Home / Suncorp Group / Determination 732377

Determination 732377

Claim declined for water damage to two strata units

FirmSuncorp Group
Decided2021-08-16
ProductGeneral Insurance · Strata
OutcomeFor the complainant
Amount awarded$103,592
Non-financial loss$4,000
Amount claimed$320,213
SourceAFCA PDF

Summary

The owner of two strata units claimed for water damage after a February 2020 rain event and sought $320,212.60. AFCA found the ground floor damage was caused by an extraordinary rain event rather than an excluded seepage, and ordered quantified payments of about $103,592, ongoing loss of rent and temporary accommodation, $4,000 non-financial loss and interest.

The insurer bore the onus of proving the seepage exclusion, and the dominant cause of the ground floor damage was the extraordinary rainfall that the existing drainage could not cope with rather than an excluded cause.

Issues

Subjects and remedies

home or building damagemental healthnatural disasterpay claimpay interestpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 732377 Financial firm AAI Limited Determination | Case number: 732377 Page 2 of 30 Case number: 732377 11 August 2021 1 Determination overview 1.1 Complaint The complainant holds strata insurance with the financial firm (insurer) for two apartments, (units 1 and 2) at the insured address. The complainant lived in number 2 (the ground unit) while renting out number 1 (the upstairs unit) for short term stays. The complainant also holds a landlord contents policy for unit 1. The complainant lodged a claim on 28 February 2020 saying recent storms had caused water inundation to the ground floor unit. The insurer appointed a make-safe team (F) who attended on 17 March 2020. Mould remediation works were required, and the complainant was moved into temporary accommodation. The insurer also appointed a building consultant (D) to assess and report on the cause of damage. D reported the cause of damage from rain water seeping through the external block walls, eventually entering the downstairs unit during rainfall on 8 and 9 February. Repairs were authorised and commenced when white ant damage was identified which meant the builder could not warrant the repairs. The insurer offered the complainant a cash settlement which she rejected. The complainant engaged an engineer (T), who reported the water ingress had only occurred after the commencement of demolition and excavation works directly across the road. T says these works meant the drainage system had been removed, resulting in collected water running off to nearby properties, either by direct overland flow or by seeping through soft soils or faults in the rock. The insurer appointed an engineer (S) who disagreed with T ‟ s opinion. S reported the cause of damage was water inundation due to inadequate drainage at the property for the high volume of water flow. While the claim has been on foot the insurer has paid the complainant $124,929.04. After consideration of the expert reports, the insurer says it is entitled to decline the claim for damage to both units 1 and 2. In recognition of delays the insurer is prepared to consider the separate damage to each unit as a single claim and has offered to settle the claims and the complaint for $64,141.75. The complainant disagrees with this decision and seeks $320,212.60. 1.2 Issues and key findings Is the insurer entitled to decline the claim? No because the available material establishes the proximate cause of the damage to the ground floor unit was not seepage but the extraordinary amount of rain in the four days in February 2020; there was seepage but ordinarily, seepage into soil from rain would be drained away by the drainage system; the drainage system was not defective but was not large enough to drain away water from the extraordinary rain event. Determination | Case number: 732377 Page 3 of 30 The panel does not accept that the damage to the upstairs unit was because of an insured event. However, the insurer has offered to cover the damage to the upstairs unit given the extensive delays in processing the claim. The panel considers this fair in all the circumstances. What is a fair settlement of the claim? A fair settlement of the claim is set out in section 2.2 of this determination. Is the complainant entitled to compensation? As there has been an unusual degree or extent of physical inconvenience and time taken to resolve the complaint which has interfered with the complainant‟s expectation of enjoyment or peace of mind she is entitled to compensation. Why is the outcome fair? The outcome is fair because the available information establishes the insurer is not entitled to decline the claim for damage to the ground floor unit. While the available information establishes the insurer is entitled to decline the claim for the upstairs unit it has offered to compensate the complainant for the damage to the upstairs unit which is fair in view of the delays in its claims management. 1.3 Determination This determination is mostly in favour of the complainant. Should the complainant accept this determination then within seven days of notification of acceptance the insurer is to make the following payments to the complainant:  $46,366.56 for the resultant damage to units 1 and 2  $875 plus interest for make safe electrical repairs  loss of rent of $1,500 per week from 1 November 2020 until the date of acceptance of the determination  a further $18,000 loss of rent for the time to find a builder a nd undertake repairs  temporary accommodation at $2,600 per week from 15 May 2021 until the date of acceptance of the determination  a further $31,200 for temporary accommodation for the time to find a builder and undertake repairs  $7,150 for mould remediati on or the complainant is to allow access to the units so the insurer can assess structural concerns and mould remediation can be carried out within the terms of the policy  $4,000 compensation for non-financial loss. If the complainant has incurred any further costs for expert reports, she is to submit the further invoices to the insurer for payment and the insurer should immediately reimburse the complainant and pay interest. The panel also recommends the complainant accepts the insurer ‟s suggestion and lodge another claim for the damage to the roof of unit 1. Otherwise, the insurer is not liable to make any further payments in relation to the claim or the matters the subject of this complaint. Determination | Case number: 732377 Page 4 of 30 2 Reasons for determination 2.1 Is the insurer entitled to decline the claim? Accidental loss or damage covered The complainant must establish on the balance of probabilities she has suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. The complainant‟s policy provides cover for accidental loss or damage to the building and common contents at the insured address in the period of insurance provided the loss or damage is not excluded and subject to the conditions of the policy. The policy describes accidental loss or damage: it is loss or damage that was not intentional and includes loss or damage from the incidents shown on pages 14 to 21 of the policy. One such incident is loss or damage caused by storm. Extracts from the policy are set out in supporting section 3 of this determination. The complainant says the cause of the damage to unit 2 (the downstairs unit) is water ingress caused by excavation and demolition works to the property across the road. Given the broad scope of cover provided under the policy, the panel is satisfied the complainant has established a valid claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. In this instance the insurer relies on the exclusion of seepage of water, saying seepage is the proximate cause of damage. It says the cash settlement offered is made on a goodwill basis and because of its delays even though the cause of damage is a stated exclusion. Submissions and expert reports from builders and engineers considered Both parties rely on expert reports from builders and engineers. Reports and photographs provided by the complainant‟s expert (engineer T), the insurer‟s experts (building consultant D and engineering consultant (S), have been reviewed and considered by the panel. A summary of the key points of these reports can be found in section 3 of this determination. The complainant‟s engineer (T) says the commencemen t of building works across the road was the cause of the excessive amount of water that entered the property through sandstone rockfaces behind the lower ground floor stud and masonry walls. T‟s first report says he visited the worksite on 10 June 2020 an d found no visible signs of an installed drainage system and / or pump out pits, which he said were „typical at this early stage of construction‟. His first report says: “ We are of the opinion that the demolition of the property across the road has resulted in the temporary removal of the drainage system at this property, leaving any collected water to run-off to the nearby properties either by direct overland flow, seeping through soft soils or seeping through faults in the rock. Due to the slope of the land, it is expected any water seepage will flow towards the (insured) Determination | Case number: 732377 Page 5 of 30 property and its immediate neighbours. The existing drainage system would not be able to cope with the additional run-off and would therefore result in water ingress into the property through the soil and faults in the rock. The owner informed the engineer that her adjacent neighbour had also experienced the water seepage after the demolition of the structure (across the road) further reinforcing this point ‟. The i nsurer‟s engineer S refutes these findings. S says the work carried out across the road did not damage the property or the drainage system but that the water inundation was caused by inadequate drainage system and lack of waterproofing. He describes the fissures as weathered and the concrete path built to redirect the flow of water saying the water flow has been occurring for a long time. S says:  there is a major gap between the two boulders behind the eastern room‟s stud wall on the ground floor and it was evident that the water was flowing behind the wall for a long period of time, based on the existence of a drainage system and small channel here and the presence of salts  t here is a drainage outlet behind the eastern bedroom‟s wall (90mm in diameter), which also indicates the flow of water predates the rock hammering activity (across the road) and is a long-term issue and not caused by the excavation works in the opposite property  the drainage system is inadequate to appropriately drain the large flow of water  cracks in the rock were extremely weathered  even though it was dry when he inspected water was seeping under the wall into the living room  T‟s report does not adequately explain how the excavation work had caused the temporary removal of the drainage system  T‟s report did not include the inspection or assessment of the existing drainage system adjacent to the wall next to the ground floor‟s bedroom, which would indicate the water flow between the cracks and fissures had existed for a period of time  In relation to T‟s opini on the stormwater runoff from the property across the road entered the insured property, S says the steeply sloping road in front of the insured property would have been designed and constructed as per RMS standards with appropriate drainage (e.g. kerb and channels on both side of the road, pits and underground drains) and this would likely capture all surface stormwater and prevent it from entering the insured property  hairline wall cracks in the first floor and staining are caused by previous roof leaks and not caused by the excavation works across the road. Both engineers provided further reports in which they reiterated their opinions. T refers to the extremely high rainfall in the four days 7-10 February 2020 and says the drainage system at the insured property was working but could not cope with the flow of water from its property and the property across the road. He also notes that now the property across the road has a functional drainage system water has not come into the insured property in recent rainfall events In a supplementary report S referred to Nearmap images taking before and after the heavy rain events on 7-10 February 2020. Based on the Nearmap images he says the houses across the road had not been demolished until after the heavy rainfall events. S says it is highly unlikely the minor clearance works seen in the images would have included removal of the drainage system prior to the rain events. S notes: „ It is our experience that storm water systems are removed after the demolition of the house normally during the earthworks for the new house and therefore at the Determination | Case number: 732377 Page 6 of 30 time of the February 2020 rain event there would not have been any additional rainwater discharging directly onto the ground (across the road) due to demolition works. As for a second property under construction across the road, S says: „ Demolition works had started at the front of the adjacent property at No.50 prior to the February rain event, however, this property is downhill from No.52 and any additional rainwater discharging onto the ground would not have flowed towards the subject property.‟ S reiterates his view that the four-day rain event would have resulted in a substantial amount of water flow in the rock fissures that overwhelmed the 90mm diameter outlet pipe, allowing water to inundate the lowe r level of the insured‟s property. He says this kind of pipe and the existing drainage was only adequate for low flows of water. S notes the complainant and T rely on the fact there has been no further water ingress since the February 2020 event and since the property across the road has a functional drainage system. However, S says the February 2020 rain event was the highest recorded rainfall level since the complainant purchased the property and it is highly likely the property was inundated during a similar event prior to that time but the inadequate drainage could not cope with the significant flow of water in February 2020. Damage to insured property not caused by works across the road The panel finds the dated aerial images of the worksite across the road to be persuasive, which show demolition works had not yet commenced until after the rain event in February 2020. The panel notes the assertions of the complainant that the works across the road must have been responsible for the damage because there has been no inundation of the insured property since February 2020 and since the property across the road has a functional drainage system. However, the panel notes the rainfall event in February 2020 was unusually sign ificant and rainfall events thereafter have not been so significant to lead to the mechanism which caused damage in February 2020. Having considered the available information including photographs and Nearmap images, the panel is satisfied the proximate (or the dominant or effective) cause of the water damage to unit 2 is the extraordinary rain event which lead to water seeping through the soil and rock fissures up alongside the property and an inadequate drainage system on the ground level, which resulted in an overflow of water into the property. The panel does not accept the works across the road caused the damage. Drainage could not cope with significant rain event In its second Notice of Response the insurer says the proximate cause of the water ingress was the inadequate drainage which allowed water to seep through fissures in the rock. In these regards, the panel notes the following exclusion clause. Defect, structural fault or design fault a defect, structural fault or design fault that you knew about (or should reasonably have known about) and did not fix before the loss or damage occurred (e.g. if there are signs that a defect previously caused damage, we will not pay a later claim for further damage from this defect). Determination | Case number: 732377 Page 7 of 30 The panel notes both engineers determined that the existing drainage system was not sufficient to drain the excessive water away during the February rain event. Proximate cause of loss was the extraordinary rain event Having considered the available material, the panel is satisfied of the following: > there was an extremely heavy rain event for four days in February 2020 > the construction across the road was not responsible for the damage at the property > as a result of the extraordinary rain event there was water run-off which seeped through soils and faults in the rock > the existing drainage system did not cope with the extraordinary rain event. Having carefully considered the expert evidence, the panel is satisfied the proximate cause of the loss was the extraordinary amount of rain in those four days. The panel acknowledges there was seepage but considers that ordinarily, seepage into soil from rain would be drained away by the drainage system. The panel considers the property was damaged because the drainage system was not good enough to drain away water that seeped into the soil and rock from the extraordinary rain event. That is, the effective or dominant cause of the loss was the extraordinary rain event which the existing drainage system could not cope with. The panel does not accept the available information establishes the proximate cause of loss was seepage. The panel does not accept the available information establishes the drainage system was defective. It was simply inadequate to capture the rainwater on those four days. The available information suggests it was adequate to capture the normal flow of water. The flow of water on these four days was not normal. The insurer‟s engineer refers to the existence of weathered rock faces displaying signs of efflorescence and notes the drainage pipe outlet, which the panel considers are indications there was significant water overflow at an earlier time. The engineer refers to the probability of similar events which occurred prior to the complainant purchasing the property. The complainant did not obtain a pre-purchase report. She said she engaged an engineer who told her the property “was solid”. Even if the drain was defective the panel accepts the available evidence does not establish the complainant knew about it or should reasonably have known about it. Insurer has not established policy exclusions apply to claimed damage In the circumstances, the panel does not accept the insurer is entitled to rely on the policy exclusions of seepage or defects. The panel is satisfied the insurer is required to pay the complainant for the resultant damage to the ground floor unit (unit 2) which was caused by the extraordinary rain event in February 2020. Complainant has not established vibrations from works caused damage The complainant also says unit 1 (the upstairs unit) was damaged by the heavy construction/worksite vibrations claiming cracks in the walls and a leaking roof. The complainant provided a letter from the neighbour of the property across the road who objected to the development across the road in 2016. One of the grounds of objection was that the excavation could create significant ground vibrations which could damage neighbouring houses. The complainant also contends other houses in the street have been damaged by the building works across the road and their insurance has met their claims. Determination | Case number: 732377 Page 8 of 30 B ased on a meeting at the property the complainant‟s builder describes rectification works required caused by vibration and storm damage. In view of the expert material provided by the engineers, the panel does not find these contentions persuasive. The letter was written by someone who was next door to the new development. The complainant was across the road. No other material has been provided from the neighbours. The c omplainant‟s builder does not provide any detail or analysis as to how vibration cause the damage. On the available information, the panel does not accept vibrations from the building works across the road caused cracking damage to the insured property or damage to the roof or the upstairs unit. 2.2 What is a fair settlement of the claim? Offers and counteroffers considered While denying the claim for both units, the insurer made an offer to settle the claim for $64,141.75 on 22 October 2020. The insurer said it agreed to accept liability for resultant damage in recognition of the delays the complainant encountered. The insurer also said it was prepared to consider the separate damages under a single claim where ordinarily it would require a second claim to be lodged for damage to the upstairs unit. As it was unable to warrant any repairs at the property the insurer was prepared to offer the cash settlement in resolution of the claim and the AFCA complaint. The insurer provided a scope of works with an itemised breakdown of repairs and the assessor‟s report which confirms the scope of works. The insurer said the repairs would reasonably be expected to be completed within six weeks. The insurer agreed to provide cover for loss of rent and temporary accommodation through to 1 November 2020 in addition to the loss of rent and temporary accommodation offered as part of its settlement. The insurer said if the complainant did not wish to accept this offer then it would require additional proof of accommodation in the form of paid invoices for the accommodation she was residing in as previously discussed. The insurer‟s offer was made up as follows: Costs to remediate the mould at the property $5,500.00 Costs to repair the resultant damage to Units 1 & 2 $35,666.59 15% Contingency applied to overall amount $6,174.98 Loss of rent for 6 weeks calculated at $214.29 per day for 42 days. This figure is based on the previously accepted Loss of Rent payments (the insurer) has provided. $9,000.18 (paid) Determination | Case number: 732377 Page 9 of 30 Temporary Accommodation for 6 weeks calculated at $1,300.00 per week. This is based on the previously offered loss of rent payments. $7,800.00 (paid) As of 9 April 2021, the panel notes the insurer has paid the complainant $124,929.04 which it says is made up of: > Loss of rental income $52,501.05 > Temporary Accommodation: $71,427.99 > Non-financial loss compensation $1,000.00 The panel notes the insurer has paid for the loss of rent and temporary accommodation offered when it issued a cash settlement of $16,800.18 on 25 February 2021. The panel notes the insurer also paid the complainant for her expert reports in the sum of $1,479.50. Additionally, the insurer advised it paid the complainant $7,588.00 for temporary accommodation (at $271 per day) from 17 April 2021 until 15 May 2021. The complainant made a counter offer of $320,212.60 consisting of:  $224,000 for all repairs (including damage to the roof of unit 1)  $57,000 loss of rental income 1 October 2020 to 9 April 2021 ($300 per day)  $5,142.60 loss of rental income due to reduced rates  $19,200 temporary accommodation costs  $10,395 for roof make-safe  $875 for electrical make-safe  $3,600 non-financial compensation. Costs to repair the resultant damage to units 1 and 2 The policy says the insurer may choose how it settles building claims. It will decide if it will repair damage to the building or pay an insured what it would cost the insurer to repair the building. It is the panel‟s usual preference that an insurer repa ir damage to a building. However, in the circumstances of this claim and complaint the insurer accepts it is fair a cash settlement is made because the relationship between the parties appears to have broken down. Further, there are issues which need to be addressed first for which the insurer is not liable, namely, white ant damage and rectification of the drainage system. In all the circumstances, the panel accepts the insurer would be unable to warrant repairs. However, a cash settlement must fairly represent the amount required to repair the damage and consider contingencies and variations which may occur once repairs commence. The insured has attempted to address this issue by providing a 15% contingency. The panel acknowledges the quotation from the complainant‟s builder but is unable to accept it as it provides insufficient detail both as to the scope of work and how the damage was caused by the water inundation in February 2020. The panel has considered the material provided by the insurer and the photographs of the damage. The panel accepts the material provided from the insurer‟s builder (JL) describes an adequate scope of works for the work required to both units. For the reasons stated, the panel does not accept the insurer is liable for vibration damage to the unit upstairs. However, the panel accepts the insurer has acted fairly by offering to pay for damage to the upstairs unit in view of the delays in its claims management. Determination | Case number: 732377 Page 10 of 30 The panel acknowledges the 15% contingency but considers it is inadequate because the quotation is now nearly a year old, building costs have increased and the pandemic has affected the supply and cost of building materials. The panel considers a contingency of 30% is fair in the circumstances. The panel is satisfied it is fair the insurer pays to the complainant $35,666.59 for t he resultant damage to units 1 and 2 . In addition, the insurer is to pay a further $10,699.97 being 30% contingency to take into account variations and contingencies which may occur once repairs commence. If the complainant accepts this determination, then within seven days of notification of acceptance of this determination the insurer is to pay to the complainant $46,366.56 for repairs to the resultant damage to units 1 and 2. Insurer not liable to repair the roof under this claim or pay for roof make safe The complainant claims costs to repair the roof ($64,240) and $10,395 for the roof make-safe. She says the roof make safe by the insurer was inadequate. She has provided invoices and quotations in support of her claim. She says there was an earlier claim at which time the insurer should have noted any issues with the roof. The insurer says it is not liable to pay for damage to the roof because there was a previous roof leak at this location which was not caused by the excavation works in the nearby property. As set out earlier in this determination, the panel agrees the excavation works across the road did not cause damage to the property or the roof. The panel notes the complainant‟s various requests for make safe. The panel considered the reports from the insurer‟s make safe (F) and the insurer‟s builder (D) and accepts the reports say the property did not require any further measures to make safe. However, the reports both appear to be dealing with damage to the ground floor unit. The insurer‟s assessor provided a report on 25 June 2020. The assessor said a new claim would need to be lodged for damage caused in Unit 1 from drilling machinery and an engineer be appointed to provide a causation report. The report noted a make safe should be completed to make the building water tight once the claim has been lodged. In July 2020, the insurer says the tarp could not be placed on the roof because it was windy and dangerous. D agreed the roof was leaking because of skylight damage and broken tiles and in lieu of the tarp D said he would replace the tiles and silicone the damage which he said appeared to be caused by hail. The assessment report 17 July 2020 notes there was an on-site meeting on 16 July 2020. The assessor noted no make safe repairs had been completed because of the strong winds and slippery tiles. D was to be followed up regarding make safe to the roof. The claim file notes show a note from D to the insurer: MS was completed 17/07 using replacement tiles and silicon to problem areas. The panel accepts a make safe of the roof took place on 17 July 2020. The panel acknowledges this is significant time since the claim was made on 28 February 2020. The panel also notes the focus of the claim initially was on the ground floor and no claim was made for the upstairs unit. Further, the insurer as agreed to pay for damage to the upstairs unit even though the available information does not establish it is liable for this damage. Determination | Case number: 732377 Page 11 of 30 In all the circumstances, the panel does not accept the insurer is liable for the make safe costs of $10,395 incurred by the complainant. The complainant has provided no report about the damage to the roof. The insurer refers to a roof leak report dated 7 August 2020 in its engineer‟s report and builder‟s assessment report. A summary of the roof leak report is set out in supporting section 3.3 of this determination. The report indicates the roof leaks because of broken tiles, an overflowing gutter and tiles which were not installed properly. On the available information, the panel is unable to accept the insurer is liable to pay for the damage to the roof because of the rain event in February 2020. Panel recommends complainant lodge a claim for damage to the roof By letter dated 30 June 2021, the insurer said the complainant can lodge another claim for the damage to the roof to have this repaired under the strata policy. The panel recommends the complainant take this action and lodge a claim for damage to the roof. Insurer to pay the complainant $875 plus interest for electrical make safe Upon review of the claim, the assessor noted the engineer (T) recommended an electrician be appointed to inspect and repair any damaged electrical components. The assessor agreed and recommended this be actioned under make safe repairs. It is not clear from the available material if the insurer actioned this recommendation. The complainant provided a report in the sum of $875 for make safe electrical repairs. On the limited available material, the panel accepts the insurer is liable to reimburse the complainant $875. The insurer is also to pay interest pursuant to section 57 of the Insurance Contracts Act (the Act) on $875 from the date of payment of the invoice until the date of settlement. Insurer to pay for any further expert reports The complainant obtained expert reports from the engineer T. The complainant submitted invoices. On 15 July 2020, the insurer paid $1,479.50 to the complainant for expert reports. The complainant obtained a pest report and 3 reports from T. If the complainant has incurred any further costs for reports, she should submit the further invoices to the insurer for payment. Upon being satisfied of the amounts incurred by the complainant for expert reports, the insurer should immediately reimburse the complainant. If the complainant has paid for the reports, the insurer is also to pay interest pursuant to section 57 of the Act on the report costs from the date of payment until the date of settlement. Insurer not liable to pay for exploratory costs or new drainage The complainant requested payment for exploratory costs and for the cost to supply and install a new drain in the amount of $17,600. The policy provides for loss or damage caused by escape of liquid and exploratory costs to find leaks from pipes and water containers. The available information does not establish the damage to the property was caused by an escape of liquid or leak from the stormwater drain. Rather, the stormwater drain overflowed. Determination | Case number: 732377 Page 12 of 30 The available evidence does not establish the pipe was damaged either by the rain event or by building works across the road. The panel is satisfied the insurer is not liable to pay for this cost. Insurer to pay loss of rent claim at $1,500 a week The complainant claims $57,000 loss of rental income from 1 October 2020 to 9 April 2021 ($300 per day) and $5,142.60 loss of rental income due to reduced rate s. She says the loss of rent continues at $300 a day. On 22 October 2020 the insurer offered $9,000.18 (and paid) loss of rent for 6 weeks calculated at $214.29 per day for 42 days from the date of the offer. The insurer agreed to provide cover for loss of rent through to 1 November 2020 in addition to the loss of rent offered as part of its settlement. This was because it said six weeks was a reasonable approximation of the time it would take to complete repairs. By letter dated 9 April 2021 the insurer advised it had paid the complainant for loss of rent $52,501.05 which included the amount offered on 22 October 2020. The policy says: If we accept your claim for loss or damage to a tenanted unit in your building due to an insured incident and we agree the unit cannot be lived in, we will pay the unit owner the weekly rental amount for the reasonable amount of time we decide it should take to repair or rebuild your building or unit so it can be lived in again. The longest period we will provide cover for is 52 weeks and the most we will pay under this feature in relation to the same insured incident is 10% of the building sum insured. Based on the policy terms initially the complainant said the insurer should pay to her $130,000 (being approximately 10% of the building sum insured). The insurer accepted the claim for loss of rent but required information to substantiate the claim. By letter dated 4 September 2020, the insurer accepted it would pay loss of rent at $1,500 per week. The insurer said the payments would continue monthly until the claim is finalised. The complainant provided screenshots showing bookings she could not accept. She said she normally received around $1,960 per week and up to $3,000 in summer months but asked for reimbursement of $1,500 per week as the likely rent for long term tenants. The insurer said the problem is the unit was rented on the short-term basis. The panel agrees. The panel has considered the available information and considers it is fair to assess the loss of rent at $1,500 per week based on long-term rental rates particularly in view of the vagaries of short term rentals and the rental market in the pandemic. Having considered the available material, the panel accepts the complainant cannot live in the ground floor unit in its present condition. As a result, in recent times she has been living in the unit she usually rents out. The panel acknowledges the offer made by the insurer on 22 October 2020 was not unreasonable, but the panel also considers the insurer had not adequately addressed the issues in the claim by continuing to deny liability under the policy for the damage to the ground floor unit. Taking all matters into account the panel considers it is fair the insurer pays the complainant loss of rent in the amount of $1,500 per week from 1 November 2020 until the date of Determination | Case number: 732377 Page 13 of 30 acceptance of this determination. In the circumstances, the panel considers it is fair that interest is not paid on this amount. The insurer made an allowance of six weeks for the complainant to undertake repairs. The panel considers a further six weeks should be allowed to enable the complainant to source a builder and materials to undertake repairs to both units. Should the complainant accept this determination then within seven days of notification of acceptance the insurer is to pay to the complainant loss of rent of $1,500 per week from 1 November 2020 until the date of acceptance of the determination and a further $18,000 loss of rent for the time to find a builder and undertake repairs. The panel acknowledges the amount payable may exceed the policy limit. However, the panel considers this outcome fair in view of the time taken to resolve the claim. Future temporary accommodation to be paid at $2,600 per week The complainant claims $19,200 temporary accommodation costs. On 22 October 2020, the insurer offered to pay $7,800.00 being further temporary accommodation for 6 weeks at $1,300 per week. This amount was paid on 25 February 2021. By letter dated 9 April 2021 the insurer advised it had paid $71,427.99 for temporary accommodation. Additi onally, the insurer advised it paid the complainant $7,588.00 for temporary accommodation (at $271 per day) from 17 April 2021 until 15 May 2021. The policy says: When an insured incident damages a unit in your building to the extent that the unit owner cannot live there, and we agree, we will pay the unit owner‟s reasonable temporary accommodation costs for the time it will take to repair or rebuild the unit to a liveable condition. We will also pay for temporary accommodation for the unit owner‟s domestic pets in a commercial boarding establishment for the same period that we pay for the unit owner‟s temporary accommodation. The most we will pay for is:  up to 4 weeks in short term accommodation agreed to by us (e.g. standard rates for a hotel, motel or serviced apartment), then if necessary up to another: 48 weeks in residential accommodation of a similar standard to the unit that has been damaged in the incident. ….. The most we will pay for all claims under this feature in relation to the same insured incident is 10% of the building sum insured and the longest period that can be claimed for is 52 weeks. The insurer does not cover temporary accommodation costs if the unit owner does not need to pay for temporary accommodation; There is considerable material about this issue. Primarily, the parties could not agree on the standard of accommodation required near the complainant‟s unit and to take account of the compl ainant‟s situation. The issue was further complicated when the complainant was not living in Sydney. Determination | Case number: 732377 Page 14 of 30 The insurer indicated it was looking to pay out a reasonable figure that aligned with rental properties around her unit at around $1,300 per week. Having reviewed the available information, the panel considers the offer of $1,300 per week was reasonable when this offer was made. This is because the insurer is only liable to pay for accommodation of a similar standard to the damaged unit. The available information shows the complainant has been living in the unit upstairs since early November 2020. The parties continued to negotiate about alternative accommodation as the complainant said it was unsafe to live there but the parties could not agree as the complainant says there was no habitable short-term accommodation for $1,300 in her area. The complainant says the temporary accommodation costs of $9,600 per month ceased on 4 September. She said she had to pay her own accommodation for two months before returning to Sydney, so she could complete treatment. She claims $19,200. Having reviewed the property, the panel does not consider it was accommodation of a similar standard to the complainant‟s unit. By letter dated 18 April 2021 the complainant said she found a place closer to home which was clean, and she moved in. By letter dated 4 May 2021 she said she found a furnished apartment which she planned to lease over winter and sign a six-month lease. She provided details for a six-month lease from 5 May 2021 at $1,590 per week. By letter dated 1 June 2021 the insurer continued to engage with the complainant in relation to temporary accommodation as it appears the complainant had not gone ahead with the lease. The insurer wanted to arrange a conference call to assist in finding temporary accommodation or salvaging the lease. It said: If the lease is able to be continued (the insurer) can issue you the first month‟s rent as an advance moving forward are able to pay month to month for these costs once confirmation has been received that the previous month‟s rent has been paid to the real estate via either bank transfer or invoice. If the lease is unable to be continued, then I urge you to consider one of the below options (3 options were provided) The parties did not communicate further. The panel accepts the complainant was paid the temporary accommodation until 1 November 2020. Then until April 2021, the complainant did not require temporary accommodation because she was living in the upstairs unit. The insurer agrees it was unsafe for the complainant to live in the upstairs unit. The panel considered some of the options provided by the complainant are not of a similar standard to the complainant‟s unit as they are bigger or more lu xurious properties. Recently, the insurer sourced three properties. One was in Manly at $246 a night. It was a one-bedroom apartment. Another was a pet friendly two-bedroom apartment in Manly at $390 a night. The third was a new studio apartment in Fairlight at $480 per week. The insurer indicated it was prepared to assist the complainant with accommodation costs while the matter is before AFCA. The available information does not show where the complainant has been living since she moved out of the upstairs unit. Determination | Case number: 732377 Page 15 of 30 The insurer paid the complainant $7,588.00 for temporary accommodation (at $271 per day) from 17 April 2021 until 15 May 2021 . The panel has considered the three options recently provided by the insurer. The average nightly rate is $372 per night or $2,600 per week. Based on this, for future temporary accommodation, the panel considers it is fair the insurer pays the complainant $2,600 per week. Should the complainant accept this determination then within seven days of notification of acceptance the insurer is to pay to the complainant temporary accommodation at $2,600 per week from 15 May 2021 until the date of acceptance of the determination and a further $31,200 for temporary accommodation for the time to find a builder and undertake repairs. The panel acknowledges the amount payable may exceed the policy limit. However, the panel considers this outcome fair in view of the time taken to resolve the claim. Complainant can accept $7,150 for mould remediation or allow insurer access The insurer offered to pay the complainant $5,500.00 plus 15% for contingencies for mould remediation. The information shows the insurer has been trying to contact the complainant regarding the attendance of the restorer (S) regarding mould and assessment of the suspected rotting timber framework. On 27 April 2021 the insurer required access to the unit for a hygienist to assess the mould and an engineer, builder and assessor to assess structural concerns. The complainant was reluctant to agree in view of health concerns and earlier reports. The insurer said it required the reports to be updated. It referred to a policy term requiring the complainant‟s cooperation. The insurer has appointed one person to look after this claim as well as the associated building claim. The panel agrees with this approach. The insurer ‟s representative said she was waiting on S to do an inventory. The latest report from S in April 2021 shows water has entered through the roof and there is visible mould and mould remediation required. Although a cost summary is said to be $1,622.90 this does not include removal of mould from beams. S further states further damage may become apparent during demolition. The panel acknowledges the complainant has suffered a significant loss and has been affected adversely by this incident. The relationship between the complainant and the insurer has deteriorated to the point where she refuses contact and will not allow the insurer access to the units to assess mould damage. In these circumstances, the complainant may wish to accept the amount offered of $5,500.00 . As set out earlier the panel considers it is fair to allow 30% for contingencies, making a total of $7,150 payable by the insurer for mould remediation. Alternatively, the complainant can allow the insurer access to the units, so it can assess structural concerns and mould remediation can be carried out within the terms of the poli cy. Should be complainant accept this determination then within seven days of notification of acceptance the complainant is to indicate to the insurer whether she accepts $7,150 for mould remediation or whether she will allow access to the units, so the insurer can assess structural concerns and mould remediation can be carried o ut within the terms of the poli cy . The determination deals with the policy response under the strata title policy. The panel notes the complainant has lodged a claim against the contents policy. This determination does not deal with issues in relation to damage to contents. The parties are encouraged to work Determination | Case number: 732377 Page 16 of 30 together to settle the contents claim. If the parties are unable to agree on the contents claim, the complainant can lodge a complaint with AFCA for a decision on that issue. 2.3 Is the complainant entitled to compensation? Compensation paid in some circumstances The complainant claims mental health costs of $3,600 during this process. No invoices have been provided. The panel acknowledges the complainant has been receiving medical treatment as evide nced by her doctor‟s report which indicates she has been receiving treatment for anxiety and depression for several weeks in September 2020. AFCA will award compensation (capped at $5,000) if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant‟s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and anxiety. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. Insurer to pay the complainant $4,000 compensation The insurer acknowledged the complainant was impacted by delays because of the unusual nature of the event, the discovery of white ant damage and the inability to determine the reason for the water ingress. It says it provided appropriate temporary accommodation but in acknowledgement of the stress and inconvenience it offered and paid $1,000 compensation. The claim was made on 28 February 2020. The insurer offered $19,020.45 to settle the claim on 29 May 2020. As set out earlier, a further offer to settle the claim was made on 22 October 2020. While the panel acknowledges the efforts made by the insurer to bring this complex claim to conclusion, the panel considers there has been an unusual degree of physical inconvenience as the complainant has not lived in her home for a considerable period. Further, the panel considers although the matter was complex, the insurer took too long to resolve the complaint and failed to take sufficient account of the vulnerability of the complainant. The panel accepts the management of the claim significantly interfered with the complainant‟s expectation of enjoyment or peace of mind. In all the circumstances, taking into account the payment of $1,000 compensation, the panel considers an award of compensation of $4,000 is appropriate. 2.4 Why is the outcome fair? Insurer not entitled to decline the claim for damage to the ground floor unit The outcome is fair because the available information establishes the insurer is not entitled to decline the claim for damage to the ground floor unit. While the available information establishes the insurer is entitled to decline the claim for the upstairs unit it has offered to compensate the complainant for the damage to the upstairs unit which is fair in view of the delays in its claims management. Determination | Case number: 732377 Page 17 of 30 3 Supporting information 3.1 Process AFCA’s approach to this complaint This matter was determined by a panel Due to the nature of this dispute, it has been referred to a panel for determination. The panel comprises the ombudsman, a member with significant experience in consumer and small business advocacy and a member with extensive experience as an insurer. The panel has decided this complaint based on what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance, good industry practice and previous relevant determinations of AFCA or predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All the provided information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. It is an accepted principle of general insurance law that the insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Case law and proximate cause Case law establishes: · The proximate cause of the loss is the dominant or effective or operative cause of the loss whether or not that be the last in time or the sole cause. · If there are several causes operating contemporaneously, each must be examined for the qualities of reality, predominance and efficiency as the active, efficient cause that sets a relevant chain of events in action. If one cause would have caused the harm in any case, and the other would not have done so in the absence of the first, the first is the proximate cause. · A common-sense approach is taken to determine proximate cause. Determination | Case number: 732377 Page 18 of 30 3.2 Relevant policy terms Policy wording Some relevant policy extracts are referred to in the correspondence between the parties and in the insurer‟s Notices of Response. Other relevant policy extracts are set out in the determination. Both the policy document and the Notices have been exchanged with the complainant. What we do not cover as your building Your building does not include:  anything that is not legally part of your building for body corporate insurance purposes according to the relevant strata  these wall, floor or ceiling coverings when they are within a unit and the strata laws in your state or territory say they are not part of your building for body corporate insurance purposes: paint, tiles, wallpaper and permanent wall, floor and ceiling coverings; o fixed floor coverings including lino, whether glued down or not; o timber floor coverings that were fitted when the building was originally built, whether secured to the floor or not.  for any business activity unless we agreed to this business activity and this is shown on your certificate of insurance or if this business activity is only: o the residential tenancy of a unit which is part of your building; or o using no more than 1 unit in your building as an administration office. To process the claim, you must  allow us to inspect the damaged building and/or common contents;  allow us to arrange for experts to assess the damaged building and/or common contents and to quote on repair or replacement;  provide us with a quote for repair or replacement if we ask for this. If you choose to use our recommended repairers (when available), there is no need to obtain your own quotes;  when requested, provide us with all proofs of ownership and value, information, co-operation and assistance in relation to a claim (including giving evidence in court) as we may reasonably require;  allow us, or a person nominated by us, to recover, salvage or take possession of your building and/or common contents. When we ask, you must send any items to us, or cooperate in our collection or retrieval of such items;  consult an expert if we ask for this. What you must not do  do not dispose of any damaged parts or items of your building or common contents without our consent;  do not carry out or authorise repairs without our consent unless you cannot contact us and need to make emergency repairs to protect your building or common contents (see additional feature „Emergency repairs‟ on page 26);  do not wash or clean or remove debris from any area damaged by fire without our consent unless you need to do this to prevent further loss; Determination | Case number: 732377 Page 19 of 30  do not admit liability or responsibility to anyone else unless we agree;  do not negotiate, pay or settle a claim with anyone else unless we agree;  do not accept payment from someone who admits fault for loss or damage to your building or common contents. Refer them to us instead. If you do not comply If you do not comply with „What you must do‟ and „What you must not do‟ we can reduce or refuse your claim and/or recover costs from you or cancel your policy. If we decline a claim We will provide reasons for our decision to decline and if you decide to lodge a claim, we will send you written confirmation of our decision How to establish your loss Establish an incident took place When making a claim you must be able to prove that an incident covered by your policy actually took place. If you do not do this, we will not be able to pay your claim. We may obtain the following from the police:  confirmation that you reported the incident;  details of any investigations they undertook. You must give us authority to access these records, if we ask. Describe your loss or damage You must also give us accurate and full details of what was lost, stolen or damaged and give us proof of value and ownership for items claimed if we request it. When your building or common contents are damaged Allowing us, a repairer or an expert appointed by us, to look at what is damaged is usually all that is needed to prove your loss. Sometimes though we might ask you to produce a copy of the most recent plans and drawings for your building, photographs of your building and/or common contents or other evidence that supports the extent of the loss you have suffered. For valuable and badly damaged items, we may ask you to provide proof of ownership and value. If we decide that you are unable to reasonably substantiate your claim, we might reduce or refuse your claim. How to prove ownership and value Determination | Case number: 732377 Page 20 of 30 For lost, damaged or stolen items that are no longer available for inspection, you must validate your claim by giving us details of when and where they were purchased and reasonable proof of ownership and value. We will decide what is reasonable proof of ownership and value depending on what you are claiming for, how old they are and their value. A statutory declaration is not of itself considered acceptable evidence of proof of ownership and value. If you are unable to reasonably substantiate your claim, we can reduce or refuse your claim. General exclusions (Cont’d) You are not covered under any section of this policy for damage, loss, cost or legal liability that is caused by, arises from or involves: Seepage of water water seeping or running:  through the earth (hydrostatic water seepage);  down the sides of earth or earth fill that is up against your property;  down the sides or underneath swimming pools or spas causing them to move, change shape, lift or leak through their hydrostatic valves;  against or through retaining walls and forcing them to move or crack;  from agricultural pipes 3.3 Extracts from material relied on by the parties Record Key points Insurer’s expert (F ) Make - safe report 17 March 2020  inspected and photographed damage 17 March 2020  exact cause of damage unk nown  likely water has pooled up against an exterior wall and migrated through brickwork, or submerged up through concrete subfloor  describes damage to timber floor and carpet  high moisture recorded in adjoining walls  v isible microbial growth on skirting boards in lounge  mould remediation works required  work required in bedroom, lounge room, cupboard, kitchen, front room, bedroom 2 and take 3 to 5 days.  complainant requests temporary accommodation while works completed Determination | Case number: 732377 Page 21 of 30 Record Key points Complainant’s scope of works (DP ) Make - safe report 30 March 2020  supply and install new drain pipe and agg line and connect to stormwat er drain $17,600 Insurer’s expert (D ) Building assessment report 29 April 2020  inspected and photographed 29 April 2020.  complainant advises rainwater entered during large storm 8 February  based on visual inspection believes cause of damage is due to water seeping through the external block walls to the downstairs area then eventua lly flooding due to the rain on 8 and 9 February  notes property is on a very steep block – downstairs area approx. 2.5 metres below street / ground level  excess rainwater from the streets drainage into the property, then has built up against external walls – water able to seep through the external wall int o bedroom 1 dispersing into surrounding areas causing damage  complainant says this kind of event (overflow) has never occurred previously  says construction work across the road could have contributed to di verting rainwat er towards the property  says there is adequate drainage against foundation of the property for standard rainfall events  agrees damage to dow nstairs unit to bedroom 1 and 2, robe , sunroom, living room, bathroom: all floor coverings affected a nd skirting boards, wall linings robe shelving.  property safe.  claim is marked for acceptance.  repair cost $19,020.45 including GST. Complainant’s expert (I ) Pest inspection r eport 10 June 2020  inspected 4 June 2020 and at time of inspection no visible evidence of live termites or borer activity.  evidence of termite (white ant) damage such as mud tubes of damaged timbers found  some visible damage appears severe  no visible evidence of wood rot  high moisture levels found to some masonry internal w alls  recommends complainant makes enquiries with vendor about termites  complainant may need to arrange for a treatment or consult a builder Complainant’s expert ( T ) Engineer report 10 June 2020  inspected and photographed water ingress to lower ground fl oor; water entered the property through the sandstone rock faces behind the lower ground floor stud and masonry walls  property directly opposite a construction site under excavation  situated on a steep sloping site  complainant says water ingress has occurred only after demolition and excavation directly across the road  construction site had no installed drainage system or pump out pits  says sudden emergence and volume of water ingress is not due to failing drainage (system)  temporary removal of draina ge system across the road has led to collected wat ers running off to nearby properties by direct overland flow, seeping through soft soils or faults in the rock Determination | Case number: 732377 Page 22 of 30 Record Key points  existing drainage system at the property would not be able to cope and would result in water in gress  recommends re - instatement of drainage system at the property Insurer’s expert ( D ) Internal assessment re port 25 June 2020  assessor engaged to review I‟s report, D‟s assessment / quote, T‟s engineer report, and to advise claim outcome  termite damage would be considered as pre - existing, so not covered  notes further damage has occurred to unit 2, recommends a further assessment / SOW  cost to install new drainage ($17,600) would not be covered  refers to complainant seeking cover and payout on bot h units  a new claim should be lodged on a without prejudice basis to assess damage to unit 1 (cracking / vibration) due to building works across the road  recommends cash settlement due to maintenance / rot issues with timber framing  recommends onsite meeting to di scuss quotes and provide advice on lodging second claim  recommends claim be referred to recovery team as the builders working on the site across the road may have been negligent in not installing drainage system Insurer’s expert ( D ) Internal assessment re port 17 July 2020  refers to onsite meeting 16 July 2020 and convers ation with complainant  notes cracking to wall, ceiling linings in unit 1 (upstairs) as well as water stains – says an engineer will be appointed to investigate cause  notes repairs not completed in unit 2, evidence of further water ingress  insured visiting sister in Brisbane last mont h  no business activity run out of either unit  $750 excess paid.  complainant says she moved to unit 1 3/2020 as tenants had moved out  recovery team awaits f urther assessment reports to determine options  will review T‟s report again and provide comments on liability from construction site  D to omit internal painting from quote as not covered under strata policy. D amended quot e $15,135. 57.  cost to install drainage pipes not covered under the policy  no make safe as strong winds Builder’s assessment report 7 August 2020  reviewed stormwat er run - off in the bottom unit and settlement cracking to upstairs bedrooms and living area believed to b e caused by jackhammering from the adjacent street construction site  recommend additional downpipes be added to gutters at the back and front and that roof tiles be re - fixed to prevent future leaks  roof report found multiple roof leaks  settlement cracking in upper unit  recommends engineer is appointed Roof leak report (C plumbing)  summary from S‟s report and above assessment report  a bove the leak in the lounge room is where it transitions from Determination | Case number: 732377 Page 23 of 30 Record Key points 7 August 2020 terrac otta to the metal roof. On the bottom row of the terracotta tiles there are broken tiles which is causing water to ingress into the property.  leak in the bedroom is caused by the second s tory gutters filling up and overflowing back into the roof cavity  terrac otta tiles above the leak in the kitchen are not installed properly as they are not straight and overlapping each other causing water to get in underneath. The gutters are also full of water and causing water to back up into the kitchen. Scope of works (JL) 24 September 2020  work required to staircase, master bedroom, lounge dining, kitchen basement bedroom, basement lounge, kitchen, entry including builder‟s mark - up and GST $35,666. 59 Insurer’s expert ( S ) Engineer report and photographs 1 October 2020  refers to T‟s report from 10 June 2020  t here is a major gap bet ween the two boulders behind the eastern room‟s stud wall in ground floor and it was evident that the water was flowing behind the wall for a long period of time, based on the existence of a drainage system and the presence of salts  t here is a drainage outlet behind the eastern bedroom‟s wall (90mm in diameter), which also indicates the flow of water predates the rock hamme ring activity, is a long - term issue and therefore was not caused by the excavation works in the opposite property  t here is also a crack in the rock where the insured also stated the water was em anating from. C onsider s this crack to be a pre - existing crack, since the edges of the crack were extremely weat hered and rounded and that coinciding with the crack is a concrete path constructed to allow the flow of water from that crack towards the drainage outlet  water seeping through from under the nort hern wall of the living room when inspected even though it was dry weather  on the first - floor hairline cracks in the walls and around the ceiling some of which are near wat er leaks and there is water staining from previous water leaks in the roof closed where there was a gap between the cornice and the wall  existing drainage and a small channel for draining the water from behind the wall of the eastern bedroom, which indicates that the gap and cracking of the boulders pre - date the excavation works at the nearby prop erty.  existing drainage system is inadequate to drain the flow of water and lack of waterproofing and an in adequate drainage system behind the wall has caused the water inundation of the room and that this has been a long - term issue  i nspection was carrie d out during dry weat her condition however it was observed that the water was seeping through from under the wall in the living room area  constant water ingress into the living room after the rain was caused by the lack of adequate drainage system and inad equate waterproofing. The pore wat er pressure from the soil would gradually seep through from the living room‟s northern wall.  if there was adequat e waterproofing and drainage system behind the sandstone wall it would have prevented the water ingress into the living room.  likely that the water could have infiltrated the soil in garden bed at the front of the building and redirected by the lower impermeable materials (rock /clay soil) and ultimately seeped through from Determination | Case number: 732377 Page 24 of 30 Record Key points under the wall in the living room due to lack of wat erproofing and adequate drainage system. Although we were not able to confirm if there is any drainage behind the sandstone wall in the living room, it is our opinion that the wat er flow has been occurring due to a lack of an adequate draina ge system and waterproofing adjacent to the wall which would have prevented water seepage alongside the wall. Additionally, the steeply sloping road in front of the property would minimise stormwater from entering from the opposite properties across the ro ad. Therefore, it is considered that the run - off stormwater emanating from the nearby property would not have flowed to the subject property.  i n relation to the possibility of surface stormwater entering the property from the roadway, the steeply sloping r oad in front of the property would have been designed and constructed as per RMS standards with appropriate drainage (e. g. kerb and channels on both side of the road, pits and underground drains ). This is expected to capture all surface stormwater and prev ent it from entering the property  floor screed to the ground floor has “bubbled” due to the long - term water and water vapour emanating from the crack and crevic es behind the walls of the living room and the eastern room, which made the screeding brittle a nd caused them to break under the live load and self - weight of the timber flooring above it.  hairline wall cracks in the first - floor area are caus ed by the gradual shrinkage and expansion of the wall materials due to the previous roof leak at this location and have not been caused by the excavation works in the nearby property  based on visual inspection from the only accessible internal area (bedroom at the ground floor), did not observe any damage which would be attributed to being caused by termites, howe ver cannot confirm the absence of termite damage. An inspection by a pest (termite) expert is required to confirm the presenc e of termites and any termite damage and may involve an invasive inspection (i.e. removal of plasterboard) Based on our inspection the structural integrity and stability of the structure appears unaffected  T‟s report does not adequat ely explain how the excavation work had caus ed the temporary removal of the drainage system. Also, the report did not include the inspection or assessment of the existing drainage system adjacent to the wall next to the ground floor‟s bedroom, which would indicate the water flow bet ween the cracks and fissures had existed. That is, the drainage system was previously constructed under the cracks to allow for the flow of water emanating from the rock adjacent to the wall  work carried out in the opposite property did not damage the drainage system around the ins ured property and the wat er inundation has been caused by the inadequate drainage system and the lack of water proofing around the property. T he fissures adjacent to the room were weat hered and the existence of concrete path adjacent to the wall (bedroom‟s wall in ground floor) indicated the concret e path was built previously to redirect the flow of water from the existing cracks and fissures in the boulders adjacent to the wall which again reject the idea that these cracks and fissures caused by the excavation works  not been a sudden emergence of water flow since there has been an existing drainage system next to the boulders and there were signs of efflorescence on the boulders whic h indicated the water flow has been occurring over a long period of time  as for run - off wat er from the opposite site, it is obvious from the Determination | Case number: 732377 Page 25 of 30 Record Key points terrain that storm water run - off wo uld not have been able to flow towards this property, regardless of water volume. The storm water run - off from the opposite site would flow away from the building and along the slope of the road and would not enter this propert y Insurer’s expert ( D ) Internal assessment re port 7 October 2020  refers to engineer‟s report (S) and liability quote from JL for repairs to ground floor ($35,666.59) and first floor and says damage on the ground floor unit was cause from water seepage  unclear what damage attributed to long - term seepage and from the February rain event insurer should repair damage noted in JL quote.  notes insurer made a business decision to include storm damage to the first - floor unit under this claim. Says cracking to the walls in the first - floor unit is due to shrinkage and expansion from ongoing roof issues and not from an insured event  water ingress has not been caused by excavation works  recommends decline for hairline cracking in first floor unit as damage not fro m an ins ured event. Water staining on walls from leaking roof is cosmetic and painting not covered under strata policy  mould contamination in ground floor from unresolved seepage  recommend remediation cost of mould in both units be included in final cash s ettlement. Complainant’s expert (T ) Reply to S‟s report 28 October 2020  typically, a property uses down - pipes to collect stormwater from the r oof and discharges this directly to council‟s stormwater network. During demolition, these down - pipes (and assoc iated in - ground pipes ) are removed  this means that during this stage of the project, there is no direct discharge of the stormwater collected into council‟s piped system. The water is trapped on site and can flow onto other properties if not properly mana ged.  claim coincides with the highest rainfall volume recorded to date at closest weather station. With no drains in place , water was able to pool and pass to the properties via overland and subterranean flow  BOM records show high rainfall on 7 (60mm) 8 (64mm) 9 (92mm) and 10 February (240mm)  drainage system at the insure d property was working, but could no t cope with the flow of water from two properties  cause of water ingress was attributable to the opposite site and temporary removal of its drainage sy stem  w hen the property is collecting and discharging run - off collected from the site ‟ s impervious area, water seeps through the channel in the boulders and discharges via the floor waste. During the high rain - fall event, this channel was not able to collec t and discharge the water of both properties fast enough, resulting in the water building - up and flowing out into the lower floor  slope in the direction of the site oppos ite towards …. is much greater than the slope down the road, which is gentle by compar is on. O ver a comparable distance, the land falls 6 mete rs towards the insured property …. where the road falls 3 meters. As the opposite site had no stormwater connection at the time of the event, it is fair to say that water is likely to have flow ed from the opposite si te and ont o the insured‟s …. (as well as its neighbouring downstream properties), through a combination of Determination | Case number: 732377 Page 26 of 30 Record Key points land overflow and subterranean flow  notes the insured has report ed the opposite site now has a functional drainage system and she has not observed any water ingress to the lower floor of the property because of recent rainfall. Complainant’s expert (T ) Report 24 December 2020  after a recent week - long rain event, (BOM records show a week of rain 16 December (23mm) to 22 December (25 mm)) and observed through a walk - through video call there is no damage or no water ingress to insured property which supports conclusion that the removal of the drainage system across the road (which now has a functional drainage system installed) caused a dditional run - off into the system exceeding its design capacity and resulting in water ingress to the insured property. Insurer’s expert ( S ) Supplementary engineer report and Near map images 18 January 2021  i n response to T‟s report dat ed 28 October 2020 agrees 240mm rain on 10 Feb 2020 i s the highest daily rainfall rec orded to date and the total rain of 456mm over a four - day period is the highest cumulative rain during the time the complainant has lived at th e property  T concluded that the issues relating to wat er ingress in to the subject property were attributable to the demolition works carried out at the opposite site at No.52 and lack of drainage during high rainfall events  understand s that the comment abo ve from T was bas ed on the property at No.52 being demolis hed which would result in the roof water from the original building discharging directly onto the ground and not into the stormwater drainage system around the house.  property at No.52 was unchanged up until the aerial image dated 22 October 2019 i.e. the aerial image dated 22 October 2019 does not show any changes to No.52 when compared to earlier aerial images  aerial image dated 21 January 2020 shows some site clearance works in the front garden o f No. 52 but the building was still evident  aerial image dated 21 January 2020 also shows demolition works had started in the adjacent property at No. 50, downhill from No.52. These works included the demolition of the front part of the building, however, most of the building was still evident  aerial image dated 28 February 2020 shows site clearance works to the front garden of No.52 i.e. the removal of trees and plants. The building at No.52 was still evident. There was no change to the demolition works a t the adjacent property at No.50  aerial image dated 15 April 2020 shows that the building at No.52 had been demolished and earthworks were underway for the new building. There was no change to the demolition works at No. 50  b ased on the Near map images th e property at No.52 was still evident after the heavy rainfall event from the 7 - 10 February 2020. Some minor site clearance works in the front garden of No.52 had commenced prior to the February 2020 rain event, however, it is highly unlikely that these wo rks would have included the removal of the stormwat er system around the hous e. The demolition of the house and earthworks for the new house started between the 28 February 2020 and 15 April 2 020 i.e. aft er the February 202 0 rain event. It is our experience that storm water systems are removed after the demolition of the hous e normally during the earthworks for the new house and therefore at the time of the February 2020 rain event there would not have been any additional rainwater Determination | Case number: 732377 Page 27 of 30 Record Key points discharging directly onto the ground at No.52 due to demolition works .  it would be possible for surface water from all the above higher - level properties further up the road would cross over to the lower level ground on the southern side of the road, however, this would be a cumula tive volume of rain water from several higher - level properties and not a single property a t No. 52 as described in T‟s report  February 2020 rain event over a 4 - day period would have res ulted in a substantial amount of water infiltration into the higher - leve l ground. This sub - surfac e water would then have flowed downhill on the rockhead and flowed into rock fissures. The concentration of sub surface water in the rock fissures over the 4 - day rain period would have resulted in a substantial amount of water flow in the rock fissures that overwhelmed the 90mm diameter outlet pipe that then allowed water to inundate the lower level of the subject property. The water flow through the rock fissures would have been the cumulative effect of rainfall on the large catchment area at a higher level than the subject property and not just one property at No.52  potential volume of sub - surface water from the rock fissures cannot be calculated due to unknown flow paths through the rock fissures. A 90mm pipe is a small diameter pipe and only adequate for low flows. There was no allowance in the drainage design for the lower level property for potential high sub - surface wat er flows through the rock f issures. For example, at the time of construction the lower floor level could have been raised by say 500mm above the channel level at the rock fissures to form a deep overflow channel bet ween the house and the exposed rock to divert high flow wat er from t he rock fissures around the house. This deep overflow channel could still have been overwhelmed during the February 2020 event, but it would have provided greater protection to the property compared to a single 90mm diameter pipe. It is for this reason exi sting drainage was deemed inadequate as there was no overflow allowance in the drainage for potential high flows from rock fissures.  T‟s report notes the owner has reported that the opposite site at No.52 now has a functional drainage system and that the y have not observed any water ingress to the lower floor of the property dur ing the recent rainfall. „As noted, the February 2020 rain event was the highest rain event since the owner has lived at the property. It is therefore our opinion that the absence of water ingress into the property is not due to the functional drainage system at No.52 but is due to there not being a similar rain event as the February 2020 rain event. It is highly likely that the property was previously inundated prior to 2017 during a similar event and we expect that it will unfortunately be inundated in the fut ure during a similar event if the piped drainage at the rock fissures remains in its present form ‟.  opinion from the first report remains unchanged.  f urther review of Near ma p aerial images has determined that the building at No.52 had not been demolished at the time of the heavy rain event on the 7 - 10 February 2020. Demolition works and earthworks for the new house at No.52 did not commence until after the 28 February 2020. S d isagree s with the conclusions in the T report that the issues relating to water ingress into the subject property at No.35 were attribut able to the demolition works carried out at the opposite site at No.52 and lack of drainage Determination | Case number: 732377 Page 28 of 30 Record Key points during high rainfall event s.  h eavy rain event in February 2020 precipit ated the water ingress in the lower floor of the subject property, however, the proximate cause of the wat er ingress was the inadequate drainage for the potential high sub - surface water flow through the rock fissures  n ot possible to calculate the potential volume of sub - surface wat er through the rock fissures but a 90mm outlet pipe is deemed inadequate without a deep overflow channel to direct sub - surface water around the building. Insurer’s expert ( D ) Intern al assessment re port 1 February 2021  reviewed both engineering reports and based on the evidence provided agrees with S's conclusion, that the issues relating to water ingress into the insured's property at No.35 were not attributable to the demolition works carried out at the opposite site (No. 52) and lack of drainage during high rainfall events. The Near map recor ds substantiate this.  refers to the letter of offer advising that under normal circumstances insurer would not accept the result ant damage to the ground floor under the Strata Policy, as the cause of damage falls within a general exclusion under the polic y. The letter further states that considering the circumstances the insurer has agreed to accept liability for the resultant damage in recognition of the delays encountered.  t he assessor believes neither of the most recent engineering reports, changes the insurer‟s position or its offer. Complainant’s neighbour ( D ) Letter 30 Nov 2016  D next door to new development. Cites the developer‟s geotechnical report which says the excavation has the potential to create significant ground vibrations which could damage neighbouring houses. Complainant’s roof ( PR ) Quote 13 Nov 2020  Quote to storm seal roof $8,888 Complainant’s roof ( PR ) Quote 25 Nov 2020  Quote to storm seal roof $8,316 Complainant’s roof ( PR ) Quote 29 Jan 2021  Quote to strip existing roof and supply and install tiles, batons, sarking, ridge capping, valley iron and all flashings $64,240 inc GST. Complainant’s roof ( PR ) Quote 12 April 2021  Quote re roof $58,400 Complainant’s roof ( RR ) Invoice 15 Nov 2020  Invoice to re - bed and point ridge caps $1,507 Complainant’s builder ( BH )  Quotation based on recent meeting at property regarding rectification works caused by vibration and storm damage. Total Determination | Case number: 732377 Page 29 of 30 Record Key points Quote Valid to 31 December 2020 price including builder‟s margin and GST $224,000. 1. Preliminaries including HOW insurance 2. Supply of scaffolding and items associated with OH&S 3. Remove and replace roof tiles 4. Adjustment of window lintels and brickwork to allow windows & doors to operate again 5. Replace broken glass in windows caused by vibration and movement 6. Remove & replac e all floor coverings affected by water ingre ss (same as existing) 7. Remove all damage and cracked render and plasterboard 8. Paint and mak e good all surfaces 9. Remove all building debris 10. Check all brickwork and foundations that may have moved (NB This is a PC item and will need Structural Engineer‟s inspection) 11. Replace water damaged ceilings Insurer’s report and photographs (S) 1 June 2020  inspected and photographed 31 May 2020. Water has entered the property due to the limestone walls and caused flooding and damage downstairs. Describes and photographs damage. No drying equipment required. Antimicrobial applied to ex posed subfloors. Insurer’s report and photographs (S) 12 April 2021  scope of works and cost summary (which does not include removal of mould from beams) $1, 622. 90  water entered the building through the roof. House not liveable in its current state. Visible mould and mould remediation required. Further damage may become apparent during demolition. 3.4 Other relevant material considered and relied on  Parties‟ submissions /emails and all attachments to all submissions/emails.  Parties‟ expert reports.  Photographs and videos.  Invoices, quotations and scopes of work.  Correspondence between the parties. Determination | Case number: 732377 Page 30 of 30

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.