Determination 732975

Claim handling and repairs following fire damage claim, including roof waterproofing and electrical supply issues

FirmSURA Pty Ltd
Decided2021-12-24
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$22,449
Non-financial loss$2,500
Amount claimed$61,133
SourceAFCA PDF

Summary

The complainant's commercial building was damaged by fire and repaired by the insurer's contractors, with later disputes over roof leaks, electrical supply, plumbing and claims costs. AFCA found the insurer liable to waterproof the roof and cover storm-related internal damage, reimburse report costs and some smaller items, and pay compensation for power supply issues and lost rent, but rejected most other claims.

The insured must establish a valid claim on the balance of probabilities, and the preponderance of independent expert evidence showed the roof was not waterproof due to installation defects, while claims preparation expenses were not incurred with the insurer's consent as the policy requires.

Issues

Subjects and remedies

financial hardshiphome or building damagepay claimpay compensationpay interestpay non financial lossrepair or rectify

Related

All SURA Pty Ltd determinations · Find similar determinations

Text of the determination

Determination Case number 732975 Financial firm SURA Pty Ltd Determination | Case number: 732975 Page 1 of 28 Case number: 732975 13 December 2021 1 Determination overview 1.1 Complaint The complainant held a Commercial Building Insurance policy (the policy) underwritten by the financial firm (insurer). The complainant lodged a claim under the policy after the insured building suffered fire damage in October 2017. The insurer accepted the claim and appointed loss adjustors (PC) to assess and coordinate reinstatement works. This complaint is about the handling of the claim by PC as well as the work completed and conduct of the appointed builder (DW) and other trades. The complainant was represented by his broker and his wife during the claim. For the sake of brevity and convenience, any reference to the complainant in this determination includes his representatives. 1.2 Issues and key findings Is the insurer liable for additional loss, damage, or rectification? The available information shows the insurer completed some repairs in line with the agreed scope of works and does not establish additional damage/rectification needs to be covered. The insurer is liable to waterproof the roof and pay for damage caused by water ingress in the storm on 7 September 2018 as set out in section 2.1 below. The costs which are required to be paid by the insurer are set out in section 2.1 below. Is the insurer required to make any other payments? Save that the insurer is to reimburse the complainant for report costs ($1,941.50) plus interest on $1,941.50 from the date the reports were paid until settlement pursuant to section 57 of the Insurance Contracts Act (the Act), the insurer is not required to make any other payments as set out in section 2.2 below. Is the complainant entitled to compensation? The available information shows that mostly the insurer did not unreasonably delay or mishandle the claim. Issues which arose in relation to electrical power supply and the steps the insurer took to address it were unsatisfactory and likely caused stress and inconvenience. As such, the insurer is to pay the complainant $2,500 non-financial loss compensation for stress and inconvenience and $5,000 financial loss compensation for loss of rent. Was the insurer required to offer renewal of the policy? The insurer exercised its right not to offer renewal of the complainant‟s policy and notified the complainant of its decision more than 14 days prior to the renewal as required under the Act. Determination | Case number: 732975 Page 2 of 28 In the circumstances, it has not breached an obligation owed to the complainant under the policy or the Act. 1.3 Determination This determination is partly in favour of the complainant. Should the complainant accept this determination then within seven days of notification of acceptance, the insurer is to:  pay to the complainant the amounts awarded by the panel as detailed in section 2.1 of this determination  act as set out in the heading “insurer liable to waterproof roof and to pay for damage caused by water ingress ” in section 2.1  pay the complainant $1,941.50 (plus interest) for report costs and  pay the complainant $2,500 non-financial loss compensation and $5,000 financial loss compensation. As for amounts awarded by the panel as addressed in section 2.1 of this determination, if the complainant has made and paid for repairs, the insurer is to pay interest pursuant to section 57 of the Act on those amounts from the date of the final decision (7 July 2020) or from the date of payment (whichever is the earlier) until settlement. Otherwise, the insurer is not required to make any other payment or take any further action in relation to the claim or the complaint. Determination | Case number: 732975 Page 3 of 28 2 Reasons for determination 2.1 Is the insurer liable for additional loss, damage or rectification? Circumstances of the complaint The complainant took out the policy with the insurer in or around April 2017 for the year commencing 30 May 2017. In October 2017, the complainant lodged a claim for fire damage under the policy. There is no dispute the complainant suffered loss covered under the policy in relation to a fire which occurred on 8 October 2017. The insurer engaged a loss adjuster (PC). As part of its assessment of the claim, PC obtained information on which it concluded the premises could be repaired/reinstated. This included building and engineering reports as well as scope of works (SOW) from the engineer (SW). The complainant says the insured property has not been reinstated to pre-incident condition and the insurer has not ensured like for like replacement as required under the policy. The complainant has made lengthy submissions detailing complaints about the management of the claim. Among other things, the complainant says:  PC/DW failed to obtain appropriate approval for roof replacement and only obtained a building certificate from the local Council after he raised this issue. He considers a Development Application (DA) rather than a certificate should have been obtained and the latter leaves him worse off  the insurer has not accepted responsibility for roof leak which occurred after roof replacement and due to failures in works completed by DW  DW did not complete some works provided for in the SOW and applicable variations appropriately and there are issues with the quality of work done which the complainant says he has incurred additional costs to address  the insurer has refused to provide warranty documents for specific items installed by DW, despite his requests  the electricity infrastructure was not installed to the pre-fire capacity  the insurer‟s handling of the claim was poor which resulted in his wife spending a lot of time managing the claim and trying to address errors by the insurer‟s contractors/sub - contractors  delays experienced caused d isruption to the „new incoming tenant that necessitated the need to offer a 4- month rent free period for the period 1 April to 1 August 2018‟. The complainant seeks a review of the above issues as well as other matters including the insurer‟s decision not to offer renewal of the policy for the period commencing in May 2018. Broker acting as complainant ’s agent when policy commenced The insurer is liable to settle at the cost to reinstate the damaged property. Determination | Case number: 732975 Page 4 of 28 The terms under which cover is provided under the complainant‟s policy are contained in the applicable policy documents. These are the Certificate of Insurance (COI) and a Product Disclosure Statement (PDS). The COI shows the complainant took out asset protection cover with a building sum insured of $240,000 with an uplift because of the insured location to $288,000. The complainant complains he was not made aware of the full extent of the policy cover and that the full limit of the insurance cover has not been used. The complainant confirmed the policy was arranged through his broker and that he has no issue with the broker‟s conduct. The broker was acting as the complainant‟s agent, not the insurer‟s agent. In these circumstances, the responsibility lies with the broker to ensure the complainant is aware of the policy terms. There is no dispute the broker was provided with the policy documents for the period of cover. In these circumstances, the panel is satisfied the insurer is entitled to rely on the policy terms and conditions in its assessment and settlement of the claim. Insurer is not liable to settle for the full limit of cover Further, the insurer is not obliged to pay the full limit of the insurance cover. The panel is satisfied the policy terms require the insurer to indemnify the complainant for the damage caused by the fire only. The insurer is required to settle the cost to reinstate the damaged property only up to the building sum insured. Insurer appointed experts to prepare SOW The insurer appointed a loss adjustor (PC), a builder (DW) and an engineer (SW) to determine the cause and extent of damage, as well as what was required to reinstate the property. The complainant mainly dealt with PC throughout the claim as it managed the claim and liaised with the complainant on the insurer‟s behalf. PC‟s initial report dated 16 October 2017 includes photographs and a list of observed damage. In the report PC notes some make safe had been conducted by a builder (WW) and that an engineer (SW) had attended the premises to provide advice and prepare a scope of works (SOW). PC reports there was significant fire damage in the rear of the building which spread into the ceiling. The report notes:  plasterboard walls were severely burnt exposing the brick walls  the footings and brick wall, shopfront façade and awning appeared „largely unaffected‟  the interior and roof structure will likely need to be gutted and rebuilt which may require council planning permission and delay rectification works into the new year. PC provided numerous other reports throughout the claim process, some of which will be discussed in this determination. SW subsequently provided a SOW to PC. PC referred the scope of works to DW and another builder who provided quotations for the cost of repairs. PC reviewed the quotations and recommended the building contract go to DW. Determination | Case number: 732975 Page 5 of 28 PC continued liaison with the complainant, the broker and the builder regarding the refined scope of works. Updated quotations were obtained. Both builders estimated construction time would take 10 weeks. The complainant indicated he would contact the council to confirm certification requirements. The complainant also indicated he may seek a further independent repair quotation. On 22 December 2017 the complainant accepted the SOW and agreed to DW carrying out repairs as evidenced by the payment of the policy excess. Having considered all the available information, the time frame in which the above took place and the broker‟s role, the panel does not accept the complainant‟s position was compromised before the complainant accepted the scope of works. Variations totalled $46,231.43 The available information also shows once repairs commenced several issues were included in variations (totalling $46,231.43). I n PC‟s 11th report dated 13 July 2018 PC noted all reinstatement works required under the policy were completed. The report notes the final invoice from DW for the works completed was $178,525.58 being the original contract price plus variations less the policy excess of $1,000. In its 12 th report dated 28 August 2018 PC noted DW completed cleaning the driveway and patching plaster to the shopfront following installation of the glass frontage. DW was paid a further $683.10. Complainant has the onus to establish his contentions The complainant has many complaints about the building cost variations, work the builder did not perform, work done badly and the conduct of DW and PC. The complainant says some of the works completed did not comply with the SOW and/or were not done correctly and require rectification. For ease of reference, these items will be considered under several headings below. The panel notes the complainant must establish on the balance of probabilities that he has suffered a loss caused by an event to which the policy responds. This is known as a valid claim. For all his complaints, the onus is on the complainant to establish on the balance of probabilities the claimed damage was caused by the fire, by the repairs, or that repairs were inadequate or not completed in accordance with policy terms and conditions. Council application/approval for the roof The complainant says DW should have obtained a DA approval prior to replacement of the roof. He says such application/approval was allowed fo r in PC‟s scope of work (SOW) as well as in DW‟s quotation, but it was not obtained. The complainant says the Building Information Certificate obtained post work is not the same as a DA and states it only lasts for 7 years. He questions what happens after the 7-year period. The complainant also says the insurer used a different material (KL) for the roof replacement and this material itself is not certified by the council‟s certificate which only deals with the roof structure. Determination | Case number: 732975 Page 6 of 28 The complainant asserts an application for a building certificate was only made after the roof repairs had commenced and raises issues about the lack of DA approval. In response the insurer says:  DW submitted the Development Application (DA) to the relevant council on 1 May 2018 for replacement work to the existing roof and a reference number and link was provided  DA is a development application, which is defined as a formal application to council for carrying out various types of development  DW did not make a mistake in submitting the DA for approval  DW received approval and a Building Certificate for the roof replacement which is available at the council‟s website  All repairs were scoped and checked by an engineer and the assessor (PC) The insurer provided a link to the relevant information in the exchanged response to the complainant on or about 2 September 2020. The panel reviewed the link to the council website. The panel notes an application was made for „replacement work to existing roof‟ at the insured address on 1 May 2018. T he council records show status as „Building Certificate Issued‟. The complainant maintains the building certificate (BC) is not the same as a DA and the latter should have been obtained. The panel has carefully considered the parties‟ submissions about BC versus DA. The complainant is adamant an error has been made, not only because a BC was obtained, but also because it was obtained after roof replacement had occurred. He says BC‟s are obtained after the fact from councils where illegally constructed building works have occurred, last for only seven years after which the council can require repair, demolition, alteration or a rebuild. DW‟s quote shows the work was to be done in accordance with Australian Standards and council requirements. The SOW includes item 15 which allowed for all necessary costs to provide plans and specifications required to submit DA (if applicable) and receive a construction certificate. The available information, including the scope of works and PC‟s reports indicate plannin g permission or approval may be required in the context of discussing possible duration of repairs. The panel has carefully reviewed information provided about the requirement (or otherwise) for council permit/authorisation in the form of a DA or a BC. The panel is not satisfied on the available information that authorisation obtained in the form of a BC is incorrect or in breach of relevant law/regulation. A review of the BC shows the council inspection occurred on 16 May 2018 and that: 1. the certificate operates to prevent council from taking certain actions in relation to the building (or part thereof), „making an order under the Environmental Planning & Assessment Act 1979 or the Local Government Act 1993 requiring the building to be repaired, demolished , altered, added to or rebuilt‟ 2. states the certificate operates to prevent the council from making an order under the legislation listed in 1 above, for a seven- year period but this is specified as being „in Determination | Case number: 732975 Page 7 of 28 relation to matters arising only from the deterioration of the building because of wear and tear‟ The complainant provided extracts from an email from what appears to be a council worker (CM) dated 26 March 2018 in support of his position that a DA is required. In the email CM says:  he had looked thro ugh „SEPP Exempt & Complying Development 2008‟ (presumably legislation/regulation) and provides excerpt from subdivision 27 which deals with minor building alterations (external) and paragraph 2.53, and  was unable to identify any exemption for external st ructural work including „new replacement roof‟  roof replacement works „could fall within the provisions of Complying Development Certificate for the remaining works (not yet completed) and a Building Certificate application for works already undertaken‟ In the panel‟s view, it is not sufficiently clear as to the capacity in which CM made this statement and what question(s) he was responding to. The statement itself does not include sufficient information on which the panel can be satisfied an error was made by the insurer in obtaining a BC. Rather as stated above, the wording of the BC and information on the council link confirms a BC is satisfactory for „replacement work to existing roof‟ as noted on the council website. Further, the panel notes CM appears to confirm BC applications can be made for works already undertaken. Finally, the SOW does not mandate a DA. In any case, even if the panel accepted a DA should have been made prior to roof works commencing (and it does not), AFCA cannot award any remedy as the complainant is seeking an acknowledgement of liability for possible future loss. AFCA cannot provide a remedy for loss which has yet to occur or has not crystallised. Insurer liable to waterproof roof and to pay for damage caused by water ingress Repairs were completed in August 2018. The building was tenanted. In early September 2018, the tenant reported water ingress from the roof in a storm on 7 September 2018. The complainant says the tenant showed him photos/video of water ingress during heavy rain and that he observed wetness to the floor, watermarks and dampness on the ceiling/ceiling join. He notes the ceiling cavity was contaminated and that there was damage to areas of electrical infrastructure which needed to be assessed for cover. The complainant considered the water ingress was a result of KL roofing used, incorrect installation/construction and overall failures in work carried out by DW when the roof was replaced which according to his expert input was “not a perfect build”. The complainant considers the insurer has not met its obligation to replace the roofing like for like as different materials to the original was used by DW (including the KL roofing). Determination | Case number: 732975 Page 8 of 28 Additionally, he considers the warranty for the roofing should be extended because of the issues with water ingress not being satisfactorily addressed (because the overflow workaround was being figured out). He seeks:  the plumber‟s work for the overflow work  the cost of the roofing reports ($726.00 and $1,215.50), and  review of warranty issues and extension of warranty  cost of time involved in attending to these matters These last 3 matters will be dealt with separately later in this determination. The insurer says the water ingress was not related to claimed incident and building works. Rather, it says the damage was caused when the complainant‟s tenant installed roof vents and other works for its dry-cleaning equipment. The complainant does not accept the tenant‟s work is the cause of water ingress. The complainant also says the tenant advised him DW undertook more (unauthorised) work, but he does not know if the roof is watertight. PC says the roof was constructed/installed correctly by DW and signed off by civil engineer (SW), local council and the builder with a warranty. The complainant says SW is not independent and DW is not able to independently provide an opinion about DW‟s work. The panel notes SW provided a construction certification for roof and ceiling structure at the insured premises in which it certif ies and confirms „that the completed roof and ceiling structures are in accordance with the above- mentioned structural drawings and details‟. In support of its position, the insurer has provided a report DW completed after the reported water leak as well a s PC‟s report (number 13) which addresses the issue. PC says after DW assessed the premises (two days after a storm); it did not find any storm related damage. It says from discussions with DW and the subcontracted roofer (AL) about the reports provided by the complainant, there is no evidence of incorrect installation and any water ingress. Relying on these conversations and photographs which are attached to the report it says:  the step design in roof installation is within amount specified by roofing sheet manufacturer  whirly- birds were installed at an appropriate location with „more than enough distance (500mm+) for water to make its way around the shaft and not back up‟  flashings were not fixed or sealed to neighbouring property as the complainant informed the builder/roofer this was not allowed  gutters installed were the same and at the same location they were in prior to the fire and made appropriate overflow provisions  water could not flow back into the building because the gutter is slotted  the mesh under the roof sheeting has nothing to do with the leak and was not installed because during installation a platform scaffold was used  several modifications had been done to the roof by the complainant‟s tenant which means the roof warranty is likely to have been voided and the modification and/or installations are likely the cause of ingress reported Determination | Case number: 732975 Page 9 of 28  photographs provided show the modifications to the roof and roof sheeting by the tenant during the installation of vents and stacks which has changed the roof structure since DW‟s construction  the insurer may want to appoint its own engineer to assess allegations re water ingress. The insurer did not appoint an engineer. Reports relied on by the parties are set out in supporting section 3.3 of this determination. DW said the cause of water ingress reported is hail build-up during a storm which allowed water to back-flow over flashing entering the roof void. DW noted minor paint damage to the centre ceiling inspection joint DW said some damage had been caused by the tenant‟s roofer during installation of content fit out for which it is not liable. In reaching its conclusion DW points out:  the tenant reported that water came „out of the dry -cleaning system exhaust, power cable next to exhaust, centre ceil ing expansion joint and mains power supply”  there was visible damage to paint work at the expansion joint only  prior to inspection, the tenant had engaged other roofers for installation of contents fit out  the tenant‟s work damaged the roof including roof clips which have been pulled apart and sheets which are damaged In response, the complainant says:  DW incorrectly assumed the tenant had installed „whirly birds‟ on the roof as the whirly birds and stepped sheeting identified were installed by DW  DW made errors regarding the location of water entry reported by the tenant. While DW suggests water came in from dry cleaning system exhaust or power cable next to it, based on the tenant‟s report to the complainant, the water came through the conduit on the northside rear wall, through the bathroom area on the north side of the property, through the middle ceiling joint (which he believes is below the step in the roof) and through the electrical cables at the northside shop front  DW is not independent, and the report is biased  water did not come through the tenant‟s flues and vents which are on the south rear of the building. The complainant relies on 3 reports which are summarised in supporting section 3.3 of this determination. The builder (DS) identifies several problems with the roof including the way the barge cappings have been installed and the inadequacy of flashing and capping and pressure seals on the northern and southern sides of the building. Relevant to the paint damage identified by DK, DS says the roof has been laid in two separate pieces and the join flashing is not big enough. The engineer (TY) identified the same issue. TY also refers to lack of apron flashings at the north side wall. TY specifically exonerates the tenant‟s work. He says: 4.5 Flashings around flue penetrations and vents in the new roof sheeting were found to be installed in a proper workmanlike manner and there was no evidence of water penetration into the interior of the occupancy from these roof penetrations. Determination | Case number: 732975 Page 10 of 28 The roof report obtained in September 2018 from AL refers to the same issues identified by DS and TY. That is, that the step in the middle of the roof is inadequate and the flashings to both sides are not sealed. AL also identifies that the whirlybird roof vents were installed in the wrong place, the gutter at the back is too small to cope and metal mesh should have been installed under the installation. The panel has carefully reviewed the reports and information provided in relation to the claimed water ingress and the installation of the roof. In the context of this claim, the complainant must establish the claimed damage was caused by the September storm and/or because the insurer‟s work to the roof was inadequate. The panel notes the complainant‟s assertions are rebu tted by PC after consultation with DW and the roofer as set out in PC‟s 13 th report. The panel also notes the claimed water ingress occurred around 5 months after the roof was replaced by the insurer and following modification and/or installation of equipment which required vents/shafts in the roof by the complainant‟s tenant. The complainant says DW is not independent. The panel acknowledges this statement but also notes the photographs provided by DW showing the roof before and after the tenant‟s installations. The panel accepts TY is independent and his report is clear and unambiguous. TY says the tenant‟s fit out has not compromised the roof. Having carefully reviewed the three reports provided by the complainant, the panel accepts that assertion. Th e panel notes the installation of the roof was approved by the insurer‟s engineer, and the local council. However, the panel is persuaded that the preponderance of expert evidence is that the roof is not waterproof for the reasons stated by DS and TY. Both reports refer to the same issues with the roof – that the two separate pieces of the roof are not properly sealed, and the apron flashings are not properly sealed. AL identifies the same issues. Only AL identified the issue regarding the mesh. The panel does not accept this is responsible for water ingress. AL also identifies that the whirlybird roof vents have been installed in the wrong place but in the absence of comment by DS and TY, and in view of PC‟s assertion on this issue, the panel does not accept this issue means the roof is not waterproof. AL says the gutters at the back are too small. DS and TY do not criticise the gutters. In view of the material provided by PC in relation to the gutters, the panel does not accept the gutters were inadequate or responsible for water ingress. The panel notes the re is no expert opinion which supports the complainant‟s contention the roof is faulty or leaked because of the KL roofing used. Based on the available information, the panel does not accept this assertion. Should the complainant accept this determination then within seven days of notification of acceptance, the insurer is to repair the roof, so it is waterproof. The waterproofing work required is identified by DS and TY in their reports. Determination | Case number: 732975 Page 11 of 28 Alternatively, the insurer may opt to obtain a quotation to cash settle the cost of waterproofing the roof. The cash settlement must include a 20% uplift to take into account any contingencies or variations which may occur once repairs commence. The insurer is also responsible to indemnify the complainant for the internal damage caused by the water ingress in September 2018. Should the complainant accept this determination then within seven days of notification of acceptance, the insurer is to repair the internal damage or indemnify the complainant if the complainant has already repaired the internal damage. If the complainant has repaired the internal damage caused by the storm in 2008 September 2018, upon provision of invoices, the insurer is to pay interest on this amount from the date it was paid until settlement pursuant to section 57 of the Act. The panel notes the complainant indicates there has been no water ingress since because of his plumber‟s overflow work. Upon provision of the relevant invoice, the insurer is to reimburse the complainant for this cost. Additionally, the insurer is to pay interest on this amount from the date it was paid until settlement pursuant to section 57 of the Act. Insurer not liable to rectify the brickwork The complainant says the insurer did not meet its policy obligation to return the premises to pre-existing condition by providing like for like replacement/repairs. He says in relation to the brickwork there was no evidence of any test performed on the brick walls to ensure the ongoing integrity of the mortar after the heat of the fire. He says painting burnt bricks with weakened mortar with white paint does not reinstate the bricks or mortar to the policy requirement of “the damaged property will be reinstated to a condition equal to, but not better than when new”. The complainant provided photographs of the fire damaged brick walls and some which appears to show the walls painted over. He considers the brickwork should have been replaced. The complainant says the insurer has not met the terms of the policy in regard to cleaning/pa inting the brick walls which had been subject to intense fire „will likely have damaged the mortar which has not been assessed or repaired‟ and it is unlikely „damaged bricks and mortar will last as long and be as strong as bricks in as new condition‟. The panel notes the complainant has not provided any information from suitably qualified persons that cleaning, or painting fire darkened brick is insufficient re-instatement or that the mortar has been fire damaged or weakened. On the available evidence, the panel does not accept the complainant‟s contentions about the brick walls. Insurer not liable to rectify further the plaster render or shop concrete floor The complainant raised concerns about repairs to plaster render and flooring. The available information shows there was disagreement in relation to the plaster render methodology used and that the complainant requested an alternative repair method against advice from the insurer‟s contractor. Determination | Case number: 732975 Page 12 of 28 The complainant‟s submissions about the render are not s upported by any expert evidence about the adequacy (or otherwise) of repairs to internal walls or which persuasively contradicts the insurer‟s assessment about the repairs. In relation to the concrete floor the complainant says at a site meeting PC agreed the front portion of the flooring (which previously had tenant‟s vinyl), would be sanded, polished and sealed and the remaining area would be cleaned following removal of tenant‟s contents. He considers this has not been adequately done as only the first four metres from the shopfront was polished and sealed rather than the whole floor space. He says holes left by removal of the tenant‟s contents were not filled and the whole area has not been finished or properly sealed. PC‟s report of 20 June 2018 shows i t agreed to seal the front portion of the concrete floor and clean the remainder. It says the cleaning which occurred at least three times, sufficiently restored/reinstated the flooring. It also notes the new tenant‟s installation of equipment meant works to seal or polish the floor was not feasible. The panel has reviewed the available information and is satisfied the insurer has completed repairs/restoration to the shop flooring in line with the agreed SOW. The panel does not consider the complainant has provided persuasive evidence (such as a report from a suitably qualified expert) that the repairs in question were inadequate or substandard. The complainant has not met the onus he has to establish the claimed loss. The insurer is not liable to rectify further the plaster render or shop concrete floor. Insurer not liable to rectify further the roller door The complainant says the current tenant complains the rear roller door is not of commercial strength. He says PC and DW have not provided data sheets or specifications, so he could check the commercial gauge of the door. PC has provided an email saying the roller door is commercial. The panel does not consider the complainant has provided persuasive evidence (such as a report from a suitably qualified expert) to establish the roller door is inadequate or substandard. PC has provided an email saying the roller door is commercial. The insurer is to provide further information to the complainant to confirm its specifications. Insurer not liable to further rectify vents and bathroom window installation The complainant says the quality of work is rough and unacceptable and no specifications have been provided on the window framing. The panel does not consider the complainant has provided persuasive evidence (such as a report from a suitably qualified expert) to meet his onus to substantiate these contentions. Insurer to pay $880 for the rear step and concrete sewer cover The complainant provided a quote for repairs to a rear external step. He says the step was damaged in the fire and/or during attendance by the fire service or by contents removal. Determination | Case number: 732975 Page 13 of 28 The insurer says the external step damage was assessed by engineer as pre-existing as information shows loose bricks two days after the fire. The panel has reviewed reports and photographs provided. It notes there is a possibility the damage existed prior to the fire but also accepts from some photographs the step could have been damaged during the fire or by the fire services. In the circumstances, the panel considers it fair the insurer pays the cost of repairing the step and concrete sewer cover to the complainant in the sum of $880. Insurer to pay $275 for the rear door jamb In relation to the complainant‟s request that the insurer paint the external concret e jamb around the roller door, PC‟s report of 30 June 2018 includes photographs and says it is satisfied the repairs have been done and area „reinstated to a suitable standard‟. The complainant says PC says this was internal fit out, but he says the area is external to the roller door. The complainant says the raw render to the door jamb and roller door area is visible from inside the building, is porous therefore the „requested painting was critical‟. The panel has considered the parties contentions and photographs. The panel accepts the areas is external to the roller door. In the circumstances the insurer is to pay to the complainant $275. Product warranties and overall quality of repairs The repairs were completed by DW and are subject to any warranties under the building contract agreed to by the complainant. The complainant has raised several questions about durability, warranties etc. The panel considers there is insufficient information (such as report(s) from a suitably qualified expert) that the warranty provided is not applicable. In any event, as the work was undertaken by the insurer‟s contractors under the insurer‟s supervision, if further future issues occur in relation to the overall quality of repairs, the insurer must act in good faith to address those issues if and when they arise. No finding can be made at this time for future possible or potential loss The complainant says electricity was not replaced to pre- fire conditions because the insurer‟s contractors did not consult with him about it and made errors by:  incorrectly applying for a new rather than existing connection which he already had with the power supplier for 300AMP entitlement connected to his „NMI‟. This meant the existing approval was lost and he is now left with 250AMP. He notes this was only obtained after he raised the issue and provided the insurer with evidence that the 125AMP approved on the new application was incorrect. It remains less than what was available at the property prior to the fire  installing new infrastructure which was inadequate and did not consider what was needed for a purpose-built dry-cleaning business. The complainant provided a statement from the electrical technician (SS) in which SS confirms the existing 300AMP power supply and infrastructure which was „sized up‟ to the Determination | Case number: 732975 Page 14 of 28 supply at the premises to suit the machinery in commission at the time the complainant‟s wife‟s family operated a dry -cleaning business from the premises. The panel notes a tenant occupied the premises at the time of the fire and after. The complainant says the power provider confirmed the insurer could have applied for 300AMP, but DW incorrectly applied for 125AMP. As a result, DW had to provide a new application for 300AMP (not revert to the old) and was treated as a new property connecting to the grid based on assessment of current need. While the current power supply meets the tenant‟s current needs, the complainant says there will be issues should the tenant expand the business in future. Future applications may mean additional costs for cables, substation etc. The complainant requires the insurer to cover the cost of infrastructure reinstatement to cater for 300AMP in the future once the tenant is no l onger „in situ‟ based on an assessment the insurer must make and pay the difference in costs. As the person alleging loss has been suffered as the result of an error by the insurer, the onus is on the complainant to provide evidence substantiating such loss. From the panel‟s review of the information provided in relation to the electrical/electricity issues raised (relating to both power and infrastructure), the panel is not satisfied the complainant has established any loss which can be substantiated because of power supply and infrastructure at the premises being 250AMP and not 300AMP. As no loss has crystallised because of the power supply issues, at this time the panel has no basis on which to award compensatory costs, however the panel has taken this into account in its review of overall claims handling as set out in section 2.3 of this determination. Insurer to contribute $1,500 to plumbing claims The complainant says plumbing work carried out by DW was insufficient and that he incurred cost in correcting errors made by DW including:  installation of residential rather than commercial plumbing facilities in the laundry area  fixing incorrect installation of pipes (with no backflow prevention facilities which according to the complainant is required by Sydney Water)  repairing overflow/rainwater head to rear  repair of leaking stormwater pipe. The complainant says the plumbing was not repaired/replaced „like for like‟ and the insurer refused to address concerns about it appropriately. As a result, he says he had to engage a plumber incurring a total of around $2,705 to return the plumbing to pre-fire conditions/specifications. The complainant provided a statement from plumber (JS) as well as photographs to support his position. JS‟s statement dated 31 March 2018 includes that JS had carried on maintenance for the dry- cleaning business run from the premises „for many years‟ and lists five items required for „Reinstatement of Services‟ The insurer says information provided by the complainant does not establish DW did not complete repairs (including plumbing repairs) correctly. It submits the complainant made numerous unsubstantiated allegations about the works carried out by the builder and its trades throughout the repair process. Determination | Case number: 732975 Page 15 of 28 After reviewing information provided in relation to the claimed unsatisfactory plumbing work, the panel is not satisfied it shows:  all repairs by DW was not in accordance with the accepted scope of works  all the plumbing work carried out by the complainant is related to claimed fire or correcting works completed by the insurer‟s contracto rs/trades or damage. The insurer is therefore not required to cover all these claimed costs, but the panel considers it is fair some of the claimed costs are paid by the insurer. Further, as set out above the overflow work is to be paid. The panel is satisfied it is fair the insurer pays to the complainant $1,500 for plumbing. Insurer to pay complainant $8,533.53 for aluminium and glass shopfront There is no dispute the insurer agreed the complainant would arrange for replacement of the glass shopfront with his own supplier (MG). PC‟s report of 30 May 2018 includes that the amount allowed for this in DW‟s quote ( $12,331) had been deducted as the complainant found other trades to complete shopfront work at the cost of $8,470. The complainant has provided an invoice from MG with total cost of replacement noted as $8,533.53. If the insurer has not already paid this cost to the complainant, it should do so within 14 days of this determination. Insurer to pay complainant $758.79 for new metering cost The complainant is seeking payment of $758.79 for new metering costs which he says the insurer had agreed to cover. The available information does not show the insurer agreed to cover this amount as claimed by the complainant but in the absence of rebuttal from the insurer, the panel considers it is fair this amount is paid Energy supply/usage during repairs to be paid by insurer ($773.70) The complainant seeks payment for:  Generator cost to tenant $623.70  Electricity usage - next door neighbour $150.00 PC‟s report of 24 April 2018 confirms unauthorised connection to neighbour‟s electricity has occurred. PC then arranged for a generator. The insurer has not provided any information to refute the estimated amount sought by the complainant in relation to electricity usage from neighbour. As such, the insurer is to pay $150 to the complainant. The complainant seeks $623.70 for 3 extra days for the generator cost for tenant use as no electricity was on site until late June 2018. He says PC delayed its response on the extension of the generator for temporary power and that he was required by the tenant to organise a generator to enable installation of the tenant‟s equipment. Determination | Case number: 732975 Page 16 of 28 In view of the issues with the electricity supply because of the AMP issues and as this assisted the tenant to be installed thereby mitigating loss, the panel considers it is fair the insurer reimburses this amount to the complainant. Insurer to pay complainant $1,675.00 for false wall cover The complainant seeks payment for a false wall/cabinet he says was installed to cover the internal electrical switchboard to make the area safe. He provided an invoice of $1,675.00 for the works and maintains that prior to the fire, a similar wall was in place. He refutes it was part of the tenant‟s fit -out. The complainant also says the area covered by the cabinet has a water meter and back-flow prevention device and  cover was required to prevent any risk of electrical shock  the area was covered prior to the fire  the „manner in which the electricals have been remediated has left cables outside the wall cavity that were previously within the double brick wall cavity and so are not encased but exposed‟ which necessitated the false wall cover being all the way to the ceiling. The insurer has not specifically addressed the false wall in its response. PC‟s report of 20 June 2018 includes that the complainant requested installation of cabinet/cupboards over internal electrical switchboards, and this is marked as „No‟ taken to mean no cover. However, no cogent reason is given for the refusal. There is insufficient evidence to make a finding that such a wall was in place prior to the incident and should have been covered under the claim or repair scope of work. The panel has considered the material provided including photographs. The panel accepts a safety issue is at play. And, in the absence of rebuttal from the insurer the panel is satisfied it is fair this amount is paid. For all payments in this determination (as set out above) if the complainant has made and paid for repairs, the insurer is to pay interest pursuant to section 57 of the Act on those amounts from the date of the final decision (7 July 2020) or from the date of payment (whichever is the earlier) until settlement. 2.2 Is the insurer required to make any other payments? Insurer to reimburse complainant for report costs ($1,941.50) Under its Rules, AFCA can require an insurer to reimburse a complainant for costs incurred in making a complaint. This may include expert report fees. If a complainant asks the insurer to contribute to such costs, AFCA will consider whether they were reasonable and whether they helped resolve the complaint. The complainant has provided invoices for the cost of obtaining roof report from AL and TY following water ingress from the roof during a heavy storm some months after repairs had been completed by DW. He seeks reimbursement for the costs which are $726 and $1,215.50 for AL and TY‟s reports, respectively. The panel has considered the reports from AL and TY. The reports assist the complainant‟s position. Further, it was appropriate for expert reports to be obtained to rebut the expert opinion from the insurer. Determination | Case number: 732975 Page 17 of 28 The panel is therefore satisfied it is fair the insurer reimburses the complainant $1,941.50 for the cost of expert reports. Additionally, the insurer is to pay interest on $1,941.50 from the date the reports were paid until settlement pursuant to section 57 of the Act. Insurer not liable for claims preparation costs The complainant provided details of time spent by his wife (as his representative) on the claim. He says his wife:  acted in the capacity of a claims manager dealing with the SOW and items selection, ensuring works/items being repaired/replaced were „Like for Like kind and quality‟, engaging with utilities suppliers and relevant local authorities to establish correct reinstatement and overall supervision of works including arranging for builder/asse ssor‟s mistakes to be corrected  needed to be involved due to poor handling of the claim and repairs by PC, DW and DW‟s trades/contractors, and the need to constantly address errors (including seeking alternative replacements for items such as the shopfront glass). In view of this, he says he is entitled to payment of $ 61,132.50 (inclusive of GST) under the policy cover for claims preparation for her time expended. He est imates this time at 370.5 hours at a „professional service‟ rate of $165/hour. The complainant provided an invoice from his wife and a timeline in support of his request for payment. Under „Asset Protection‟ cover, the complainant‟s „claims preparation expenses” may be covered when loss or damage occurs. The policy defines claims preparation expenses as set out in supporting section 3.2 of this determination. The panel is satisfied the definition is clear and unambiguous. The benefit operates such that:  the types of expenses listed are „reasonably and necessarily‟ incurred  need to be for preparing and certifying of covered claims  includes a list of the types of expenses which contextually relate to expertise needed for actual building work (engineers, architects, surveyor etc). This does not apply to the complainant‟s case as his wife does fall within this category nor is she an accountant  there is allowance for „executive overtime‟ incurred by insured, but this is limited to time incurred to mitigate claims  the definition specifically states the insurer‟s consent is required. The available information does not establish the claimed expenses relate to professional costs as described in the definition or were incurred to mitigate claims. Most significantly, the substantial costs were not incurred with the insurer‟s consent. The panel is not satisfied the complainant has established an entitlement to claims preparation expenses under the policy terms. Determination | Case number: 732975 Page 18 of 28 2.3 Is the complainant entitled to compensation? Compensation is awarded in some circumstances The complainant seeks review of the insurer‟s overall claim s handling, the conduct of its representatives/contractors/staff members, and the extent of time it has taken to finalise the claim. AFCA will award compensation (capped at $5,000) if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant‟s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and anxiety. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. AFCA reviews any claim of misconduct to determine whether compensation is warranted. AFCA is not the industry regulator and cannot review the insurer‟s internal processes or policies, including its decision about who carries out its claims assessment. In the present case this means the panel cannot review any commercial relationship between any of the experts appointed to provide services as professionals in their distinct fields. Save for power supply issue insurer did not unreasonably delay the claim The available information includes:  the fire incident occurred on 8 October 2017  the claim was lodged on 9 October 2017 and PC attended at the premises on that date  the insurer arranged immediate make-safe to board up the premises  the insurer‟s structural engineer attended the premises on 11 October 2017  time taken to assess, and complete a SOW was impacted by investigations of the claim. As the premises was tenanted this also meant time taken was also affected by assessment/investigation by the tenant‟s insurer (incidentally also the same insurer)  repair quotes were obtained in early November 2017 following tender on the SOW completed by the insurer‟s engineer. The estimated repair time was 1 0 weeks noting delays would occur over the Christmas break  further time elapsed until the complainant agreed to DW‟s SOW and paid the applicable policy deductible for works to commence on 22 December 2017  repair works commenced on or around 22 January 2018. Given closure of the construction industry over the Christmas/New Year period, the time taken is not unreasonable.  issues arose in April including in relation to electricity, changes by the complainant to approved plumbing and request for changes to method of repair, service provider etc  repairs were mainly completed around July 2018. There is an extensive history of communications between the parties which show several changes needing to be made requiring discussions and in some instances variation to t he SOW. PC‟s reports show several variations. PC notes DW‟s work progressing to schedule however amendment to the SOW for items including roofing materials, internal render, aluminium shopfront etc. it considered the variations reasonable. Determination | Case number: 732975 Page 19 of 28 The insurer says it/PC received a total of over 100 emails/communications from complainant between 9 March and 23 April 2018 and trades experienced interruptions onsite from the complainant. The complainant‟s submission and timeline show the number of times the complaina nt attended the premises and the extent of communications. PC‟s report of 23 April 2018 shows the complainant had signed a new lease/tenancy agreement and subsequently requested “upgrade to a number of items in the original scope of works in line with guar antees made to the tenant …” and that further issues arose relating to electricity supply which needed to be addressed. The overall time taken to complete repairs was about six months. While this is less than the original estimate of 10 weeks the available information shows time taken to address concerns raised by the complainant about some works including the method of repairs, internal render, roof, electrical infrastructure, shopfront glass etc. It is not uncommon issues arise during a claim of this nature which need to be addressed; the subject premises ran a specialised type of business; and works raised complexities that needed to be sorted through, resulting in additional time being taken for repairs to be completed. The panel notes PC foreshadowed in its report of 1 February 2018 that possible variations would be required due to possible concealed damage. The time taken is generally not considered unreasonable if there are no periods of extended inaction by the insurer. While the claim/repairs were not finalised until August 2019, the panel considers the available information does not show an extended period of inaction by the insurer. Overall, the panel considers the time taken was not unreasonable in all the circumstances. Fair the insurer pays $2,500 compensation for power supply issue The panel notes the complainant was involved in the repair process, supervised the works, obtained information to address issues/concerns about the building works being conducted including in relation to:  Council requirements for the roof  addressing the reduced AMP of power supply and infrastructure which DW applied for in relation to premises and getting information on how this should be corrected. While the need to work with the insurer to address concerns about works being carried is not of itself evidence of any failure by the insurer, the panel accepts the extent to which the complainant was required to act to correct the error made in relation to power supply/infrastructure to the premises caused delay. Further the panel accepts this would have interfered with the complainant‟s expectation of enjoyment or peace of mind. The panel is satisfied it fair the insurer pays the complainant $2,500 non-financial loss compensation. Determination | Case number: 732975 Page 20 of 28 No specific policy cover for loss of rent The complainant claims site delays caused interruption to the new incoming tenant which necessitated the need to offer four months‟ rent -free period from 1 April to 1 August 2018. He claims $24,815.82. He says he was told the building would be completed and ready for use on or before 1 April 2018. He says the building certificate for the roof was not received from the council until 18 May 2018, there was no electricity on site until late June 2018 and as the fire safety statement was not completed until 6 July 2018, the tenant could not move in. The available information shows the work commenced on 22 January 2018. It was estimated the work would take 10 weeks. The available information also shows due to the extent of damage, variations due to concealed damage were likely to occur, there were numerous site meetings about the work and variations eventually totalled $46,231.43. There is no specific cover for loss of rent under the policy. Further, cover for consequential loss of any kind is specifically excluded under the policy terms. AFCA can award indirect financial loss compensation in certain circumstances Under the AFCA Rules, we can award up to $5,000 compensation for indirect financial loss. This may include the loss of use of a damaged item, the cost of renting a replacement item, loss of income, or a loss of business opportunities. The complainant‟s policy excludes cover for consequential loss. As this is the case, the panel cannot award this type of compensation for loss caused by the fire. However, the panel can consider if the complainant has suffered any additional loss because of the insurer‟s claims management. When reviewing whether compensation should be paid for this reason, the panel will consider whether loss was caused (wholly/partly) by the insurer, or by the complainant or by factors outside the insurer‟s control. Insurer’s conduct caused some of the loss of rent claimed As set out above the panel found the insurer did not unreasonably delay the claim although delay would have been incurred because of action required to correct the error made in relation to power supply/infrastructure to the premises. In the circumstances the panel considers it is fair the insurer pays to the complainant $5,000 financial loss compensation. 2.4 Was the insurer required to offer renewal of the policy? Insurer notified complainant it would not renew policy When renewable insurance is due to expire, the insurer must provide a notice under the Insurance Contracts Act 1984 (Act). The notice must:  be provided at least 14 days before the policy expires  say when the policy will expire  say whether the insurer is willing to renew the policy. There is no dispute the insurer notified the complainant the policy would not be renewed. The complainant says he was notified of the insurer‟s decision on 11 May 2018 through his broker. Determination | Case number: 732975 Page 21 of 28 The certificate of insurance provided shows the policy term was due to end on 30 May 2018. On the available information, the complainant was notified of the insurer‟s decision at least 19 days prior to the policy expiry. This exceeds the 14-day notification requirement under the Act. Insurer entitled to decide whether to offer insurance The complainant says:  the insurer has not given a valid reason for its decision not to offer insurance renewal as he had a clear claims history for the subject building in the 20 years preceding the subject claim  suggests the decision not to renew appears to have been due to investigation of the subject claim (which was found to be attributable to tenant not himself)  The decision disadvantaged him as: > his broker withdrew service, > he had to disclose the insurer‟s decline of insurance when seeking cover elsewhere, and > meant he had to go through a rigorous and time-consuming process including engaging a lawyer to prepare a letter required for new insurance. AFCA‟s jurisdiction to consider disputes about an insurer‟s decision to offer/renew insurance is limited. We cannot consider a complaint about the insurer‟s decision not to offer insurance unless there is evidence the decision was made indiscriminately, maliciously, or based on incorrect information. The complainant has not provided evidence which shows the insurer relied on any specific incorrect information or made the decision not to offer cover indiscriminately or maliciously. In the circumstances, based on the available information, the panel makes no finding adverse to the insurer on this issue. Determination | Case number: 732975 Page 22 of 28 3 Supporting information 3.1 Process This matter was determined by a panel Due to the nature of this dispute, it has been referred to a panel for determination. The panel comprises the ombudsman, a member with significant experience in consumer and small business advocacy and a member with extensive experience as an insurer. The panel has decided this complaint based on what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance, good industry practice and previous relevant determinations of AFCA or predecessor schemes (which are not binding). AF CA’s approach to this complaint A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All the provided information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. It is an accepted principle of general insurance law that the insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 732975 Page 23 of 28 3.2 Relevant policy terms Both the policy document and the Notice have been exchanged with the complainant. What’s covered This Asset Protection insuranc e covers property against physical loss or damage occurring during the policy period. Coverage is provided at insured loc ations and in transit up to the relevant limits. POST LOSS EXPENSES When covered loss or damage occurs cover includes, in addition to the location limit, expenses incurred by the Insured for: ……. claims preparation expenses under Asset Protection. Cover is provided up to the Asset Protection post loss expenses limit. What’s not covered (the insurer) will not be liable for loss or damage arising out of or in connection with: ….. consequential loss of any kind except as may be provided under Business Income Protection. HOW CLAIMS ARE SETTLED (the insurer) will make payments to the Insured or to others with the authority of the Insured to settle covered claims. … CLAIM SETTLEMENTS Claims for property (other than contents more specifically valued) will be settled at the cost to reinstate the lost or damaged property, without deduction for depreciation, if reinstated within a reasonable period of time following a covered loss. - (The insurer‟s) payment to reinstate property will not exceed the amount actually spent by the Insured to reinstate the property with property of like kind and quality. - … - If original materials, machinery or equipment are no longer available, the settlement will be based on the cost of suitable alternatives. - The damaged property will be reinstated to a condition equal to, but not better than when new. Claims for lost or damaged property that are not reinstated will be settled at their indemnity value. ….. Determination | Case number: 732975 Page 24 of 28 DEFINITIONS claims preparation expenses that the Insured reasonably and necessarily incurred for preparation and certifying of covered claims including: > professional fees for architects, engineers, surveyors and > accountants; and > executive overtime that the Insured necessarily incurs with (the insurer‟s) consent for mitigating claims under Asset Protection and Business Income Protection which are not otherwise recoverable under this policy. Indemnity value Cost to repair or replace less an amount for age, wear and tear and depreciation and less an adjustment for general condition and remaining useful life at the time of loss. 3.3 Extracts from material relied on by the parties Date Action Report (DW) after inspection 10 September 2018  DW i nspected and photographed roof 10 September 2018 because complainant advised on 7 September 2018 the main roof leaked during a storm.  Attached were also phot ographs of DW‟s work on completion of roof .  Minor paint damage was noted to the centre ceiling expansion joint, the tenant said water has come out of the dry - cleaning system exhaust, power cable next to the exhaust, the centre ceiling expansion joint and the mains power supply of the building.  Only visible damage was to paint work in at the expans ion joint.  Landlord has engaged a roofer to look over the roof prior to my inspection, the tenant had engaged a roofer to complete his content fit out after the building claim was complet e.  Damage related to the installation of the tenant‟s content fit o ut was found and should show up on the landlord‟s roof report, the roof clips have been pulled apart and the sheets have been damaged during the fit out of the content.  DW hold no liability in replacing or fixing any damage related to the content fit out and or any further damage related to wat er leaks as the damage to the roof has occurred after the completion of the roof by another trade not related to DW but the tenant.  At the time of our inspection, damage was visible to the following: Minor paint dam age - Located to the centre expansion joint.  Property is safe and does not require any emergency measures to make safe.  Caus e of the damage is due to a large hailstorm on the 7/9/2018 hail has built up and allowed water to back - flow over flashing entering the roof void and damaging paint work.  Work required: Roof sheet damage related to the tenant‟s content fit out. Complainant’s builders report (DS)  DS inspec ted after tenant‟s flue venting.  Roof has very recently been replac ed with Lysaught Determination | Case number: 732975 Page 25 of 28 Email 30 May 2018 speed deck roofing. The above roof has been laid in 2 separate piec es with a flashing suppos edly sealing the join. This join flashing is only 100 mm under the top roof sheet and because it's not big enough and flat will cause capillary action and leak .  Top roof needs to be raised and a larger apron installed to combat this poor flashing detail .  Barge cappings are literally on both sides of the building have simply been tucked into the cavity and this channels the wat er directly into the void and create long term moisture problems between both buildings which will then turn into rising damp in the brick walls .  Barges have been laid incorrectly over the join; they should have been following eac h roof plane separately .  Southern side parapet should have been completely covered in Colourbond flashing and capping to prevent water ingress in this area .  Nort hern side needs to be installed wit h a pressure seal to sto p water ingress into the cavity.  Western gutter end and under apron flashing in middle of roof screws have been driven thru the pans this compromises the sheet and voiding any warranty . Complainant’s consulting engineer’s report (TY) 19 November 2018  Inspected and inspected property on 4 and 19 October 2018 to assess the cause of the roof leak.  Reviewed fire damage scope of works .  After heavy rain, water is discharging in ceilings next to the WC‟s and above the electrical distribution board .  Recent repairs complet ed in a workmanlike manner except for localised areas which we identified a s the primary causes of the roof leaks .  Caus e of roof leaks adjacent to WC‟s is:  4.3.1 KLIP - LOK 700 Hi - Strengt h roof sheeting is overlapped with a step down approximately at centre span of the roof where rainwater is wicking back into the roof void at the roof sheet overlaps and at the interface between the roof vent back flashing and roof sheeting.  4.3.2 Displac ement evident in roof sheeting at the mid span overlap combined with lack of visible foam infills to eliminate voids in the roof sheet overlaps al lows rainwater to wick into the roof void during heavy rain periods when water volume is greater and cannot discharge with sufficient velocity due to the low roof pitch.  4.3.3 Concealed turn up pans at the lower roof sheet ends may not be adequately detail ed where the roof sheets overlap which may also allow rainwater to enter the roof void during heavy rain periods.  The primary causes of roof leaks above the electrical distribution board is due to:  4.4.1 Lack of provision of apron flashing at the abutment between new metal capping and the adjacent north side properties masonry wall allows rainwater to enter void between adjacent buildings and ent er the northeast Determination | Case number: 732975 Page 26 of 28 section of the subject building likely through a concealed penetration in the subject property‟ s north elevation wall.  4.5 Flashings around flue penetrations and vents in the new roof sheeting were found to be installed in a proper workmanlike manner and there was no evidence of water penetration into the interior of the occupancy from these roof p enetrations.  New roof sheeting has not been installed at the mid span overlap in a way which complies with Code, so advis e attempt to lift the upper roof sheets at the mid span to install two rows of suitable durable foam infill weat her strips.  Apron flash ing not installed at the abutment between new metal capping and the adjacent north side masonry wall in non - c ompliance with code and recommend installing suitable apron flashing . Complainant’s roof report (AL) 20 September 2018  Inspected roof 18 September 2018 in relation to water entry and noted 5 main issues contributing to water entry with poor design and installation as depicted in images.  1.Step in the middle of the roof has insufficient lap between roof sheet causing rainw ater to penetrate roof during severe storms and high winds. Lap is only 120mm with current installed roof pitch at 4 - 5degree which clearly is insufficient as depicted in image 1. Therefore, it requires to be increased to at least 400mm on this shallow pitc h of roof to accommodate heavy rain and wind.  2. Whirlybird roof vents have been installed in the wrong place and to close to shallow lap of stepped roof sheets. During heavy rain falls, rainwater is backing up the roof on the tray of the vent and penet ra ting the shallow lap roof on the step. As depicted in the image 2 to state this is where the leak came from. Roof vents need to be at the top of the roof away from the step to allow all hot air to exhaust from roof space and to stop any leaks at junction s tep of roof.  3. Flashings to both sides are not sealed and not correctly flashed to neighbour‟s brick wall therefore allowing rainwater to penetrate the void between the two buildings as depicted in image 3. This can cause water ingress through cracks in t he mortar on the brickwork and damp issues in the future.  4. Gutter at the back of the shop is small to cope with large volume of water. The design of the gutter has a high front fac e forcing which forces water back under roof sheets of roof into cavity i n large rooms. So, gutters should allow water to flow over front during heavy rain falls stopping any chance of wat er entry to building.  5. No installation of mesh under insulation as it a Determination | Case number: 732975 Page 27 of 28 compulsory component when installing metal roofing in commercial b uildings per AS4389 roof safety standard for commercial building.  Roof will need to be removed and installed correctly with metal mesh over timber rafters, correct lap at step junction of roof to stop water entry, moving whirlybird closer to top of roof a way from step junction. Flashing of walls and end capping is required and then installing 200mm half round gutter at bottom of roof to allow overflow of water during heavy rain fall. Plumbing report (JS) 31 March 2018  Says he has carried out installation s and maintenance at this dry cleaner for many years and identifies 5 services which need to be reinstated.  $560 charged for inspection and report. Plumbing invoice (WN) 23 June 2019  To supply and fix new Colourbond awning roof and flashings. Paint wall above. $3, 080. 00 GST .  One new rainwat er head to rear gutter. $385.00 GST .  Paint front tiles on both sides of shop. $440.00 GST .  Repair storm water pipe at front ground level. $330.00 GST .  Remove concret e and re concrete rear entry to shop. Replace lid to pit by making new prefab concrete. $880.00 GST .  Paint awning sealing metal angles on both ends and install new Colourbond flashings. $660. 00 GST .  Extra work. Paint internal walls of roller door entry to rear pick up area. $275.00 GST  Total $6,050 . Plumbi ng Invoice (BKS) 9 August 2018  Plumbing copper pipe section required to be specially made to fit broken terracotta pipe in ground. Fitted to main water drain at south rear wall below laundry tub area $770 including GST . Shopfront Invoice (MG) 10 October 2018  Supply and install to Australian Standards and replace existing aluminium framed shopfront as per original configuration .  Revised subt otal $7,700 + GST for Clear anodised frames. Terms of Payment: Deposit $3,850.00+GST Paid on invoice 50779. Revised balance: $3850+GST ($4,235) . 3.4 Other relevant material considered and relied on  Parties‟ submissions/emails and all attachments to all submissions/emails .  Parties‟ expert reports and attachments.  Assessment reports (15) and all attachments to reports.  Photographs, invoices, quotations, and scopes of work. Determination | Case number: 732975 Page 28 of 28  Correspondence between the parties.