Text of the determination
Determination
Case number 732377
Financial firm AAI Limited
Determination | Case number: 732377 Page 2 of 30
Case number: 732377 11 August 2021
1 Determination overview
1.1 Complaint
The complainant holds strata insurance with the financial firm (insurer) for two apartments,
(units 1 and 2) at the insured address. The complainant lived in number 2 (the ground unit)
while renting out number 1 (the upstairs unit) for short term stays. The complainant also holds
a landlord contents policy for unit 1.
The complainant lodged a claim on 28 February 2020 saying recent storms had caused water
inundation to the ground floor unit.
The insurer appointed a make-safe team (F) who attended on 17 March 2020. Mould
remediation works were required, and the complainant was moved into temporary
accommodation. The insurer also appointed a building consultant (D) to assess and report on
the cause of damage.
D reported the cause of damage from rain water seeping through the external block walls,
eventually entering the downstairs unit during rainfall on 8 and 9 February.
Repairs were authorised and commenced when white ant damage was identified which
meant the builder could not warrant the repairs. The insurer offered the complainant a cash
settlement which she rejected.
The complainant engaged an engineer (T), who reported the water ingress had only occurred
after the commencement of demolition and excavation works directly across the road.
T says these works meant the drainage system had been removed, resulting in collected
water running off to nearby properties, either by direct overland flow or by seeping through
soft soils or faults in the rock.
The insurer appointed an engineer (S) who disagreed with T ‟ s opinion. S reported the cause
of damage was water inundation due to inadequate drainage at the property for the high
volume of water flow.
While the claim has been on foot the insurer has paid the complainant $124,929.04.
After consideration of the expert reports, the insurer says it is entitled to decline the claim for
damage to both units 1 and 2. In recognition of delays the insurer is prepared to consider the
separate damage to each unit as a single claim and has offered to settle the claims and the
complaint for $64,141.75.
The complainant disagrees with this decision and seeks $320,212.60.
1.2 Issues and key findings
Is the insurer entitled to decline the claim?
No because the available material establishes the proximate cause of the damage to the
ground floor unit was not seepage but the extraordinary amount of rain in the four days in
February 2020; there was seepage but ordinarily, seepage into soil from rain would be
drained away by the drainage system; the drainage system was not defective but was not
large enough to drain away water from the extraordinary rain event.
Determination | Case number: 732377 Page 3 of 30
The panel does not accept that the damage to the upstairs unit was because of an insured
event. However, the insurer has offered to cover the damage to the upstairs unit given the
extensive delays in processing the claim. The panel considers this fair in all the
circumstances.
What is a fair settlement of the claim?
A fair settlement of the claim is set out in section 2.2 of this determination.
Is the complainant entitled to compensation?
As there has been an unusual degree or extent of physical inconvenience and time taken to
resolve the complaint which has interfered with the complainant‟s expectation of enjoyment or
peace of mind she is entitled to compensation.
Why is the outcome fair?
The outcome is fair because the available information establishes the insurer is not entitled to
decline the claim for damage to the ground floor unit. While the available information
establishes the insurer is entitled to decline the claim for the upstairs unit it has offered to
compensate the complainant for the damage to the upstairs unit which is fair in view of the
delays in its claims management.
1.3 Determination
This determination is mostly in favour of the complainant.
Should the complainant accept this determination then within seven days of notification of
acceptance the insurer is to make the following payments to the complainant:
$46,366.56 for the resultant damage to units 1 and 2
$875 plus interest for make safe electrical repairs
loss of rent of $1,500 per week from 1 November 2020 until the date of acceptance of the
determination
a further $18,000 loss of rent for the time to find a builder a nd undertake repairs
temporary accommodation at $2,600 per week from 15 May 2021 until the date of
acceptance of the determination
a further $31,200 for temporary accommodation for the time to find a builder and
undertake repairs
$7,150 for mould remediati on or the complainant is to allow access to the units so the
insurer can assess structural concerns and mould remediation can be carried out within
the terms of the policy
$4,000 compensation for non-financial loss.
If the complainant has incurred any further costs for expert reports, she is to submit the
further invoices to the insurer for payment and the insurer should immediately reimburse the
complainant and pay interest.
The panel also recommends the complainant accepts the insurer ‟s suggestion and lodge
another claim for the damage to the roof of unit 1.
Otherwise, the insurer is not liable to make any further payments in relation to the claim or the
matters the subject of this complaint.
Determination | Case number: 732377 Page 4 of 30
2 Reasons for determination
2.1 Is the insurer entitled to decline the claim?
Accidental loss or damage covered
The complainant must establish on the balance of probabilities she has suffered a loss
caused by an event to which the policy responds. This is known as a prima facie or valid
claim.
The complainant‟s policy provides cover for accidental loss or damage to the building and
common contents at the insured address in the period of insurance provided the loss or
damage is not excluded and subject to the conditions of the policy.
The policy describes accidental loss or damage: it is loss or damage that was not intentional
and includes loss or damage from the incidents shown on pages 14 to 21 of the policy. One
such incident is loss or damage caused by storm.
Extracts from the policy are set out in supporting section 3 of this determination.
The complainant says the cause of the damage to unit 2 (the downstairs unit) is water ingress
caused by excavation and demolition works to the property across the road.
Given the broad scope of cover provided under the policy, the panel is satisfied the
complainant has established a valid claim.
Once so established, the onus shifts to the insurer to prove on the balance of probabilities
that an exclusion applies if it seeks to deny or limit its liability for the loss.
In this instance the insurer relies on the exclusion of seepage of water, saying seepage is the
proximate cause of damage. It says the cash settlement offered is made on a goodwill basis
and because of its delays even though the cause of damage is a stated exclusion.
Submissions and expert reports from builders and engineers considered
Both parties rely on expert reports from builders and engineers.
Reports and photographs provided by the complainant‟s expert (engineer T), the insurer‟s
experts (building consultant D and engineering consultant (S), have been reviewed and
considered by the panel.
A summary of the key points of these reports can be found in section 3 of this determination.
The complainant‟s engineer (T) says the commencemen t of building works across the road
was the cause of the excessive amount of water that entered the property through sandstone
rockfaces behind the lower ground floor stud and masonry walls.
T‟s first report says he visited the worksite on 10 June 2020 an d found no visible signs of an
installed drainage system and / or pump out pits, which he said were „typical at this early
stage of construction‟.
His first report says:
“ We are of the opinion that the demolition of the property across the road has
resulted in the temporary removal of the drainage system at this property, leaving
any collected water to run-off to the nearby properties either by direct overland
flow, seeping through soft soils or seeping through faults in the rock. Due to the
slope of the land, it is expected any water seepage will flow towards the (insured)
Determination | Case number: 732377 Page 5 of 30
property and its immediate neighbours. The existing drainage system would not
be able to cope with the additional run-off and would therefore result in water
ingress into the property through the soil and faults in the rock. The owner
informed the engineer that her adjacent neighbour had also experienced the
water seepage after the demolition of the structure (across the road) further
reinforcing this point ‟.
The i nsurer‟s engineer S refutes these findings. S says the work carried out across the road
did not damage the property or the drainage system but that the water inundation was caused
by inadequate drainage system and lack of waterproofing. He describes the fissures as
weathered and the concrete path built to redirect the flow of water saying the water flow has
been occurring for a long time. S says:
there is a major gap between the two boulders behind the eastern room‟s stud wall on the
ground floor and it was evident that the water was flowing behind the wall for a long period
of time, based on the existence of a drainage system and small channel here and the
presence of salts
t here is a drainage outlet behind the eastern bedroom‟s wall (90mm in diameter), which
also indicates the flow of water predates the rock hammering activity (across the road) and
is a long-term issue and not caused by the excavation works in the opposite property
the drainage system is inadequate to appropriately drain the large flow of water
cracks in the rock were extremely weathered
even though it was dry when he inspected water was seeping under the wall into the living
room
T‟s report does not adequately explain how the excavation work had caused the temporary
removal of the drainage system
T‟s report did not include the inspection or assessment of the existing drainage system
adjacent to the wall next to the ground floor‟s bedroom, which would indicate the water
flow between the cracks and fissures had existed for a period of time
In relation to T‟s opini on the stormwater runoff from the property across the road entered
the insured property, S says the steeply sloping road in front of the insured property would
have been designed and constructed as per RMS standards with appropriate drainage
(e.g. kerb and channels on both side of the road, pits and underground drains) and this
would likely capture all surface stormwater and prevent it from entering the insured
property
hairline wall cracks in the first floor and staining are caused by previous roof leaks and not
caused by the excavation works across the road.
Both engineers provided further reports in which they reiterated their opinions.
T refers to the extremely high rainfall in the four days 7-10 February 2020 and says the
drainage system at the insured property was working but could not cope with the flow of water
from its property and the property across the road. He also notes that now the property
across the road has a functional drainage system water has not come into the insured
property in recent rainfall events
In a supplementary report S referred to Nearmap images taking before and after the heavy
rain events on 7-10 February 2020. Based on the Nearmap images he says the houses
across the road had not been demolished until after the heavy rainfall events.
S says it is highly unlikely the minor clearance works seen in the images would have included
removal of the drainage system prior to the rain events. S notes:
„ It is our experience that storm water systems are removed after the demolition of
the house normally during the earthworks for the new house and therefore at the
Determination | Case number: 732377 Page 6 of 30
time of the February 2020 rain event there would not have been any additional
rainwater discharging directly onto the ground (across the road) due to demolition
works.
As for a second property under construction across the road, S says:
„ Demolition works had started at the front of the adjacent property at No.50 prior
to the February rain event, however, this property is downhill from No.52 and any
additional rainwater discharging onto the ground would not have flowed towards
the subject property.‟
S reiterates his view that the four-day rain event would have resulted in a substantial amount
of water flow in the rock fissures that overwhelmed the 90mm diameter outlet pipe, allowing
water to inundate the lowe r level of the insured‟s property. He says this kind of pipe and the
existing drainage was only adequate for low flows of water.
S notes the complainant and T rely on the fact there has been no further water ingress since
the February 2020 event and since the property across the road has a functional drainage
system. However, S says the February 2020 rain event was the highest recorded rainfall level
since the complainant purchased the property and it is highly likely the property was
inundated during a similar event prior to that time but the inadequate drainage could not cope
with the significant flow of water in February 2020.
Damage to insured property not caused by works across the road
The panel finds the dated aerial images of the worksite across the road to be persuasive,
which show demolition works had not yet commenced until after the rain event in February
2020. The panel notes the assertions of the complainant that the works across the road must
have been responsible for the damage because there has been no inundation of the insured
property since February 2020 and since the property across the road has a functional
drainage system.
However, the panel notes the rainfall event in February 2020 was unusually sign ificant and
rainfall events thereafter have not been so significant to lead to the mechanism which caused
damage in February 2020.
Having considered the available information including photographs and Nearmap images, the
panel is satisfied the proximate (or the dominant or effective) cause of the water damage to
unit 2 is the extraordinary rain event which lead to water seeping through the soil and rock
fissures up alongside the property and an inadequate drainage system on the ground level,
which resulted in an overflow of water into the property.
The panel does not accept the works across the road caused the damage.
Drainage could not cope with significant rain event
In its second Notice of Response the insurer says the proximate cause of the water ingress
was the inadequate drainage which allowed water to seep through fissures in the rock. In
these regards, the panel notes the following exclusion clause.
Defect, structural fault or design fault
a defect, structural fault or design fault that you knew about (or should reasonably
have known about) and did not fix before the loss or damage occurred (e.g. if
there are signs that a defect previously caused damage, we will not pay a later
claim for further damage from this defect).
Determination | Case number: 732377 Page 7 of 30
The panel notes both engineers determined that the existing drainage system was not
sufficient to drain the excessive water away during the February rain event.
Proximate cause of loss was the extraordinary rain event
Having considered the available material, the panel is satisfied of the following:
> there was an extremely heavy rain event for four days in February 2020
> the construction across the road was not responsible for the damage at the property
> as a result of the extraordinary rain event there was water run-off which seeped through
soils and faults in the rock
> the existing drainage system did not cope with the extraordinary rain event.
Having carefully considered the expert evidence, the panel is satisfied the proximate cause of
the loss was the extraordinary amount of rain in those four days. The panel acknowledges
there was seepage but considers that ordinarily, seepage into soil from rain would be drained
away by the drainage system.
The panel considers the property was damaged because the drainage system was not good
enough to drain away water that seeped into the soil and rock from the extraordinary rain
event. That is, the effective or dominant cause of the loss was the extraordinary rain event
which the existing drainage system could not cope with. The panel does not accept the
available information establishes the proximate cause of loss was seepage.
The panel does not accept the available information establishes the drainage system was
defective. It was simply inadequate to capture the rainwater on those four days. The available
information suggests it was adequate to capture the normal flow of water. The flow of water
on these four days was not normal.
The insurer‟s engineer refers to the existence of weathered rock faces displaying signs of
efflorescence and notes the drainage pipe outlet, which the panel considers are indications
there was significant water overflow at an earlier time. The engineer refers to the probability
of similar events which occurred prior to the complainant purchasing the property.
The complainant did not obtain a pre-purchase report. She said she engaged an engineer
who told her the property “was solid”.
Even if the drain was defective the panel accepts the available evidence does not establish
the complainant knew about it or should reasonably have known about it.
Insurer has not established policy exclusions apply to claimed damage
In the circumstances, the panel does not accept the insurer is entitled to rely on the policy
exclusions of seepage or defects. The panel is satisfied the insurer is required to pay the
complainant for the resultant damage to the ground floor unit (unit 2) which was caused by
the extraordinary rain event in February 2020.
Complainant has not established vibrations from works caused damage
The complainant also says unit 1 (the upstairs unit) was damaged by the heavy
construction/worksite vibrations claiming cracks in the walls and a leaking roof.
The complainant provided a letter from the neighbour of the property across the road who
objected to the development across the road in 2016. One of the grounds of objection was
that the excavation could create significant ground vibrations which could damage
neighbouring houses.
The complainant also contends other houses in the street have been damaged by the
building works across the road and their insurance has met their claims.
Determination | Case number: 732377 Page 8 of 30
B ased on a meeting at the property the complainant‟s builder describes rectification works
required caused by vibration and storm damage.
In view of the expert material provided by the engineers, the panel does not find these
contentions persuasive. The letter was written by someone who was next door to the new
development. The complainant was across the road. No other material has been provided
from the neighbours. The c omplainant‟s builder does not provide any detail or analysis as to
how vibration cause the damage.
On the available information, the panel does not accept vibrations from the building works
across the road caused cracking damage to the insured property or damage to the roof or the
upstairs unit.
2.2 What is a fair settlement of the claim?
Offers and counteroffers considered
While denying the claim for both units, the insurer made an offer to settle the claim for
$64,141.75 on 22 October 2020. The insurer said it agreed to accept liability for resultant
damage in recognition of the delays the complainant encountered. The insurer also said it
was prepared to consider the separate damages under a single claim where ordinarily it
would require a second claim to be lodged for damage to the upstairs unit.
As it was unable to warrant any repairs at the property the insurer was prepared to offer the
cash settlement in resolution of the claim and the AFCA complaint.
The insurer provided a scope of works with an itemised breakdown of repairs and the
assessor‟s report which confirms the scope of works. The insurer said the repairs would
reasonably be expected to be completed within six weeks.
The insurer agreed to provide cover for loss of rent and temporary accommodation through to
1 November 2020 in addition to the loss of rent and temporary accommodation offered as
part of its settlement. The insurer said if the complainant did not wish to accept this offer then
it would require additional proof of accommodation in the form of paid invoices for the
accommodation she was residing in as previously discussed.
The insurer‟s offer was made up as follows:
Costs to remediate the mould at the property $5,500.00
Costs to repair the resultant damage to Units 1 & 2 $35,666.59
15% Contingency applied to overall amount $6,174.98
Loss of rent for 6 weeks calculated at $214.29 per day for 42
days. This figure is based on the previously accepted Loss of
Rent payments (the insurer) has provided.
$9,000.18 (paid)
Determination | Case number: 732377 Page 9 of 30
Temporary Accommodation for 6 weeks calculated at $1,300.00
per week. This is based on the previously offered loss of rent
payments.
$7,800.00 (paid)
As of 9 April 2021, the panel notes the insurer has paid the complainant $124,929.04 which it
says is made up of:
> Loss of rental income $52,501.05
> Temporary Accommodation: $71,427.99
> Non-financial loss compensation $1,000.00
The panel notes the insurer has paid for the loss of rent and temporary accommodation
offered when it issued a cash settlement of $16,800.18 on 25 February 2021.
The panel notes the insurer also paid the complainant for her expert reports in the sum of
$1,479.50.
Additionally, the insurer advised it paid the complainant $7,588.00 for temporary
accommodation (at $271 per day) from 17 April 2021 until 15 May 2021.
The complainant made a counter offer of $320,212.60 consisting of:
$224,000 for all repairs (including damage to the roof of unit 1)
$57,000 loss of rental income 1 October 2020 to 9 April 2021 ($300 per day)
$5,142.60 loss of rental income due to reduced rates
$19,200 temporary accommodation costs
$10,395 for roof make-safe
$875 for electrical make-safe
$3,600 non-financial compensation.
Costs to repair the resultant damage to units 1 and 2
The policy says the insurer may choose how it settles building claims. It will decide if it will
repair damage to the building or pay an insured what it would cost the insurer to repair the
building.
It is the panel‟s usual preference that an insurer repa ir damage to a building. However, in the
circumstances of this claim and complaint the insurer accepts it is fair a cash settlement is
made because the relationship between the parties appears to have broken down. Further,
there are issues which need to be addressed first for which the insurer is not liable, namely,
white ant damage and rectification of the drainage system. In all the circumstances, the panel
accepts the insurer would be unable to warrant repairs.
However, a cash settlement must fairly represent the amount required to repair the damage
and consider contingencies and variations which may occur once repairs commence. The
insured has attempted to address this issue by providing a 15% contingency.
The panel acknowledges the quotation from the complainant‟s builder but is unable to accept
it as it provides insufficient detail both as to the scope of work and how the damage was
caused by the water inundation in February 2020.
The panel has considered the material provided by the insurer and the photographs of the
damage. The panel accepts the material provided from the insurer‟s builder (JL) describes an
adequate scope of works for the work required to both units.
For the reasons stated, the panel does not accept the insurer is liable for vibration damage to
the unit upstairs. However, the panel accepts the insurer has acted fairly by offering to pay for
damage to the upstairs unit in view of the delays in its claims management.
Determination | Case number: 732377 Page 10 of 30
The panel acknowledges the 15% contingency but considers it is inadequate because the
quotation is now nearly a year old, building costs have increased and the pandemic has
affected the supply and cost of building materials. The panel considers a contingency of 30%
is fair in the circumstances.
The panel is satisfied it is fair the insurer pays to the complainant $35,666.59 for t he resultant
damage to units 1 and 2 . In addition, the insurer is to pay a further $10,699.97 being 30%
contingency to take into account variations and contingencies which may occur once repairs
commence.
If the complainant accepts this determination, then within seven days of notification of
acceptance of this determination the insurer is to pay to the complainant $46,366.56 for
repairs to the resultant damage to units 1 and 2.
Insurer not liable to repair the roof under this claim or pay for roof make safe
The complainant claims costs to repair the roof ($64,240) and $10,395 for the roof make-safe.
She says the roof make safe by the insurer was inadequate. She has provided invoices and
quotations in support of her claim.
She says there was an earlier claim at which time the insurer should have noted any issues
with the roof.
The insurer says it is not liable to pay for damage to the roof because there was a previous
roof leak at this location which was not caused by the excavation works in the nearby
property. As set out earlier in this determination, the panel agrees the excavation works
across the road did not cause damage to the property or the roof.
The panel notes the complainant‟s various requests for make safe. The panel considered the
reports from the insurer‟s make safe (F) and the insurer‟s builder (D) and accepts the reports
say the property did not require any further measures to make safe. However, the reports
both appear to be dealing with damage to the ground floor unit.
The insurer‟s assessor provided a report on 25 June 2020. The assessor said a new claim
would need to be lodged for damage caused in Unit 1 from drilling machinery and an
engineer be appointed to provide a causation report. The report noted a make safe should be
completed to make the building water tight once the claim has been lodged.
In July 2020, the insurer says the tarp could not be placed on the roof because it was windy
and dangerous. D agreed the roof was leaking because of skylight damage and broken tiles
and in lieu of the tarp D said he would replace the tiles and silicone the damage which he said
appeared to be caused by hail.
The assessment report 17 July 2020 notes there was an on-site meeting on 16 July 2020.
The assessor noted no make safe repairs had been completed because of the strong winds
and slippery tiles. D was to be followed up regarding make safe to the roof.
The claim file notes show a note from D to the insurer:
MS was completed 17/07 using replacement tiles and silicon to problem areas.
The panel accepts a make safe of the roof took place on 17 July 2020. The panel
acknowledges this is significant time since the claim was made on 28 February 2020. The
panel also notes the focus of the claim initially was on the ground floor and no claim was
made for the upstairs unit. Further, the insurer as agreed to pay for damage to the upstairs
unit even though the available information does not establish it is liable for this damage.
Determination | Case number: 732377 Page 11 of 30
In all the circumstances, the panel does not accept the insurer is liable for the make safe
costs of $10,395 incurred by the complainant.
The complainant has provided no report about the damage to the roof.
The insurer refers to a roof leak report dated 7 August 2020 in its engineer‟s report and
builder‟s assessment report. A summary of the roof leak report is set out in supporting
section 3.3 of this determination. The report indicates the roof leaks because of broken tiles,
an overflowing gutter and tiles which were not installed properly.
On the available information, the panel is unable to accept the insurer is liable to pay for the
damage to the roof because of the rain event in February 2020.
Panel recommends complainant lodge a claim for damage to the roof
By letter dated 30 June 2021, the insurer said the complainant can lodge another claim for
the damage to the roof to have this repaired under the strata policy.
The panel recommends the complainant take this action and lodge a claim for damage to the
roof.
Insurer to pay the complainant $875 plus interest for electrical make safe
Upon review of the claim, the assessor noted the engineer (T) recommended an electrician
be appointed to inspect and repair any damaged electrical components. The assessor agreed
and recommended this be actioned under make safe repairs. It is not clear from the available
material if the insurer actioned this recommendation.
The complainant provided a report in the sum of $875 for make safe electrical repairs.
On the limited available material, the panel accepts the insurer is liable to reimburse the
complainant $875.
The insurer is also to pay interest pursuant to section 57 of the Insurance Contracts Act (the
Act) on $875 from the date of payment of the invoice until the date of settlement.
Insurer to pay for any further expert reports
The complainant obtained expert reports from the engineer T. The complainant submitted
invoices. On 15 July 2020, the insurer paid $1,479.50 to the complainant for expert reports.
The complainant obtained a pest report and 3 reports from T. If the complainant has incurred
any further costs for reports, she should submit the further invoices to the insurer for
payment.
Upon being satisfied of the amounts incurred by the complainant for expert reports, the
insurer should immediately reimburse the complainant.
If the complainant has paid for the reports, the insurer is also to pay interest pursuant to
section 57 of the Act on the report costs from the date of payment until the date of settlement.
Insurer not liable to pay for exploratory costs or new drainage
The complainant requested payment for exploratory costs and for the cost to supply and
install a new drain in the amount of $17,600.
The policy provides for loss or damage caused by escape of liquid and exploratory costs to
find leaks from pipes and water containers.
The available information does not establish the damage to the property was caused by an
escape of liquid or leak from the stormwater drain. Rather, the stormwater drain overflowed.
Determination | Case number: 732377 Page 12 of 30
The available evidence does not establish the pipe was damaged either by the rain event or
by building works across the road.
The panel is satisfied the insurer is not liable to pay for this cost.
Insurer to pay loss of rent claim at $1,500 a week
The complainant claims $57,000 loss of rental income from 1 October 2020 to 9 April 2021
($300 per day) and $5,142.60 loss of rental income due to reduced rate s. She says the loss
of rent continues at $300 a day.
On 22 October 2020 the insurer offered $9,000.18 (and paid) loss of rent for 6 weeks
calculated at $214.29 per day for 42 days from the date of the offer.
The insurer agreed to provide cover for loss of rent through to 1 November 2020 in addition to
the loss of rent offered as part of its settlement. This was because it said six weeks was a
reasonable approximation of the time it would take to complete repairs.
By letter dated 9 April 2021 the insurer advised it had paid the complainant for loss of rent
$52,501.05 which included the amount offered on 22 October 2020.
The policy says:
If we accept your claim for loss or damage to a tenanted unit in your building due
to an insured incident and we agree the unit cannot be lived in, we will pay the
unit owner the weekly rental amount for the reasonable amount of time we decide
it should take to repair or rebuild your building or unit so it can be lived in again.
The longest period we will provide cover for is 52 weeks and the most we will pay
under this feature in relation to the same insured incident is 10% of the building
sum insured.
Based on the policy terms initially the complainant said the insurer should pay to her
$130,000 (being approximately 10% of the building sum insured).
The insurer accepted the claim for loss of rent but required information to substantiate the
claim. By letter dated 4 September 2020, the insurer accepted it would pay loss of rent at
$1,500 per week. The insurer said the payments would continue monthly until the claim is
finalised.
The complainant provided screenshots showing bookings she could not accept. She said she
normally received around $1,960 per week and up to $3,000 in summer months but asked for
reimbursement of $1,500 per week as the likely rent for long term tenants.
The insurer said the problem is the unit was rented on the short-term basis. The panel
agrees. The panel has considered the available information and considers it is fair to assess
the loss of rent at $1,500 per week based on long-term rental rates particularly in view of the
vagaries of short term rentals and the rental market in the pandemic.
Having considered the available material, the panel accepts the complainant cannot live in
the ground floor unit in its present condition. As a result, in recent times she has been living in
the unit she usually rents out. The panel acknowledges the offer made by the insurer on 22
October 2020 was not unreasonable, but the panel also considers the insurer had not
adequately addressed the issues in the claim by continuing to deny liability under the policy
for the damage to the ground floor unit.
Taking all matters into account the panel considers it is fair the insurer pays the complainant
loss of rent in the amount of $1,500 per week from 1 November 2020 until the date of
Determination | Case number: 732377 Page 13 of 30
acceptance of this determination. In the circumstances, the panel considers it is fair that
interest is not paid on this amount.
The insurer made an allowance of six weeks for the complainant to undertake repairs. The
panel considers a further six weeks should be allowed to enable the complainant to source a
builder and materials to undertake repairs to both units.
Should the complainant accept this determination then within seven days of notification of
acceptance the insurer is to pay to the complainant loss of rent of $1,500 per week from 1
November 2020 until the date of acceptance of the determination and a further $18,000 loss
of rent for the time to find a builder and undertake repairs.
The panel acknowledges the amount payable may exceed the policy limit. However, the
panel considers this outcome fair in view of the time taken to resolve the claim.
Future temporary accommodation to be paid at $2,600 per week
The complainant claims $19,200 temporary accommodation costs.
On 22 October 2020, the insurer offered to pay $7,800.00 being further temporary
accommodation for 6 weeks at $1,300 per week. This amount was paid on 25 February 2021.
By letter dated 9 April 2021 the insurer advised it had paid $71,427.99 for temporary
accommodation. Additi onally, the insurer advised it paid the complainant $7,588.00 for
temporary accommodation (at $271 per day) from 17 April 2021 until 15 May 2021.
The policy says:
When an insured incident damages a unit in your building to the extent that the
unit owner cannot live there, and we agree, we will pay the unit owner‟s
reasonable temporary accommodation costs for the time it will take to repair or
rebuild the unit to a liveable condition. We will also pay for temporary
accommodation for the unit owner‟s domestic pets in a commercial boarding
establishment for the same period that we pay for the unit owner‟s temporary
accommodation.
The most we will pay for is:
up to 4 weeks in short term accommodation agreed to by us (e.g. standard
rates for a hotel, motel or serviced apartment), then if necessary up to
another: 48 weeks in residential accommodation of a similar standard to
the unit that has been damaged in the incident.
…..
The most we will pay for all claims under this feature in relation to the same
insured incident is 10% of the building sum insured and the longest period that
can be claimed for is 52 weeks. The insurer does not cover temporary
accommodation costs if the unit owner does not need to pay for temporary
accommodation;
There is considerable material about this issue. Primarily, the parties could not agree on the
standard of accommodation required near the complainant‟s unit and to take account of the
compl ainant‟s situation. The issue was further complicated when the complainant was not
living in Sydney.
Determination | Case number: 732377 Page 14 of 30
The insurer indicated it was looking to pay out a reasonable figure that aligned with rental
properties around her unit at around $1,300 per week.
Having reviewed the available information, the panel considers the offer of $1,300 per week
was reasonable when this offer was made. This is because the insurer is only liable to pay for
accommodation of a similar standard to the damaged unit.
The available information shows the complainant has been living in the unit upstairs since
early November 2020. The parties continued to negotiate about alternative accommodation
as the complainant said it was unsafe to live there but the parties could not agree as the
complainant says there was no habitable short-term accommodation for $1,300 in her area.
The complainant says the temporary accommodation costs of $9,600 per month ceased on 4
September. She said she had to pay her own accommodation for two months before
returning to Sydney, so she could complete treatment. She claims $19,200. Having reviewed
the property, the panel does not consider it was accommodation of a similar standard to the
complainant‟s unit.
By letter dated 18 April 2021 the complainant said she found a place closer to home which
was clean, and she moved in.
By letter dated 4 May 2021 she said she found a furnished apartment which she planned to
lease over winter and sign a six-month lease. She provided details for a six-month lease from
5 May 2021 at $1,590 per week.
By letter dated 1 June 2021 the insurer continued to engage with the complainant in relation
to temporary accommodation as it appears the complainant had not gone ahead with the
lease. The insurer wanted to arrange a conference call to assist in finding temporary
accommodation or salvaging the lease. It said:
If the lease is able to be continued (the insurer) can issue you the first month‟s
rent as an advance moving forward are able to pay month to month for these
costs once confirmation has been received that the previous month‟s rent has
been paid to the real estate via either bank transfer or invoice.
If the lease is unable to be continued, then I urge you to consider one of the below
options (3 options were provided)
The parties did not communicate further.
The panel accepts the complainant was paid the temporary accommodation until 1 November
2020. Then until April 2021, the complainant did not require temporary accommodation
because she was living in the upstairs unit.
The insurer agrees it was unsafe for the complainant to live in the upstairs unit.
The panel considered some of the options provided by the complainant are not of a similar
standard to the complainant‟s unit as they are bigger or more lu xurious properties.
Recently, the insurer sourced three properties. One was in Manly at $246 a night. It was a
one-bedroom apartment. Another was a pet friendly two-bedroom apartment in Manly at $390
a night. The third was a new studio apartment in Fairlight at $480 per week.
The insurer indicated it was prepared to assist the complainant with accommodation costs
while the matter is before AFCA. The available information does not show where the
complainant has been living since she moved out of the upstairs unit.
Determination | Case number: 732377 Page 15 of 30
The insurer paid the complainant $7,588.00 for temporary accommodation (at $271 per day)
from 17 April 2021 until 15 May 2021 .
The panel has considered the three options recently provided by the insurer. The average
nightly rate is $372 per night or $2,600 per week.
Based on this, for future temporary accommodation, the panel considers it is fair the insurer
pays the complainant $2,600 per week.
Should the complainant accept this determination then within seven days of notification of
acceptance the insurer is to pay to the complainant temporary accommodation at $2,600 per
week from 15 May 2021 until the date of acceptance of the determination and a further
$31,200 for temporary accommodation for the time to find a builder and undertake repairs.
The panel acknowledges the amount payable may exceed the policy limit. However, the
panel considers this outcome fair in view of the time taken to resolve the claim.
Complainant can accept $7,150 for mould remediation or allow insurer access
The insurer offered to pay the complainant $5,500.00 plus 15% for contingencies for mould
remediation.
The information shows the insurer has been trying to contact the complainant regarding the
attendance of the restorer (S) regarding mould and assessment of the suspected rotting
timber framework.
On 27 April 2021 the insurer required access to the unit for a hygienist to assess the mould
and an engineer, builder and assessor to assess structural concerns. The complainant was
reluctant to agree in view of health concerns and earlier reports. The insurer said it required
the reports to be updated. It referred to a policy term requiring the complainant‟s cooperation.
The insurer has appointed one person to look after this claim as well as the associated
building claim. The panel agrees with this approach. The insurer ‟s representative said she
was waiting on S to do an inventory.
The latest report from S in April 2021 shows water has entered through the roof and there is
visible mould and mould remediation required. Although a cost summary is said to be
$1,622.90 this does not include removal of mould from beams. S further states further
damage may become apparent during demolition.
The panel acknowledges the complainant has suffered a significant loss and has been
affected adversely by this incident. The relationship between the complainant and the insurer
has deteriorated to the point where she refuses contact and will not allow the insurer access
to the units to assess mould damage.
In these circumstances, the complainant may wish to accept the amount offered of $5,500.00 .
As set out earlier the panel considers it is fair to allow 30% for contingencies, making a total
of $7,150 payable by the insurer for mould remediation.
Alternatively, the complainant can allow the insurer access to the units, so it can assess
structural concerns and mould remediation can be carried out within the terms of the poli cy.
Should be complainant accept this determination then within seven days of notification of
acceptance the complainant is to indicate to the insurer whether she accepts $7,150 for
mould remediation or whether she will allow access to the units, so the insurer can assess
structural concerns and mould remediation can be carried o ut within the terms of the poli cy .
The determination deals with the policy response under the strata title policy. The panel notes
the complainant has lodged a claim against the contents policy. This determination does not
deal with issues in relation to damage to contents. The parties are encouraged to work
Determination | Case number: 732377 Page 16 of 30
together to settle the contents claim. If the parties are unable to agree on the contents claim,
the complainant can lodge a complaint with AFCA for a decision on that issue.
2.3 Is the complainant entitled to compensation?
Compensation paid in some circumstances
The complainant claims mental health costs of $3,600 during this process. No invoices have
been provided. The panel acknowledges the complainant has been receiving medical
treatment as evide nced by her doctor‟s report which indicates she has been receiving
treatment for anxiety and depression for several weeks in September 2020.
AFCA will award compensation (capped at $5,000) if there has been an unusual degree or
extent of physical inconvenience, time taken to resolve a complaint or interference with the
complainant‟s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to awarding compensation. We do not award
compensation because the complainant has suffered some inconvenience and anxiety. AFCA
expects complainants to be moderately robust and to bear the normal degree of
inconvenience experienced when a problem occurs and to take reasonable steps to manage
the situation.
Insurer to pay the complainant $4,000 compensation
The insurer acknowledged the complainant was impacted by delays because of the unusual
nature of the event, the discovery of white ant damage and the inability to determine the
reason for the water ingress. It says it provided appropriate temporary accommodation but in
acknowledgement of the stress and inconvenience it offered and paid $1,000 compensation.
The claim was made on 28 February 2020. The insurer offered $19,020.45 to settle the claim
on 29 May 2020. As set out earlier, a further offer to settle the claim was made on 22 October
2020. While the panel acknowledges the efforts made by the insurer to bring this complex
claim to conclusion, the panel considers there has been an unusual degree of physical
inconvenience as the complainant has not lived in her home for a considerable period.
Further, the panel considers although the matter was complex, the insurer took too long to
resolve the complaint and failed to take sufficient account of the vulnerability of the
complainant.
The panel accepts the management of the claim significantly interfered with the complainant‟s
expectation of enjoyment or peace of mind.
In all the circumstances, taking into account the payment of $1,000 compensation, the panel
considers an award of compensation of $4,000 is appropriate.
2.4 Why is the outcome fair?
Insurer not entitled to decline the claim for damage to the ground floor unit
The outcome is fair because the available information establishes the insurer is not entitled to
decline the claim for damage to the ground floor unit. While the available information
establishes the insurer is entitled to decline the claim for the upstairs unit it has offered to
compensate the complainant for the damage to the upstairs unit which is fair in view of the
delays in its claims management.
Determination | Case number: 732377 Page 17 of 30
3 Supporting information
3.1 Process
AFCA’s approach to this complaint
This matter was determined by a panel
Due to the nature of this dispute, it has been referred to a panel for determination. The panel
comprises the ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive experience as an insurer.
The panel has decided this complaint based on what is fair in all the circumstances, having
regard to legal principles, applicable industry codes or guidance, good industry practice and
previous relevant determinations of AFCA or predecessor schemes (which are not binding).
A full exchange of the relevant information has taken place between the respective parties.
Each party has had the opportunity of addressing any issues raised. All the provided
information has been reviewed and considered. The parties have raised numerous issues in
their submissions to AFCA. However, commentary in this determination is restricted to those
issues considered relevant to the outcome.
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an event to
which the policy responds. This is known as a prima facie or valid claim. Once so established,
the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies
if it seeks to deny or limit its liability for the loss.
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence. When we assess complaints, we consider available
documents, the recollections of the parties, and all relevant circumstances. We give more
weight to documents created at the time the events occurred. If there is no relevant
documentation, we will decide what is most likely to have occurred based on the information
provided to us. If there are conflicting recollections and these are evenly weighted, we may
find that a claim cannot be established.
Case law and proximate cause
Case law establishes:
· The proximate cause of the loss is the dominant or effective or operative cause of the
loss whether or not that be the last in time or the sole cause.
· If there are several causes operating contemporaneously, each must be examined for
the qualities of reality, predominance and efficiency as the active, efficient cause that sets a
relevant chain of events in action. If one cause would have caused the harm in any case, and
the other would not have done so in the absence of the first, the first is the proximate cause.
· A common-sense approach is taken to determine proximate cause.
Determination | Case number: 732377 Page 18 of 30
3.2 Relevant policy terms
Policy wording
Some relevant policy extracts are referred to in the correspondence between the parties and
in the insurer‟s Notices of Response. Other relevant policy extracts are set out in the
determination. Both the policy document and the Notices have been exchanged with the
complainant.
What we do not cover as your building
Your building does not include:
anything that is not legally part of your building for body corporate insurance
purposes according to the relevant strata
these wall, floor or ceiling coverings when they are within a unit and the strata
laws in your state or territory say they are not part of your building for body
corporate insurance purposes: paint, tiles, wallpaper and permanent wall, floor
and ceiling coverings;
o fixed floor coverings including lino, whether glued down or not;
o timber floor coverings that were fitted when the building was originally built,
whether secured to the floor or not.
for any business activity unless we agreed to this business activity and this is
shown on your certificate of insurance or if this business activity is only: o the
residential tenancy of a unit which is part of your building; or
o using no more than 1 unit in your building as an administration office.
To process the claim, you must
allow us to inspect the damaged building and/or common contents;
allow us to arrange for experts to assess the damaged building and/or
common contents and to quote on repair or replacement;
provide us with a quote for repair or replacement if we ask for this. If you
choose to use our recommended repairers (when available), there is no need to
obtain your own quotes;
when requested, provide us with all proofs of ownership and value,
information, co-operation and assistance in relation to a claim (including giving
evidence in court) as we may reasonably require;
allow us, or a person nominated by us, to recover, salvage or take
possession of your building and/or common contents. When we ask, you must
send any items to us, or cooperate in our collection or retrieval of such items;
consult an expert if we ask for this.
What you must not do
do not dispose of any damaged parts or items of your building or common
contents without our consent;
do not carry out or authorise repairs without our consent unless you cannot
contact us and need to make emergency repairs to protect your building or
common contents (see additional feature „Emergency repairs‟ on page 26);
do not wash or clean or remove debris from any area damaged by fire without
our consent unless you need to do this to prevent further loss;
Determination | Case number: 732377 Page 19 of 30
do not admit liability or responsibility to anyone else unless we agree;
do not negotiate, pay or settle a claim with anyone else unless we agree;
do not accept payment from someone who admits fault for loss or damage to
your building or common contents. Refer them to us instead.
If you do not comply
If you do not comply with „What you must do‟ and „What you must not do‟ we can
reduce or refuse your claim and/or recover costs from you or cancel your policy.
If we decline a claim
We will provide reasons for our decision to decline and if you decide to lodge a
claim, we will send you written confirmation of our decision
How to establish your loss
Establish an incident took place
When making a claim you must be able to prove that an incident covered by your
policy actually took place. If you do not do this, we will not be able to pay your
claim.
We may obtain the following from the police:
confirmation that you reported the incident;
details of any investigations they undertook.
You must give us authority to access these records, if we ask.
Describe your loss or damage
You must also give us accurate and full details of what was lost, stolen or
damaged and give us proof of value and ownership for items claimed if we
request it.
When your building or common contents are damaged
Allowing us, a repairer or an expert appointed by us, to look at what is damaged is
usually all that is needed to prove your loss. Sometimes though we might ask you
to produce a copy of the most recent plans and drawings for your building,
photographs of your building and/or common contents or other evidence that
supports the extent of the loss you have suffered. For valuable and badly
damaged items, we may ask you to provide proof of ownership and value.
If we decide that you are unable to reasonably substantiate your claim, we might
reduce or refuse your claim.
How to prove ownership and value
Determination | Case number: 732377 Page 20 of 30
For lost, damaged or stolen items that are no longer available for inspection, you
must validate your claim by giving us details of when and where they were
purchased and reasonable proof of ownership and value.
We will decide what is reasonable proof of ownership and value depending on
what you are claiming for, how old they are and their value. A statutory
declaration is not of itself considered acceptable evidence of proof of ownership
and value.
If you are unable to reasonably substantiate your claim, we can reduce or refuse
your claim.
General exclusions (Cont’d)
You are not covered under any section of this policy for damage, loss, cost or
legal liability that is caused by, arises from or involves:
Seepage of water
water seeping or running:
through the earth (hydrostatic water seepage);
down the sides of earth or earth fill that is up against your property;
down the sides or underneath swimming pools or spas causing them to
move, change shape, lift or leak through their hydrostatic valves;
against or through retaining walls and forcing them to move or crack;
from agricultural pipes
3.3 Extracts from material relied on by the parties
Record Key points
Insurer’s expert (F )
Make - safe report
17 March 2020
inspected and photographed damage 17 March 2020
exact cause of damage unk nown
likely water has pooled up against an exterior wall and migrated
through brickwork, or submerged up through concrete subfloor
describes damage to timber floor and carpet
high moisture recorded in adjoining walls
v isible microbial growth on skirting boards in lounge
mould remediation works required
work required in bedroom, lounge room, cupboard, kitchen, front
room, bedroom 2 and take 3 to 5 days.
complainant requests temporary accommodation while works
completed
Determination | Case number: 732377 Page 21 of 30
Record Key points
Complainant’s scope of
works (DP )
Make - safe report
30 March 2020
supply and install new drain pipe and agg line and connect to
stormwat er drain $17,600
Insurer’s expert (D )
Building assessment report
29 April 2020
inspected and photographed 29 April 2020.
complainant advises rainwater entered during large storm 8
February
based on visual inspection believes cause of damage is due to
water seeping through the external block walls to the downstairs
area then eventua lly flooding due to the rain on 8 and 9 February
notes property is on a very steep block – downstairs area approx.
2.5 metres below street / ground level
excess rainwater from the streets drainage into the property, then
has built up against external walls – water able to seep through
the external wall int o bedroom 1 dispersing into surrounding areas
causing damage
complainant says this kind of event (overflow) has never occurred
previously
says construction work across the road could have contributed to
di verting rainwat er towards the property
says there is adequate drainage against foundation of the
property for standard rainfall events
agrees damage to dow nstairs unit to bedroom 1 and 2, robe ,
sunroom, living room, bathroom: all floor coverings affected a nd
skirting boards, wall linings robe shelving.
property safe.
claim is marked for acceptance.
repair cost $19,020.45 including GST.
Complainant’s expert (I )
Pest inspection r eport
10 June 2020
inspected 4 June 2020 and at time of inspection no visible
evidence of live termites or borer activity.
evidence of termite (white ant) damage such as mud tubes of
damaged timbers found
some visible damage appears severe
no visible evidence of wood rot
high moisture levels found to some masonry internal w alls
recommends complainant makes enquiries with vendor about
termites
complainant may need to arrange for a treatment or consult a
builder
Complainant’s expert ( T )
Engineer report
10 June 2020
inspected and photographed water ingress to lower ground fl oor;
water entered the property through the sandstone rock faces
behind the lower ground floor stud and masonry walls
property directly opposite a construction site under excavation
situated on a steep sloping site
complainant says water ingress has occurred only after demolition
and excavation directly across the road
construction site had no installed drainage system or pump out
pits
says sudden emergence and volume of water ingress is not due
to failing drainage (system)
temporary removal of draina ge system across the road has led to
collected wat ers running off to nearby properties by direct
overland flow, seeping through soft soils or faults in the rock
Determination | Case number: 732377 Page 22 of 30
Record Key points
existing drainage system at the property would not be able to
cope and would result in water in gress
recommends re - instatement of drainage system at the property
Insurer’s expert ( D )
Internal assessment re port
25 June 2020
assessor engaged to review I‟s report, D‟s assessment / quote,
T‟s engineer report, and to advise claim outcome
termite damage would be considered as pre - existing, so not
covered
notes further damage has occurred to unit 2, recommends a
further assessment / SOW
cost to install new drainage ($17,600) would not be covered
refers to complainant seeking cover and payout on bot h units
a new claim should be lodged on a without prejudice basis to
assess damage to unit 1 (cracking / vibration) due to building
works across the road
recommends cash settlement due to maintenance / rot issues with
timber framing
recommends onsite meeting to di scuss quotes and provide advice
on lodging second claim
recommends claim be referred to recovery team as the builders
working on the site across the road may have been negligent in
not installing drainage system
Insurer’s expert ( D )
Internal assessment re port
17 July 2020
refers to onsite meeting 16 July 2020 and convers ation with
complainant
notes cracking to wall, ceiling linings in unit 1 (upstairs) as well as
water stains – says an engineer will be appointed to investigate
cause
notes repairs not completed in unit 2, evidence of further water
ingress
insured visiting sister in Brisbane last mont h
no business activity run out of either unit
$750 excess paid.
complainant says she moved to unit 1 3/2020 as tenants had
moved out
recovery team awaits f urther assessment reports to determine
options
will review T‟s report again and provide comments on liability from
construction site
D to omit internal painting from quote as not covered under strata
policy. D amended quot e $15,135. 57.
cost to install drainage pipes not covered under the policy
no make safe as strong winds
Builder’s assessment
report
7 August 2020
reviewed stormwat er run - off in the bottom unit and settlement
cracking to upstairs bedrooms and living area believed to b e
caused by jackhammering from the adjacent street construction
site
recommend additional downpipes be added to gutters at the back
and front and that roof tiles be re - fixed to prevent future leaks
roof report found multiple roof leaks
settlement cracking in upper unit
recommends engineer is appointed
Roof leak report (C
plumbing)
summary from S‟s report and above assessment report
a bove the leak in the lounge room is where it transitions from
Determination | Case number: 732377 Page 23 of 30
Record Key points
7 August 2020 terrac otta to the metal roof. On the bottom row of the terracotta
tiles there are broken tiles which is causing water to ingress into
the property.
leak in the bedroom is caused by the second s tory gutters filling
up and overflowing back into the roof cavity
terrac otta tiles above the leak in the kitchen are not installed
properly as they are not straight and overlapping each other
causing water to get in underneath. The gutters are also full of
water and causing water to back up into the kitchen.
Scope of works (JL)
24 September 2020
work required to staircase, master bedroom, lounge dining,
kitchen basement bedroom, basement lounge, kitchen, entry
including builder‟s mark - up and GST $35,666. 59
Insurer’s expert ( S )
Engineer report and
photographs
1 October 2020
refers to T‟s report from 10 June 2020
t here is a major gap bet ween the two boulders behind the eastern
room‟s stud wall in ground floor and it was evident that the water
was flowing behind the wall for a long period of time, based on the
existence of a drainage system and the presence of salts
t here is a drainage outlet behind the eastern bedroom‟s wall
(90mm in diameter), which also indicates the flow of water
predates the rock hamme ring activity, is a long - term issue and
therefore was not caused by the excavation works in the opposite
property
t here is also a crack in the rock where the insured also stated the
water was em anating from. C onsider s this crack to be a pre -
existing crack, since the edges of the crack were extremely
weat hered and rounded and that coinciding with the crack is a
concrete path constructed to allow the flow of water from that
crack towards the drainage outlet
water seeping through from under the nort hern wall of the living
room when inspected even though it was dry weather
on the first - floor hairline cracks in the walls and around the ceiling
some of which are near wat er leaks and there is water staining
from previous water leaks in the roof closed where there was a
gap between the cornice and the wall
existing drainage and a small channel for draining the water from
behind the wall of the eastern bedroom, which indicates that the
gap and cracking of the boulders pre - date the excavation works at
the nearby prop erty.
existing drainage system is inadequate to drain the flow of water
and lack of waterproofing and an in adequate drainage system
behind the wall has caused the water inundation of the room and
that this has been a long - term issue
i nspection was carrie d out during dry weat her condition however it
was observed that the water was seeping through from under the
wall in the living room area
constant water ingress into the living room after the rain was
caused by the lack of adequate drainage system and inad equate
waterproofing. The pore wat er pressure from the soil would
gradually seep through from the living room‟s northern wall.
if there was adequat e waterproofing and drainage system behind
the sandstone wall it would have prevented the water ingress into
the living room.
likely that the water could have infiltrated the soil in garden bed at
the front of the building and redirected by the lower impermeable
materials (rock /clay soil) and ultimately seeped through from
Determination | Case number: 732377 Page 24 of 30
Record Key points
under the wall in the living room due to lack of wat erproofing and
adequate drainage system. Although we were not able to confirm
if there is any drainage behind the sandstone wall in the living
room, it is our opinion that the wat er flow has been occurring due
to a lack of an adequate draina ge system and waterproofing
adjacent to the wall which would have prevented water seepage
alongside the wall. Additionally, the steeply sloping road in front of
the property would minimise stormwater from entering from the
opposite properties across the ro ad. Therefore, it is considered
that the run - off stormwater emanating from the nearby property
would not have flowed to the subject property.
i n relation to the possibility of surface stormwater entering the
property from the roadway, the steeply sloping r oad in front of the
property would have been designed and constructed as per RMS
standards with appropriate drainage (e. g. kerb and channels on
both side of the road, pits and underground drains ). This is
expected to capture all surface stormwater and prev ent it from
entering the property
floor screed to the ground floor has “bubbled” due to the long - term
water and water vapour emanating from the crack and crevic es
behind the walls of the living room and the eastern room, which
made the screeding brittle a nd caused them to break under the
live load and self - weight of the timber flooring above it.
hairline wall cracks in the first - floor area are caus ed by the gradual
shrinkage and expansion of the wall materials due to the previous
roof leak at this location and have not been caused by the
excavation works in the nearby property
based on visual inspection from the only accessible internal area
(bedroom at the ground floor), did not observe any damage which
would be attributed to being caused by termites, howe ver cannot
confirm the absence of termite damage. An inspection by a pest
(termite) expert is required to confirm the presenc e of termites and
any termite damage and may involve an invasive inspection (i.e.
removal of plasterboard) Based on our inspection the structural
integrity and stability of the structure appears unaffected
T‟s report does not adequat ely explain how the excavation work
had caus ed the temporary removal of the drainage system. Also,
the report did not include the inspection or assessment of the
existing drainage system adjacent to the wall next to the ground
floor‟s bedroom, which would indicate the water flow bet ween the
cracks and fissures had existed. That is, the drainage system was
previously constructed under the cracks to allow for the flow of
water emanating from the rock adjacent to the wall
work carried out in the opposite property did not damage the
drainage system around the ins ured property and the wat er
inundation has been caused by the inadequate drainage system
and the lack of water proofing around the property. T he fissures
adjacent to the room were weat hered and the existence of
concrete path adjacent to the wall (bedroom‟s wall in ground floor)
indicated the concret e path was built previously to redirect the flow
of water from the existing cracks and fissures in the boulders
adjacent to the wall which again reject the idea that these cracks
and fissures caused by the excavation works
not been a sudden emergence of water flow since there has been
an existing drainage system next to the boulders and there were
signs of efflorescence on the boulders whic h indicated the water
flow has been occurring over a long period of time
as for run - off wat er from the opposite site, it is obvious from the
Determination | Case number: 732377 Page 25 of 30
Record Key points
terrain that storm water run - off wo uld not have been able to flow
towards this property, regardless of water volume. The storm
water run - off from the opposite site would flow away from the
building and along the slope of the road and would not enter this
propert y
Insurer’s expert ( D )
Internal assessment re port
7 October 2020
refers to engineer‟s report (S) and liability quote from JL for
repairs to ground floor ($35,666.59) and first floor and says
damage on the ground floor unit was cause from water seepage
unclear what damage attributed to long - term seepage and from
the February rain event insurer should repair damage noted in JL
quote.
notes insurer made a business decision to include storm damage
to the first - floor unit under this claim. Says cracking to the walls in
the first - floor unit is due to shrinkage and expansion from ongoing
roof issues and not from an insured event
water ingress has not been caused by excavation works
recommends decline for hairline cracking in first floor unit as
damage not fro m an ins ured event. Water staining on walls from
leaking roof is cosmetic and painting not covered under strata
policy
mould contamination in ground floor from unresolved seepage
recommend remediation cost of mould in both units be included in
final cash s ettlement.
Complainant’s expert (T )
Reply to S‟s report
28 October 2020
typically, a property uses down - pipes to collect stormwater from
the r oof and discharges this directly to council‟s stormwater
network. During demolition, these down - pipes (and assoc iated in -
ground pipes ) are removed
this means that during this stage of the project, there is no direct
discharge of the stormwater collected into council‟s piped system.
The water is trapped on site and can flow onto other properties if
not properly mana ged.
claim coincides with the highest rainfall volume recorded to date at
closest weather station. With no drains in place , water was able to
pool and pass to the properties via overland and subterranean
flow
BOM records show high rainfall on 7 (60mm) 8 (64mm) 9 (92mm)
and 10 February (240mm)
drainage system at the insure d property was working, but could
no t cope with the flow of water from two properties
cause of water ingress was attributable to the opposite site and
temporary removal of its drainage sy stem
w hen the property is collecting and discharging run - off collected
from the site ‟ s impervious area, water seeps through the channel
in the boulders and discharges via the floor waste. During the high
rain - fall event, this channel was not able to collec t and discharge
the water of both properties fast enough, resulting in the water
building - up and flowing out into the lower floor
slope in the direction of the site oppos ite towards …. is much
greater than the slope down the road, which is gentle by
compar is on. O ver a comparable distance, the land falls 6 mete rs
towards the insured property …. where the road falls 3 meters. As
the opposite site had no stormwater connection at the time of the
event, it is fair to say that water is likely to have flow ed from the
opposite si te and ont o the insured‟s …. (as well as its
neighbouring downstream properties), through a combination of
Determination | Case number: 732377 Page 26 of 30
Record Key points
land overflow and subterranean flow
notes the insured has report ed the opposite site now has a
functional drainage system and she has not observed any water
ingress to the lower floor of the property because of recent rainfall.
Complainant’s expert (T )
Report
24 December 2020
after a recent week - long rain event, (BOM records show a week of
rain 16 December (23mm) to 22 December (25 mm)) and
observed through a walk - through video call there is no damage or
no water ingress to insured property which supports conclusion
that the removal of the drainage system across the road (which
now has a functional drainage system installed) caused a dditional
run - off into the system exceeding its design capacity and resulting
in water ingress to the insured property.
Insurer’s expert ( S )
Supplementary engineer
report and Near map
images
18 January 2021
i n response to T‟s report dat ed 28 October 2020 agrees 240mm
rain on 10 Feb 2020 i s the highest daily rainfall rec orded to date
and the total rain of 456mm over a four - day period is the highest
cumulative rain during the time the complainant has lived at th e
property
T concluded that the issues relating to wat er ingress in to the
subject property were attributable to the demolition works carried
out at the opposite site at No.52 and lack of drainage during high
rainfall events
understand s that the comment abo ve from T was bas ed on the
property at No.52 being demolis hed which would result in the roof
water from the original building discharging directly onto the
ground and not into the stormwater drainage system around the
house.
property at No.52 was unchanged up until the aerial image dated
22 October 2019 i.e. the aerial image dated 22 October 2019
does not show any changes to No.52 when compared to earlier
aerial images
aerial image dated 21 January 2020 shows some site clearance
works in the front garden o f No. 52 but the building was still
evident
aerial image dated 21 January 2020 also shows demolition works
had started in the adjacent property at No. 50, downhill from
No.52. These works included the demolition of the front part of the
building, however, most of the building was still evident
aerial image dated 28 February 2020 shows site clearance works
to the front garden of No.52 i.e. the removal of trees and plants.
The building at No.52 was still evident. There was no change to
the demolition works a t the adjacent property at No.50
aerial image dated 15 April 2020 shows that the building at No.52
had been demolished and earthworks were underway for the new
building. There was no change to the demolition works at No. 50
b ased on the Near map images th e property at No.52 was still
evident after the heavy rainfall event from the 7 - 10 February 2020.
Some minor site clearance works in the front garden of No.52 had
commenced prior to the February 2020 rain event, however, it is
highly unlikely that these wo rks would have included the removal
of the stormwat er system around the hous e. The demolition of the
house and earthworks for the new house started between the 28
February 2020 and 15 April 2 020 i.e. aft er the February 202 0 rain
event. It is our experience that storm water systems are removed
after the demolition of the hous e normally during the earthworks
for the new house and therefore at the time of the February 2020
rain event there would not have been any additional rainwater
Determination | Case number: 732377 Page 27 of 30
Record Key points
discharging directly onto the ground at No.52 due to demolition
works .
it would be possible for surface water from all the above higher -
level properties further up the road would cross over to the lower
level ground on the southern side of the road, however, this would
be a cumula tive volume of rain water from several higher - level
properties and not a single property a t No. 52 as described in T‟s
report
February 2020 rain event over a 4 - day period would have res ulted
in a substantial amount of water infiltration into the higher - leve l
ground. This sub - surfac e water would then have flowed downhill
on the rockhead and flowed into rock fissures. The concentration
of sub surface water in the rock fissures over the 4 - day rain period
would have resulted in a substantial amount of water flow in the
rock fissures that overwhelmed the 90mm diameter outlet pipe
that then allowed water to inundate the lower level of the subject
property. The water flow through the rock fissures would have
been the cumulative effect of rainfall on the large catchment area
at a higher level than the subject property and not just one
property at No.52
potential volume of sub - surface water from the rock fissures
cannot be calculated due to unknown flow paths through the rock
fissures. A 90mm pipe is a small diameter pipe and only adequate
for low flows. There was no allowance in the drainage design for
the lower level property for potential high sub - surface wat er flows
through the rock f issures. For example, at the time of construction
the lower floor level could have been raised by say 500mm above
the channel level at the rock fissures to form a deep overflow
channel bet ween the house and the exposed rock to divert high
flow wat er from t he rock fissures around the house. This deep
overflow channel could still have been overwhelmed during the
February 2020 event, but it would have provided greater
protection to the property compared to a single 90mm diameter
pipe. It is for this reason exi sting drainage was deemed
inadequate as there was no overflow allowance in the drainage for
potential high flows from rock fissures.
T‟s report notes the owner has reported that the opposite site at
No.52 now has a functional drainage system and that the y have
not observed any water ingress to the lower floor of the property
dur ing the recent rainfall. „As noted, the February 2020 rain event
was the highest rain event since the owner has lived at the
property. It is therefore our opinion that the absence of water
ingress into the property is not due to the functional drainage
system at No.52 but is due to there not being a similar rain event
as the February 2020 rain event. It is highly likely that the property
was previously inundated prior to 2017 during a similar event and
we expect that it will unfortunately be inundated in the fut ure
during a similar event if the piped drainage at the rock fissures
remains in its present form ‟.
opinion from the first report remains unchanged.
f urther review of Near ma p aerial images has determined that the
building at No.52 had not been demolished at the time of the
heavy rain event on the 7 - 10 February 2020. Demolition works
and earthworks for the new house at No.52 did not commence
until after the 28 February 2020. S d isagree s with the conclusions
in the T report that the issues relating to water ingress into the
subject property at No.35 were attribut able to the demolition works
carried out at the opposite site at No.52 and lack of drainage
Determination | Case number: 732377 Page 28 of 30
Record Key points
during high rainfall event s.
h eavy rain event in February 2020 precipit ated the water ingress
in the lower floor of the subject property, however, the proximate
cause of the wat er ingress was the inadequate drainage for the
potential high sub - surface water flow through the rock fissures
n ot possible to calculate the potential volume of sub - surface wat er
through the rock fissures but a 90mm outlet pipe is deemed
inadequate without a deep overflow channel to direct sub - surface
water around the building.
Insurer’s expert ( D )
Intern al assessment re port
1 February 2021
reviewed both engineering reports and based on the evidence
provided agrees with S's conclusion, that the issues relating to
water ingress into the insured's property at No.35 were not
attributable to the demolition works carried out at the opposite site
(No. 52) and lack of drainage during high rainfall events. The Near
map recor ds substantiate this.
refers to the letter of offer advising that under normal
circumstances insurer would not accept the result ant damage to
the ground floor under the Strata Policy, as the cause of damage
falls within a general exclusion under the polic y. The letter further
states that considering the circumstances the insurer has agreed
to accept liability for the resultant damage in recognition of the
delays encountered.
t he assessor believes neither of the most recent engineering
reports, changes the insurer‟s position or its offer.
Complainant’s neighbour
( D )
Letter
30 Nov 2016
D next door to new development. Cites the developer‟s
geotechnical report which says the excavation has the potential to
create significant ground vibrations which could damage
neighbouring houses.
Complainant’s roof ( PR )
Quote
13 Nov 2020
Quote to storm seal roof $8,888
Complainant’s roof ( PR )
Quote
25 Nov 2020
Quote to storm seal roof $8,316
Complainant’s roof ( PR )
Quote
29 Jan 2021
Quote to strip existing roof and supply and install tiles, batons,
sarking, ridge capping, valley iron and all flashings $64,240 inc
GST.
Complainant’s roof ( PR )
Quote
12 April 2021
Quote re roof $58,400
Complainant’s roof ( RR )
Invoice
15 Nov 2020
Invoice to re - bed and point ridge caps $1,507
Complainant’s builder
( BH )
Quotation based on recent meeting at property regarding
rectification works caused by vibration and storm damage. Total
Determination | Case number: 732377 Page 29 of 30
Record Key points
Quote
Valid to 31 December 2020
price including builder‟s margin and GST $224,000.
1. Preliminaries including HOW insurance
2. Supply of scaffolding and items associated with OH&S
3. Remove and replace roof tiles
4. Adjustment of window lintels and brickwork to allow windows &
doors to operate again
5. Replace broken glass in windows caused by vibration and
movement
6. Remove & replac e all floor coverings affected by water ingre ss
(same as existing)
7. Remove all damage and cracked render and plasterboard
8. Paint and mak e good all surfaces
9. Remove all building debris
10. Check all brickwork and foundations that may have moved (NB
This is a PC item and will need Structural Engineer‟s inspection)
11. Replace water damaged ceilings
Insurer’s report and
photographs (S)
1 June 2020
inspected and photographed 31 May 2020. Water has entered the
property due to the limestone walls and caused flooding and
damage downstairs. Describes and photographs damage. No
drying equipment required. Antimicrobial applied to ex posed
subfloors.
Insurer’s report and
photographs (S)
12 April 2021
scope of works and cost summary (which does not include
removal of mould from beams) $1, 622. 90
water entered the building through the roof. House not liveable in
its current state. Visible mould and mould remediation required.
Further damage may become apparent during demolition.
3.4 Other relevant material considered and relied on
Parties‟ submissions /emails and all attachments to all submissions/emails.
Parties‟ expert reports.
Photographs and videos.
Invoices, quotations and scopes of work.
Correspondence between the parties.
Determination | Case number: 732377 Page 30 of 30
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.