Home / Lloyd's / Determination 713153
Determination 713153
Claim for mould damage to partly built home denied as no insured Event occurred
Summary
The owner-builder complainant claimed for mould that developed in a partly built home after heavy rain over June and July 2019. The insurer denied the claim because the damage was not caused by a sudden event at a specific point in time, and AFCA agreed.
Insured Damage requires an Event at a specific point in time, and the Loss Accumulation Clause cannot extend to a series of rain events over two months.
Issues
- Claim denial primary · not upheld“I do not accept the complainant has established a valid claim. The insurer can deny the claim on this basis.”
- Product terms interpretation secondary · not upheld“The definition of Event must have an event within a specific point in time; the Loss Accumulation Clause cannot cover storms over four days.”
Subjects and remedies
no remedy
Related
Text of the determination
Determination
Case number 713153
Financial firm Lloyd's Australia Limited
Determination | Case number: 713153 Page 1 of 7
Case number: 713153 14 September 2020
1 Determination overview
1.1 Complaint
The complainant arranged an owner-builder construction policy with the financial firm
(insurer). Mould developed throughout the framing and hempcrete blocks of the
partially constructed home. The complainant lodged a claim for this damage.
The insurer says mould formed due to rainfall which fell over a period of time. The
insurer says the damage is excluded as the policy only covers events which occur at
a specific point it time. It also says damage caused by mould is excluded.
The complainant says mould is not the cause of damage, but the damage itself. The
complainant also says the cause of the damage was a period of unusually high
rainfall. This constitutes an event covered by the policy.
1.2 Issues and key findings
Has the complainant established a valid claim under the policy?
No. The available information does not show the damage was caused by an ‘Event’
as defined by the policy.
1.3 Determination
This determination is in favour of the insurer.
The insurer can deny the claim.
Determination | Case number: 713153 Page 2 of 7
2 Reasons for determination
2.1 Has the complainant established a valid claim under the policy?
Complainant has onus to establish a loss
The complainant is required to establish a valid claim, within the terms of the policy.
Should the complainant establish a valid claim, the onus shifts to the insurer to
establish that an exclusion applies, or that it is otherwise entitled to refuse the claim.
The policy responds in the following circumstances:
We will cover You up to the Sums Insured stated in the Schedule, for Insured
Damage to the Construction Works during the Construction Period.
Insured Damage is defined as follows:
Physical loss or damage not otherwise excluded, arising out of an Event within
the Territorial Limits during the Period of Insurance
Event is defined as:
A sudden and unforeseen happening that has taken place at a specific point in
time.
There is no dispute damage occurred to Construction Works during the Construction
Period. However, the insurer says there is no Insured Damage as the loss did not
arise out of an ‘Event’.
Complainant was undertaking construction when a large rain event occurred
External hemp block work construction took place between 9 and 29 May 2019.
Internal hempcrete installation works took place from 31 May 2019 and was
completed toward the end of June 2019. The roof was completed on 30 July 2019.
June and July 2019 saw a large volume of rain fall on the exposed structure.
On 10 August 2019 the complainant and his builder observed mould had developed in
the timber framing and hempcrete. Estimates suggest the severity of mould is such
that the entire structure must be demolished and rebuilt.
The complainant lodged a claim for this damage at or around this time.
The insurer’s assessor took m oisture readings from the timber framing at various
points. The results exceeded 40%. The insurer says recommended acceptable
moisture levels for timber framing are between 9% and 14%.
Determination | Case number: 713153 Page 3 of 7
The insurer says the combined total rainfall over the period is not unusual for winter
months. However, the complainant referred to media reports which reported that
Perth, located approximately 10km from the insured property, had recorded its wettest
June in 14 years. This followed Perth’s second driest May on record.
Policy covers events happening at a specific point in time
The insurer says the building, without a completed roof, was exposed to the elements
for two months. It supplied rainfall data recorded at the nearby weather station from
January 2019 to October 2019. Review of this information shows over June and July,
rain was recorded over numerous days, and first on 7 June 2019.
The complainant disputes the insurer’s interpretation of ‘specific point in time’. She
says a sustained period of unusually high rainfall is an event occurring at a specific
point in time.
The complainant points to the loss accumulation clause within the policy, outlined in
full in section 3 of this determination. In summary, this clause says that damage
occurring over 96 hours caused by storm will be deemed a single event. The
complainant says the policy must therefore consider a period of 96 hours can be a
specific point in time.
Numerous rainfall events in June and July
Bureau of Meteorology daily rainfall data recorded rain from 7 to 13 June. The
evening of 6 June is described as a significant storm in media reports. Other storms
were reported during the period.
This rainfall data does show other days of similar or high rainfall periods compared to
the period between 7 and 13 June. This includes 23 June (39.6mm), 27 June
(18.8mm), 28 June (17.4mm), 5 July (45.6mm) and 20 July (18.2mm).
Policy does not respond
The complainant has argued the reference to specific point in time is unclear,
particularly given the ‘Loss Accumulation Clause’.
Having carefully considered the policy, I note the following.
The definition of ‘Event’ must have, at least, an event (‘a sudden and unforeseen
happening’) that occurs within a specific point in time. Whilst ‘specific point in time’
can be stretched to hours, or possibly a day or two, it clearly cannot be more four
days. Otherwise, the ‘Loss Accumulation Clause’ adds not hing to the policy coverage.
Therefore, I do not accept this provision can apply to a series of different storms that
occurred over a period of time greater than four days.
In this case, the rainfall records show there were rainfall periods at different times
throughout this two-month period. The mould could have readily been caused by
Determination | Case number: 713153 Page 4 of 7
these different rainfall events over this two-month period. At the least, the evidence is
far from clear the mould was caused by a specific storm or from a ‘sudden and
unfor eseen happening’ within a four-day period.
Given this, I do not accept the complainant has established a valid claim. The insurer
can deny the claim on this basis.
Determination | Case number: 713153 Page 5 of 7
3 Supporting information
3.1 Policy wording
SCOPE OF COVER
During the Construction Period
We will cover You up to the Sums Insured stated in the Schedule, for Insured
Damage to the Construction Works during the Construction Period.
DEFINITIONS
Insured Damage
Physical loss or damage not otherwise excluded, arising out of an Event within
the Territorial Limits during the Period of Insurance.
Event
A sudden and unforeseen happening that has taken place at a specific point in
time.
Storm
Violent wind (including cyclones and tornadoes), thunderstorms or hailstorms
which may be accompanied by snow or rain.
EXCLUSIONS
We will not be liable for any loss or damage:
…
j) caused by mould, mildew, fungus, spores or other micro organism of any type,
nature or description including but not limited to any substance whose presence
poses an actual or potential threat to human health. This Exclusion additionally
applies to any loss of use, occupancy or functionality, or any costs or expense
arising from its removal, clean up, abatement, disposal or other steps taken to
control its future presence or medical and/or legal concern.
Determination | Case number: 713153 Page 6 of 7
Loss Accumulation Clause
For the purpose of the application of the Section 1 – Material Damage Excess, any
Insured Damage arising during any one period of Ninety Six (96) consecutive
hours caused by flood, Storm, earthquake or bushfire, will be deemed to be a
single Event and therefore to constitute one loss. You may select the time from
which any such period will commence but no two such selected periods will
overlap.
Summary of relevant submissions
Item Summary
Certificate of Conformity –
Hempcrete
23 August 2017
OzHemp Tradical® Hempcret e is permitted to be used as
an internal or external wall system (incorporating timber or
steel framing) in loadbearing applications or as a floor
system.
Complies with the following BCA provisions…
Weat herproofing P2.2.2
The OzHemp Tradic al® Hempcrete cont ribut es to the
weat herproofing when installed in accordance with OzHemp
Tradical® Hempcrete Installation Manual Version 01 March
2016
The OzHemp Tradic al® Hempcrete Wall System is a vapour
permeable sys tem and care must be taken to avoid trapped
moisture through the inappropriate use or positioning of
Vapour Control Layers (VCL), low vapour permeability or
vapour impermeable materials in the construction or as
external or internal finishes and Hempcrete Australia.
In common with good working practices, it is important that
the OzHemp Tradical® Hempcrete is protected from water
ingress during construction. In particular, especially whilst
the shuttering is in place, the top of formwork lifts should be
adeq uately protected to prevent wat er ingress into the walls.
Claim Form Hempcrete cont ractor said he needed to install the
hempcrete before the roof was on.
Technical Asse ssing
Report
27 September 2019
MS are a single operator and only recently started offering
hemp blockwork construction with the subject site being only
the second job the Builder has been engaged to construct.
We have obtained from the Bureau of Meteorology, the daily
rainfall observat ions for the local area whic h indicates that
between the commenced states of the construction of the
timber framing works to the property and the fitting of the
roof, there was a recorded 278.2mm of rainfall, which
continued to fall throughout the month of August and early
September. A copy of the observation document is attached
for reference as Appendix 1.
Determination | Case number: 713153 Page 7 of 7
Item Summary
We further note that at the time of our attendance, we took
moisture readings of the timber frame at various points
throughout the property which retu rned a reading exceeding
40%, which far exceeds the recommended accept able
levels of bet ween 9% and 14%.
The Insured has advised that at no time during the
construction of the timber frame and hemp block work, had
the building works being protected and sh ielded from the
heavy rainfall.
The Insured raised the question with M S as to whether the
timber frame hemp block work required protection, and was
advis ed that the hemp blockwork is a natural product and
will allow wat er evaporation to occur, eventually drying to an
acceptable level.
What appears to have occurred, however, is that due to the
amount of rainfall that has occurred over a sustained period,
the hemp block work has caused the rain waters to stay into
direct contact with the timber framework un til such time as
mould has been allowed to cultivate between the two
materials.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.