Determination 720431
Shed fire repairs delayed and defective; contents settlement
Summary
A customer's shed fire claim was repaired by the insurer's preferred repairers with defects and delay, and he sought contents top-up and compensation. AFCA ordered an independent expert assessment and remediation, payment of any substantiated contents increase, and $2,000 for non-financial loss.
Repair quality and claim handling fell short, but no expert evidence supported a full slab rebuild, so an independent expert assessment was ordered first.
Issues
- Repairs or contractors primary · upheld“The panel accepts the final work is not adequate, given the seal is deteriorating.”
- Claim amount dispute secondary · upheld“The panel considers it is fair the insurer pays any increase to replace the settled contents items, substantiated by the complainant.”
- Complaint handling failure secondary · upheld“Complaints were not responded to by the insurer in the required time.”
- Delay secondary · upheld“The complainant raised delays in repairs of more than six months initially, with ongoing repair quality issues.”
- Misleading conduct secondary · not upheld“The panel is not satisfied the complainant has shown the insurer misled him by not advising of the policy limitation for car parts.”
Subjects and remedies
home or building damagepay claimpay non financial lossreassess claimrepair or rectify
Related
Text of the determination
Determination
Case number 720431
Financial firm Insurance Manufacturers of Australia Pty Ltd
Determination | Case number: 720431 Page 2 of 7
Case number: 720431 23 December 2020
1 Determination overview
1.1 Complaint
The complainant lodged a claim for fire damage to his shed. The financial firm
(insurer) assessed the damage and accepted the claim. It then used its preferred
repairers to repair the shed.
The complainant says the repairs were delayed a nd were not completed to an
acceptable standard. He also says due to the delay in repairs to the shed, the
replacement price for his contents has increased. The complainant also says that at
the time of purchasing insurance, he was misled about the level of cover he would
receive for his contents.
The complainant is seeking the shed to be replaced, additional settlement for his
contents and to be compensated due to his experience.
1.2 Issues and key findings
Has the shed been repaired adequately?
The shed floor has clear workmanship issues. However, as no report has been
obtained by either party to identify the remediation required, it is unclear what needs
to be done.
Therefore, this aspect of the claim should be resolved as set out in section 2.1.
Has the complainant been settled correctly for his contents?
There is no evidence the insurer misled the complainant at the time of policy
inception. If the complainant can show that he has spent more to replace contents
than has been settled, the insurer is to pay the difference. The complainant can
submit to the insurer any additional contents items he did not include for the insurer to
review and consider.
Should the insurer pay the complainant any non-financial loss?
Considering the delay and inconvenience suffered by the complainant due to the
insurer ’ s actions, the insurer should pay $2,000 in non-financial loss compensation.
Determination | Case number: 720431 Page 3 of 7
1.3 Determination
This determination is partially in favour of the complainant.
The issues with the shed should be settled in the manner set out in section 2.1.
The complainant is to submit evidence of any additional cost for the settled contents.
He is also to advise the insurer of any contents items he believe he did not include in
the initial settlement. The insurer is to settle any items fairly.
The insurer is to pay the complainant $2,000 in non-financial loss compensation.
Determination | Case number: 720431 Page 4 of 7
2 Reasons for determination
2.1 Has the shed been adequately repaired?
The complainant has shown issues with the repairs
The complainant has provided photos showing several issues with the repairs
completed by the insurer. Some of these issues have been rectified after the
complainant sought remediation. However, the floor slab remains a main issue.
The complainant has shown photos of a depression in the concrete slab which was
ground down due to fire debris being stuck to the original slab. This was then filled
with a levelling material and sealed. Since the seal was completed, the complainant
had instances of paint peeling and slipping, becoming a hazard for him while
completing work in the shed.
The challenge faced in this situation is neither the complainant nor the insurer has
provided an expert report about the specific issues with the slab and a proposed
rectification method to fix it.
Further assessment is required to establish extent of rectification
During the complaint process, the parties did agree to select an expert to inspect the
shed to identify any remediation required. However, as the insurer did not do this
within the expected timeframe post conciliation, the complainant has instead
requested a full rebuild to remediate the situation and refused the option for an
inspection to occur.
The insurer says due to the Covid 19 related challenges, it was difficult to locate
available experts. The exchanged information shows the insurer provided the
complainant with a list of electricians and engineers.
The panel accepts the final work is not adequate, given the seal is deteriorating.
However, in the absence of any expert opinion to support the complainant’s position,
the panel is not satisfied that a full removal and rebuild of the slab is the most
appropriate outcome.
The insurer is required to engage an expert to assess the shed
The panel considers it is fair in all the circumstances the insurer engages qualified
experts to assess the method and extent of the rectification (if any).
The insurer is to provide the details of three electricians and three engineers for the
complainant to choose from. The chosen electrician and engineer are to undertake an
inspection and to assess any issues, including the slab. This should include a detailed
and itemised scope of works of any rectification works required. The scope of works
should be completed by the engineer after taking input from the electrician.
Determination | Case number: 720431 Page 5 of 7
Within 14 days of the complainant accepting this determination, the insurer is to email
the complainant with the details of the proposed experts. If the complainant is
dissatisfied with the options provided, he may offer at least two experts of his
choosing and the insurer can choose one.
The insurer is to pay the cost of the inspections.
Once an expert is engaged, the insurer is to:
arrange for these experts to complete their inspection and assessme nt of the
damage within 28 days
within 14 days of the inspection, ensure the written report and scope of works are
made available to both parties.
Once this report is available, the insurer is to complete any remediation works
required. This would likely include the removal and storage of any contents in the
shed and their reinstallation once works are completed. Alternatively, should both
parties agree to this, the insurer can cash settle the complainant based on an
actionable quote on the engineer’s scope of works with a 10% contingency for
potential variances and the transfer of risk.
2.2 Has the complainant been settled correctly for his contents?
There is no evidence of misrepresentation at the time of policy inception
The complainant says when he incepted his polic y, he specifically advised the
consultant that he utilised his shed for repairs to vehicles and at no time was he
advised of any limit in the policy for these items. He did provide details of other items
to be insured separately for additional cover and be lieves that he was misled because
the consultant did not advise of the policy limit for car parts.
The insurer has responded to this by advising the policy was taken out in a branch
and the employee who incepted the policy no longer works at the branch. It cannot
therefore get records of the conversation that occurred.
Given the minimal contemporaneous information, the panel is not satisfied that the
complainant has shown the insurer misled him by not advising of the policy limitation
for car parts. The panel also notes there is no dispute he received the policy wording
(PDS). This outlines the coverage it provides and clearly highlights the policy limits.
The insurer is to consider and assess any increase in contents settlement
The complainant has advised that he was settled for his contents quickly. However,
as the repairs to the shed were not completed until much later, he was not able to
purchase replacement items until this was completed. He says this timeframe resulted
in the items being more expensive than he had originally obtained quotes for.
Determination | Case number: 720431 Page 6 of 7
The insurer has agreed to review any additional costs incurred by the complainant.
The complainant has asked for compensation for the time it will take for him to retrace
this information to support his claim.
The panel considers it is fair the insurer pays any increase to replace the settled
contents items. This does need to be substantiated by the complainant. To this end,
the complainant must show he has paid more, in total, for the contents he was settled
for.
The panel is not satisfied the insurer should pay any compensation for the time this
takes. It is the complainant’s responsibility to prove his loss and this does take time
and effort.
Some contents items were not claimed correctly
The complainant says he did not correctly list all the contents items that were lost in
the fire, as he was attempting to minimise the complexity of the contents replacement
process. The insurer has not responded to this concern.
The complainant is to submit to the insurer the items he believes were not included in
the original settlement. This must include prices or quotes for replacement and any
evidence of proof of ownership and value. The insurer is to assess these items.
2.3 Should the insurer pay any non-financial loss compensation?
AFCA may award compensation in certain circumstances
Under paragraph D.3.3 of the AFCA Rules, we may award compensation for
non-financial loss (capped at $5,000) where there has been an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
We take a conservative approach to compensation and expect a complainant to bear
a normal degree of inconvenience during a claim.
The complainant has suffered an unusual degree of inconvenience
The complainant raised several issues during the complaint. This included delays in
repairs of more than six months initially, with ongoing repair quality issues to date. He
also raised complaints that were not responded to by the insurer in the required time .
The complainant says he lost the use of his shed for a significant period and this
impacted his mental and physical health.
It is important to note that some inconvenience is expected after a significant event,
such as the one the complainant suffered. The panel is satisfied however that a lot of
the inconvenience could have been avoided with more astute management of the
claim and complaint.
Determination | Case number: 720431 Page 7 of 7
The insurer is to pay the complainant $2,000 in non-financial loss compensation.