Home / American Express / Determination 726026
Determination 726026
Chargeback declined for renovation payment where work allegedly not completed
Summary
The complainant paid $11,039.19 upfront to a merchant for property renovations, then sought a chargeback when the work was not completed. AFCA found the firm raised the chargeback for the right reason, accepted the merchant's response reasonably, and ordered no refund.
A card issuer must claim a valid chargeback for the most appropriate reason, but it is not required to assess the quality of building works, and any dispute over the works belongs with the merchant.
Issues
- Unauthorised transaction primary · not upheld
“I am satisfied the financial firm complied with its chargeback obligations and did not make an error which caused any loss to the complainant.”
- Poor claim handling secondary · not upheld
“I consider that on the available information, the financial firm has acted reasonably in accepting the merchant's response to the chargeback claim.”
Subjects and remedies
no remedy
Text of the determination
Determination
Case number 726026
Financial firm American Express Australia Limited
Determination | Case number: 726026 Page 2 of 6
Case number: 726026 5 October 2020
1 Determination overview
1.1 Complaint
The complainant holds a business credit card (the card) with the financial firm.
On 29 August 2018, the complainant paid a merchant (the merchant) an amount of
$11,039.19 (the disputed transaction) for goods and services. He says he did not
receive the goods and services that he paid the merchant for.
On 9 April 2020, the complainant reported the disputed transaction to the financial
firm and requested a chargeback be raised. He is not satisfied with the financial firm’s
conduct in relation to the chargeback. He is seeking a refund of the disputed
transaction from the financial firm.
1.2 Issues and key findings
Did the financial firm comply with its chargeback obligations?
I am satisfied the financial firm complied with its chargeback obligations and did not
make an error which caused any loss to the complainant. I can find no basis to
compel the financial firm to refund the disputed transaction to the complainant.
The complainant should obtain independent legal advice about his options for any
potential recovery from the merchant separate to this complaint.
1.3 Determination
This determination is in favour of the financial firm.
The financial firm is not required to pay compensation to the complainant or take any
further action.
Determination | Case number: 726026 Page 3 of 6
2 Reasons for determination
2.1 Did the financial firm comply with its chargeback obligations?
The financial firm has chargeback obligations
A chargeback can be raised under reasons specified by the card scheme, which in
this case is set out by the financial firm’s own rules (the rules). AFCA takes the view
that if a cardholder disputes a transaction and a chargeback right exists under the
applicable rules, the financial firm is obliged to:
process the disputed transaction as a chargeback
take care in exercising any chargeback right. This would include using the most
appropriate reason code for the chargeback so that the cardholder’s reasons are
properly represented
properly completing chargeback documentation under the rules
satisfy itself that the response to the chargeback given by the merchant’s financial
firm is a proper response to the situation and consistent with the rules.
The financial firm raised the chargeback out of time
Under the rules, the complainant had 120 days from the transaction date or the date
the goods and services were received, to raise the chargeback with the financial firm.
The complainant says the disputed transaction was authorised on 29 August 2018, in
accordance with an invoice received from the merchant. The invoice was for
renovation works to be performed on a property.
However, the complainant says that even though he authorised the payment on 29
August 2018, he allowed the merchant until 23 July 2019 to complete the works and
provide the goods and services paid for in the invoice.
The complainant did not raise the chargeback with the financial firm until 9 April 2020.
Therefore, the complainant was out of time under the rules, on either of the above
dates. The financial firm agreed to raise the chargeback for the complainant, on a
good will basis, even though the chargeback was out of time under the rules.
The financial firm used the most appropriate reason code
The complainant when he raised the chargeback said:
I ordered and paid for the goods and services in full upfront, gave a lengthy time to the
provider, after all never received anything.
The complainant says he paid the full amount of the disputed transaction to the
merchant for property renovations and paid it upfront to assist the merchant with cash
flow issues. He has been trying to get the work completed ever since.
Determination | Case number: 726026 Page 4 of 6
The financial firm raised the chargeback under the reason code “goods and services
only partially received or not received at all”.
Even though the chargeback was raised well out of time under the rules, I consider
this was the most appropriate reason code for the financial firm to use in the
circumstances.
The merchant responded to the financial firm
I have reviewed the correspondence provided between the parties to the dispute. The
merchant informed the financial firm that the work had been performed as invoiced,
was authorised by the complain ant’s wife and subsequently the property purchase
was settled on 23 July 2019.
In summary, the merchant responded to the chargeback request by saying:
the disputed transaction was for amendments to drawings (for the property
renovations) and electrical updates
the amendments were approved by the complainant
the amendments were confirmed as 90% completed as of 29 August 2018, and
the remaining amendments were later completed once the site was secure.
The merchant also provided supporting invoices and emails to demonstrate its
position.
The financial firm reasonably accepted the merchant’s response
The financial firm informed the complainant of the merchant’s response and
supporting information on 8 May 2020. The complainant was advised he should go
back to the merchant to clarify if anything was still in dispute in accordance with the
rules.
The complainant was dissatisfied with the financial firm’s decision to accept the
merchant’s response , and the financial firm requested further clarification from the
merchant.
A further letter was sent to the complainant on 6 July 2020 by the financial firm,
informing him that it was unable to reverse the disputed transaction. The complainant
sent further information, including photographs to the financial firm. On the 30 July
2020, it acknowledged the information but that its decision was to continue to accept
the merchant’s response , which it considered reasonable.
I consider it is not the financial firm’s role to conduct a complete review of the works
performed by the merchant. The financial firm is not an electrical or building expert.
The complainant accepted the merchant’s quotation for the works to be performed
and authorised the payment . The financial firm was entitled to accept the merchant’s
response in these circumstances.
Determination | Case number: 726026 Page 5 of 6
Any dispute the complainant has with the merchant about the goods and services is
more appropriately dealt with in another forum. The financial firm was not required to
arbitrate the dispute about the itemised goods and services, only be satisfied that the
merchant provided an itemised invoice and reasonable explanation about what work
was performed by the merchant. I am satisfied there was sufficient information
provided by the merchant for the financial firm to make this assessment.
I consider that on the available information, the financial firm has acted reasonably in
accepting the merchant’s response to the chargeback claim.
The financial firm met its chargeback obligations
On the available information, I am satisfied the financial firm:
raised the chargeback claim for the most appropriate reason (goods and services
not received)
accepted the chargeback well out of time on a good will basis
completed chargeback documentation
considered information from the complainant
confirmed the response from the merchant and that the explanation provided by
the merchant was reasonable
requested further information from the merchant as required.
The financial firm was not qualified to assess the scope of electrical and building
works performed on the property. It was required to comply with its chargeback
obligations only, which I am satisfied it did.
The financial firm was not required to do any more to assist the complainant to seek a
chargeback for the disputed transaction in these circumstances.
The complainant is liable for the transaction
AFCA can only award compensation if we are satisfied that the financial firm’s
conduct caused the complainant loss or damage.
The complainant has not been happy with the goods and services provided by the
m erchant. However, he accepted the merchant’s quotatio n and authorised the
payment. He should seek his own independent legal advice about any potential action
he may have against the merchant, if he is of the view that outstanding works are still
to be perf ormed under the merchant’s invoice .
As the financial firm did not make any error or breach an obligation that caused any
loss to the complainant, I can find no basis to compel the financial firm to refund the
disputed transaction.
Determination | Case number: 726026 Page 6 of 6
3 Supporting information
3.1 The determination is made under the AFCA Rules
This complaint has been determined based on what is fair in all the circumstances,
having regard to factors such as legal principles, good industry practice, codes of
practice and previous decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All material provided has been reviewed and considered.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues which are
considered directly relevant to the outcome only.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.