Home / Defence Service Homes Insurance Scheme / Determination 714294
Determination 714294
Declined swimming pool storm damage claim relying on defect and maintenance exclusions
Summary
The complainant's home building insurer partly accepted a storm and flood claim but declined pool damage, attributing it to design, workmanship and maintenance defects. AFCA found rainfall caused the damage and no exclusion applied, and ordered settlement of the pool repair quote of $25,983 plus $750 non-financial loss.
Once the complainant establishes a valid claim, the insurer must prove an exclusion applies, and it could not show that defects or maintenance rather than the rainfall were the proximate cause.
Issues
- Claim denial primary · upheld
“The insurer's initial claims decision was incorrect; rainfall caused the pool damage and no exclusion was established.”
- Delay secondary · upheld
“The incorrect claim decision unreasonably delayed resolution of the claim and caused stress.”
Subjects and remedies
pay claimpay non financial loss
Text of the determination
Determination
Case number 714294
Financial firm Defence Service Homes Insurance Scheme
Determination | Case number: 714294 Page 2 of 8
Case number: 714294 31 March 2021
1 Determination overview
1.1 Complaint
The complainant holds a home building insurance policy with the financial firm
(insurer). He lodged a claim for damage to his property following the Townsville
flood/storm event in 2019. The insurer partially accepted the claim for a damaged air
conditioner and waste water pump. However, it declined cover for damage to the
swimming pool.
The insurer says the storm event did not cause the damages to the swimming pool.
Rather, it says a defect in the design of the pool and defects in the building work
caused the damages.
1.2 Issues and key findings
Is the insurer entitled to decline cover for the pool damage?
No. I am satisfied, on balance, the complainant has established a valid claim for the
damages and the insurer has not established an exclusion applies in the
circumstances.
Is the complainant entitled to compensation?
Yes. The circumstances of the dispute warrant an award of compensation.
1.3 Determination
This determination is in favour of the complainant.
The insurer is to settle the complainant based on his quote to repair the damage to
the pool. Payment should be made within 14 days of the insurer being notified that the
complainant has accepted this determination.
The insurer is also to pay the complainant $750 in non-financial loss compensation.
Determination | Case number: 714294 Page 3 of 8
2 Reasons for determination
2.1 Is the insurer entitled to decline cover for the pool damage?
Complainant has initial onus to establish a valid claim
The initial onus is with the complainant to establish the loss is covered by the policy.
This is known as establishing a valid (or prima facie ) claim.
Once the complainant has established a valid claim, the onus shifts to the insurer to
establish, on balance, the application of a policy exclusion or that it is otherwise
entitled to decline the claim under the policy.
The product disclosure statement (PDS) says the insurer covers damage caused by
rain. This includes ‘that par t of the rainfall that is not absorbed by the soil but runs off
as surface water’. The policy also provides cover for accidental loss or damage to the
property, caused by a ‘sudden and unexpected event’ , up to $5,000.
Complainant says rain event caused the damages
The complainant says the pool was built around 2012 and was in perfect condition
until the rain event. He provided photographs of the pool during the rain event, saying
there were no cracks or any other problems with the tiles. He says the 2019
Townsville flood/storm event caused torrential rain to continuously fill the pool and
wash off the area damaged. He says photographs show the amount of water running
through the area before and after the event. He says if the rain had not occurred, the
pool would not be damaged.
The complainant provided a report from a concreting company (SNS), which states:
the complainant showed it photographs of the pool during its construction, which
showed no abnormalities and what would be expected from a normal installation
procedure
the footings consisted of compacted crusher dust
crusher dust can be used as a filling and packing material, but erosion can wear
away crusher dust around footings
erosion can originate from several sources, such as a burst water pipe or other
uncontrolled water flow
during removal of the concrete slab, it was noted the excessive amount of rain had
run over the pool wall and run down the crack (join) between the pool and coping,
which eroded most of the original footings, causing the weight of the coping slab to
collapse.
The complainant also provided a letter from his pool company (SCP), which states it
has been servicing the pool for over three years. It states prior to the February 2019
event, the tiled coping and extended surrounds were completely intact, with no
drummy tiles or cracking. SCP states prolonged submersion under water during the
Determination | Case number: 714294 Page 4 of 8
event resulted in the tiles becoming drummy and there was visible cracking that had
not been there prior.
The complainant says by the time the ins urer’s engineer inspected the pool eight
months later, the damage had increased, and all record of the event had diminished.
He says:
the engineer’s assessment of the pool is not exhaustive and did not include an
invasive investigation
the engineer does not prove that poor workmanship is the cause of the damage
it does not rely on any physical evidence, but bases its conclusions on innuendo,
verbalisation, theory and unproven findings and opinions
there are errors in the engineer’s report, because if the engineer had carried out an
invasive investigation, it would have noticed the area was in fact filled with concrete
before the footings were laid and crusher dust had been laid and compacted
the engineer refers to subsidence but did not provide physical evidence of this
voiding beneath the paving slab was due to the rain water gushing between the
pool and pavement joint.
The complainant provided a quote to repair the exterior of the pool for $25,983.
Insurer says damages are excluded
The insurer appointed an engineer (FCE) to attend t he property. FCE’s report dated
21 October 2019 states:
the concrete paving slab cast along the rear western end of the swimming pool had
issues, with the soil observed to have subsided, most likely as a result of poor
compaction of the fill soil during its original placement
some tiles laid over the paving slab to the western end were cracked as a result of
the paving slab subsidence
some tiles laid over the paving slab to the western end were completely debonded
from the paving slab and many were drummy
similar paving slab subsidence and tile damage was not observed to the northern,
eastern and southern sides of the pool.
FCE stated the western side of the pool has been built against an easement line and
council records show a non-compliance notice was issued saying that the pool had
encroached into the easement space. It says revised pool plans were approved,
however FCE expects the western pool wall was moved in, requiring the pool
excavation space to be filled in. Based on this, FCE believes poorly compacted soil fill
material has been placed along the western end and south-western corner of the
pool. It says defective building work during original construction caused the
subsidence and cracking damage.
FCE provided a supplementary report dated 12 May 2020 having reviewed SNS’s
report. It says based on new site information from works SNS carried out, this has
Determination | Case number: 714294 Page 5 of 8
revealed an erosion-based loss of crusher dust bedding material beneath the western
pool paving slab rather than subsidence of soil backfill behind the western pool wall. It
says it largely agrees with SNS’s claims that:
the now apparent concrete backfill to the over-excavated area behind the western
swimming pool wall does not appear to have subsided as we had previously
expected it had and the claimed paving slab damage has rather been caused by
erosion of loose crusher dust bedding material beneath the western paving slab.
FCE states for this erosion to occur, water would have needed to ingress through a
sealed joint between the pool shell and pool coping tiles and/or via what should be a
sealed construction joint. This indicates the sealant at these locations was not sound
before and/or during the rain event, which is a building maintenance matter. It says it
is unlikely the erosion occurred from a single one-off and recent rain event. It also
maintains there was defective installation and detachment of the tiles from the pool
paving slab.
FCE then provided further comments dated 5 March 2021, in which it states a single
exposure to rainwater would not have caused the pool edge tiles to come adrift.
The insurer says the damage was contained to the western and south western corner
of the pool. The insurer says heavy rain undoubtedly occurred over the entire pool
area. The insurer says poorly compacted soil fill material had been placed along the
western end where the damage occurred. It also raises concerns with the
complainant’s report. It says SCP is not an engineering company and is not in a
position to comment on the structural soundness of the pool.
The insurer says rain does not cause the failure of tiles nor does it account for the
poor workmanship beneath it. It says tiles are installed in external wet areas because
they are suited to this and are designed to resist water. It says the damage was
therefore caused by a defect in the design and workmanship of the pool. It also says
there is no cover for rain if rain enters the home due to failing to property maintain the
home. It says the deteriorated condition of the control joint sealant allowed water to
seep in and erode under slab bedding material. It says this is a maintenance issue.
The insurer refers to the following exclusions in the PDS:
We do not insure you for loss or damage caused by rain seeping into or entering
the home because of:
• defects in the structure or design of the home
• defects in building work done on the home
…
• failing to property maintain the home.
It also refers to the following general exclusion in the PDS:
We do not insure you for loss or damage or legal liability caused by:
Determination | Case number: 714294 Page 6 of 8
• failing to keep the home or site in good repair and condition
• the home or site settling or shrinking or expanding
• hydrostatic pressure, or the earth movin g (other than from earthquake),
erosion
• defects in structure, design, work done, or materials used on the home or
at the site
Insurer required to accept the claim
In its supplementary report, FCE says for erosion to occur from water ingress, it
indicates the applied sealant at these locations was not sound before and/or during
the rain event. FCE says this is a building maintenance issue.
I have some concerns regarding this conclusion.
Firstly, there is no evidence of any damage to the pool area prior to the storm event.
The company regularly servicing the pool stated there were no issues with the pool. It
is likely SCP would have noticed the lack of sealant if this was an ongoing issue prior
to the event. In the absence of any further evidence in support of this view, it is
difficult to accept the pool had maintenance issues present if regularly serviced.
Secondly, there is no dispute the storm event was significant. The Townsville
flood/storm event caused significant damage to properties. E vidence from the
complainant suggests the pool area was subject to significant rainfall events over an
extended period of time. I consider it highly plausible that significant and ongoing
rainfall events could have caused the damage claimed . This is supported by SNS’s
report.
Thirdly, FCE inspected the property many months after the significant event, which
means the damage may have been further exacerbated in that time.
Having regard to all the circumstances of the dispute, I am satisfied, on balance,
rainfall from the significant event caused damages to the pool. The complainant has
therefore established a valid claim and the onus shifts to the insurer to show it is
entitled to decline the claim.
I do not consider the insurer has provided sufficient information to establish the
damage was due to a defect in the construction of the pool. FCE refers to the initial
council plans for the pool. However, it has not provided sufficient information to show
the subsequent plans and building of the pool were not compliant. FCE appears to
have made some assumptions regarding the construction of the pool. However, given
the lack of invasive investigations, I do not find this reasoning persuasive. The insurer
also has not provided any information to show the pool was not built according to any
applicable building codes.
I am also not satisfied the insurer has established the cause of damage was the
complainant failing to maintain his home. As the information provided shows, on
Determination | Case number: 714294 Page 7 of 8
balance, he was regularly maintaining the pool and the damage manifested after this
significant event.
Given I am satisfied the proximate cause of the damage was the rainfall, I do not
consider the general exclusions apply to defeat the claim. This means I consider it fair
in all the circumstances for the insurer to accept the claim.
The insurer is to settle the complainant based on his quote to repair the damage to
the pool. Payment should be made within 14 days of the insurer being notified that the
complainant has accepted this determination.
2.2 Is the complainant entitled to compensation?
Compensation may be awarded in certain circumstances
Under our Rules, the Australian Financial Complaints Authority (AFCA) may award
compensation for non-financial loss (capped at $5,000) where there has been an
unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with a complainant’s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to compensation and expects a complainant to
bear a normal degree of inconvenience during a claim.
Complainant entitled to compensation
The complainant seeks non-financial loss compensation based on the way the insurer
handled the claim.
The complainant says he is a retired disabled veteran with many disabling pain
inducing injuries. He says this claim has caused him mental stress for nearly two
years.
I am satisfied the insurer’s initial claims decision was incorrect. I am also satisfied this
incorrect claim decision unreasonably delayed the resolution of the claim and caused
the complaint undue stress and inconvenience.
The insurer is required to pay the complainant $750 in non-financial loss
compensation.
Determination | Case number: 714294 Page 8 of 8
3 Supporting information
3.1 Process
AFCA’s approach to this complaint
This complaint has been determined based on what is fair in all the circumstances,
having regard to the legal principles, applicable industry codes or guidance, good
industry practice and previous decisions of AFCA or its predecessor schemes (which
are not binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised. All of the
provided information has been reviewed and considered. The parties have raised
numerous issues in their submissions to AFCA. However, commentary in this
determination is restricted to those issues considered relevant to the outcome.
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test e vidence on
oath, or to require third parties to give evidence. When we assess complaints, we
consider available documents, the recollections of the parties, and all relevant
circumstances. We give more weight to documents created at the time the events
occurred. If there is no relevant documentation, we will decide what is most likely to
have occurred based on the information provided to us. If there are conflicting
recollections and these are evenly weighted, we may find that a claim cannot be
established.