Project manager fees not covered under storm building claim

FirmSuncorp Group
Decided2020-12-22
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$19,707
Non-financial loss$3,000
Amount claimed$50,000
SourceAFCA PDF

Summary

Storm claimants sought about $50,000 in project manager fees under the policy's rebuilding costs cover. AFCA found the fees not shown to be reasonable and necessary, but ordered an additional $19,707.14 building settlement (including the insurer's $7,390.14 offer and a 10% contingency) and $3,000 non-financial loss.

Professional fee cover applies only to reasonable and necessary costs, and the complainants did not show the project management services required professional skills.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 725752 Financial firm AAI Limited Determination | Case number: 725752 Page 2 of 6 Case number: 725752 14 December 2020 1 Determination overview 1.1 Complaint The complainants lodged a claim for storm damage to their property with their insurer, the financial firm (insurer). The insurer accepted the claim. However, following concerns with the insurer’s contractors, the complainants engaged a project manager (N) to assist with the claim and repairs. N did so. The insurer dealt with N, following which all outstanding claim related repairs and other losses have been settled. The remaining issue is N’s fees. N has charged around $50,000 for his services. The complainants say this is payable under the additional feature for ‘Other repair/rebuilding costs’. The insurer disputes this. The insurer says N’s costs does not meet this provision and is otherwise not covered by the policy. 1.2 Issues and key findings Is the insurer liable for N’s fees ? No. The available information does not show N’s fees are covered by the policy. Therefore, the insurer’s offer to contribute $7,390.14 is fair. How should the building claim be settled? The insurer should pay an additional $19,707.14 i n full and final settlement of the building claim. This includes a 10% contingency on the building repairs and the $7,390.14 contribution to N’s fees. Should the insurer pay non-financial loss? Yes. The insurer should pay $3,000 given the complainant’s cla im experience. 1.3 Determination This determination is partially in favour of the complainant. The insurer should pay $19,707.14 in full and final settlement of the building claim. The insurer should pay $3,000 in non-financial loss. Determination | Case number: 725752 Page 3 of 6 2 Reasons for determination 2.1 Is the insurer liable for N’s fees ? Policy responds to professional fees if they are reasonable and necessary The relevant provision the complainants are seeking to claim from says: When we are rebuilding or repairing damaged parts of your home, we will pay the reasonable and necessary costs: …  for the services of professionals, such as architects or surveyors, to repair or rebuild at the insured address; As evident, this requires the complainants to establish that the costs were both reasonable and necessary. Necessary is defined by the online Macquarie and Oxford dictionaries to mean: That cannot be dispensed with [Macquarie] Needed to be done, achieved, or present; essential [Oxford] The insurer notes this provision would respond to services that can only be provided by those with specific professional training and qualifications to do so. I would agree. The examples provided refer to architects and surveyors. This plainly refers to their professional skills being utilised when repairing or rebuilding a damaged building. Therefore, i n order to show the costs were reasonable and necessary, the complainants must show N’s services could only be performed by a professional of his skills and experience. At the least, it cannot extend to services that could have been performed by any non- professional, such as the complainants themselves. Information does not show N’s costs fall within the policy coverage The complainants say N’s services were necessary because the insure r and its nominated builder were not adequately managing the hail storm rectification project. N has described his services as project management. I have carefully revie wed N’s invoices. I note the services charged include the following:  meeting and communicating with various contractors on site  review and analysing assessments and roofing reports  communicating with the insurer’s contractors Determination | Case number: 725752 Page 4 of 6  communications with the insurers ‘re: failings by their builder and the builder’s contractors’  communicating with owners  liaising with relevant contractors Much of these services, as well as others not included in this decision, would be activities normally done by an insured. For instance, in most building claims where the claim is cash settled, an insured would be expected to:  meet and communicate with contractors  review reports  communicate with the insurer about any concerns with their contents Further, t here is nothing to indicate that only a professional with N’s skills and experience could perform these services. For instance, an insured would be expected to be able to liaise and communicate with contractors and insurers. In addition, an insured is capable of reviewing quotes and scopes. I also note there is no evidence to show these particular complainants were incapable of doing these activities. I appreciate N’s engagement assisted them in managing these tasks, and reduced the stress associated with this type of claim. However, I do not accept this shows, or means, it was both reasonable and necessary for them to engage a professional in N ’s field to complete these activities. Therefore, I am not persuaded N’s fees falls within this provision. Insurer’s offer is fair The insurer has agreed to pay an additional $7,390.14 for supervision costs. This was on top of th e complainants’ actionable quote from E. The complainants note that N’s services extended beyond this. However, for reasons explained, I am not persuaded the complainants have shown N’s costs fall within the policy coverage. Many of the activities provided appear, on the face of it, to be works that can be done by an insured or a non-professional. Further, I am not satisfied the complainants have shown:  what specific activities, if any, N performed that could only be done by someone with N’s professional skills and experience, and  how much these activities costed. The complainants have said that N was able to save the insurer more than the fees charged. This cannot be confirmed as there is no evidence to show what the cost would have been if N had not been engaged. Therefore, after careful consideration of all the available information, I accept the insurer’s offer of $7,390.14 is fair in all the circumstances. Determination | Case number: 725752 Page 5 of 6 2.2 How should the claim be settled? Insurer should add a 10% contingency A case manager issued a preliminary assessment on this dispute. She awarded a 15% contingency for the building cash settlement. This would result in an additional payment of $18,475.35. The insurer had accepted the preliminary assessment. However, after t he complainants rejected the preliminary assessment, the insurer said it has paid for variations and the contingency should be reduced. The complainants say the carpets and blinds should have been included in the contingency as it is in the builder’s scope . The insurer correctly noted these are contents. Having considered these circumstances, I agree with the insurer that 15% is too high. The insurer has paid for variations. Normally, a contingency is to include possible variations in the works. Further:  there is no evidence to show there have been other variances, and  the insurer has paid out based on actionable quotes. Given this, I consider it fair that the contingency be reduced to 10%. Further, I agree this should be limited to the building repairs. This is because a contingency normally applies to building repairs, not contents. Insurer should pay $19,707.14 in full and final settlement of the claim Accordingly, after careful consideration of all the available information, I accept it is fair in all the circumstances the insurer should pay an additional $19,707.14 in full and final settlement of the claim. This includes the $12,317 contingency and the insurer’s offer to pay $7,390.14 towards N’s fees. 2.3 Should the insurer pay non-financial loss? Insurer should pay $3,000 The case manager awarded $3,000 for this. This was based on the fact the male complainant was required to prevent further damage to the house by getting to the roof to seal cracks, lay tarps and weigh them down. As a result, he suffered a back injury. Both complainants also say their physical health and safety were compromised, as well as their mental health. The insurer accepted the case manager’s assessment for non-financial loss. Determination | Case number: 725752 Page 6 of 6 The complainants say this should be increased to $5,000 given the stress and inconvenience of not being compensated in full for N’s fees . I do not agree. The reason the complainants are not being compensated is because N’s fees are not covered by the policy. I agree with the case manager that the complainants have suffered an unusual degree of inconvenience and stress in the early stages of the claim. Given this, and considering our conservative approach, I also agree the award of $3,000 is fair in all the circumstances.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.