Determination 717475

Storm damage garage settlement amount and asbestos removal handling

FirmAllianz Australia
Decided2021-08-03
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,000
Amount claimed$64,020
SourceAFCA PDF

Summary

A homeowner disputed the insurer's storm damage settlement for his garage, seeking a full rebuild, and complained about incomplete asbestos removal by its contractors. AFCA found the garage need not be rebuilt but ordered $2,000 non-financial loss compensation for the contractors' poor asbestos removal.

The evidence did not show the storm or asbestos required demolition, but the contractors' substandard asbestos removal caused stress and interference with enjoyment of the home.

Issues

Subjects and remedies

home or building damagenatural disasterpay non financial loss

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 717475 Financial firm Allianz Australia Insurance Limited Determination | Case number: 717475 Page 1 of 8 Case number: 717475 19 July 2021 1 Determination overview 1.1 Complaint The complainant lodged a claim for storm damage under his home insurance policy with the financial firm (insurer). The damage was mainly to the rear wall of his garage which was blown out during the storm. The wall was constructed with asbestos material. Therefore, the insurer arranged for asbestos removal/make-safe shortly after the claim was lodged. Following its assessment, the insurer agreed to cover damage it considered was caused by the storm. The insurer obtained a scope of works and quotes for repairs. A complaint initially arose about the conduct of the insurer‟s contractors who were appointed to remove asbestos from the premises. The complainant says the contractors did not completely remove asbestos from the premises during their initial attendances. Further, despite several subsequent attendances, asbestos has not been properly removed from the premises. The complainant is dissatisfied with the insurer‟s assessment that the garage is repairable. The complainant says the garage should be demolished and rebuilt. He wants the insurer to pay him the quote he obtained for this. The complainant also says the insurer mishandled his claim. 1.2 Issues and key findings Is the insurer required to increase its settlement amount? No. The insurer is not required to meet the costs of rebuilding the garage. This is because the available information does not show the garage needs to be rebuilt to repair the claim related damage. Is an award of compensation warranted? Yes. T he insurer‟s contractors handl ed asbestos removal from the premises poorly. This would have caused the complainant stress, inconvenience and interreference with his expectation of enjoyment or peace of mind. The insurer should pay $2,000 in non-financial loss. 1.3 Determination This determination is partly in favour of the complainant. The insurer is to pay $2,000 non-financial loss to the complainant. The insurer is to pay this within 14 days of receiving notification that the complainant accepts this determination. Determination | Case number: 717475 Page 2 of 8 2 Reasons for determination 2.1 Is the insurer required to increase its settlement amount? Circumstances of the complaint The insurer appointed assessor (CR) and builder (AB) to inspect and report on the cause and extent of damage shortly after the claim was lodged. CR arranged make-safe including removal of asbestos from the site. The complainant says he raised concerns about the asbestos removal. This was after he discovered asbestos in debris had been left in the garage by the insurer‟s contractor. The insurer subsequently arranged for re-attendance by its contractor to address the asbestos issue. The contractor attended to remove asbestos in March 2020. The complainant remains dissatisfied with the insurer (and its contractor‟s) conduct. He says the contractor‟s failure to properly r emove asbestos from the site in the first instance, and the way the insurer handled this, has resulted in him losing confidence in them and their abilities. Parties disagree about claims settlement There is no dispute the complainant has a valid claim for storm. The core issue in this complaint is the claim settlement and whether the insurer is liable for any further payment for the storm damaged garage. It should be noted that other items (such as mould and issues with main building) were previously raised by the complainant and are mentioned in some reports. However, during a conciliation held by AFCA, the complainant confirmed he is not pursuing a complaint in relation to those items. He seeks settlement for the garage damage, based on his quote. C omplainant says the insurer’s settlement is inadequate The complainant disputed the insurer‟s accepted scope of work after he was made aware of it. He subsequently obtained a repair quote from his own builder (GE) as well as a quote for further asbestos removal for $51,480 and $12,540 respectively. He is seeking a cash settlement of the quoted amounts. After reviewing the quotes, the insurer expressed willingness to cash settle the claim. However , it did not accept the complainant‟s repair quote . It says the quote incorrectly includes demolition and rebuild of the garage which is not warranted due to the storm damage. To determine if asbestos material was disturbed by the storm and during the claim, the insurer arranged for sampling/testing by hygienist „VA”. The available information shows VA found asbestos and lead from its sampling around the garage . Based on VA‟s findings, t he insurer tried to arrange for its contractor „ FR ‟ to complete additional asbestos abatement however, the complainant declined. The insurer subsequently obtained a quote from FR for asbestos and lead abatement as recommended by VA, for the garage only. The insurer proposed settlement of the claim based on the scope of works and building quote it had obtained from AB as well as FR‟s quotes. To settle the claim the insurer offered: Determination | Case number: 717475 Page 3 of 8  a total of $16,380.49 for garage repairs based on AB‟s quote of $15,276.36, less $385 (rectification of existing wall deemed a defect/maintenance issues) plus 10% contingency.  a total of $2,215.51 comprising $1,464.10 for asbestos and lead abatement, $550 for condition 2 cleaning plus a 10% contingency of $201.41. The complainant rejected the offer. The complainant maintains the garage needs to be rebuilt. Insurer obtained building consultant input The insurer appointed „CD‟ to provide a causation report. This was completed by a building consultant. Available information shows CD was instructed to inspect and report on whether the garage needs to be rebuilt due to the storm event and/or any event related asbestos contamination. After reviewing its expert report(s), including CD‟s , the insurer maintained its assessed scope of works (SOW) and quote for garage repairs was sufficient. I have carefully reviewed the causation report and subsequent clarifying email from CD. In reaching its conclusion, CD says:  it reviewed reports/SOW/quote previously obtained by the insurer as well as the complainant‟s bu ilding quote.  based on AB‟s report, the A/C damage was due to storm, however says: > any roof damage (garage and main building) observed were maintenance issues > interior water damage and hairline cracking in the main building observed was not caused by the claimed storm event. In relation to the complainant ‟s repair quote, CD opined that items included in the quote such as plasterboard and roof panels are not incident related. CD produced a SOW for claim related damage. This is limited to site preparation, termite protection, supply and installation of single PVC down pipe to the corner of the garage, prepare and paint the 6m2 of external fibre cement sheeting which has been replaced (as part of make-safe) to the rear of the garage, removal of debris and clean up. CD concluded that a rebuild of the garage, including carpentry and electrical provided for in the complainant‟s quote , is not required due to the claimed incident. It says there was “only minor damage to the garage” from the storm and while it was not able to inspect the garage slab during its attendance, “it is unlikely that the damage highlighted on my report would have significantly damaged the structural integrity of the slab”. Further, CD says based on VA‟s report there is no current debris visible in garage. It also notes:  further abatement/remediation and checks are recommended and provided for  there is no suggestion by VA that the existing slab should be demolished due to the asbestos fragments identified. No evidence garage rebuild is required due to claimed event or asbestos The complainant suggests the garage should be demolished and rebuilt due to structural issue (including from asbestos contamination). I have carefully reviewed the complainant complainant‟s quote s and note:  the cause of damage is not mentioned Determination | Case number: 717475 Page 4 of 8  the quote says, “Project Type: Removal & Construction of an existing garage as well as repair to existing residence.”  the quote includes roofing and ceiling works which are not covered by the claim Further, the complainant‟s asbestos removal quote assumes that the g arage is to be demolished. For reasons set out, I am not persuaded the garage needs to be demolished. The reports from AB (including photographs) and CR clearly shows the damage observed shortly after the storm event was limited to garage downpipe, garage roller door, garage sliding window, the air conditioning unit and some guttering. AB‟s roof report does not show hail/storm damage to the roofing (garage or main building) itself. Rather, it shows areas of pre-existing or maintenance related issues. This is not in dispute. On the available information, particularly the hygienists and CD‟s reports, the evidence does not support a conclusion that complete demolition and rebuild of the garage is required due to the storm or presence of asbestos/lead debris from that incident. While the complainant maintains there was no pre-existing issues with the garage structure and any structural damage is due to the claimed incident and asbestos, he has not provided evidence (such as a report from a suitably qualified expert) to support this. In view of the above, I am not satisfied the garage needs to be demolished and rebuilt. Insurer’s settlement is fair I am satisfied the insurer‟s assessed SOW and quote from AB is consistent with the claim- related damage identified i n the reports provided by the insurer‟s contractors /experts following their assessment. I am also satisfied FR‟s quote reasonably covers additional asbestos removal identified by VA. I also note t he insurer‟s payment to the com plainant includes a 10% contingency added to AB and FR‟s quote totals. Given all this, I accept the insurer‟s offer is fair in all the circumstances . 2.2 Is an award of compensation warranted? The complainant says the insurer mishandled the claim The complainant has expressed dissatisfaction with the way the insurer managed his claim. Among other things, the complainant says the insurer and its contractors:  failed to adequately complete the asbestos removal although numerous agents attended the premises, and  put his and his family‟s saf ety at risk He says the issues with the asbestos removal required him to constantly follow matters up with the insurer, unreasonably delayed the resolution of his claim and caused stress and inconvenience. The complainant seeks compensation for his negative claims experience. Determination | Case number: 717475 Page 5 of 8 Insurer does not dispute issues with asbestos abatement The insurer says it recognises the complainant‟s concerns relating to the asbestos removal from the property. It acknowledges the time taken after initial attendance and make-safe to remove material from the garage and surround “was longer than expected”. During a conciliation held by AFCA, the insurer further acknowledged its initial asbestos removal was not completed as it should have been. However, it says after the complainant raised further concerns about the adequacy of its asbestos removal, it authorised for a hygienist to attend and conduct testing and was unable to get authority from the complainant for the hygienist to attend until 20 May 2020. Compensation may be awarded in certain circumstances Under our Rules, the Australian Financial Complaints Authority (AFCA) may award compensation for non-financial loss (capped at $5,000) where there has been an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with a complainant‟s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to compensation and expects a complainant to bear a normal degree of inconvenience during a claim Compensation appropriate in the present circumstances While the insurer recognises and acknowledges the issues with the asbestos removal, it considers it has taken urgent steps to address the complainant‟s conce rns as soon as they were raised and also offered urgent asbestos abatement a fter VA‟s inspection . However, the complainant refused attendance by its contractors. The undisputed chronology provided by the insurer does not show any lengthy periods of inaction or unreasonable delay by the insurer. However, there is no dispute the asbestos has not been properly removed by the insurer‟s contractors. The insurer says after 27 May 2020, its contractors/trades “were ready willing and able to arrange abatement works based on the report finding and scope of works discussed” however the complainant did not agree to this. I have reviewed the available information. I accept that while the insurer acted on concerns raised by the complainant, the failure of its contractors to properly remove the asbestos was below standard. Particularly given the known potential danger of disturbed asbestos material. This failure would have caused and/or contributed to undue stress and inconvenience and interfered with the complainant‟s expectation of enjoyment of peace of mind. It is therefore fair in all the circumstances that the insurer pays $2,000 compensation non- financial loss to the complainant. Determination | Case number: 717475 Page 6 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Expert report Record Key points Determination | Case number: 717475 Page 7 of 8 Financial firm’s expert (VA) Hygienist report 18 - 06 - 2020  conducted assessment on 27 May 2020 following complaint of incomplet e asbestos removal abatement  provided assessment on mould/moisture within the main building (not claim related)  concluded “Asbestos - containing building materials and lead - based paint are present on the exterior of the property as debris resulting from the storm”  reco mmended in relation to asbestos: “Due to the identification of ACM and lead - paint fragments on the ground around the Garage and to the backyard, further abatement works are recommended. Visible fragments of cement board require careful collection from the areas with soil. Vacuuming of the concrete pad with HEPA filtration would collect any residual small cement board fragments as well as paint chips. Collection of paint chips from soil may not be feasible and may require removal of the top layer of soil. A ll remediation and abatement works should be conducted by an accredited, suitably qualified and experienc ed remediator, employing methods in accordance with the following reference or equivalent: - Work Safe NSW Code of Practice: How to Safely Remove Asbestos 2016; - Managing asbestos in workplac es compliance code 2018; - Removing asbestos in work places compliance code 2018. - AS/NZD 4361.2: 2017 Guide to Hazardous Management, Part 2: Lead paint in resid ential, public an commercial buildings. … Sampling of settled dusts within the Garage is recommended to ensure that there is not residual as bestos fibres present that would create potential exposures to occupants.” Determination | Case number: 717475 Page 8 of 8 Financial firm’s expert (CD) Caus ation report 18 - 06 - 2020  appointed to inspect premises and review information to confirm among other things > whet her there is any structural damage to garage, if so, > whet her it is due to the storm event claimed > whet her any roof damage (building and garage) that can reasonably be attributed to the storm event > whet her storage of debris, consisting of material cont aining asbestos, in the garage has res ulted in the garage being contaminated and, as a result, must be demolished and re - built or can be repaired > scope of works for damage reasonably attributable to the storm event  attended premises on 27 May 2020  reviewed building quotes of AB and GE, A/C as well as hygienist (FR) report  Concluded: > evidence of maintenance issues with roof (garage and main building) identif ied in AB‟s reports > observed minor internal water damage and hairline cracking to main building which are not related to storm > AB‟s report confirms A/C damage due to storm > considers “[ v] arious items included in the Scope of Works prepared by [AB] and [GE] do not pertain to the resultant damage of a storm event”. Examples of items given are plasterboard and roof panels in GE‟s report. > produced scope of works for garage damage attributable to storm event limited to - site preparation - termite protection - Supply a nd install single PVC down pipe to the corner of the garage - Prepare and paint the external fibre cement sheeting whic h has been replaced to the rear of the garage (6m2) - clean - up, removal of debris Financial firm’s expert (CD) Email/statement 24 - 06 - 2020 In response to clarification sought by the insurer, CR says:  “full replacement of the garage is not required. We note only minor damage to the garage” from storm event  it was “not able to inspect this but it is unlikely that the damage highlighted on my re port would have significantly damaged the structural integrity of the slab”.  Carpentry, internal lining and roofing - rebuild not required.  Electrical – not required.  Based on hy gienist report there is no current debris visible in garage and further abat em ent/remediation and checks recommended, no suggestion by hygienist that the existing slab should be demolished.