Home / IAG / Determination 720694

Determination 720694

storm damage claim scope, loss of rent and service delays

FirmIAG
Decided2021-11-10
ProductGeneral Insurance · Other general
OutcomeFor the complainant in part
Amount awarded$11,289
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for storm damage to a rental property and related loss of rent and delay. AFCA found the insurer liable for water damage repairs plus 20% contingencies, $4,000 for contents, loss of rent of $7,288.65 with interest, and $1,000 for service delays, but not for subsidence damage.

Policy covers accidental storm damage, but damage progressed from long-term subsidence and complainant-caused delays, so the insurer is liable only for water damage from the storm and the service failures warrant compensation.

Issues

Subjects and remedies

health or medicalhome or building damagenatural disasterthird party authoritypay claimpay compensationpay interestpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 720694 Financial firm Insurance Australia Limited Determination | Case number: 720694 Page 2 of 11 Case number: 720694 9 August 2021 1 Determination overview 1.1 Complaint The complainant lodged a claim on 28 January 2014 for damage to her property she says was caused by a storm event on 8 October 2013. The financial firm (insurer) accepted the claim, repaired the roof in a make safe and made an offer of settlement for internal damages. The offer was rejected by the complainant who obtained independent quotes in varying amounts. To resolve the complaint, the complainant seeks to be indemnified for building damage, fixed contents, loss of rent and compensation for delays. 1.2 Issues and key findings Has the insurer assessed the full extent of its liability in relation to the claim? No. The insurer has assessed the full extent of its liability in relation to the scope of works. This is because on balance, it has shown it is liable only for cosmetic damage to the property as it existed in 2015. However, the insurer has not accounted for contingencies or potentially concealed damage caused by the insurable event. It has also not accounted for damaged contents including carpets, nor addressed loss of rent. Due to the above, it is considered fair in the circumstances for the insurer to settle the complainant the current cost of repair based on the 2015 scope of works and adding a margin for contingencies and damage potentially concealed at the time of the original scope. In the interest of bringing finality to the matter, the insurer should also settle loss of rent as outlined in section 2.1 of this determination. It is fair that the insurer pays the sum of $4,000 for the damage to the contents. Is the complainant entitled to compensation for service issues and delays? Yes . The insurer’s customer service and its review of the complainant’ s service concerns were, on balance, below the standard expected of an insurer. The insurer acknowledged service delays and agreed to cover loss of rent as a result. The panel also notes significant delays caused by the complainant. Although outside the complainant’s control, these delays cannot be attributed to the insurer’s actions. The Panel awards $1,000 for non-financial compensation Why is the outcome fair? The insurer has not accounted for contingencies or potentially concealed damages inside walls and the roof cavity at the time of the original scope. It is therefore fair for the insurer to increase the offer of settlement accordingly. The events the complainant has described are unfortunate. On review of the complaint however, the panel is unable to attribute the complainant’s hardship to the insurer’s actions and the insurer has assessed the claim correctly based on the expert material provided, acted in line with good industry practice, and complied with applicable industry codes. As such, it Determination | Case number: 720694 Page 3 of 11 would not be fair to require it to compensate the complainant beyond the payments noted above. 1.3 Determination This determination is partially in favour of the complainant. The complainant is to obtain an actionable quote based on J’s 2015 scope of works. The insurer is to then settle that amount plus 20% for contingencies. The insurer is to pay $4,000 for damaged contents. The insurer is to pay loss of rent in the amount of $7,288.65 plus interest calculated from 9 May 2020 for reasons set out in section 2.1 of this determination. The insurer is to pay the complainant $1,000 non-financial compensation for service issues and delays. 2 Reasons for determination 2.1 Has the insurer assessed the full extent of its liability in relation to the claim? Policy covers storm damage The complainant held a Rental Protection Plus policy with the insurer at the time of the claimed event and says all damage was caused by the October 2013 storm. Section 1 of the policy covers accidental damage to building and contents subject to certain terms and conditions. The policy says: We will cover your buildings and your cont ents for any accidental damage or accidental loss including that caused by:  Landslide or subsidence but only if it occurs within 72 hours after one of the following: - storm, flood, rainwat er or wind - earthquake - explosion - liquid that escapes from a fixed pipe or something attached to a pipe, fixed gutter, fixed tank or a drain. This cover also applies to gates, fences or retaining walls that are attached to, and are part of, the structure of your buildings.  Storm, flood, rainwater or wind … Exclusions …we do not pay for loss or damage caused by:  erosion  rust, corrosion, gradual deterioration, depreciation, wear or tear  a defect in an item, faulty workmanship, structural defects or faulty design What you must do when you make a claim Determination | Case number: 720694 Page 4 of 11 You must make your claim as soon as possible after you suffer a loss. If you do not make it within 30 days, we may reduce what we pay you by an amount to take into account of any disadvant age we suffer by the delay. You must also: • take all reasonable steps to stop any further los s from occurring The insurer agrees the complainant established a valid claim and accepts damage caused in the initial storm event. However, the insurer denies liability for damage it says was caused by ground movement. It also denies liability for the progression of damage it says was caused by the complainant delaying claim lodgement, and long periods of time during which the complainant did not respond to the insurer’s attempts to pursue a resolution to the claim. Expert reports indicate long term ground movement and subsidence On claim lodgement, the insurer arranged a make safe. The accompanying report dated 24 February 2014 says approximately 40 tiles were dislodged, and/or broken during a wind storm. This allowed water to enter the property causing internal damage. The report noted the house was very old and the wiring was in poor condition. Approximately 20 tiles and a fan required replacement. The trade provided colour photographs showing the damaged tiles and overall condition of the roof. The insurer then appointed builder J to investigate the cause and extent of the damage. This attendance took place on 15 February 2014 and J met with the tenant who advised the roof had been leaking since at least October 2013, and electrical shortages were a regular occurrence. J noted the property had large cracks on internal and external walls due to long term subsidence and bowing to timber floor boards in bedroom 2 caused by long term water ingress. The cost of repair for resulting damage was estimated at $7,015.80 including margins and GST. J said the property was in very poor condition overall. It was acknowledged the concrete roof was likely damaged in the October 2013 event, as was water damage to internal ceilings and walls. It also said the delay in lodgement would have caused the damage to progress significantly. Colour photographs were provided to support J’s conclusions. J noted that make safe was not required, despite the fact that the roof tiles were missing. The complainant says that more rain entered the property before the make safe occurred on 24 February 2014. The complainant disputed the insurer’s findings and obt ained in independent quote from R dated 12 August 2014 in the amount of $94,450 with additional costs to be determined. However, this document does not comment on causation. As such, the panel is unable to say which items may be attributable to the storm event or subsequent water ingress. The insurer then appointed engineer M who attended 13 January 2015. M met the complainant at the property and was informed she first became aware of the damage in February 2014 when she drove past the house and saw the broken roof tiles. The complainant and real estate agent both say the tenant did not notify either about damage prior to this date. In the absence of information to the contrary, the panel accepts the complainant likely first became aware of the damage in February 2014 causing the delayed lodgement. Determination | Case number: 720694 Page 5 of 11 M said the property was constructed sometime between the 1950’s and 1960’s with the complainant purchasing it between 2000 and 2005. Overall, the property appeared to be in a poorly maintained and soiled condition The following damages were noted:  soiled carpets  cracks to internal and external walls, and cornices  water damage to ceilings and internal walls  sunken floors  movement to external gables, stumps and subfloor  various non-storm related damages such as impact damage to doors Overall, M attributed all movement related damage including stumps, flooring and building cracks to long term subsidence primarily caused by unpaved external areas and insufficient drainage. It said minimal damage was caused by water ingress from tiles damaged in a storm event. The insurer says the claim was closed for extended periods of time due to non-response from the complainant. There appears to be no correspondence from the complainant to the insurer between M’s report and a report from the complainant’s engineer LP dated 16 May 2019. The insurer has provided copies of emails sent to the complainant during this time to follow up the claim. The complainant’s engineer LP conducted a visual non-invasive inspection to assess the cause and extent of the damage. It is important to note, at the time of this report the damage had been progressing for almost 6 years. LP noted the following damage:  cracking to internal concrete walls, throughout corners on a continuous basis  sloping and subsided floor directed toward the northwest corner of the bedroom at the rear of the property  cracking and displacement to external concrete walls, particularly at control joints  water damage/seepage into habitable areas  displaced floor boards and jammed doors  weakened/broken tiles in the bathroom attributable to wall movement. LP estimated the property at 65 years old and found paving to the southern half of the yard, with the northern half being unpaved. LP noted remedial works had been carried out to the roof but said water ingress had occurred during periods of rain from October 2013 to February 2014. LP said: The supplementary information provided to date indicates that the significant wall cracking during the duration that the roof as exposed due to the dislodged roof tiles. The J report confirms that water had entered the property following roof damage. Lastly, LP recommended a return inspection two-years after repairing the damage to …determine the integrity of key matters following remediation. Given LP’s attendance was almost 6 years after the event, the inspection was non -invasive, and LP recommended attendance 2 years after remediation to verify if damage would re- occur, the panel finds it difficult to lend more weight to this report than those completed around the time of the event. The complainant also provided a quote from MZ dated 26 April 2020 in the amount of $119,400. This quote does not comment on causation. Determination | Case number: 720694 Page 6 of 11 The insurer commissioned a further report by engineer RC dated 28 June 2020 and provided it with all previous reports. RC also found separating cornices, gaps in joints, uneven floors and water staining on ceilings, walls and carpet. RC attributed the damage to the following causes: Damage to precast concrete wall Joints:  subsidence to the north western corner  rusting of the precast links Stains to ceilings, cornices, walls and carpet in all bedrooms  Storm water entering through roof tiles Subsiding stumps in north west corner  Lack of civil drainage to the northern corner where the subsidence occurred  Possible leaking plumbing or disconnected downpipe RC also observed:  Most of the missing tiles were replaced during the make safe  Effective civil drainage existed to the south, but was not present to the north or most of the west  The soil level surrounding the dwelling was higher than the subfloor along the north and west sides promoting stormwater runoff being directed under the dwelling  Many issues such as deep growing grass in the northwest corner, the gutter to the front of the dwelling was rusted through, roof pointing was missing, and major cracking was identified throughout the property RC said the property was vacant and should remain so due to the northern roof structure being close to failure due to subsidence. It said repairs may not be warrantable without drainage upgrades. RC was provided with a copy of a condition report dated 31 August 2012 which indicated walls, doors and ceilings were clean and undamaged at that time. A statutory declaration was provided by the real estate agent who completed the inspection saying the property showed no signs of cracks at that time. However, no photos were provided, the tenant had not signed the document and several other issues bring the report in to question. It is also important to note a condition report from a real estate agent is unlikely to reveal any underlying issues as would be expected of an actual building report. RC estimated around 940lt of water entered the property on the eastern side between the event and the replacement of tiles approximately 4 months later. RC believed the subsidence in the north west corner was due to the lack of civil drainage causing soils to become saturated leading to localised bearing failure and cyclic ratcheting effects. This caused the stumps to sink. RC said:  Corrosion of the wall reinforcements caused cracking and spalling in the concrete walls.  Subsidence of the subfloors likely occurred due to the precast wall panels dropping.  Although the roof tiles were repaired in 2014, photos show cracking widened considerably between that time and RC’s attendance. This indicates the original event did not cause or likely contribute to the cracks as movement has continued after the stated cause of the event was remedied. In conclusion, RC said the cause of subsidence and building movement which caused the concrete wall panels and floor to drop was likely poor or non-existent civil drainage. Determination | Case number: 720694 Page 7 of 11 It said movement would likely continue in the absence of upgrades to the civil drainage and possible repairs to the storm water system. Lastly, RC said J’s scope of works for aesthetic damage caused by storm water ingress was accurate and should be undertaken. No costing was provided at that time. The complainant arranged a report by property inspector S who attended on 20 October 2020. S noted the defects and damages as per previous reports and concluded: Major defect was caused by water entering the subfloor from the broken and missing roof tiles (approx 40) over the period that they were not repaired. There was 2 major storms, the first one did the damage to the tiles and then the second storm, the roof still had not been repaired. As the photos show there was large amounts of water running down all three bedroom walls over this time. Photos have shown that yes there was some small cracking in the concrete wall joins before, but not hing like the 30mm there is now, that makes this house uninhabitable. In my opinion the storm damage made this uninhabit able as it stands today . The complainant also provided a quote from builder D in the amount of $219,160 plus GST. This quote does not comment on causation and is undated. Conclusions It is not in dispute an event covered by the policy caused damage to the property. That is, tiles were blown off or damaged in a wind event and storm water was able to enter the property causing damage to ceilings, walls, cornices, flooring and carpet. The complainant also says ground movement and building cracks occurred due to this water ingress, which occurred between October 2013 and February 2014 when the tiles were replaced by the insurer. Movement has continued since that time and the property is now uninhabitable. Many expert reports have been provided by the parties. Broadly speaking, the insurer’s reports favour the insurer, and the complainant’s reports favour the complainant. The panel is of the view reports obtained around the time of the event are, on balance, likely to be more accurate. On review of the reports, the panel accepts the property has continued to move and damage progress in the years since the event. Given the passage of time and the progression of damage, the panel also accepts it would become increasingly difficult to say with certainty which damage came first. This is because movement appears to have widened gaps in the walls and created more openings for water and moisture to enter. In the 8 years since the event, and due to the many events likely to have occurred during that time which would have been exacerbated by movement related openings and multiple seasons without remediation being carried out, the damage has progressed well beyond the point of being able to determine the extent of damage caused by the original event itself. With the aid of colour photographs s upplied by each of the experts, it is the panel’s view the subsidence and widespread cracking is unlikely to have been caused by 4 months of water ingress. Insurer liable for internal repairs relating to water damage Although the insurer is not considered liable for cracking attributable to subsidence and ongoing movement, it has agreed to pay for water damage per J’s scope and quote provided in 2015. That is, damage to ceilings, cornices, walls, floors and carpets. It is not however liable for the progression of such damage caused by any delays instigated by the complainant. The issue of delays is dealt with in section 2 of this determination. Determination | Case number: 720694 Page 8 of 11 On consideration of the materials, the panel considers it fair in the circumstances for the insurer to pay for the cost of repairs as set out in the scope provided by J in 2015. However, given the insurer cannot warrant the repairs, the quote accompanying J’s scope is unactionable. In order to bring finality to the claim, the complainant may provide an independent, actionable, quote based on J’s scope of works for settlement. An additional 20% is to be added to the settlement for contingencies and damage that may have been concealed behind walls and inside the roof cavity at the time of J’s attendance. This outcome is considered fair because the insurer is not considered liable for the progression of damage caused by events not covered by the policy. Given the complainant’s reports did not ultimately provide a more favourable outcome, the insurer is not required to reimburse the cost of those reports. Insurer liable for contents The insurer confirmed water damage to carpets, walls, ceilings and cornices throughout the home. Although the property was tenanted, the insurer is still liable for fixed content items such as carpets and blinds The insurer says that there was no damage to the contents however given the ingress of water the Panel is of the view that water damage must have occurred. Due to the effluxion of time it is not possible to quantify the damage to the carpets and blinds. However, the Panel accepts that there was likely to have been some damage to the floor coverings and blinds in bedroom 1, bedroom 3 and the lounge room. This is based on M’s report from 9 January 2015 where he noted soiled and general stains to the carpets in those rooms. The photos provided do not establish whether it was water staining. It is fair and reasonable that the insurer pays the sum of $4,000 in final settlement of this part of the claim Insurer liable for loss of rent The policy covers rent default. Specifically, it covers rent default where a tenant leaves before the rental period ends for up to 6 weeks including a 2-week rental period. The policy also covers loss of rent caused by an insurable event up to the sum insured. In this case, the loss of rent sum insured was $13,300. The insurer agreed the property was uninhabitable and also acknowledged some claim delays early on. It also acknowledged the tenants left before the end of the lease due to the property damage. The insurer’s claim file notes also indicate loss of rent was accepted. However, no information has been provided to show how much was being covered or if any payment was made to the complainant. A rental agreement was provided showing rent to be $1,173 per month, or $269.95 per week. In its claim file notes, the insurer wrote it had received the complainant’s rental documents on 9 May 2020. However, loss of rent was not addressed in the notice of response. On further review of the notes, the insurer agreed to cover loss of rent from the date the tenant vacated the premises until the date of the decision letter 4 February 2015 due to insurer delays. It is unclear when the tenant vacated. However, the tenant was still at the property when J attended on 19 February 2014. The rental ledger indicates rent was paid up to 31 July 2014. Determination | Case number: 720694 Page 9 of 11 As such, the insurer is liable for loss of rent from 31 July 2014 to 4 February 2015 or 13 October 2014 to 4 February 2015 or 27 weeks. Based on the above, the insurer is to pay the complainant $269.95 x 27 weeks = $7,288.65 plus interest. Interest is to be calculated from 9 May 2020 as this is the date the insurer confirms sighting the rental documents. 2.2 Is the complainant entitled to compensation for service issues and delays? Yes. The insurer’s customer service and its review of the complainants’ service concerns fell short of an acceptable standard, caused significant upset and inconvenience, which warrants compensation. AFCA can award compensation in limited circumstances AFCA rules allow the payment of compensation (capped at $5,000) for non-financial loss (stress and inconvenience). AFCA may decide an insurer should compensate a complainant for such loss only where there has been  an unusual amount of physical inconvenience  time taken to resolve a situation  interference with the complainant’s expectation of enjoyment or peace of mind. The inconvenience warrants non-financial loss The Panel reviewed the available evidence to determine how the insurer handled the claim and the effect of its conduct on the complainants. Firstly, it appears the initial claim decision was made within a timeframe which was normal for a claim of this nature given the extent of the damage and overall condition of the property. The insurer arranged a make- safe and initial builder’s attendance in a reasonable time frame. The Panel has noted that there was a short delay between the attendance of J and the make safe, however it is unlikely that further damage would have occurred, given that the roof tiles had been missing for approximately four months before the insurer was notified. However, the insurer’s internal review of the complainants’ concerns was less than ideal. In addition to disputing the claim denial, the complainants raised customer service issues. Among other things, the complainants said the insurer delayed the claim and, per claim file notes, the insurer agreed on this point. Based on correspondence between the parties, it is also evident the complainant delayed the claim for significant periods of time. An explanation has been provided for these periods of non-response, being health concerns and other issues. While regrettable, the Panel is unable to say the insurer is liable for these delays. It is also noted the insurer failed to provide a response regarding content items and rent loss in its submission. It is also worth noting the complainants’ vulnerability, which might reasonably have prompted a more proactive and prioritised response by the insurer. The Panel considers it fair in the circumstances to award compensation of $1,000. 2.3 Why is the outcome fair? It is fair in the circumstances for the insurer to pay compensation due to delays attributable to the insurer and given the complainant’s personal circumstances which should have warranted a more proactive approach to handling of the claim. Determination | Case number: 720694 Page 10 of 11 Further, given the inconvenience suffered it is fair in the circumstances the insurer pays the complainants a total of $1,000 in compensation for non-financial loss. Determination | Case number: 720694 Page 11 of 11 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A Panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience as a [field of expertise]. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.