Home / Defence Service Homes Insurance Scheme / Determination 714294

Determination 714294

Declined swimming pool storm damage claim relying on defect and maintenance exclusions

FirmDefence Service Homes Insurance Scheme
Decided2021-04-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$25,983
Non-financial loss$750
Amount claimed$25,983
SourceAFCA PDF

Summary

The complainant's home building insurer partly accepted a storm and flood claim but declined pool damage, attributing it to design, workmanship and maintenance defects. AFCA found rainfall caused the damage and no exclusion applied, and ordered settlement of the pool repair quote of $25,983 plus $750 non-financial loss.

Once the complainant establishes a valid claim, the insurer must prove an exclusion applies, and it could not show that defects or maintenance rather than the rainfall were the proximate cause.

Issues

Subjects and remedies

pay claimpay non financial loss

Related

All Defence Service Homes Insurance Scheme determinations · Find similar determinations

Text of the determination

Determination Case number 714294 Financial firm Defence Service Homes Insurance Scheme Determination | Case number: 714294 Page 2 of 8 Case number: 714294 31 March 2021 1 Determination overview 1.1 Complaint The complainant holds a home building insurance policy with the financial firm (insurer). He lodged a claim for damage to his property following the Townsville flood/storm event in 2019. The insurer partially accepted the claim for a damaged air conditioner and waste water pump. However, it declined cover for damage to the swimming pool. The insurer says the storm event did not cause the damages to the swimming pool. Rather, it says a defect in the design of the pool and defects in the building work caused the damages. 1.2 Issues and key findings Is the insurer entitled to decline cover for the pool damage? No. I am satisfied, on balance, the complainant has established a valid claim for the damages and the insurer has not established an exclusion applies in the circumstances. Is the complainant entitled to compensation? Yes. The circumstances of the dispute warrant an award of compensation. 1.3 Determination This determination is in favour of the complainant. The insurer is to settle the complainant based on his quote to repair the damage to the pool. Payment should be made within 14 days of the insurer being notified that the complainant has accepted this determination. The insurer is also to pay the complainant $750 in non-financial loss compensation. Determination | Case number: 714294 Page 3 of 8 2 Reasons for determination 2.1 Is the insurer entitled to decline cover for the pool damage? Complainant has initial onus to establish a valid claim The initial onus is with the complainant to establish the loss is covered by the policy. This is known as establishing a valid (or prima facie ) claim. Once the complainant has established a valid claim, the onus shifts to the insurer to establish, on balance, the application of a policy exclusion or that it is otherwise entitled to decline the claim under the policy. The product disclosure statement (PDS) says the insurer covers damage caused by rain. This includes ‘that par t of the rainfall that is not absorbed by the soil but runs off as surface water’. The policy also provides cover for accidental loss or damage to the property, caused by a ‘sudden and unexpected event’ , up to $5,000. Complainant says rain event caused the damages The complainant says the pool was built around 2012 and was in perfect condition until the rain event. He provided photographs of the pool during the rain event, saying there were no cracks or any other problems with the tiles. He says the 2019 Townsville flood/storm event caused torrential rain to continuously fill the pool and wash off the area damaged. He says photographs show the amount of water running through the area before and after the event. He says if the rain had not occurred, the pool would not be damaged. The complainant provided a report from a concreting company (SNS), which states:  the complainant showed it photographs of the pool during its construction, which showed no abnormalities and what would be expected from a normal installation procedure  the footings consisted of compacted crusher dust  crusher dust can be used as a filling and packing material, but erosion can wear away crusher dust around footings  erosion can originate from several sources, such as a burst water pipe or other uncontrolled water flow  during removal of the concrete slab, it was noted the excessive amount of rain had run over the pool wall and run down the crack (join) between the pool and coping, which eroded most of the original footings, causing the weight of the coping slab to collapse. The complainant also provided a letter from his pool company (SCP), which states it has been servicing the pool for over three years. It states prior to the February 2019 event, the tiled coping and extended surrounds were completely intact, with no drummy tiles or cracking. SCP states prolonged submersion under water during the Determination | Case number: 714294 Page 4 of 8 event resulted in the tiles becoming drummy and there was visible cracking that had not been there prior. The complainant says by the time the ins urer’s engineer inspected the pool eight months later, the damage had increased, and all record of the event had diminished. He says:  the engineer’s assessment of the pool is not exhaustive and did not include an invasive investigation  the engineer does not prove that poor workmanship is the cause of the damage  it does not rely on any physical evidence, but bases its conclusions on innuendo, verbalisation, theory and unproven findings and opinions  there are errors in the engineer’s report, because if the engineer had carried out an invasive investigation, it would have noticed the area was in fact filled with concrete before the footings were laid and crusher dust had been laid and compacted  the engineer refers to subsidence but did not provide physical evidence of this  voiding beneath the paving slab was due to the rain water gushing between the pool and pavement joint. The complainant provided a quote to repair the exterior of the pool for $25,983. Insurer says damages are excluded The insurer appointed an engineer (FCE) to attend t he property. FCE’s report dated 21 October 2019 states:  the concrete paving slab cast along the rear western end of the swimming pool had issues, with the soil observed to have subsided, most likely as a result of poor compaction of the fill soil during its original placement  some tiles laid over the paving slab to the western end were cracked as a result of the paving slab subsidence  some tiles laid over the paving slab to the western end were completely debonded from the paving slab and many were drummy  similar paving slab subsidence and tile damage was not observed to the northern, eastern and southern sides of the pool. FCE stated the western side of the pool has been built against an easement line and council records show a non-compliance notice was issued saying that the pool had encroached into the easement space. It says revised pool plans were approved, however FCE expects the western pool wall was moved in, requiring the pool excavation space to be filled in. Based on this, FCE believes poorly compacted soil fill material has been placed along the western end and south-western corner of the pool. It says defective building work during original construction caused the subsidence and cracking damage. FCE provided a supplementary report dated 12 May 2020 having reviewed SNS’s report. It says based on new site information from works SNS carried out, this has Determination | Case number: 714294 Page 5 of 8 revealed an erosion-based loss of crusher dust bedding material beneath the western pool paving slab rather than subsidence of soil backfill behind the western pool wall. It says it largely agrees with SNS’s claims that: the now apparent concrete backfill to the over-excavated area behind the western swimming pool wall does not appear to have subsided as we had previously expected it had and the claimed paving slab damage has rather been caused by erosion of loose crusher dust bedding material beneath the western paving slab. FCE states for this erosion to occur, water would have needed to ingress through a sealed joint between the pool shell and pool coping tiles and/or via what should be a sealed construction joint. This indicates the sealant at these locations was not sound before and/or during the rain event, which is a building maintenance matter. It says it is unlikely the erosion occurred from a single one-off and recent rain event. It also maintains there was defective installation and detachment of the tiles from the pool paving slab. FCE then provided further comments dated 5 March 2021, in which it states a single exposure to rainwater would not have caused the pool edge tiles to come adrift. The insurer says the damage was contained to the western and south western corner of the pool. The insurer says heavy rain undoubtedly occurred over the entire pool area. The insurer says poorly compacted soil fill material had been placed along the western end where the damage occurred. It also raises concerns with the complainant’s report. It says SCP is not an engineering company and is not in a position to comment on the structural soundness of the pool. The insurer says rain does not cause the failure of tiles nor does it account for the poor workmanship beneath it. It says tiles are installed in external wet areas because they are suited to this and are designed to resist water. It says the damage was therefore caused by a defect in the design and workmanship of the pool. It also says there is no cover for rain if rain enters the home due to failing to property maintain the home. It says the deteriorated condition of the control joint sealant allowed water to seep in and erode under slab bedding material. It says this is a maintenance issue. The insurer refers to the following exclusions in the PDS: We do not insure you for loss or damage caused by rain seeping into or entering the home because of: • defects in the structure or design of the home • defects in building work done on the home … • failing to property maintain the home. It also refers to the following general exclusion in the PDS: We do not insure you for loss or damage or legal liability caused by: Determination | Case number: 714294 Page 6 of 8 • failing to keep the home or site in good repair and condition • the home or site settling or shrinking or expanding • hydrostatic pressure, or the earth movin g (other than from earthquake), erosion • defects in structure, design, work done, or materials used on the home or at the site Insurer required to accept the claim In its supplementary report, FCE says for erosion to occur from water ingress, it indicates the applied sealant at these locations was not sound before and/or during the rain event. FCE says this is a building maintenance issue. I have some concerns regarding this conclusion. Firstly, there is no evidence of any damage to the pool area prior to the storm event. The company regularly servicing the pool stated there were no issues with the pool. It is likely SCP would have noticed the lack of sealant if this was an ongoing issue prior to the event. In the absence of any further evidence in support of this view, it is difficult to accept the pool had maintenance issues present if regularly serviced. Secondly, there is no dispute the storm event was significant. The Townsville flood/storm event caused significant damage to properties. E vidence from the complainant suggests the pool area was subject to significant rainfall events over an extended period of time. I consider it highly plausible that significant and ongoing rainfall events could have caused the damage claimed . This is supported by SNS’s report. Thirdly, FCE inspected the property many months after the significant event, which means the damage may have been further exacerbated in that time. Having regard to all the circumstances of the dispute, I am satisfied, on balance, rainfall from the significant event caused damages to the pool. The complainant has therefore established a valid claim and the onus shifts to the insurer to show it is entitled to decline the claim. I do not consider the insurer has provided sufficient information to establish the damage was due to a defect in the construction of the pool. FCE refers to the initial council plans for the pool. However, it has not provided sufficient information to show the subsequent plans and building of the pool were not compliant. FCE appears to have made some assumptions regarding the construction of the pool. However, given the lack of invasive investigations, I do not find this reasoning persuasive. The insurer also has not provided any information to show the pool was not built according to any applicable building codes. I am also not satisfied the insurer has established the cause of damage was the complainant failing to maintain his home. As the information provided shows, on Determination | Case number: 714294 Page 7 of 8 balance, he was regularly maintaining the pool and the damage manifested after this significant event. Given I am satisfied the proximate cause of the damage was the rainfall, I do not consider the general exclusions apply to defeat the claim. This means I consider it fair in all the circumstances for the insurer to accept the claim. The insurer is to settle the complainant based on his quote to repair the damage to the pool. Payment should be made within 14 days of the insurer being notified that the complainant has accepted this determination. 2.2 Is the complainant entitled to compensation? Compensation may be awarded in certain circumstances Under our Rules, the Australian Financial Complaints Authority (AFCA) may award compensation for non-financial loss (capped at $5,000) where there has been an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with a complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to compensation and expects a complainant to bear a normal degree of inconvenience during a claim. Complainant entitled to compensation The complainant seeks non-financial loss compensation based on the way the insurer handled the claim. The complainant says he is a retired disabled veteran with many disabling pain inducing injuries. He says this claim has caused him mental stress for nearly two years. I am satisfied the insurer’s initial claims decision was incorrect. I am also satisfied this incorrect claim decision unreasonably delayed the resolution of the claim and caused the complaint undue stress and inconvenience. The insurer is required to pay the complainant $750 in non-financial loss compensation. Determination | Case number: 714294 Page 8 of 8 3 Supporting information 3.1 Process AFCA’s approach to this complaint This complaint has been determined based on what is fair in all the circumstances, having regard to the legal principles, applicable industry codes or guidance, good industry practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. How we assess complaints AFCA is not a court of law. We do not have the power to take or test e vidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.