Extent of liability for bathroom waterproofing membrane and external pipe re-route after burst pipe repairs
Text of the determination
Determination
Case number 727427
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 727427 Page 2 of 17
Case number: 727427 9 December 2020
1 Determination overview
1.1 Complaint
The complainant and her husband are beneficiaries under a strata policy with the
financial firm (insurer) and lodged a claim after a burst hot water pipe leaked and
required repair.
For the sake of brevity, the complainant and her husband will be referred to in this
determination as the complainant.
The insurer accepted the claim for the repair of the burst pipe, including the re-run of
the pipework and reinstatement of the bathroom repairs.
The complainant says the plumber damaged the waterproofing membrane and seeks
to be indemnified for the replacement of the entire membrane. The complainant is
also dissatisfied with the re-route of the pipe and seeks for it to be returned to its
original route.
The insurer says it is not liable for the complete replacement of the membrane
because its contractor did not cause the damage and there is evidence of pre -existing
deterioration to the membrane. The insurer also denies liability to replace the pipe.
The case analyst provided the parties with a preliminary assessment on the issues in
dispute. The preliminary assessment was in favour of the insurer.
The insurer accepted the preliminary assessment, but it was not accepted by the
complainant . In the circumstances, the com plaint has been referred to me for
determination .
1.2 What is the extent of the insurer’s liability to the complainant?
As the available information establishes on the balance of probabilities the damage to
the membrane was caused accidentally and was also pre-existing, it is fair the insurer
pays to the complainant 50% of the costs to reinstate the membrane and bathroom.
As the available information does not establish a valid claim in relation to the return of
the pipe to the original route, the insurer is not required to pay anything further than its
current offer.
Determination | Case number: 727427 Page 3 of 17
1.3 Determination
This determination is partly in favour of the complainant.
Should the complainant accept this determination then within seven days of
notification of acceptance:
the insurer is to pay to the complainant $8,973.25
upon satisfactory proof of the weekly rent, the insurer is to pay to the complainant
three weeks loss of rent.
the insurer is to obtain a quote for the cost to make the external pipework
compatible with its surrounds and cash settle the complainant that amount.
Otherwise, the insurer is not required to take any further action in relation to the claim
or the complaint.
Determination | Case number: 727427 Page 4 of 17
2 Reasons for determination
I have decided this complaint based on what is fair in all the circumstances, having
regard to legal principles, applicable industry codes or guidance, good industry
practice and previous relevant determinations of AFCA or predecessor schemes
(which are not binding). I have considered all the material submitted by the parties,
both before and after the preliminary assessment. I am satisfied that the
documentation I have relied on has been provided to both parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
After the preliminary assessment was rejected, the complainant made a further
lengthy submission in which the position was essentially reiterated. The complainant
provided no further new material. Where relevant, the further submission will be
referred to in this determination.
2.1 What is the extent of the insurer’s liability to the complainant?
Circumstances of the claim
In June 2019 the strata title manager arranged for a plumber (AP) to investigate a
water leak from the complainant’s unit (Unit 92) into the unit below (Unit 89).
After testing, AP found a hot water pipe had burst in the concrete slab. AP repaired
the hot water pipe and re-ran the pipe to an outside balcony area and rectified
damage caused by the repairs. AP sent an invoice for the investigation work, the
plumbing repair and reinstatement in the sum of $5,538.50.
The complainant arranged for a plumber (PB) to inspect the bathroom. PB noted that
AP had rectified the broken pipe but did not reinstate the continuous membrane as
required by the relevant Building Codes and Australian Standard.
PB provided a quote to rectify the damaged membrane which included significant
work to the bathroom totalling $10,879.
The complainant also arranged for another contractor (DC) to inspect the bathroom.
DC says the waterproofing has been compromised and may leak in the future and so
the bathroom needs to be waterproofed again to eliminate the risk of water ingressing
into the unit below. He estimated the cost to do this work and reinstate the bathroom
is $16,315 plus GST.
He also estimated it will cost $11,895 plus GST to remove the exposed water pipes
on the external balcony wall and reinstate them to their original hidden position.
Determination | Case number: 727427 Page 5 of 17
Insurer’s submissions considered
The insurer paid the invoice from AP (as per policy terms, less excess and GST) but
as for the further amounts claimed says:
it accepts there is evidence of waterproofing membrane in the bathroom and this
was compromised in the investigation and repair of the burst pipe
the membrane was already compromised as there is unrelated water damage next
to the shower resulting from a deteriorated shower waterproofing membrane
where there is evidence of deterioration the insurer is not obliged to make good
the compromise of the membrane by AP does not trigger accidental damage cover
under the policy because it does not arise from a sudden and unexpected event
but arises from the faulty workmanship of AP to the exte nt he breached the
membrane and did not reinstate it
the insurer did not engage the plumber and has been prejudiced as it did not
assess the damage at the outset
The insurer made several offers. It offered to make the external pipework compatible
with its surrounds (yet to be quoted); it offered to pay 50% of PB’s quote less GST
($4,945). It was also willing to pay the cost of reinstating the waterproofing membrane
to all floors and walls as per the Australian Standard (quoted by PB at $1,089
including bui lder’s margin and GST) and pay the reasonable costs to address the
externally run pipes in a colour in keeping with the existing works in the area.
In its response to AFCA on 18 September 2020, the insurer said its offer was:
50% offer on the (PB) quote (which covers the membrane replacement) plus Cost
to dress external pipework - yet to be quoted (stet)
Complainant’s submissions considered
The complainant made lengthy submissions both before and after the preliminary
assessment. The complainant requires the insurer to act with the utmost good faith
and honour the terms of the contract and reinstate the property back to a condition it
was in when it was new.
The complainant seeks the cost to put a hot water pipe in the slab and to connect it to
all plumbing facilities internally, to make good all damage caused by the installation,
to reinstate the bathroom in accordance with Australian Standards (claimed costs of
$28,210 plus GST) and to be paid loss of rent during repairs.
After the preliminary assessment, the complainant said it would take six weeks to
return the unit back to the position it was in prior to the damage caused by the burst
pipe.
Determination | Case number: 727427 Page 6 of 17
Relevantly, the complainant submits:
the complainant was not consulted about the work to be done by AP but notes an
insured must take all reasonable steps to mitigate a loss which was done when the
leaking to the unit below was stopped by AP’s work
AP’s work was an emergency make safe/repairs during which AP re- routed a pipe,
damaged the waterproof membrane in the shower alcove and disfigured tiles in the
shower
AP ran a pipe around the outside of the building so he could bypass the leak, so
the tenant could use the shower and not be inconvenienced until more permanent
repairs could be done
the work undertaken by AP was not faulty workmanship as, to repair the leak, he
had to remove tiles and could not avoid damaging the waterproof membrane
when the waterproofing membrane was compromised by AP, the entire wet area
needs to be reinstated according to Australian Standards
the membrane cannot be replaced without stripping out the bathroom
the cause of the leak has not yet been found
the re-routed pipe is a temporary repair, is unsightly and diminishes the value of
the unit and the complex
the proposed solution to paint the pipe is not fair and not in accordance with the
policy
AP’s work did not rectify damage in the complainant’s unit
the policy responds to damage arising from an accident
the policy requires reinstatement as defined and work is to comply with current
Building Codes and Australian Standards
there is a minor defect in the bathroom as identified by the assessor, but it has not
contributed to the damage claimed
the opinion of the assessor is not an expert opinion and there is no relationship
between the maintenance issues identified and the claim
The complainant says the reinstatement of the tiles was a temporary repair, so the
tenants could continue using the bathroom. Photographs were provided showing
mismatched tiles. The complainant says the waterproofing membrane must be
installed to comply with statutory requirements.
Contractor’s information considered
Several contractors have provided opinion and information. A summary is provided in
supporting section 3 of this determination.
In the invoice dated 27 June 2019 AP says:
he found the hot water pipe had burst in the concrete slab
Determination | Case number: 727427 Page 7 of 17
he employed a pipe location company to search and locate the entry and exit
points of the copper water pipe from the concrete slab and marked the points for a
hot water pipe re-run
he re-ran the pipe from in the laundry to around to the bathroom area and deleted
existing pipework in the concrete slab
he used lag copper to run from the laundry to up through the bulkhead to outside
the balcony area and into the bathroom
he then connected pipework and deleted the copper hot water pipes that were run
in the concrete slab.
In an email 11 May 2020 AP denies he did faulty work and says the damage claimed
was resultant damage. He says:
to repair the burst water pipe, the wall tiles had to be removed to trace and locate
the lines to locate and repair the burst water pipe to prevent the leak
a re-run was required as it was the most feasible option as the pipes run in the
concrete slab and walls of the unit
when removing the wall tiles and render to expose the copper water pipes he
damaged the waterproofing membrane.
the membrane was not faulty or defective but was damaged during the repairs of
the burst water line
In an email to the insurer’s assessor on 9 June 2020 PB said:
the bathroom was a 1980’s renovation
photographs indicate a waterproofing membrane
in the process of plumbing repairs the membrane was damaged
The insurer arranged for assessor to inspect the bathroom and provide an opinion.
The assessor met the complainant on 10 June 2020 and after inspection said:
the bathroom was renovated in the 1980s
the membrane in the shower would run across the bathroom floor
there is sign of long-term damage next to the shower at the base of the wall
this is consistent with water escaping from the shower
the damage is evidence the waterproofing in the shower is now perished
there is no pipe in this area – the pipes are located on the opposite wall
had the insurer instructed the plumber in the repair it would have declined the cost
to reinstate membrane in the bathroom as it was a pre-existing issue which also
required the bathroom to be stripped and renewed to achieve waterproofing
compliance and integrity
Determination | Case number: 727427 Page 8 of 17
as for the external works completed by AP (the re-run of the burst pipes), as this
work was not directly authorised by the insurer then any workmanship not under
control of the insurer is not covered under the policy.
DB’s quote refers to the work he will do which includes allowing for a plumber to
rough in a new hot water line from the laundry to the kitchen and then to the
bathroom. His quote refers to the cost to reinstate the plumbing pipes back into the
wall where they were originally installed and hidden from sight.
DB also says the waterproofing has been compromised and may have the potential to
leak in the future and the bathroom needs to be re-waterproofed to eliminate the risk
of water running into the unit below again.
Complainant established a valid claim for damage to the membrane
The complainant must establish on the balance of probabilities she has suffered a
loss caused by an event to which the policy responds. This is known as a prima facie
or valid claim.
Both parties have made references to the policy terms which they support their
position. The policy terms referred to by the parties are set out in supporting section
2.2 of this determination.
The policy provides cover against damage to the property which occurs during the
period of insurance. Damage is defined to mean:
any partial or total accidental physical loss of, or destruction of property from any
sudden and accidental cause not otherwise excluded by this Policy.
Accidental is not defined in the p olicy. Courts have defined “accidental” in an
insurance context as something that is unintended and unexpected.
Having reviewed the available information, I am satisfied the plumber AP accidentally
damaged the waterproofing membrane in the complainant’s bathroom when trying to
locate the cause of the leak in the complainant’s bathroom.
I accept when AP was removing the wall tiles and render to expose the copper water
pipes he damaged the membrane. In the circumstances, I accept the damage to the
membrane by AP was unintended and unexpected and the complainant has
established a valid claim.
Damage to membrane not caused by plumber’s faulty workmanship
Once so established, the onus shifts to the insurer to prove on the balance of
probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss.
Determination | Case number: 727427 Page 9 of 17
The insurer says the policy does not respond if the sudden and accidental cause was
otherwise excluded by the policy. The insurer says it is entitled to decline the claim
because it is not liable to pay for the cost of rectifying faulty or defective workmanship.
The insurer has not identified the faulty workmanship of AP save to say the insurer
alleges AP breached the membrane and did not reinstate it.
AP was engaged to locate and stop the leak. The available material does not
establish AP was negligent when he breached the membrane. Rather, the available
information establishes this was an inevitable consequence of the work AP was doing
in trying to locate the leak.
There is no evidence the breached membrane was causing damage to the unit below.
In the circumstances, I do not accept the insurer has established the damage claimed
to the membrane was caused by AP’s faulty workmanship and the work required to
locate and stop the leak.
Co mplainant not required to obtain insurer’s approval before engaging plumber
The insurer says it did not engage AP and was prejudiced as it did not assess the
damage at the outset.
The policy provides for the reasonable cost of temporary protection and safety or
emergency repairs in pursuance of the insured’s duty to minimise insured loss and
avoid further losses.
I accept the insurer was not able to assess the damage at the outset. As water was
leaking from the complainant’s unit to the unit below I also accept it was reasonable
for the strata manager to engage AP on behalf of the complainant to find the leak and
stop it to prevent further damage to the unit below.
In the circumstances, I am satisfied the complainant was not required to obtain the
insurer’s approval before engaging AP to locate and stop the leak.
Membrane already compromised near shower and was also damaged by AP
I accept the available information establishes the membrane was probably already
compromised as evidenced by the damage next to the shower.
While the membrane may have caused some damage to the complainant’s bathroom,
it was not leaking to the unit below.
The insurer’s policy says it will pay for the reaso nable exploratory costs incurred in
locating the source of the leak. The policy says it will also pay for the reasonable
costs incurred in repairing the area of the property damaged by such exploratory
works. The membrane was damaged in the exploratory work.
Determination | Case number: 727427 Page 10 of 17
The available material does not establish the leaking pipe was caused by faulty
workmanship.
Fair the insurer pays 50% of the claimed costs
If the claim is established, then the policy says the insurer may choose to either
rebuild, replace, repair or pay the amount it would cost to do so.
The complainant says she is entitled to full replacement of the membrane because of
the policy definition of replacement. She says this means the reasonable costs of
repairing to a condition which is equivalent to or substantially the same as but not
better than when it was new.
The insurer says where there is evidence of deterioration it is not obliged to make
good.
The complainant must establish the proximate cause (the dominant or effective
cause) of the loss is the insured event.
I accept the policy provides the insurer is not required to pay for the cost of rectifying
faulty or defective materials. Having reviewed the available material and photographs,
I accept it is probable the waterproof membrane was already damaged in the area
near the shower stall. I do not accept the complainant’s contention the assessor does
not have the necessary expertise to comment. Having reviewed the photographs, I
also do not accept the damage referred to by the assessor was a minor defect.
As previously stated I accept the membrane was accidentally damaged by AP in a
separate area when attempting to locate the cause of the leak.
In replacing the membrane, I am satisfied the available information establishes the
bathroom would need to be completely stripped as per the quote from DC.
In view of my findings about the causes of damage to the membrane, I am not
satisfied all the loss was caused by the insured event.
In the circumstances, I am satisfied it is fair the insurer pays to the complainant 50%
of the cost of repairs to the membrane as set out in DC’s quote.
Insurer to pay to the complainant $8,973.25
DC quoted the cost to repair the membrane at $16,315 plus GST.
In view of the deterioration in the relationship between the parties I am satisfied it is
fair the claim is cash settled as per DC’s recent quote.
Should the complainant accept this determination then the insurer is to pay to the
complainant $8,973.25.
Determination | Case number: 727427 Page 11 of 17
Insurer to pay to the complainant three weeks loss of rent
While the membrane in the bathroom is being replaced I accept the unit would be
unfit to be occupied. The complainant says this work will take six weeks. This has not
been challenged by the insurer.
Upon satisfactory proof of the weekly rent, the insurer is to pay to the complainant
three weeks loss of rent.
Complainant has not established a valid claim for external pipework
The complainant also claims $11,895 plus GST for the cost to remove the exposed
water pipes on the external balcony wall and reinstate them back into wall into the
wall where they were originally installed.
The insurer offered to make the external pipework compatible with its surrounds (yet
to be quoted).
As set out earlier in this determination the policy covers the complainant for damage
to the insured property. I am not satisfied the complainant has established the
external pipework was damaged as defined in the policy.
The work done by AP was done pursuant to instructions from the complainant’s
agent, the strata manager. AP was lawfully on the property to identify the cause of the
leak and damage to the unit below the complainant’s unit.
The complainant says the cause of the leak has not yet been found yet AP
unequivocally identifies the cause of the leak as the hot water pipe which had burst in
the slab.
The complainant argues the work done by AP was only temporary and now the pipes
should be reinstated to where they were before the leak occurred. I do not accept this
contention in view of the available evidence from AP. He describes the re-run was
“the most feasible option” because the pipes run in the slab and walls. I do not accept
the available information establishes AP’s work was temporary.
Taking all matters into account I am not satisfied the complainant has established a
valid claim for the external pipework.
Insurer to cash settle cost to make external pipes compatible with surrounds
Should the complainant accept this determination then within seven days of
notification of acceptance the insurer is to obtain a quote fo r the cost to make the
external pipework compatible with its surrounds and cash settle the complainant that
amount.
Determination | Case number: 727427 Page 12 of 17
3 Supporting information
3.1 Our Approach
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie or valid claim.
Once so established, the onus shifts to the insurer to prove on the balance of
probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Relevant policy extracts
The relevant policy extracts are referred to in the correspondence between the parties
and in the insurer’s Notice of Response. Both the policy document and the Notice
have been exchanged with the complainant.
Policy wording
Damage, Damaged
means any partial or total accidental physical loss of, or destruction of property
from any sudden and accidental cause not otherwise excluded by this Policy.
Replacement means:
a. the reasonable cost of rebuilding, replacing or repairing to a condition
which is equivalent to or substantially the same as but not better nor more
extensive than when it was new; and
b. the extra costs necessarily incurred to alter or upgrade Your Insured
Property to comply with Public, Statutory or Environmental Protection
Authority requirements, but does not include:
i. any costs that would have been incurred in complying with orders
issued prior to the happening of the loss;
ii. any extra costs to alter or upgrade any portion of Your undamaged
Insured Property if the cost to rebuild, replace or repair the Damaged
portion is less than twenty five percent (25%) of what the cost would
have been had Your Insured Property been totally destroyed.
Claims Conditions
What you must do
5. Our approval needed for repairs
Except for essential temporary repairs permitted under Additional Benefit 2 -
Emergency and temporary protection costs of Policy 1 – Insured Property, You
are not authorised to commence repairs without Our approval.
Determination | Case number: 727427 Page 13 of 17
Policy 1 - Insured Property
What We insure
If selected and shown in the Schedule, We will insure You up to the Sum Insured
shown for Policy 1 – Insured Property in the Schedule against Damage to Your
Insured Property which occurs during the Period of Insurance.
Additional Benefits
When Your Sum Insured under Policy 1 – Insured Property is not otherwise
expended We will pay the following incurred as a result of Damage to Your
Insured Property that is admitted as a claim under Policy 1 – Insured Property for:
You necessarily incur in the Replacement of Your Insured Property.
2. Emergency and temporary protection costs
reasonable cost of temporary protection and safety or emergency repairs in
pursuance of Your duty to minimise insured loss and avoid further losses.
We will not pay more than $7,500 for this Additional Benefit unless You first obtain
Our written consent prior to You incurring costs in excess of this amount.
Special Benefits
The following Special Benefits are included in addition to Your Sum Insured for
Policy 1 – Insured Property.
b. Rent
When You have leased out or can substantiate by means of a signed agreement
that You would have leased out Your Lot/Unit or Common Area We will pay the
actual Rent You lose or would have lost if Your Lot/Unit or Common Area is made
unfit to be occupied for its intended purpose by:
i. Damage to Your Insured Property that is admitted as a claim under Policy
1 – Insured Property; or
ii. reasonable access to or occupancy of Your Lot/Unit or Common Area
being prevented by Damage from an Event claimable under Policy 1 –
Insured Property happening to other property in the immediate vicinity;
iii. disruption to Your Tenants’ occupancy of Your Lot/Unit or Common Area
that is made partially unfit to be occupied for its intended purpose.
We will pay:
under Clause b.i. from the time of the Event until the time Your Lot/Unit or
Common Area is relet following completion of rebuilding, repairs or
Replacement provided You demonstrate You have taken all reasonable
actions to obtain a new tenant; and
Determination | Case number: 727427 Page 14 of 17
under Clause b.ii. from the time of the Event until the time when access to
Your Lot/Unit or Common Area is reestablished;
under Clause b. iii, the cost You necessarily incur to abate the Rent of
Your Tenant during this disruption from the time of the Event until the time
when this disruption has ceased but in all not exceeding a maximum of
three (3) months.
9. Exploratory costs, Replacement of defective parts
We will pay for the reasonable exploratory costs You necessarily incur in locating
the source of bursting, leaking, discharging or overflowing of tanks, apparatus or
pipes used to hold or carry liquid of any kind.
We will also pay for reasonable costs incurred in:
a. repairing the area of Your Insured Property Damaged by such exploratory
work;
b. repairing or replacing the defective part or parts of such tanks, apparatus
or pipes, to a limit of $1,000;
c. rectifying contamination Damage or pollution Damage to land at Your
Situation caused by the escape of liquid, to a limit of $1,000.
We will not pay for any of these costs if the bursting, leaking, discharging or
overflowing is caused by a building defect, building movement, faulty
workmanship, rust, oxidation, corrosion, Wear and Tear, gradual corrosion,
gradual deterioration, Earth Movement or by trees, plants or their roots.
Claims - how We will settle Your claim
1. Replacement
If Your Insured Property is Damaged, We may choose to either rebuild, replace,
repair or pay the amount it would cost to rebuild, replace or repair.
The amount We pay under Policy 1 – Insured Property will be the cost of
Replacement at the time of Replacement subject to the following provisions:
a. the necessary work of rebuilding, replacing or repairing (which may be
carried out upon another site or in any manner suitable to Your
requirements provided Our liability is not increased), must be commenced
and carried out without unreasonable delay;
Determination | Case number: 727427 Page 15 of 17
Exclusions
1. We will not pay for loss or damage caused by or arising directly or
indirectly from:
a. Storm or Rainwater to retaining walls, or caused by Flood if shown in the
Schedule as not selected;
b. lack of maintenance, rust, oxidation, corrosion, Wear and Tear, fading,
gradual corrosion or gradual deterioration, concrete or brick cancer,
developing flaws, wet or dry rot, or failure to maintain Your Insured
Property in a reasonably good state of repair;
….
3. We will not pay for:
a. demolition ordered by any Public or Statutory Authority as a result of Your
failure, or the failure of anyone acting on Your behalf, to comply with any
lawful requirement or due to the incorrect siting of Your Insured Property;
b. non-rectification of an Insured Property defect, error or omission that You
were aware of, or should reasonably have been aware of;
c. the cost of rectifying faulty or defective materials or faulty or defective
workmanship, design or specification;
d. consequential loss, loss of use or Depreciation other than as specifically
provided under an operative Additional Benefit or Special Benefit.
3.3 Extracts from material relied on by the parties
Date Action
Invoice plumber to strata title
manager (AP)
27 June 2019
Investigat e water leak from unit 92 into unit 89.
Pressure tested pipes lines and found hot water pipe
had burst in the concrete slab.
Pipe location company searched and located the entry
and exit points of the copper water pipe from the
concrete slab: mark the points for a hot water pipe re -
run.
Describes plumbing repairs including expose the turn
ups of the hot water line from the conc rete slab, reru n
pipe from in laundry to around to bathroom area and
delete existing pipework in concrete slab; use lag
copper to run from laundry to up through bulk head to
outside balcony area and into bathroom; connect up
pipework; delete copper hot water pipes that w ere run
in the concret e slab. Re - pressure test hot wat er line –
all ok.
Determination | Case number: 727427 Page 16 of 17
Date Action
Rectified the damaged areas and completed various
repairs throughout following plumbing repairs, toilet,
laundry, shower, outside shower.
Work done to search and find, plumbing repai r,
reinstatement: total $5,538.50.
Claim form
2 August 2019
13 June 2019 water leak from unit 93 into the unit
below unit 89 due to burst hot water pipe in the
concrete slab.
AP plumbing attended and repaired. Amount:
$5,538.50
Complainant’s plumber (PB)
14 April 2020
Inspected bat hroom. After plumber had rectified the
broken pipe in the shower recess they are not able to
reinstate the continuous membrane as required per
Building Code and Australian Standards.
Provided scope of works detailing works required to
rectify the damaged membrane include removal,
salvage and reinstatement of fittings, wall and floor
tiles, repair of substrate, supply and apply membrane
to all floors and walls, supply and lay floor and wall
tiles, paint walls, and supply and install new toilet pan,
towel rails etc. $10,879.
Complainant’s quote (DC)
16 September 2020
Cost to remove exposed water pipes on external
balcony wall – reinstate the plumbing pipes back into
the wall where the y originally installed and hidden from
site $11,895 plus GST.
After attending site and looking at the pictures
provided the waterproof has been compromised inside
the shower and outside the shower and may have the
potential to leak in the future.
B athroom needs to be re waterproofed to eliminate the
risk of water ingress into the unit below.
C ost to reinstate the bathroom including al lowance for
the bathroom to be completely stripped ready for
waterproofing , 3 coats of waterproof, supply and install
of ti les to walls and floors, new PC items, patch work,
re - painting, supply and install new shower screen
$16,315 plus GST.
Determination | Case number: 727427 Page 17 of 17
3.4 Other relevant material considered and relied on
Parties’ submissions /emails and all attachments to all submissions/emails both
before and after the preliminary assessment.
Parties’ expert reports.
Photographs, invoices and quotes.
Correspondence between the insurer and its assessor and the strata manager.
Correspondence between the parties.