internal damage caused
by the water ingress in September 2018.
Should the complainant accept this determination then within seven days of notification of
acceptance, the insurer is to repair the internal damage or indemnify the complainant if the
complainant has already repaired the internal damage.
If the complainant has repaired the internal damage caused by the storm in 2008 September
2018, upon provision of invoices, the insurer is to pay interest on this amount from the date it
was paid until settlement pursuant to section 57 of the Act.
The panel notes the complainant indicates there has been no water ingress since because of
his plumber‟s overflow work. Upon provision of the relevant invoice, the insurer is to
reimburse the complainant for this cost.
Additionally, the insurer is to pay interest on this amount from the date it was paid until
settlement pursuant to section 57 of the Act.
Insurer not liable to rectify the brickwork
The complainant says the insurer did not meet its policy obligation to return the premises to
pre-existing condition by providing like for like replacement/repairs.
He says in relation to the brickwork there was no evidence of any test performed on the brick
walls to ensure the ongoing integrity of the mortar after the heat of the fire. He says painting
burnt bricks with weakened mortar with white paint does not reinstate the bricks or mortar to
the policy requirement of “the damaged property will be reinstated to a condition equal to, but
not better than when new”.
The complainant provided photographs of the fire damaged brick walls and some which
appears to show the walls painted over. He considers the brickwork should have been
replaced.
The complainant says the insurer has not met the terms of the policy in regard to
cleaning/pa inting the brick walls which had been subject to intense fire „will likely have
damaged the mortar which has not been assessed or repaired‟ and it is unlikely „damaged
bricks and mortar will last as long and be as strong as bricks in as new condition‟.
The panel notes the complainant has not provided any information from suitably qualified
persons that cleaning, or painting fire darkened brick is insufficient re-instatement or that the
mortar has been fire damaged or weakened.
On the available evidence, the panel does not accept the complainant‟s contentions about the
brick walls.
Insurer not liable to rectify further the plaster render or shop concrete floor
The complainant raised concerns about repairs to plaster render and flooring.
The available information shows there was disagreement in relation to the plaster render
methodology used and that the complainant requested an alternative repair method against
advice from the insurer‟s contractor.
Determination | Case number: 732975 Page 12 of 28
The complainant‟s submissions about the render are not s upported by any expert evidence
about the adequacy (or otherwise) of repairs to internal walls or which persuasively
contradicts the insurer‟s assessment about the repairs.
In relation to the concrete floor the complainant says at a site meeting PC agreed the front
portion of the flooring (which previously had tenant‟s vinyl), would be sanded, polished and
sealed and the remaining area would be cleaned following removal of tenant‟s contents. He
considers this has not been adequately done as only the first four metres from the shopfront
was polished and sealed rather than the whole floor space. He says holes left by removal of
the tenant‟s contents were not filled and the whole area has not been finished or properly
sealed.
PC‟s report of 20 June 2018 shows i t agreed to seal the front portion of the concrete floor and
clean the remainder. It says the cleaning which occurred at least three times, sufficiently
restored/reinstated the flooring. It also notes the new tenant‟s installation of equipment meant
works to seal or polish the floor was not feasible.
The panel has reviewed the available information and is satisfied the insurer has completed
repairs/restoration to the shop flooring in line with the agreed SOW.
The panel does not consider the complainant has provided persuasive evidence (such as a
report from a suitably qualified expert) that the repairs in question were inadequate or
substandard.
The complainant has not met the onus he has to establish the claimed loss. The insurer is not
liable to rectify further the plaster render or shop concrete floor.
Insurer not liable to rectify further the roller door
The complainant says the current tenant complains the rear roller door is not of commercial
strength. He says PC and DW have not provided data sheets or specifications, so he could
check the commercial gauge of the door.
PC has provided an email saying the roller door is commercial.
The panel does not consider the complainant has provided persuasive evidence (such as a
report from a suitably qualified expert) to establish the roller door is inadequate or
substandard.
PC has provided an email saying the roller door is commercial. The insurer is to provide
further information to the complainant to confirm its specifications.
Insurer not liable to further rectify vents and bathroom window installation
The complainant says the quality of work is rough and unacceptable and no specifications
have been provided on the window framing.
The panel does not consider the complainant has provided persuasive evidence (such as a
report from a suitably qualified expert) to meet his onus to substantiate these contentions.
Insurer to pay $880 for the rear step and concrete sewer cover
The complainant provided a quote for repairs to a rear external step. He says the step was
damaged in the fire and/or during attendance by the fire service or by contents removal.
Determination | Case number: 732975 Page 13 of 28
The insurer says the external step damage was assessed by engineer as pre-existing as
information shows loose bricks two days after the fire.
The panel has reviewed reports and photographs provided. It notes there is a possibility the
damage existed prior to the fire but also accepts from some photographs the step could have
been damaged during the fire or by the fire services.
In the circumstances, the panel considers it fair the insurer pays the cost of repairing the step
and concrete sewer cover to the complainant in the sum of $880.
Insurer to pay $275 for the rear door jamb
In relation to the complainant‟s request that the insurer paint the external concret e jamb
around the roller door, PC‟s report of 30 June 2018 includes photographs and says it is
satisfied the repairs have been done and area „reinstated to a suitable standard‟.
The complainant says PC says this was internal fit out, but he says the area is external to the
roller door.
The complainant says the raw render to the door jamb and roller door area is visible from
inside the building, is porous therefore the „requested painting was critical‟.
The panel has considered the parties contentions and photographs. The panel accepts the
areas is external to the roller door.
In the circumstances the insurer is to pay to the complainant $275.
Product warranties and overall quality of repairs
The repairs were completed by DW and are subject to any warranties under the building
contract agreed to by the complainant.
The complainant has raised several questions about durability, warranties etc.
The panel considers there is insufficient information (such as report(s) from a suitably
qualified expert) that the warranty provided is not applicable.
In any event, as the work was undertaken by the insurer‟s contractors under the insurer‟s
supervision, if further future issues occur in relation to the overall quality of repairs, the insurer
must act in good faith to address those issues if and when they arise.
No finding can be made at this time for future possible or potential loss
The complainant says electricity was not replaced to pre- fire conditions because the insurer‟s
contractors did not consult with him about it and made errors by:
incorrectly applying for a new rather than existing connection which he already had with
the power supplier for 300AMP entitlement connected to his „NMI‟. This meant the existing
approval was lost and he is now left with 250AMP. He notes this was only obtained after
he raised the issue and provided the insurer with evidence that the 125AMP approved on
the new application was incorrect. It remains less than what was available at the property
prior to the fire
installing new infrastructure which was inadequate and did not consider what was needed
for a purpose-built dry-cleaning business.
The complainant provided a statement from the electrical technician (SS) in which SS
confirms the existing 300AMP power supply and infrastructure which was „sized up‟ to the
Determination | Case number: 732975 Page 14 of 28
supply at the premises to suit the machinery in commission at the time the complainant‟s
wife‟s family operated a dry -cleaning business from the premises.
The panel notes a tenant occupied the premises at the time of the fire and after.
The complainant says the power provider confirmed the insurer could have applied for
300AMP, but DW incorrectly applied for 125AMP. As a result, DW had to provide a new
application for 300AMP (not revert to the old) and was treated as a new property connecting
to the grid based on assessment of current need.
While the current power supply meets the tenant‟s current needs, the complainant says there
will be issues should the tenant expand the business in future. Future applications may mean
additional costs for cables, substation etc.
The complainant requires the insurer to cover the cost of infrastructure reinstatement to cater
for 300AMP in the future once the tenant is no l onger „in situ‟ based on an assessment the
insurer must make and pay the difference in costs.
As the person alleging loss has been suffered as the result of an error by the insurer, the
onus is on the complainant to provide evidence substantiating such loss.
From the panel‟s review of the information provided in relation to the electrical/electricity
issues raised (relating to both power and infrastructure), the panel is not satisfied the
complainant has established any loss which can be substantiated because of power supply
and infrastructure at the premises being 250AMP and not 300AMP.
As no loss has crystallised because of the power supply issues, at this time the panel has no
basis on which to award compensatory costs, however the panel has taken this into account
in its review of overall claims handling as set out in section 2.3 of this determination.
Insurer to contribute $1,500 to plumbing claims
The complainant says plumbing work carried out by DW was insufficient and that he incurred
cost in correcting errors made by DW including:
installation of residential rather than commercial plumbing facilities in the laundry area
fixing incorrect installation of pipes (with no backflow prevention facilities which according
to the complainant is required by Sydney Water)
repairing overflow/rainwater head to rear
repair of leaking stormwater pipe.
The complainant says the plumbing was not repaired/replaced „like for like‟ and the insurer
refused to address concerns about it appropriately. As a result, he says he had to engage a
plumber incurring a total of around $2,705 to return the plumbing to pre-fire
conditions/specifications.
The complainant provided a statement from plumber (JS) as well as photographs to support
his position. JS‟s statement dated 31 March 2018 includes that JS had carried on
maintenance for the dry- cleaning business run from the premises „for many years‟ and lists
five items required for „Reinstatement of Services‟
The insurer says information provided by the complainant does not establish DW did not
complete repairs (including plumbing repairs) correctly. It submits the complainant made
numerous unsubstantiated allegations about the works carried out by the builder and its
trades throughout the repair process.
Determination | Case number: 732975 Page 15 of 28
After reviewing information provided in relation to the claimed unsatisfactory plumbing work,
the panel is not satisfied it shows:
all repairs by DW was not in accordance with the accepted scope of works
all the plumbing work carried out by the complainant is related to claimed fire or correcting
works completed by the insurer‟s contracto rs/trades or damage.
The insurer is therefore not required to cover all these claimed costs, but the panel considers
it is fair some of the claimed costs are paid by the insurer.
Further, as set out above the overflow work is to be paid.
The panel is satisfied it is fair the insurer pays to the complainant $1,500 for plumbing.
Insurer to pay complainant $8,533.53 for aluminium and glass shopfront
There is no dispute the insurer agreed the complainant would arrange for replacement of the
glass shopfront with his own supplier (MG).
PC‟s report of 30 May 2018 includes that the amount allowed for this in DW‟s quote ( $12,331)
had been deducted as the complainant found other trades to complete shopfront work at the
cost of $8,470.
The complainant has provided an invoice from MG with total cost of replacement noted as
$8,533.53.
If the insurer has not already paid this cost to the complainant, it should do so within 14 days
of this determination.
Insurer to pay complainant $758.79 for new metering cost
The complainant is seeking payment of $758.79 for new metering costs which he says the
insurer had agreed to cover.
The available information does not show the insurer agreed to cover this amount as claimed
by the complainant but in the absence of rebuttal from the insurer, the panel considers it is
fair this amount is paid
Energy supply/usage during repairs to be paid by insurer ($773.70)
The complainant seeks payment for:
Generator cost to tenant $623.70
Electricity usage - next door neighbour $150.00
PC‟s report of 24 April 2018 confirms unauthorised connection to neighbour‟s electricity has
occurred. PC then arranged for a generator.
The insurer has not provided any information to refute the estimated amount sought by the
complainant in relation to electricity usage from neighbour.
As such, the insurer is to pay $150 to the complainant.
The complainant seeks $623.70 for 3 extra days for the generator cost for tenant use as no
electricity was on site until late June 2018. He says PC delayed its response on the extension
of the generator for temporary power and that he was required by the tenant to organise a
generator to enable installation of the tenant‟s equipment.
Determination | Case number: 732975 Page 16 of 28
In view of the issues with the electricity supply because of the AMP issues and as this
assisted the tenant to be installed thereby mitigating loss, the panel considers it is fair the
insurer reimburses this amount to the complainant.
Insurer to pay complainant $1,675.00 for false wall cover
The complainant seeks payment for a false wall/cabinet he says was installed to cover the
internal electrical switchboard to make the area safe.
He provided an invoice of $1,675.00 for the works and maintains that prior to the fire, a similar
wall was in place. He refutes it was part of the tenant‟s fit -out.
The complainant also says the area covered by the cabinet has a water meter and back-flow
prevention device and
cover was required to prevent any risk of electrical shock
the area was covered prior to the fire
the „manner in which the electricals have been remediated has left cables outside the wall
cavity that were previously within the double brick wall cavity and so are not encased but
exposed‟ which necessitated the false wall cover being all the way to the ceiling.
The insurer has not specifically addressed the false wall in its response.
PC‟s report of 20 June 2018 includes that the complainant requested installation of
cabinet/cupboards over internal electrical switchboards, and this is marked as „No‟ taken to
mean no cover. However, no cogent reason is given for the refusal.
There is insufficient evidence to make a finding that such a wall was in place prior to the
incident and should have been covered under the claim or repair scope of work. The panel
has considered the material provided including photographs. The panel accepts a safety
issue is at play. And, in the absence of rebuttal from the insurer the panel is satisfied it is fair
this amount is paid.
For all payments in this determination (as set out above) if the complainant has made and
paid for repairs, the insurer is to pay interest pursuant to section 57 of the Act on those
amounts from the date of the final decision (7 July 2020) or from the date of payment
(whichever is the earlier) until settlement.
2.2 Is the insurer required to make any other payments?
Insurer to reimburse complainant for report costs ($1,941.50)
Under its Rules, AFCA can require an insurer to reimburse a complainant for costs incurred in
making a complaint. This may include expert report fees. If a complainant asks the insurer to
contribute to such costs, AFCA will consider whether they were reasonable and whether they
helped resolve the complaint.
The complainant has provided invoices for the cost of obtaining roof report from AL and TY
following water ingress from the roof during a heavy storm some months after repairs had
been completed by DW. He seeks reimbursement for the costs which are $726 and
$1,215.50 for AL and TY‟s reports, respectively.
The panel has considered the reports from AL and TY. The reports assist the complainant‟s
position. Further, it was appropriate for expert reports to be obtained to rebut the expert
opinion from the insurer.
Determination | Case number: 732975 Page 17 of 28
The panel is therefore satisfied it is fair the insurer reimburses the complainant $1,941.50 for
the cost of expert reports.
Additionally, the insurer is to pay interest on $1,941.50 from the date the reports were paid
until settlement pursuant to section 57 of the Act.
Insurer not liable for claims preparation costs
The complainant provided details of time spent by his wife (as his representative) on the
claim. He says his wife:
acted in the capacity of a claims manager dealing with the SOW and items selection,
ensuring works/items being repaired/replaced were „Like for Like kind and quality‟,
engaging with utilities suppliers and relevant local authorities to establish correct
reinstatement and overall supervision of works including arranging for builder/asse ssor‟s
mistakes to be corrected
needed to be involved due to poor handling of the claim and repairs by PC, DW and DW‟s
trades/contractors, and the need to constantly address errors (including seeking alternative
replacements for items such as the shopfront glass).
In view of this, he says he is entitled to payment of $ 61,132.50 (inclusive of GST) under the
policy cover for claims preparation for her time expended. He est imates this time at 370.5
hours at a „professional service‟ rate of $165/hour. The complainant provided an invoice from
his wife and a timeline in support of his request for payment.
Under „Asset Protection‟ cover, the complainant‟s „claims preparation expenses” may be
covered when loss or damage occurs. The policy defines claims preparation expenses as set
out in supporting section 3.2 of this determination.
The panel is satisfied the definition is clear and unambiguous. The benefit operates such that:
the types of expenses listed are „reasonably and necessarily‟ incurred
need to be for preparing and certifying of covered claims
includes a list of the types of expenses which contextually relate to expertise needed for
actual building work (engineers, architects, surveyor etc). This does not apply to the
complainant‟s case as his wife does fall within this category nor is she an accountant
there is allowance for „executive overtime‟ incurred by insured, but this is limited to time
incurred to mitigate claims
the definition specifically states the insurer‟s consent is required.
The available information does not establish the claimed expenses relate to professional
costs as described in the definition or were incurred to mitigate claims.
Most significantly, the substantial costs were not incurred with the insurer‟s consent.
The panel is not satisfied the complainant has established an entitlement to claims
preparation expenses under the policy terms.
Determination | Case number: 732975 Page 18 of 28
2.3 Is the complainant entitled to compensation?
Compensation is awarded in some circumstances
The complainant seeks review of the insurer‟s overall claim s handling, the conduct of its
representatives/contractors/staff members, and the extent of time it has taken to finalise the
claim.
AFCA will award compensation (capped at $5,000) if there has been an unusual degree or
extent of physical inconvenience, time taken to resolve a complaint or interference with the
complainant‟s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to awarding compensation. We do not award
compensation because the complainant has suffered some inconvenience and anxiety. AFCA
expects complainants to be moderately robust and to bear the normal degree of
inconvenience experienced when a problem occurs and to take reasonable steps to manage
the situation.
AFCA reviews any claim of misconduct to determine whether compensation is warranted.
AFCA is not the industry regulator and cannot review the insurer‟s internal processes or
policies, including its decision about who carries out its claims assessment. In the present
case this means the panel cannot review any commercial relationship between any of the
experts appointed to provide services as professionals in their distinct fields.
Save for power supply issue insurer did not unreasonably delay the claim
The available information includes:
the fire incident occurred on 8 October 2017
the claim was lodged on 9 October 2017 and PC attended at the premises on that date
the insurer arranged immediate make-safe to board up the premises
the insurer‟s structural engineer attended the premises on 11 October 2017
time taken to assess, and complete a SOW was impacted by investigations of the claim.
As the premises was tenanted this also meant time taken was also affected by
assessment/investigation by the tenant‟s insurer (incidentally also the same insurer)
repair quotes were obtained in early November 2017 following tender on the SOW
completed by the insurer‟s engineer. The estimated repair time was 1 0 weeks noting
delays would occur over the Christmas break
further time elapsed until the complainant agreed to DW‟s SOW and paid the applicable
policy deductible for works to commence on 22 December 2017
repair works commenced on or around 22 January 2018. Given closure of the construction
industry over the Christmas/New Year period, the time taken is not unreasonable.
issues arose in April including in relation to electricity, changes by the complainant to
approved plumbing and request for changes to method of repair, service provider etc
repairs were mainly completed around July 2018.
There is an extensive history of communications between the parties which show several
changes needing to be made requiring discussions and in some instances variation to t he
SOW.
PC‟s reports show several variations. PC notes DW‟s work progressing to schedule however
amendment to the SOW for items including roofing materials, internal render, aluminium
shopfront etc. it considered the variations reasonable.
Determination | Case number: 732975 Page 19 of 28
The insurer says it/PC received a total of over 100 emails/communications from complainant
between 9 March and 23 April 2018 and trades experienced interruptions onsite from the
complainant.
The complainant‟s submission and timeline show the number of times the complaina nt
attended the premises and the extent of communications.
PC‟s report of 23 April 2018 shows the complainant had signed a new lease/tenancy
agreement and subsequently requested “upgrade to a number of items in the original scope
of works in line with guar antees made to the tenant …” and that further issues arose relating
to electricity supply which needed to be addressed.
The overall time taken to complete repairs was about six months. While this is less than the
original estimate of 10 weeks the available information shows time taken to address concerns
raised by the complainant about some works including the method of repairs, internal render,
roof, electrical infrastructure, shopfront glass etc.
It is not uncommon issues arise during a claim of this nature which need to be addressed; the
subject premises ran a specialised type of business; and works raised complexities that
needed to be sorted through, resulting in additional time being taken for repairs to be
completed.
The panel notes PC foreshadowed in its report of 1 February 2018 that possible variations
would be required due to possible concealed damage.
The time taken is generally not considered unreasonable if there are no periods of extended
inaction by the insurer.
While the claim/repairs were not finalised until August 2019, the panel considers the available
information does not show an extended period of inaction by the insurer.
Overall, the panel considers the time taken was not unreasonable in all the circumstances.
Fair the insurer pays $2,500 compensation for power supply issue
The panel notes the complainant was involved in the repair process, supervised the works,
obtained information to address issues/concerns about the building works being conducted
including in relation to:
Council requirements for the roof
addressing the reduced AMP of power supply and infrastructure which DW applied for in
relation to premises and getting information on how this should be corrected.
While the need to work with the insurer to address concerns about works being carried is not
of itself evidence of any failure by the insurer, the panel accepts the extent to which the
complainant was required to act to correct the error made in relation to power
supply/infrastructure to the premises caused delay.
Further the panel accepts this would have interfered with the complainant‟s expectation of
enjoyment or peace of mind.
The panel is satisfied it fair the insurer pays the complainant $2,500 non-financial loss
compensation.
Determination | Case number: 732975 Page 20 of 28
No specific policy cover for loss of rent
The complainant claims site delays caused interruption to the new incoming tenant which
necessitated the need to offer four months‟ rent -free period from 1 April to 1 August 2018. He
claims $24,815.82.
He says he was told the building would be completed and ready for use on or before 1 April
2018. He says the building certificate for the roof was not received from the council until 18
May 2018, there was no electricity on site until late June 2018 and as the fire safety
statement was not completed until 6 July 2018, the tenant could not move in.
The available information shows the work commenced on 22 January 2018. It was estimated
the work would take 10 weeks. The available information also shows due to the extent of
damage, variations due to concealed damage were likely to occur, there were numerous site
meetings about the work and variations eventually totalled $46,231.43.
There is no specific cover for loss of rent under the policy. Further, cover for consequential
loss of any kind is specifically excluded under the policy terms.
AFCA can award indirect financial loss compensation in certain circumstances
Under the AFCA Rules, we can award up to $5,000 compensation for indirect financial loss.
This may include the loss of use of a damaged item, the cost of renting a replacement item,
loss of income, or a loss of business opportunities.
The complainant‟s policy excludes cover for consequential loss. As this is the case, the panel
cannot award this type of compensation for loss caused by the fire.
However, the panel can consider if the complainant has suffered any additional loss because
of the insurer‟s claims management. When reviewing whether compensation should be paid
for this reason, the panel will consider whether loss was caused (wholly/partly) by the insurer,
or by the complainant or by factors outside the insurer‟s control.
Insurer’s conduct caused some of the loss of rent claimed
As set out above the panel found the insurer did not unreasonably delay the claim although
delay would have been incurred because of action required to correct the error made in
relation to power supply/infrastructure to the premises.
In the circumstances the panel considers it is fair the insurer pays to the complainant $5,000
financial loss compensation.
2.4 Was the insurer required to offer renewal of the policy?
Insurer notified complainant it would not renew policy
When renewable insurance is due to expire, the insurer must provide a notice under the
Insurance Contracts Act 1984 (Act). The notice must:
be provided at least 14 days before the policy expires
say when the policy will expire
say whether the insurer is willing to renew the policy.
There is no dispute the insurer notified the complainant the policy would not be renewed. The
complainant says he was notified of the insurer‟s decision on 11 May 2018 through his
broker.
Determination | Case number: 732975 Page 21 of 28
The certificate of insurance provided shows the policy term was due to end on 30 May 2018.
On the available information, the complainant was notified of the insurer‟s decision at least 19
days prior to the policy expiry. This exceeds the 14-day notification requirement under the
Act.
Insurer entitled to decide whether to offer insurance
The complainant says:
the insurer has not given a valid reason for its decision not to offer insurance renewal as
he had a clear claims history for the subject building in the 20 years preceding the subject
claim
suggests the decision not to renew appears to have been due to investigation of the
subject claim (which was found to be attributable to tenant not himself)
The decision disadvantaged him as:
> his broker withdrew service,
> he had to disclose the insurer‟s decline of insurance when seeking cover elsewhere,
and
> meant he had to go through a rigorous and time-consuming process including engaging
a lawyer to prepare a letter required for new insurance.
AFCA‟s jurisdiction to consider disputes about an insurer‟s decision to offer/renew insurance
is limited. We cannot consider a complaint about the insurer‟s decision not to offer insurance
unless there is evidence the decision was made indiscriminately, maliciously, or based on
incorrect information.
The complainant has not provided evidence which shows the insurer relied on any specific
incorrect information or made the decision not to offer cover indiscriminately or maliciously. In
the circumstances, based on the available information, the panel makes no finding adverse to
the insurer on this issue.
Determination | Case number: 732975 Page 22 of 28
3 Supporting information
3.1 Process
This matter was determined by a panel
Due to the nature of this dispute, it has been referred to a panel for determination. The panel
comprises the ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive experience as an insurer.
The panel has decided this complaint based on what is fair in all the circumstances, having
regard to legal principles, applicable industry codes or guidance, good industry practice and
previous relevant determinations of AFCA or predecessor schemes (which are not binding).
AF CA’s approach to this complaint
A full exchange of the relevant information has taken place between the respective parties.
Each party has had the opportunity of addressing any issues raised. All the provided
information has been reviewed and considered. The parties have raised numerous issues in
their submissions to AFCA. However, commentary in this determination is restricted to those
issues considered relevant to the outcome.
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an event to
which the policy responds. This is known as a prima facie or valid claim. Once so established,
the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies
if it seeks to deny or limit its liability for the loss.
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence. When we assess complaints, we consider available
documents, the recollections of the parties, and all relevant circumstances. We give more
weight to documents created at the time the events occurred. If there is no relevant
documentation, we will decide what is most likely to have occurred based on the information
provided to us. If there are conflicting recollections and these are evenly weighted, we may
find that a claim cannot be established.
Determination | Case number: 732975 Page 23 of 28
3.2 Relevant policy terms
Both the policy document and the Notice have been exchanged with the complainant.
What’s covered
This Asset Protection insuranc e covers property against physical loss or damage occurring
during the policy period.
Coverage is provided at insured loc ations and in transit up to the relevant limits.
POST LOSS EXPENSES
When covered loss or damage occurs cover includes, in addition to the location limit, expenses
incurred by the Insured for:
…….
claims preparation expenses under Asset Protection.
Cover is provided up to the Asset Protection post loss expenses limit.
What’s not covered
(the insurer) will not be liable for loss or damage arising out of or in connection with:
…..
consequential loss of any kind except as may be provided under Business Income Protection.
HOW CLAIMS ARE SETTLED
(the insurer) will make payments to the Insured or to others with the authority of the Insured to
settle covered claims.
…
CLAIM SETTLEMENTS
Claims for property (other than contents more specifically valued) will be settled at the cost to
reinstate the lost or damaged property, without deduction for depreciation, if reinstated within a
reasonable period of time following a covered loss.
- (The insurer‟s) payment to reinstate property will not exceed the amount actually spent by
the Insured to reinstate the property with property of like kind and quality.
- …
- If original materials, machinery or equipment are no longer available, the settlement will be
based on the cost of suitable alternatives.
- The damaged property will be reinstated to a condition equal to, but not better than when
new.
Claims for lost or damaged property that are not reinstated will be settled at their indemnity
value.
…..
Determination | Case number: 732975 Page 24 of 28
DEFINITIONS
claims preparation expenses that the Insured reasonably and necessarily incurred for
preparation and certifying of covered claims including:
> professional fees for architects, engineers, surveyors and
> accountants; and
> executive overtime that the Insured necessarily incurs with (the insurer‟s) consent for
mitigating claims under Asset Protection and Business Income Protection which are not
otherwise recoverable under this policy.
Indemnity value
Cost to repair or replace less an amount for age, wear and tear and depreciation and less an
adjustment for general condition and remaining useful life at the time of loss.
3.3 Extracts from material relied on by the parties
Date Action
Report (DW) after
inspection
10 September 2018
DW i nspected and photographed roof 10 September
2018 because complainant advised on 7 September
2018 the main roof leaked during a storm.
Attached were also phot ographs of DW‟s work on
completion of roof .
Minor paint damage was noted to the centre ceiling
expansion joint, the tenant said water has come out of
the dry - cleaning system exhaust, power cable next to
the exhaust, the centre ceiling expansion joint and the
mains power supply of the building.
Only visible damage was to paint work in at the
expans ion joint.
Landlord has engaged a roofer to look over the roof
prior to my inspection, the tenant had engaged a roofer
to complete his content fit out after the building claim
was complet e.
Damage related to the installation of the tenant‟s
content fit o ut was found and should show up on the
landlord‟s roof report, the roof clips have been pulled
apart and the sheets have been damaged during the fit
out of the content.
DW hold no liability in replacing or fixing any damage
related to the content fit out and or any further damage
related to wat er leaks as the damage to the roof has
occurred after the completion of the roof by another
trade not related to DW but the tenant.
At the time of our inspection, damage was visible to the
following: Minor paint dam age - Located to the centre
expansion joint.
Property is safe and does not require any emergency
measures to make safe.
Caus e of the damage is due to a large hailstorm on the
7/9/2018 hail has built up and allowed water to back -
flow over flashing entering the roof void and damaging
paint work.
Work required: Roof sheet damage related to the
tenant‟s content fit out.
Complainant’s builders
report (DS)
DS inspec ted after tenant‟s flue venting.
Roof has very recently been replac ed with Lysaught
Determination | Case number: 732975 Page 25 of 28
Email 30 May 2018 speed deck roofing. The above roof has been laid in 2
separate piec es with a flashing suppos edly sealing the
join. This join flashing is only 100 mm under the top roof
sheet and because it's not big enough and flat will
cause capillary action and leak .
Top roof needs to be raised and a larger apron installed
to combat this poor flashing detail .
Barge cappings are literally on both sides of the building
have simply been tucked into the cavity and this
channels the wat er directly into the void and create long
term moisture problems between both buildings which
will then turn into rising damp in the brick walls .
Barges have been laid incorrectly over the join; they
should have been following eac h roof plane separately .
Southern side parapet should have been completely
covered in Colourbond flashing and capping to prevent
water ingress in this area .
Nort hern side needs to be installed wit h a pressure seal
to sto p water ingress into the cavity.
Western gutter end and under apron flashing in middle
of roof screws have been driven thru the pans this
compromises the sheet and voiding any warranty .
Complainant’s consulting
engineer’s report (TY)
19 November 2018
Inspected and inspected property on 4 and 19 October
2018 to assess the cause of the roof leak.
Reviewed fire damage scope of works .
After heavy rain, water is discharging in ceilings next to
the WC‟s and above the electrical distribution board .
Recent repairs complet ed in a workmanlike manner
except for localised areas which we identified a s the
primary causes of the roof leaks .
Caus e of roof leaks adjacent to WC‟s is:
4.3.1 KLIP - LOK 700 Hi - Strengt h roof sheeting is
overlapped with a step down approximately at centre
span of the roof where rainwater is wicking back into the
roof void at the roof sheet overlaps and at the interface
between the roof vent back flashing and roof sheeting.
4.3.2 Displac ement evident in roof sheeting at the mid
span overlap combined with lack of visible foam infills to
eliminate voids in the roof sheet overlaps al lows
rainwater to wick into the roof void during heavy rain
periods when water volume is greater and cannot
discharge with sufficient velocity due to the low roof
pitch.
4.3.3 Concealed turn up pans at the lower roof sheet
ends may not be adequately detail ed where the roof
sheets overlap which may also allow rainwater to enter
the roof void during heavy rain periods.
The primary causes of roof leaks above the electrical
distribution board is due to:
4.4.1 Lack of provision of apron flashing at the abutment
between new metal capping and the adjacent north side
properties masonry wall allows rainwater to enter void
between adjacent buildings and ent er the northeast
Determination | Case number: 732975 Page 26 of 28
section of the subject building likely through a
concealed penetration in the subject property‟ s north
elevation wall.
4.5 Flashings around flue penetrations and vents in the
new roof sheeting were found to be installed in a proper
workmanlike manner and there was no evidence of
water penetration into the interior of the occupancy from
these roof p enetrations.
New roof sheeting has not been installed at the mid
span overlap in a way which complies with Code, so
advis e attempt to lift the upper roof sheets at the mid
span to install two rows of suitable durable foam infill
weat her strips.
Apron flash ing not installed at the abutment between
new metal capping and the adjacent north side masonry
wall in non - c ompliance with code and recommend
installing suitable apron flashing .
Complainant’s roof report
(AL)
20 September 2018
Inspected roof 18 September 2018 in relation to water
entry and noted 5 main issues contributing to water
entry with poor design and installation as depicted in
images.
1.Step in the middle of the roof has insufficient lap
between roof sheet causing rainw ater to penetrate roof
during severe storms and high winds. Lap is only
120mm with current installed roof pitch at 4 - 5degree
which clearly is insufficient as depicted in image 1.
Therefore, it requires to be increased to at least 400mm
on this shallow pitc h of roof to accommodate heavy rain
and wind.
2. Whirlybird roof vents have been installed in the wrong
place and to close to shallow lap of stepped roof sheets.
During heavy rain falls, rainwater is backing up the roof
on the tray of the vent and penet ra ting the shallow lap
roof on the step. As depicted in the image 2 to state this
is where the leak came from. Roof vents need to be at
the top of the roof away from the step to allow all hot air
to exhaust from roof space and to stop any leaks at
junction s tep of roof.
3. Flashings to both sides are not sealed and not
correctly flashed to neighbour‟s brick wall therefore
allowing rainwater to penetrate the void between the
two buildings as depicted in image 3. This can cause
water ingress through cracks in t he mortar on the
brickwork and damp issues in the future.
4. Gutter at the back of the shop is small to cope with
large volume of water. The design of the gutter has a
high front fac e forcing which forces water back under
roof sheets of roof into cavity i n large rooms. So, gutters
should allow water to flow over front during heavy rain
falls stopping any chance of wat er entry to building.
5. No installation of mesh under insulation as it a
Determination | Case number: 732975 Page 27 of 28
compulsory component when installing metal roofing in
commercial b uildings per AS4389 roof safety standard
for commercial building.
Roof will need to be removed and installed correctly
with metal mesh over timber rafters, correct lap at step
junction of roof to stop water entry, moving whirlybird
closer to top of roof a way from step junction. Flashing of
walls and end capping is required and then installing
200mm half round gutter at bottom of roof to allow
overflow of water during heavy rain fall.
Plumbing report (JS)
31 March 2018
Says he has carried out installation s and maintenance
at this dry cleaner for many years and identifies 5
services which need to be reinstated.
$560 charged for inspection and report.
Plumbing invoice (WN)
23 June 2019
To supply and fix new Colourbond awning roof and
flashings. Paint wall above. $3, 080. 00 GST .
One new rainwat er head to rear gutter. $385.00 GST .
Paint front tiles on both sides of shop. $440.00 GST .
Repair storm water pipe at front ground level. $330.00
GST .
Remove concret e and re concrete rear entry to shop.
Replace lid to pit by making new prefab concrete.
$880.00 GST .
Paint awning sealing metal angles on both ends and
install new Colourbond flashings. $660. 00 GST .
Extra work. Paint internal walls of roller door entry to
rear pick up area. $275.00 GST
Total $6,050 .
Plumbi ng Invoice (BKS)
9 August 2018
Plumbing copper pipe section required to be specially
made to fit broken terracotta pipe in ground. Fitted to
main water drain at south rear wall below laundry tub
area $770 including GST .
Shopfront Invoice (MG)
10 October 2018
Supply and install to Australian Standards and replace
existing aluminium framed shopfront as per original
configuration .
Revised subt otal $7,700 + GST for Clear anodised
frames. Terms of Payment: Deposit $3,850.00+GST
Paid on invoice 50779. Revised balance: $3850+GST
($4,235) .
3.4 Other relevant material considered and relied on
Parties‟ submissions/emails and all attachments to all submissions/emails .
Parties‟ expert reports and attachments.
Assessment reports (15) and all attachments to reports.
Photographs, invoices, quotations, and scopes of work.
Determination | Case number: 732975 Page 28 of 28
Correspondence between the parties.