Determination 729204

Insurer ceased flood repairs and cash settled remainder; settlement amount and loss of rent disputed

FirmSuncorp Group
Decided2020-12-14
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded$17,931
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant's flood-damaged property was partly repaired before the insurer stopped work and cash settled the remainder. AFCA found the settlement insufficient and the claim unreasonably delayed, and ordered further building settlement and additional loss of rent.

The insurer must pay the shortfall in remediation costs and additional rent because its decision to part-complete repairs rather than cash settle delayed the claim.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensation

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 729204 Financial firm AAI Limited Determination | Case number: 729204 Page 2 of 11 Case number: 729204 10 December 2020 1 Determination overview 1.1 Complaint The complainant is represented by his broker (NP). For the sake of convenience, reference to the complainant will include both. The complainant lodged a claim with the financial firm (insurer), after his property was damaged by flood. The insurer decided to repair the damage. This included the strip out and remediation works. However, the insurer ceased repairs . This is because the insurer’s builder says it is unable to warrant the repairs as aspects of the property are non-compliant with the relevant building code. The insurer seeks to cash settle the remaining repairs. The complainant accepts the insurer ’ s decision to cash settle the repair portion of the downstairs section of the claim. However, a dispute has arisen over the insurer ’ s refusal to complete the strip out and remediation works and whether the insurer is responsible to rectify the underlying defe cts discovered to the property’s concrete slabs. 1.2 Issues and key findings Have the insurer ’s actions led to the complainant’s detriment ? No. The available information does not show that:  the complainant would have used an alternative method of repair, or  that alternative method would have successfully repaired the damage. Is the insurer required to complete the remediation works? No. The insurer has previously cash settled the complainant $8,145 for some of these works. Further, it is possible other contractors not engaged by the insurer have undertaken work at the site. In such circumstances, it would not be reasonable for the insurer to proceed with the works. The p anel accepts the complainant’s position that the settlement amount is insufficient. Accordingly, the insurer should settle the complainant the additional amount as set out in section 2.2 of this determination. Determination | Case number: 729204 Page 3 of 11 Is the complainant entitled to further loss of rent payments? Yes. The claim has been unreasonably delayed due to the insurer’s incorrect decision to part-complete the repairs. The insurer should pay an additional amount as set out in section 2.3. Should the insurer pay non-financial loss No. Whilst the complainant did suffer an unusual degree of inconvenience, the additional amount of rent awarded should mitigate this. 1.3 Determination This determination is partially in favour of the complainant. Within 14 days of the complainant accepting the determination, the insurer is required to pay the amounts set out in sections 2.2 and 2.3 . Determination | Case number: 729204 Page 4 of 11 2 Reasons for determination There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. This decision has been made by a panel consisting of an Ombudsman, an individual with extensive insurance experience and another individual with extensive consumer experience. The decision follows consideration of all the material exchanged. It is based on what is fair in all the circumstances having regard to the relevant legal principles, terms of the policy, good industry practice (including codes of practice) and previous decisions where applicable. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome. 2.1 Have the insurer’s actions led to the complainant’s detriment ? No dispute the complainant has established a valid claim There is no dispute the complainant’s property sustained damage as a result of a severe weather event in early 2019, to which the policy responds. However, a dispute has arisen over whether the insurer ’ s actions to stop repairs part way prejudiced the complainant. The complainant says the insurer was aware of the non-compliance of the downstairs ceiling during the initial assessment. As the insurer was aware of this, it should not have authorised the repairs. The complainant says by authorising these repairs in error, and commencing the strip out works, the insurer has removed his ability to explore alternative methods of remediation to the effected tiles. The complainant says these alternative methods would not involve the uplifting of the tiles. A less invasive method of remediation may have been able to be conducted The complainant has provided an email from PP in support of his position that there was a less invasive method of remediation. PP is a mould remediation and cleaning company. PP’s email describes a potential method of remediation . However, it is not clear if PP’s proposed method would have resulted in the tiles not having to be lifted. For instance, w hen reviewing PP’s process, it noted that: If the area passed this interim PRV validating the method of remediation adopted, then we would remove the remaining grout … Determination | Case number: 729204 Page 5 of 11 This indicates the method of repair is contingent on passing at least this test. It is not clear that the test would inevitably be favourable, or whether the method would continue to be viable if the test failed. Based on this, the panel does not accept the evidence shows PP’s method would have repaired this damage. Further, the panel notes that if PP’s method was followed though up to this stage, and it was identified that it was not a viable method of repair, then the complainant’s costs would have increased compared to the insurer’s method from the start. Therefore, it is not clear the complainant would have explored this option given this risk. In addition, when the complainant signed off on the original scope of wo rks, no concerns were raised with the insurer ’s chosen method. Instead, it appears the remediation method became a concern when the potential defect of the underlying slab(s) became apparent. Accordingly, the panel is not persuaded the information shows that if the insurer had decided to cash settle the claim in the first place:  the complainant would have followed through with PP’s method of repairs, or  that PP’s method would have successfully repaired the damage. 2.2 Is the insurer required to complete the remediation works? Lifetime guarantee does not advance the complainant’s position The complainant is seeking for the insurer to complete the remediation works it commenced. The complainant says during the remediation process, the insurer ’ s builder caused damage to the slab when removing the tile bed. Further, the complainant says the amount he was settled for the remaining strip out works was insufficient to have the works completed by his appointed trades. The complainant says the act of damaging the tile bed is faulty workmanship, which is covered under the insurer ’s lifetime guarantee. It is not clear if the tile bed was damaged by the insurer’s builders or by the complainant’s contractors. Regardless, based on the complainant’s own evidence from B, it appears likely the slab was going to be damaged when lifting the tile bed. In this regard, B said: … the tiles are laid in sections on a mixture of bedding and some direct stuck to the concrete slab when poured. The concrete slabs are not very thick in areas and find that when we try to lift the tiles the Chisel blade from the jack hammer on makinex trolley goes straight through the concrete to the dirt. There is fabric steel Determination | Case number: 729204 Page 6 of 11 mesh in some of the slabs but the concrete is of very poor quality, there for being able to hole the concrete through to the soil below Given this, the panel is not satisfied that any damage caused to the underlying slab would be considered faulty workmanship. However, the panel is satisfied any damage caused during the strip out of the tiles should be covered as a part of the claim. This is because it is reasonable to except that if additional damage occurs during claim related repairs that were likely unavoida ble, then it is expected the insurer’s liability would extend to rectify it. The panel considers this is the case here for these works. The information from B shows the concrete was likely going to be damaged once contractors were committed to the insurer ’s method of repairs. Insurer has settled the complainant for the cost of the strip out and remediation There is no dispute the insurer has previously settled the complainant $8,145 for the works required to complete the remediation works. Further, it is not clear if other contractors have attended the site since the insurer stopped works. B’s report noted they attended the site to start removing the bedding and tiles. They then said: As a result when using the jackhammer to life the tiles it was discovered that it was putting holes in the slab. Given this, it would not be feasible for the insurer to now complete the repairs. Instead, it is fair in all the circumstances for this to be cash settled. Insurer required to increase its settlement for remediation works The complainant says his appointed trades are unable to complete the remediation works for the amount the insurer has settled. The complainant has provided a quote from his chosen builder BCBG for $21,125.10 including GST. The complainant says this quote is to relevel the slab to a condition which would allow new flooring to be re- laid. The insurer has not disputed this amount is fair to relevel the floor. The insurer has previously settled $8,145 for the remediation works. Accordingly, this leaves a difference of $12,980.10. The panel is also satisfied the insurer should add a further 10% on the total repairs allowed. This will account for any potential variances and the transfer of risk. Given this, insurer is required to settle:  $12,980.10 for remediation Determination | Case number: 729204 Page 7 of 11  10% of the remediation works $1,298.01  10% of the cash settled portion of the claim $3,652.76  Total building settlement $17,930.87. The panel is satisfied this is a fair and reasonable settlement to the complainant to complete the works. Section 46 does not advance the complainant’s position The complainant has referred to section 46 of the Insurance Contracts Act 1984 in his submissions. This does not assist. This is because it only applies to a policy provision that limits or excludes the insurer’s liability by reference to a pre -existing defect. The insurer is not relying on such a provision. Whilst there is a provision that excludes defects, it does not do so by reference to the fact the defect pre-existed the policy. 2.3 Is the complainant entitled to further compensation for loss of rent? Policy covers loss of rent There is no dispute the complainant ’ s policy covers loss of rent in the circumstances. Further there is no dispute the maximum policy benefit payable under the policy is 52 weeks. The insurer says that prior to the loss, the property was being leased for $300 per week. This does not appear to be dispute. The insurer has made the following settlements in relation to loss of rent:  $9,300 (31 weeks)  $3,000 (10 weeks)  $2,400 (8 weeks)  $900 (3 weeks)  Total $15,600 (52 weeks) The insurer has settled the complainant the maximum policy benefit within the terms and conditions of the policy. The complainant acknowledges this. However, he is seeking an additional payment given the further delays associated with the file. Additional rent should be paid due to the claim delay The panel is persuaded this claim was delayed due to the insurer’s incorrect decision to part complete the repairs rather than cash settle the claim in the first place. Further, the panel is also persuaded the insurer’s settlement was not fair in all the circumstances given it did not include an allowance to relevel the floor. Determination | Case number: 729204 Page 8 of 11 In addition, the complainant was unable to mitigate his position to complete the repairs given the insurer was engaging various builders and assessors to inspect the issue and report back. In such a case, it was reasonable for the complainant to await the outcome of those investigations before finalising the repairs. The panel does accept though that by the time the insurer issued its final decision letter on 23 March 2020, it was plain the insurer was not going to contribute anything further. Given this, and the fact the complainant had received over $60,000 funds already, he ought to have been able to mitigate his situation to complete the necessary repairs such that the property could be rented. It is not clear how long the balance of the claim related repairs would have taken. The insurer’s builder’s quotation appeared to allow for four weeks. Given there are other additional works that were not included, it would be fair to add another two weeks. Accordingly, the panel accepts the insurer should pay additional rent until 4 May 2020. Reletting expenses not payable The complainant is also seeking reletting expenses. This was not payable under the policy. Further, this would be an expense associated with th e claim, not the insurer’s conduct. The insurer is not liable to pay for this. 2.4 Should the insurer pay non-financial loss? Insurer not required to pay non-financial loss The complainant has sought compensation for his claims experience. The panel accepts there were aspect of the insurer’s claims handling that could have been improved. This included its decision to part-complete the repairs and not including a sufficient allowance in its settlement. However, the panel considers this impact has been mitigated by the additional rent awarded outside the policy limits. The panel also provided no discount despite the fact the complainant was seeking for the slabs to be replaced at some stage, which was not substantiated and likely contributed to the delay. Given this, the panel does not consider it is fair in all the circumstances to award non- financial loss. Determination | Case number: 729204 Page 9 of 11 3 Supporting information 3.1 Relevant policy wording Product Disclosure Statement Claims (pages 58 – 71) How we settle your claim We choose how we settle property claims If we agree to pay a claim for loss, theft or damage to your property, we will decide if we will:  repair damage to your property;  rebuild your property;  pay you what it would cost us to repair or rebuild your property;  pay you the sum insured for your property. If we rebuild (or pay you what it would cost us to rebuild), we will do so on a `new for old’ basis. If we repair (or pay you what it would cost us to repair), we will at our option do so on a `new for old’ basis or to a similar condition to what your property was in before the loss or damage occurred . We may offer you a voucher or stored value card for the amount it would cost us to repair or rebuild an item. .. Lifetime guarantee on property repairs When we repair or rebuild yo ur property, we guarantee the quality of materials and workmanship of that work for the lifetime of your property if we:  authorise;  arrange; and  pay the builder or repairer directly for this work. What we guarantee We guarantee the material used and stan dard of the workmanship to be free of defects. If a defect arises in the lifetime of your property as a result of poor quality workmanship or use of incorrect materials, then we will rectify the problem. This guarantee does not apply:  to repairs you authorise or make yourself; Determination | Case number: 729204 Page 10 of 11 Claims (pages 58 – 71)  to loss, damage or failure of any electrical or mechanical appliances or machines;  to wear and tear consistent with normal gradual deterioration of your property (e.g. paint peeling off after its expected life cycle, wood rottin g from moisture in the air or ground, roofs weathering or a hot water tank leaking after its guaranteed life);  where we agree with a repair quote and we give you, or the builder or repairer, payment for the cost of the repairs and you arrange the repairs . Dealing with defects .. If undamaged defective parts of your property will not support repairs If undamaged defective parts of your property you knew about (or should reasonably have known about) will not support repairing the damage caus ed by an incid ent covered by your policy, we will only pay what it would have cost us to repair the damage had your property not been defective. 3.2 Expert reports Record Key points financial firm ’s expert ( JH ) Report 23 January 2020  given that each section still features the mortar bedding on top of the concrete slabs it is difficult to make a proper assessment on the condition of the slabs  whilst the topping slabs may be patch and re - bed, it is the condition of the pavement slabs beneat h that is critical in order to guarantee any remedial works to the tiling  in order to better understand the condition of the supporting slabs, the top layer of mot or bedding will need to be removed throughout the entire downstairs area so each slab can be evaluated more effectively.  after inspection of the property it is not practical to assess the current condition of the concret e slabs are they are not fully visible, and no guarantees can be made on the longevity and performance of the slabs should the tiles be re - laid.  it is recom mended that the mortar bedding is completely removed in each section of the downstairs area, so a more accurat e judgement can be made about the condition of the concret e slabs below. Once this work has been completed JH should reinspect the site and make a formal assessment  the only section that can be clearly identified as defective and needing replacement at this stage is 40 - 50mm topping slab in room A. Complainant’s expert (BCBG )  We attended site to start to remove the tiles and the bedding. We discovered that the concret e that the bedding and tiles are on is Determination | Case number: 729204 Page 11 of 11 Record Key points Report 15 October 2019 quite thin. As a result when using the jackhammer to lift the tiles it was discovered that it was putting holes in the slab. Please see below from cont ractor inc (sic) pictures;  the tiles are laid in sections on a mixture of bedding and some direct stuck to the concrete slab when poured. The concrete slabs are not very thick in areas and find that when we try to lift the tiles the Chisel blade from the jack hammer on makinex trolley goes straight through the concrete to the dirt. There is fabric steel mesh in some of the slabs but the concrete is of very poor quality, there for (sic) being able to hole the concret e through to th e soil below.  We believe that the best course of action is to remove the slab and reinstate a new slab with reinforcing. We would recommend and engineer be engage to determine the best course of action moving forward. Please advise if you wish for us to pr oceed forward and engage an engineer 3.3 Relevant material considered and relied on  parties’ submissions  correspondence between the parties