A homeowner disputed the insurer's refusal to cover movement and cracking damage from a 2011 flood and the cash settlement for poor flood repairs. AFCA found the cracking was not flood damage, but ordered a cash settlement with a 20% uplift plus accommodation, and $4,000 for non-financial loss due to unreasonable handling.

Damage consistent with foundation movement and drainage issues was not caused by the flood, while the insurer must fund the rectification of poor repairs with the uplift and its handling caused non-financial loss.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 719393 Financial firm AAI Limited Determination | Case number: 719393 Page 2 of 4 Case number: 719393 11 November 2020 1 Determination overview 1.1 Complaint The complainant lodged a claim for damage due to flooding in 2011 with his home insurer, the financial firm (insurer). The insurer accepted the claim and undertook repairs In 2019, the complainant raised concerns with the quality of repairs undertaken. The complainant also identified movement and cracking damage to the northern brickwork and internal finishes. The insurer agreed to pay for the cost to rectify the poor repairs. The insurer did not accept it was liable for the movement and cracking damage claimed. The complainant disputes the insurer’s position. He wants the insurer to undertake the rectification and to accept the movement and cracking damage. He has also complained about his claims experience. 1.2 Issues and key findings Is the insurer liable for the movement and cracking damage? No. The available information does not show this damage was caused by the flood in 2011. Is the insurer’s offer for the rectification work fair ? Mostly. The insurer should include a 20% uplift to its quote and two days of temporary accommodation. Should the insurer pay non-financial loss? Yes. The insurer’s handling of the claim was unreasonable given poor repairs are evident over eight years after the claim was lodged. The insurer should pay $4,000 in non-financial loss. 1.3 Determination This determination is partially in favour of the complainant. The insurer is not liable for the movement and cracking damage. The insurer should settle the rectification issues as set out in section 2.2. The insurer sho uld pay $4,000 in non-financial loss. Determination | Case number: 719393 Page 3 of 4 2 Reasons for determination 2.1 Is the insurer liable for the movement and cracking damage? Insurer not liable for movement and cracking damage The insurer engaged an engineer (KB) in 2019 to assess the movement and cracki ng damage. KB did not agree that this damage was caused by the flood. KB said the cause was a combination of natural ground movement, brick growth and the construction method (i.e. lack of brickwork articulation/expansion joints). KB also identified site drainage issues at this part of the home. This included the fact the ground slopes towards the home and both a downpipe and an air conditioner discharge water to this area. These issues were also identified by a previous engineer (J) back in 2015. I note that in 2011, an engineer (M) did identify flood damage to the brickwork. This was due to the brickwork bulging outwards with no signs of vertical movement, rotation of lower level brickwork or other movement. This is not the case here. The information shows this cracking and movement is consistent with foundation movement. Therefore, the damage is different to that identified in 2011. It is also consistent with normal ground movement given the issues identified by J and KB, which are unrefuted. Therefore, I accept this damage is not caused by the flood or covered by the policy. The insurer is not liable for this damage. 2.2 Is the insurer’s offer for the rectification work fair? Insurer should add 20% to its quote and include two days of accommodation In a preliminary assessment, the case manager concluded on this issue:  it was fair for the insurer to cash settle the claim given various maintenance issues that needed to be addressed  the insurer’s offer to rectify the poor repairs ($27,469.40) was fair, subject to a 20% uplift The complainant, in rejecting this assessment, said the scope of works does not include temporary accommodation. He noted two days should be allowed given the work to the flooring. Also, the complainant was dissatisfied with the fact he would lose the lifetime guarantee. It appears the complainant does not otherwise dispute the insurer’s scope of works for rectifying the poor repairs. No evidence has been provided to say these scope of works are insufficient. Determination | Case number: 719393 Page 4 of 4 Therefore, I accept the insurer’s offer for these works, excluding the temporary accommodation, is fair subject to a 20% uplift. In terms of the loss of lifetime guarantee, I accept this is an unfortunate consequence to the cash settlement. However, it would be impractical for the insurer to attempt to rectify the repairs. This is because of the maintenance issues required for the property’s foundation movement which would need to be done to ensure the repairs are effective. Further, the insurer cannot be expected to warrant the work of contractors it has not engaged or authorised. For the complainant’s requests of two days accommodation, the insurer has provided no submission addressing this. This appears reasonable given the works to the floor. The insurer is to provide an estimate for the two days of short term accommodation and include this in the cash settlement. 2.3 Should the insurer pay non-financial loss Insurer should pay $4,000 for non-financial loss The preliminary assessment awarded $4,000 for this issue. The complainant did not dispute this aspect of the assessment. The insurer provided no submission disputing this award or the basis of it. Given rectification issues remain outstanding more than eight years after the original claim , I agree the insurer’s handling of the claim is unreasonable. Therefore, the amount of $4,000 for non-financial loss is fair.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.