Determination 723581

Cash settlement amount for building damage

FirmSuncorp Group
Decided2021-05-25
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$149,860
Non-financial loss—
Amount claimed$342,520
SourceAFCA PDF

Summary

The insurer offered a cash settlement of $115,277.10 for leak-related building damage, and the complainants sought $342,519.52 based on their builder's quote. AFCA ordered payment of $149,860.23 in full and final settlement, including a 30% contingency for possible footing repairs.

A cash settlement removes the insurer's workmanship guarantee, so the settlement must be fair and include a substantive contingency for uncertain footing repairs, while the insurer's quotes were preferred over the builder's unexplained scope.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 723581 Financial firm AAI Limited Determination | Case number: 723581 Page 1 of 7 Case number: 723581 21 May 2021 1 Determination overview 1.1 Complaint The complainants lodged a claim with the financial firm (insurer) in June 2019 for movement damage to their investment property. This followed an escape of liquid from stormwater pipes. The insurer accepted the claim. The insurer says before it can quantify and pay for the repairs, there needs to be a drying period. However, water is continuing to pool under the house and the drying period cannot start until the source of water ingress is found and addressed. Since lodging the complaint with AFCA, the complainants say they repaired the stormwater pipes and now want the claim finalised. The insurer agreed to cash settle the claim. The complainants disagree with its offer and say it does not include the repair of structural areas of the property. The complainants seek the insurer to settle their claim based o n their repair quote. 1.2 Issue and key findings Is the insurer’s offer fair? It is fair for the insurer to increase its current offer of $115,277.10 by 30% ($34,583.13) to include allowances for:  the possibility the foundation and footings requiring repair after a drying out period had finalised  such repairs are likely to be substantive  the transfer of risk and loss of the lifetime guarantee That brings the total settlement to $149,860.23. 1.3 Determination This determination is partially in favour of the complainants. The insurer must pay $149,860.23 in full and final settlement of this dispute . Determination | Case number: 723581 Page 2 of 7 2 Reasons for determination 2.1 Is the insurer’s offer fair? Parties disagree on scope of works and cost of repairs After the insurer accepted the claim, it initiated a drying period to establish the appropriate scope of works (SOW) for the necessary repair. The parties disagree as to the adequacy of the insurer’s SOW for settlement of the building damage. The insurer offered a cash settlement of $115,277.10 based on repairer BB’s SOW and quotes. The complainants are not confident BB’s quote reflects the total cost required to repair the property. The complainants want the insurer to cash settle them in accordance with their builder’ s (JL) quote, which is higher than BB’s quote. This quote totals $342,519.52 and excludes mark-up and GST. The insurer says some of the disputed damage is not claim related. Insurer must settle claim fairly The product disclosure statement (PDS) says the insurer may choose whether to repair, rebuild, pay what it would cost to repair or rebuild or pay the sum insured for the property. The insurer must exercise this discretion fairly and, when making a cash settlement, the amount must be fair. It is also important the cash settlement be based on a quote which is actionable by the complainants given the insurer does not intend to repair the damage. Further, when the insurer repairs the building, it guarantees the workmanship and the quality of materials. This means, it will rectify any issues related to poor quality workmanship or materials. A cash settlement means the insured gives up this guarantee. All the risk of the work transfers from the insurer to the insured , including the risk of additional unforeseen damage and further work required once repairs commence. In these circumstances, it is fair an additional allowance be included in the cash settlement amount. The insurer prefers to cash settle the claim. The insurer says repairing the property would result in a rebuild and it is unable to warrant the works given the pre-existing and unrelated issues, such as the poor drainage at the property. The complainants also prefer a cash settlement, as the insurer is unable to guarantee the repair. The panel considers it is appropriate for the claim to be cash settled. Determination | Case number: 723581 Page 3 of 7 Parties disagree about footings The complainants submitted a quote from builder JL in the amount of $342,519.52. The insurer obtained the following quotes from BB to repair the claim related damage:  building repair for $87,166.01  carpet replacement for $6,435.69  restoration of property for $21,774.79 The complainants say the reports from the insurer’s soil expert SE and engineer HE, indicate there are structural issues with the footings. However, BB’s SOW does not include allowances for any structural repairs. The insurer says the building does not require underpinning, but rather the existing stumps will be suitable for reuse. The insurer says there is no evidence the building requires demolition or that it is required to settle the claim over and above its current offer. Having reviewed BB’s quotes, the panel confirms no allowance has been provided for replacement of stumps and footings. In the panel’s view, BB’s quotes cover most of the identified damage. Further, the basis of JL’s SOW has not been provided . In addition, there is no accompanying report or explanation to support the inclusion of items in JL’s SOW. The panel accepts BB’s quotes can be relied upon to form the basis of the claim settlement. This is because the quotes have been carefully determined following a SOW from the insurer’s building consultant QT and engineering assessment from HE. Notwithstanding this, further regard needs to be given to whether the footings also need repairs and, if so, whether this should be included in the settlement of the claim. A substantive contingency should be allowed The insurer appointed its soil experts SG, SE and engineer HE to investigate the adequacy of the footings and foundations once the source of leak is identified and addressed. A summary of their opinions can be found in section 3.3 below. In brief, both SG and SE agree there may be concerns with potential gradual settlement of footings and bearing capacity of silt after the drying period. SE recommends strip footings to be underpinned. HE says the existing stumps will be suitable for re-use and the footings may continue to experience seasonal movement from seasonal wetting/drying after the effects of the leaking service pipe have been removed. The panel is satisfied a drying period needs to occur to ascertain if the footings are adequate or would require repairs or replacement. The soil experts’ view has been Determination | Case number: 723581 Page 4 of 7 strong that the potential of heave or shrinking of the footings are unknown until such time the source of leak is addressed and dries out. However, given the age of the claim, and the inability of the parties to stop the subfloor from being affected by water, it is fair for the complainants to seek a cash settlement to resolve this matter. Further, the panel considers it is fair a substantive contingency should be allowed given:  the uncertainty about whether the footings and foundations should be added to the settlement,  any such costs are likely to be substantive, and  the final cost is also uncertain given the current SOW may not reflect the actual works required at the end of the drying period. In this regard, the panel is satisfied it is fair in all these particular circumstances that the insurer pays a further 30% of the cash settlement already offered (that is, $34,583.13 in addition to $115,277.10). This is to address the real possibility that at the end of the drying period, repairs to footings may be required and there is uncertainty as to the final scope of works and cost of repairs. This brings the total cash settlement for building repairs to $149,860.23. Interest is not payable given this should be based on current rates. Determination | Case number: 723581 Page 5 of 7 3 Supporting information 3.1 Process AFCA’s approach to this complaint This complaint has been determined based on what is fair in all the circumstances, having regard to the legal principles, applicable industry codes or guidance, good industry practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the parties. Each party has had the opportunity of addressing any issues raised. All information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. Commentary in this determination is restricted to those issues considered relevant to the outcome. This matter was determined by a panel Due to the nature of this dispute, it has been referred to a panel for determination. The panel comprises the lead ombudsman, a member with significant experience in consumer and small business advocacy and a member with extensive experience as an industry expert. How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred . If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant terms of the policy Record Key points How we settle your claim We choose how we settle property claims If we agree to pay a claim for loss, theft or damage to your property, we will decide if we will:  repair damage to your property;  rebuild your property;  pay you what it would cost us to repair or rebuild your property;  pay you the sum insured for your property;  … If we rebuild (or pay you what it would cost us to rebuild), we will do so Determination | Case number: 723581 Page 6 of 7 Record Key points on a ‘new for old’ basis. If we repair (or pay you what it would cost us to repair), we will at our option repair on a ‘new for old’ basis or repair to a similar condition to what your property was in before the loss or damage occurred. 3.3 Relevant expert reports Record Key points Insurer’s soil expert ( SG ) Report 24 December 2020  The depth of the existing stump footings is unknown.  It is not possible to quantify the bearing capacity available.  We do not anticipat e signific ant heave or shrink of the stump footing s due to wetting/ drying or the clays .  It depends on the whether the drainage has been addressed as to whet her strip footing movement (shrink or swell) will occur.  If the cause of the excess water is found and addressed, then a gradual settlement of the footings can be anticipated as the underlying clays gradually dry out.  If the source is not determined and the wat er table remains , no heave/shrink is antic ipated.  While the strip footings may continue to perform adequately under current conditions, if the wat er issues are addressed some movement can be anticipated. Insurer’s soil expert ( SE ) Report 7 January 2021  A bnormal moisture conditions in the sub - floor due to a leaking pipe which has not been fixed.  The silty clay in the subfloor area shows no signs of abnormal moisture conditions. Recommends a 24 - month drying period after the leaking water pipe has been fixe d. After which, a secondary soil test is required to confirm the silt has dried out in the subfloor area and if pad footings can be re - us ed.  Due to the lack of bearing capacity in the clayey silt and its tendency to weaken during heavy rainfall, we recomme nd the strip footings be underpinned.  I f the bearing capacity of the silt in the sub - floor does not increas e after the drying period, the dwelling may need to be re - stumped. Insurer’s engineer ( HE ) Report 14 January 2021  Minimal movement of the stumps and strip footings expected during the drying out period.  The bearing capacity of the silt on which the stumps are founded will increase once the soil dries.  It is expected that once the soil dries the existing stumps will be able to be re - used .  Base d on the soil report by SE , the concrete strip footings may continue to experience seas onal movement, even aft er the effects of the leaking service pipe are removed, as they are subject to seasonal wetting/drying and are founded in silt. Insurer’s plumber ( LP )  The die test to the suspended stormwater system was carrie d out on Determination | Case number: 723581 Page 7 of 7 Record Key points Rep ort 21 December 2020 17 December 2020 and indicated no leaks.  While carrying out the die test, we noted damage to the pipework of the external tap at the rear of the property.  While on site, we capped this off and returned to test the associated pipework.  The test indicated no leak or drop in pressure.