Determination 711101
Delayed fire repairs and temporary accommodation after neighbouring townhouse fire
Summary
After a neighbouring townhouse fire in August 2019 the complainant's home was repaired after a long delay caused by the neighbour's demolition, and she was given temporary accommodation. AFCA found the insurer handled the claim reasonably and ordered no compensation.
Delay caused by third-party demolition outside the insurer's control, with no extended inaction by the insurer, does not justify non-financial loss compensation under AFCA Rule D3.3.
Issues
- Delay primary · not upheld
“The delays in the repair process were not caused by the insurer's claims handling but due to delays in the demolition of the adjoining property.”
- Repairs or contractors secondary · not upheld
“The insurer has met its obligations under the policy in relation to the rectification of the driveway and painting.”
Subjects and remedies
health or medicalhome or building damageno remedy
Text of the determination
Determination
Case number 711101
Financial firm Allianz Australia Insurance Limited
Determination| Case number: 711101 Page 2 of 5
Case number: 711101 8 April 2021
1 Determination overview
1.1 Complaint
The complainant held a home building contents policy with the financial firm (insurer).
On the 2 August 2019 the complainant‟s home was damaged when an adjoining
townhouse caught fire.
The insurer accepted the claim but were delayed in commencing repairs due to
ongoing delays in the demolition of the adjoining townhouse. The repairs have now
been completed. Temporary accommodation was provided whilst repairs were
completed.
The complainant still has concern with some of the rectification works. The
complainant says the ongoing delays and claims handling has aggravated her anxiety
and caused stress and inconvenience.
1.2 Issues and key findings
Has the insurer completed the repairs in accordance with the terms of the
policy?
Yes. The insurer has completed the repairs to the property including relevant
rectifications works accordance with the terms and policy. Any ongoing issues with
the repairs are covered under the terms of the policy.
Is the complainant entitled to compensation for non-financial loss?
The available information indicates that the insurer acted reasonably and fairly in
completing their repairs and providing temporary accommodation.
The delays in the repair process were not caused by the insurer‟s claims handling but
due to delays in the demolition of the adjoining property which was outside the
insurer‟s control.
Determination
This determination is in favour of the insurer.
The insurer has completed repairs in accordance with the terms and conditions of the
policy. Should further issues arise with the repairs the complainant can lodge a further
claim with the insurer.
Determination| Case number: 711101 Page 3 of 5
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
This complaint has been subject to a recommendation. The recommendation was in
favour of the insurer. A copy of the recommendation is attached to this determination.
This determination follows consideration of all the rele vant information including
information received following rejection of the recommendation. The determination is
based on what is fair in the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice including codes of practice and
prior determinations where applicable.
2.1 Has the insurer meet its liability in accordance with the terms of the
policy?
Policy provides cover for damage caused by fire and for temporary
accommodation.
The complainant policy is a home contents policy. The policy provides cover for a
series of insured events including fire. The policy also provides temporary
accommodation benefits where the building is damaged to such an extent that it
cannot be live in. Temporary accommodation is payable for the period that is
reasonably necessary or the 12 months or whatever is the lesser.
The insurer has completed repairs in accordance with the terms of the policy.
There is no dispute that the complainant‟s property was damaged in the fire on 19
August 2019. According to the available information the adjoining property was
significantly damaged and required demolish. The demolition of the property was
outside the control of the insurer.
Papers approving demolition were not signed until February 2020. O n completion of
the demolition of the adjoining property the insurer completed repairs as required
under the terms of the policy. A certificate of satisfaction of works was signed by the
complainant on 27 August 2020 and the complainant was returned to the property.
Insurer provided temporary accommodation benefits
The insurer obtained an engineering report which indicated the firewall between the
complainant property and the adjoining property had prevented the complainant‟s
property suffering structural damage. The engineer believed the complainant could
return to her property after appropriate cleaning and certification of safety occupation.
The complainant expressed discomfort with resuming occupation prior to demolition
being completed. The complainant suffers from health issues and would be likely
Determination| Case number: 711101 Page 4 of 5
suffer stress and pressure during the demolition faze of the adjoining property if
temporary accommodation was not granted. It is reasonable in these circumstances
that temporary accommodation be granted. The insurer agreed to provide temporary
accommodation and says as a gesture of good will it extended the temporary
accommodation offer in excess of the policy limits.
I do not agree with the insurers comment that it extended the benefits on several
occasions beyond the policy limits. The policy provides the temporary accommodation
of up to 12 months whilst it is reasonably necessary. The complainant‟s temporary
accommodation benefits were provided for approximately 12 months until August
2020.
The insurer has meet its obligations under the policy.
The complainant raised issues with the quality of the repairs. Rectification of some of
the repair work was required in particular:
remediation of a scratch on the driveway
repainting of a brick peer at the front of the townhouse.
The complainant has since raised concerns with the rectification works as follows:
only 1 coat of sealing paint was on the driveway
the painting of the rendered brick wall had left it with a blackened appearance
the rear fence was damaged during the fire
There is no information to support the complainants claims with respect to the further
rectification work. The insurer‟s builders indicate the damage to the fence was a result
of the natural drying of the timber and not a result of the fire. There is no evidence
that more than 1 coat would be required to complete the repairs to the driveway. The
insurer says the paint should dry similar to the rest of the render.
Based on the available information, I accept the insurer has met its obligations under
the policy. Should the complainant have further concerns with the repairs then under
the terms of the policy the complainant can notify the insurer who remains liable to
meet the cost of repairs arising from the fire.
Is the complainant entitled to compensation of non-financial loss?
AFCA can award compensation for non-financial loss
Under Rule D3.3 of the AFCA Rules, AFCA can award compensation of up to $5,000
for non-financial loss where a complainant suffers an unusual degree of physical
inconvenience or time taken to resolve a situation. AFCA expects a complainant to be
moderately robust in dealing with a complaint as there will always be inconvenience
and delays associated with a claim.
Determination| Case number: 711101 Page 5 of 5
Delays caused by demolition of neighbouring property
There is no dispute that there was considerable delay between the fire and the
commencement of any repairs. The repairs could not commence until the demolition
of the adjoining property had been completed.
The demolition of the adjoining property was delayed. It is not clear exactly why the
demolition was delayed but this was outside the control of either the complainant or
the insurer. Authority to demolish the premises was eventually signed in February
2020. The demolition of the property was completed on 1 May 2020.
It is not in dispute between the parties that following the completion of the demolition
the insurer attended to the repairs including cleaning of the property. The complainant
acknowledges this by signing a certificate of completion on 27 August 2020 which
allowed the complainant to return to the property. Until that time the insurer had
agreed to cover temporary accommodation costs. Further the insurer agreed to cover
storage costs of contents even though it considered the house inhabitable from 2019
and during the repairs.
Insurer has acted reasonably
There is no dispute that there were some rectification works required. The
complainant identified some minor damage to the driveway and some ongoing issues
with the painting of the front pier. of the house. The insurer has acted reasonably in
rectifying these repairs. I accept the complainant has some ongoing issues with the
damage however the builder reports confirm this damage is not related to the fire.
There is no dispute that it has taken some time for the insurer to complete the repairs.
The complainant has suffered considerable stress and inconveniences because of the
fire. This is however not a result of the insurer‟s conduct. The inconvenience and
delay is associated with the fire to the adjoining premises and the delays in the
demolitions of those premises.
In the circumstances the insurer is not liable to pay compensation for non-financial
loss.
Recommendation
Case number 711101
Financial firm Allianz Australia Insurance Limited
Recommendation | Case number: 711101 Page 1 of 8
Case number: 711101 1 October 2020
3 Overview
3.1 Complaint
The complainant‟s home suffered fire damage on 2 August 2019 and she lodged a
claim under her home building and contents insurance policy with the financial firm
(insurer).
The insurer accepted the claim.
Initially, the complainant was dissatisfied with the insurer‟s report that the home was
safe to occupy after the impact of the fire. She asked that the insurer:
re-examines the home, and
covers her for temporary accommodation until all the necessary examination and
building work was completed.
The re-examination, temporary accommodation and repairs requested have been
completed/provided, however, the complainant remains dissatisfied with the insurer‟s
handling of the claim which she says increased her anxiety and caused stress and
inconvenience.
3.2 Issues and key findings
Is the complainant entitled to compensation?
I do not accept the insurer caused unreasonable delays or mishandled the
complainant‟s claim.
The insurer is not required to pay any compensation.
Other matters
The complainant raised and continues to raise new concerns following completion of
repairs to the property in July 2020. The insurer has sufficiently addressed the issues
relating to driveway rectification and shown the claimed damage to a lounge suite is
not due to the fire event or repairs/rectification it conducted.
3.3 Recommendation
This recommendation is in favour of the insurer.
The insurer is not required to pay compensation to the complainant.
Recommendation | Case number: 711101 Page 2 of 8
4 Reasons for recommendation
4.1 Is the complainant entitled to compensation?
Complainant says the insurer mishandled the claim and caused delays
The complainant says the insurer did not handle her claim appropriately because she
constantly had to pursue it before any action was taken, particularly in relation to the
status of demolition and reconstruction of the neighbouring fire damaged home. She
says:
she had to deal with different organisations involved (such as the neighbour‟s
demolition company and builder, local council etc) to ensure progress was made
but for her persistence, repairs would have taken longer and some issues (such as
damage to common wall during neighbour‟s demolition) would not have been
identified
through the course of the claim, the i nsurer did not respond to her communications
promptly
the insurer‟s conduct has caused her stress and exacerbated her mental health
condition (anxiety and depression).
AFCA approach to delay
In considering claim handling/delays, there is no standard formula to assess what is a
„reasonable‟ time for an insurer to resolve a claim. However, the following are
considered:
the individual facts and circumstances of each claim, and
the conduct of both parties.
If a claim takes an extended period of time to resolve, the time taken would not
necessarily be considered unreasonable on the insurer‟s part if there were no
extended periods of inaction and/or any delay was due to the conduct of other parties
or factors that were outside of its control.
Compensation payable in some circumstances
Under the AFCA Rules, it can award up to $5,000 compensation for non-financial
loss. We will only award this type of compensation if you suffer an unusual degree of
stress, inconvenience, or delay because the insurer mishandled your claim.
AFCA recognises that making a claim can be stressful and time-consuming, even if
the insurer handles the claim correctly. We will not award compensation for the
ordinary degree of inconvenience that comes with making a claim.
Recommendation | Case number: 711101 Page 3 of 8
Insurer did not unreasonably delay or mishandle the claim
The timeline provided in section 3.2 of this recommendation identifies key
occurrences from the date of loss (2 August 2019) until July 2020 when the building
repair works were completed, and the complainant returned permanently to her home.
The timeline also shows some issues raised during the claim process and the actions
taken to address them. Information in the timeline is taken from exchanged email
bet ween the complainant and insurer/insurer‟s agents and the insurer‟s file notes.
Neither party has disputed the content/accuracy of these documents.
After carefully reviewing the available information, I do not accept the insurer took an
inordinate amount o f time to process the complainant‟s claim and complete repairs. I
have taken the following into account:
The insurer arranged inspection of the property within weeks of claim lodgement
on 4 August 2019. The insurer‟s assessor (C) first inspected the premis es on 5
August 2020; between 5 and 29 August 2019 a building consultant inspection as
well as make-safe was also conducted.
The insurer took immediate steps to obtain the neighbour/neighbour‟s insurer‟s
details and follow up with them about demolition as the insurer could not
commence cleaning, re-inspection and any required building repairs until the
demolition was completed.
Demolition of the neighbouring property was not completed until end April 2020
despite the insurer‟s effort in contacting the neighbour‟s insurer/contractor/builder
and local council to expedite it.
Shortly after the demolition was completed, the insurer arranged re -inspection by
its building consultant and took steps to organise building and cleaning work
identified in the consultant ‟s report.
While the available information shows the complainant regularly followed -up
concerns with demolition, concerns about cleaning/repairs etc , it also shows there
was no extended or unreasonable period of inaction by the insurer.
The available information does show the complainant repeatedly contacted the
insurer when her temporary accommodation was due to expire. However, given the
ongoing uncertainty about when demolition would occur, I do not think it was
unreasonable for the insurer to book short stays and review/extend as necessary.
Considering the above and in all the circumstances of the claim, I am satisfied the
insurer handled the claim appropriately and did not cause unreasonable delays. The
overall duration/delay of the claim was not due to inaction or failure by the insurer,
rather it was mainly due to delays in demolition by a third -party which was outside of
the insurer‟s control.
I understand the circumstances and duration would likely have caused a level of
stress and inconvenience to the complainant. However, the insurer is not required to
Recommendation | Case number: 711101 Page 4 of 8
pay any compensation to the complainant as these did not arise due to its
mishandling of the claim.
4.2 Other matters
The insurer‟s proposed actions in relation to arranging repairs and its handling of the
claim (addressed above) were the main issues in this complaint.
The repairs have been completed, therefore it is not necessary to address that issue
further. However, the complainant has raised concerns about a lounge suite/couch
and damage to her driveway. They are addressed below:
Driveway
The available information shows the insurer has addressed the concerns about fixing
minor damage to driveway during repairs. As this is not in dispute, it is not addressed
in this recommendation
Couch
The available information does not show the couch damage was as a direct result of
the claimed fire event or cleaning authorised by the insurer. In the absence of any
evidence to the contrary, the insurer is not required to cover the damage.
The insurer is not required to take any action in relation to these matters.
Should the complainant raise any other/new issues with repairs, these need to be
addressed with the insurer in the first instance.
Recommendation | Case number: 711101 Page 5 of 8
5 Supporting information
5.1
A full exchange of the relevant information has taken place between the respective
parties and each party has had the opportunity of addressing any issue raised.
All the provided material has been read and considered. The parties raised numerous
issues in their submission to AFCA. For this recommendation, commentary is
restricted to only those issues considered relevant.
5.2 Relevant timeline
Date Details
02 - 08 - 2019 Fire incident - neighbouring townhouse burnt down
04 - 08 - 2019 Claim lodged: “The townhouse beside me has caught fire. This is affected my
property. Police has advised me not to stay here. This is in the news.”
loss adjuster (C) appointed
05 - 08 - 2019 C inspected premises
06 - 08 - 2019 Complainant rais ed questions about claiming for contents
07 - 08 - 2019 C reports short - term accommodation arranged for complainant
13 - 08 - 2019 C obtained approval to appoint engineer/consultant to assess possible fire damage,
any impact on structural integrity of complainant‟s building
14 - 08 - 2019 C arranged extension of complainant‟s emergency accommodation
19 - 08 - 2019 Insurer‟s building consultant (T) report. The report includes:
> complainant‟s building is safe for re - occupation after cleaning
> post demolition inspection should be carried out to check walls, any damage
during demolition or heat effect of fire
21 - 08 - 2019 C wrote to neighbour‟s insurer (I) about when its demolition will occur
27 - 08 - 2019 C‟s report includes:
> information obtained about owner/ insurer of neighbouring property
> that „I‟ refused to provide owner‟s contact details
> inquires made with original builder and awaiting response
> contacted local council and they advised emergency order placed on
neighbouring property, and awaiting furt her information from council
Recommendation | Case number: 711101 Page 6 of 8
Date Details
> cleaning to occur after demolition of neighbour‟s property
> emergency accommodation at „Q‟ serviced apartments for 13 nights
29 - 08 - 2019 C wrote to complainant‟s neighbour regarding ogress of demolition
09 - 09 - 2019 C‟s report includes:
> make safe information
> conducted independent enquiry, letter sent to the owner of neighbouring
townhous e with no response to dat e
> further contact with „I‟. „I‟ advised neighbour to be cash - settled - including for
demolition of property.
> temporary accommodation extended
> concerns about demolition delay by neighbour
08 - 10 - 2019 insurer instructed C to issue notices to neighbour and her insurer regarding their
ongoing delay in demolition
23 - 10 - 2019 C wrote to „I‟ following up demolition and demanding immediate commencement
C‟s report includes:
> neighbour and „I‟ had not res ponded
> information obtained suggests neighbour arranging demolition
> temporary accommodation to 30 October
> complainant dissatisfied with insurer‟s earlier request that she seek reasonable
short - term accommodation due to high cost of „Q‟
> request for approval of th ree - month stay proposed by Q
25 - 10 - 2019 Complainant‟s neighbour responds to C saying:
> still awaiting engineers‟ report for slab
> once report received demolition should commence
> “I do not understand how this affects your client living in her townhouse as each
townhous e is an individually built townhouse…the rest of the neighbours are
able to”
29 - 10 - 2019 C report including:
> three - month temporary accommodation at Q approved from 30 October 2019
> still no response from neighbour and/or her ins urer about demol ition
27 - 11 - 2019 C report:
> letter received from neighbour saying awaiting engineering report to commence
demolition
Recommendation | Case number: 711101 Page 7 of 8
Date Details
28 - 10 - 2019 Complainant says “anxiety” being caus ed due to constant follow - up of temporary
accommodation and insurer asked C to look into getting 3 months stay arrangement
with Q again. It also advised the complainant of its instruction to C.
07 - 11 - 2019 complainant says Q no longer providing room cleaning and linen changes under new
arrangement and expressed dissatisfaction
06 - 02 - 2020 complainant contacted insurer and:
> advis ed demolition documents received from third party
> asked damage that may be caused during demolition by neighbour
29/02/ 2020 C report:
> complainant has signed paperwork wit h third - party demolition company.
> Awaiting advice on when demolition to commence
> accommodation extended to 1 March 2020 at whic h time temporary
accommodation monetary limit under the policy exceeded.
13 - 03 - 2020 insurer looked into extension of temporary accommodation arrangement with Q
insurer con sidered if complainant home habitable if cleaned
C advised demolition and debris removal of neighbouring property yet to occur.
C said local council will be contacted to apply pressure to complete demolition.
21 - 03 - 2020 S wrote to C confirming he sent a text message to the complainant arranging for
cleaning to commence 23 March 2020 (following a site meeting) and that
complainant has declined
30 - 03 - 2020 Insurer‟s building consultant (T) re - attended site post demolition of neighbouring
townhous e to review complainant‟s concerns about structural int egrity and smoke
residue
31 - 03 - 2020 complainant contacted the insurer and complained about temporary accommodation
expiry
insurer extended accommodation to 03 - 04 - 2020
01 - 04 - 2020 AFCA complaint lodged
02 - 04 - 2020 Complainant called insurer about:
> temporary accommodation and insurer‟s consideration of moving her back into
the home prior to demolition of neighbouring property
> complainant about having waited 6 months
> complained about not being contacted by the insurer since 25 March 2020
Recommendation | Case number: 711101 Page 8 of 8
Date Details
insurer agreed to further 2 months temporary accommodation
insurer noted concern that complainant had almost exhausted sum insured to
temporary accommodation
08 - 04 - 2020 Restorer (S) email to insurer advising complainant declined cleaning of premises the
following week
05 - 05 - 2020 Complainant‟s structural engineer (B) inspected building post - demolition
05 - 05 - 2020 T‟s report. T identified issues for repair and concluded building safe to occupy.
08 - 05 - 2020 B‟s report on co ndition of the complainant‟s building. The report includes:
> no structural damage from fire
> external cement sheet singed and should be fixed
> some structural damage likely caused during demolition of neighbouring
property. Replacement to be completed by qualified builder.
> further cleaning recommended
08 - 05 - 2020 S supplementary report showing cleaning/restoration work completed
15 - 05 - 2020 C report:
> “demolition of the adjoining property was finally completed”
> damage to the side wall of complainant‟s dwelling during demolition
> T re - attendance report, scope of works has been provided to a builder for
quotation of repairs identified
> S for cleaning occurred. However, outstanding items of cleaning remain.
07 - 07 - 2020 R informs insurer that complainant has returned signed contract
09 - 07 - 2020 Building permit application
July 2020 Building work complete
Cleaning complete
complainant moved back into home