Home / Suncorp Group / Determination 710755

Determination 710755

Water leak claim: cracking and movement damage denied; cash settlement offer

FirmSuncorp Group
Decided2020-09-02
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for a water leak and for cracking and foundation movement damage to the home. AFCA found the movement damage was long-standing and not caused by the leak or an insured event, and that the insurer's cash settlement offer for the bathroom repairs was fair.

The complainant must establish a loss caused by an insured event during the period of insurance, and expert evidence showed long-term foundation movement rather than the leak.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 710755 Financial firm AAI Limited Determination | Case number: 710755 Page 2 of 21 Case number: 710755 2 September 2020 1 Determination overview 1.1 Complaint The complainant held a home and contents policy with the financial firm (insurer). On 4 September 2019, the complainant lodged a claim after discovering a water leak in the bathroom. After assessing the claim, the insurer offered to cash settle the complai nant for the repairs to the bathroom, less excess. However, the insurer denied other aspects of the claim, namely cracking and movement related damage throughout the property. The insurer says this damage was not due to the leak and is not covered under the policy. The complainant disputes the insurer’s assessment stating that the movement related damage was caused by the water leaking in the bathroom and under the property. This has caused the foundations to subside. Therefore, the complainant is seeking the insurer to cover the additional repairs required. This includes re-stumping the property. 1.2 Issues and key findings Is the insurer’s settlement offer fair ? Yes. The available information does not show the movement and cracking damage was caused by the leaking pipe or is otherwise covered by the policy. Therefore, the insurer’s settlement is fair. 1.3 Determination This determination is in favour of the insurer. The insurer ’s settlement offer is fair. Determination | Case number: 710755 Page 3 of 21 2 Reasons for determination 2.1 Is the insurer’s settlement offer fair? Complainant must show a valid claim The initial onus is on the insured to show, on the balance of probabilities, a loss claimed falls within the cover provided by the policy of insurance. This is known as establishing a valid claim. If the complainant can establish a valid claim, the onus transfers to the insurer to establish it is entitled to decline the claim. The complainant ’s p olicy covers loss or damage caused by an insured event during the period of insurance. One of these events is escape of liquid. The PDS defines an ‘ event ’ or ‘incident’ as: a single event, accident or occurrence which you did not intend or expect to happen There is no dispute that a leaking pipe was identified in the bathroom a nd this has caused damage. Therefore, a valid claim has been established for this damage. The dispute is whether this event caused the movement and cracking damage throughout the property. Various expert reports have been provided The insurer has produced various reports to support its position. All of these have been summarised in section 3. The panel does not propose to go through them in detail. The main report is from engineer JH. JH concluded the movement damage is associated with poor foundation performance over many years. The complainant has provided no expert evidence in support. The complainant says that when they levelled the house in 2017, the contractors did not observe the subfloor being wet. However, no evidence was provided from these contractors directly. JH’s evidence is persua sive Based on the available information, the panel does not accept the information shows the movement and cracking damage is due to the leaking pipe. This is because JH’s evidence is persuasive. JH noted that a leak would cause localised footing movement. However, floor level surveys show footing movement is global and significant. Determination | Case number: 710755 Page 4 of 21 There are numerous examples of the property suffering long term footing movement. This includes the following:  plasterboard cracking that is aged and not proximate to the leak  patched areas in the home that have re-opened  stepped cracking in the brickwork with evidence of repatching  a ‘crudely lain line of concrete’ at the rear of the dwelling which shows an attempt to keep excessive water from flowing into the property JH, and other experts, identified several long-term issues with the site drainage. This includes the following:  insufficient grading of the perimeter – the line of concrete installed at the rear is consistent with this  a stormwater line was installed above the west side of the property and is discharging to the surface of the garden – it is unclear when this was installed but confirms there is an issue with this aspect of the stormwater system  a drain at the rear of the property that was still connected to the original and disconnected damaged stormwater line – water from the rear of the property is channelled to the damaged plumbing lines  damage to a sewer line between the kitchen and toilet  a non-compliant plumbing line installed to extend the rear gulley outlet The long-term movement is consistent with the fact the complainant said he had to level the property in 2017. Based on all this, the panel is not persuaded the movement and cracking damage was caused by the leaking pipe in the bathroom. Movement and cracking damage is not covered The panel has considered whether the policy could apply to some of the site drainage issues identified (e.g. damaged sewer line). The panel does not accept it does for the following reasons. The information must show the loss or damage was caused by a single event, accident or occurrence. It is not clear from the available information that one specific incident caused the long-term foundation movement or that this incident is an insured event. Further, it is far from clear if the event occurred during the period of insurance. The complainant had incepted the policy on 21 June 2016. The policy lapsed on 21 June 2017. On 26 January 2019, a new policy was arranged which the claim was lodged under. Determination | Case number: 710755 Page 5 of 21 The issues identified by JH are long-standing and could have readily occurred before the insurer was on risk. This is consistent with the fact that when the insurer inspected the property for a previous claim on 9 June 2016, there was pre -existing damage and patching evident. This shows the movement was occurring before then. Accordingly, the information does not show the loss occurred whilst the insurer was on risk or was caused by an insured event. Therefore, the panel does not accept the insurer is liable for the movement and cracking damage claimed. Insurer’s offer is fair The insurer has provided a scope of works to repair the bathroom damage. This includes mould remediation limited to the bathroom. There is no evidence to show this scope of works is unreasonable. The insurer has agreed to cash settle the complainant as follows:  $17,439.51 – this is based on the builder’s quote for these scope of works  $3,487.90 – this is a 20% uplift/transfer of risk given the insurer is cash settling the claim  $3,000 for temporary accommodation – this is based on a daily rate of $150 over 20 days The panel accepts it is reasonable for the insurer to cash settle the claim given the other maintenance issues identified. The panel also agrees the amount is reasonable. It is based on a quote with a 20% uplift. This uplift should account for the fact the quote is not actionable and the risk of the works are being transferred to the complainant. There is also no evidence to refute the fact that the rate of accommodation or the time required to conduct the mould remediation (two weeks) in the bathroom is reasonable. Accordingly, the panel accepts the insurer’s cash settlement is fair in all the circumstances. Determination | Case number: 710755 Page 6 of 21 3 Supporting information 3.1 AFCA Approach This complaint has not been the subject of a recommendation. Due to the nature of the complaint, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the AFCA Rules. The panel consists of an Ombudsman and two representatives with consumer and insurance experience . The panel has decided this complaint based on what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance, good industry practice and previous relevant determinations of AFCA or predecessor schemes (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. 3.2 Relevant Policy Terms Page Product Di sclosure Statement 22 Escape of Liquid We cover Loss or damage to the building caused by liquid leaking, overflowing or bursting from any of the following:  refrigerators, freezers, dishwas hers and washing machines;  any drain, fixed pipes, roof gutters or guttering and rainwater downpipes, drainage and sewage systems  fixed tanks  swimming pools or spas  waterbeds  baths, sinks, toilets and basins  fixed heating or cooling system;  water main, fire hydrant or water supply pipe;  an aquarium. We do not cover  loss or damage caus ed by flood or storm surge; Determination | Case number: 710755 Page 7 of 21 Page Product Di sclosure Statement  wear and tear, or loss or damage by the escape of liquid occurring as a result of a gradual process of leaking, splashing, dripping or overflowing over a period of time when you could reasonably be expected to be aware of this condition 37 What we do not cover – general exclusions (cont’d) You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: Defect, structural fault or design fault a defect, structural fault or design fault that you knew about (or should reasonably have known about) and did not fix before the loss or damage occurred (e.g. if there are signs that a defect previously caused damage, we will not pay a later claim for further damage from this defect). a defect, structural fault or design fault that you knew about (or should reasonably have known about) and did not fix before the loss or damage occurred (e.g. if there are signs that a defect previously caused damage, we will not pay a later claim for further damage from this defect). Ground movement erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover landslide or subsidence that is specifically covered under the following insured events: • ‘Storm’; • ‘Flood’ (but only if you have cover for ins ured event ‘Flood’); • ‘Earthquak e and Tsunami’; • ‘Explosion’. 40 What we do not cover - general exclusions (cont’d) You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: Wear, tear and gradual deterioration wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration such as, but not limited to: • tiles and their adhesive or grouting breaking down; Determination | Case number: 710755 Page 8 of 21 Page Product Di sclosure Statement • weathering of roof tiles or roof ridge capping; • gradual weathering and breakdown of bricks, mortar or concret e. 55 Well maintained and in good condition means the building does not have any faults or defects that might cause loss or damage to building, loss or damage to property of others or injury to people. This includes but is not limited to the following: • the roof does not leak when it rains; • there are no areas of the roof that are rusted through; • there is no wood rot, termite or white ant damage to the building; • there are no holes in floors, walls, ceilings or any other parts of your building (e.g. external wall cladding, internal plaster, floorboards); • there are no boarded up or broken windows; • there are no steps, gutters, flooring, walls, ceilings or any other areas of the buildi ng that are loose, falling down, missing or rusted through; • all previous damage including damage caused by flood has been repaired; • the building is not infested with vermin; • there are no squatters or unauthorised persons occupying the building. 3.3 Relevant Expert Reports Record Key points Insurer Plumber ( BB ) Report 6 September 2019  a rrived on site to conduct a leak detection.  a hissing noise could be heard in the main bathroom.  t he cold line pressure test failed.  u sed acoustic listening to locate the burst.  t raced noise to below the bath tub area.  g ained limited access to under the house, noted the ground is very wet with water pooling.  t he burst could be seen on the plastic line near to the bat h trap as indicate d in the photo.  a dvis ed the Insured to isolat e at the meter when not i n use. Determination | Case number: 710755 Page 9 of 21 Record Key points  Repair the burst on the cold line unde r the hous e near the bath trap Insurer Builder (A1) Report 9 September 2019   the customer has informed approximately a week ago a noticeable hissing sound could be heard in the bathroom  the sound was occurring continuously and the ground beneath the house was wet  cracks have occurred to the wall in the living room which may be related to the leak  it was explained to the customer that to repair the leak was not claimable and should be rectified immediat ely to prevent any damage occurring  the customer advised that they were unable to find a prompt plumber to repair the leak  a leak could be heard occurring wit hin the lower wall cavity in the bathroom adjoining the laundry  the subfloor area beneath the house was wet from the leak.  the cracks observed in and around the living room archway to the entry were observed to be old and not considered to be consistent with damage caused by the eve nt as they were not in the vicinity of the leak  leak from cold water pipe in bathroom  a hissing noise could be heard in the main bathroom.  the cold line pressure test failed.  used acoustic listening to locate the burst.  traced noise to below the bath tu b area.  gained limited access to under the house, noted the ground is very wet with water pooling.  the burst could be seen on the plastic line near to the bat h trap  repair the burst on the cold line under the house near the bat trap  old hairline cracks t hroughout the hous e wall and ceiling linings – general wear and tear  old cracks to several floor tiles in kitchen - general wear and tear  water damage to laundry ceiling – not related to event.  inadequate drainage to rear of property allowing water to flow towards and under hous e extension Insurer Builder (A1) Amended Report 9 October 2019  arrived on site to conduct a leak detection  burst pipe located on the previous inspection has been repaired, mains pressure test passed  carried out a leak detection to the shower, breach test passed  there is no silicone behind the spindle penetrations allowing large amounts of water to escape, moisture was  seen with the thermal to adjacent walls and flooring in the hallway water will be discharging under ho use  w hen flood testing the shower base water was escaping onto floor tiles from the screen. Determination | Case number: 710755 Page 10 of 21 Record Key points  i nspected the laundry.  t he trough breac h passed.  s ome wat er is leaking to the below cabinetry from the washing machine waste entry.  w ashing machine is sound.  REPAIRS TO BE CARRIED OUT:  r epair the leaking shower enclosure. · Repair sealing around the trough Insurer Mould Remediation (FR) Scope of Works 14 October 2019  t he following quotation has been prepared based on the information gathered from the onsite inspection conducted by our Project Manager on 02/10/19 in the presence o f Mrs. Insured and A1 Builders  t he leaking pipe was underneath the bathroom floor, the bath has been remove d in order to rectify the leak  t he Insured has installed new tile underlay over the sub - floor where the bath was and up the walls  p erformed moisture readings with the use of a moisture met er set on hammer probe mode which indicated timber sub - floor is 80% moisture affected at depth throughout  i nspected photos from the plumbing leak detection report, which showed evidence of visual mould growt h on timbers underneath the house  n on - claim related damages evident in the bathroom around the shower and vanity;  e ntire house has a lot of non - claim related issues;  s ource removal to be undert aken in bathroom before crawl space drying can be fully quot ed for;  h ouse is very old and a high chance of containing asbestos, testing may be required before source removal is undertaken;  Insurer Asse ssor (AS) Report 22 October 2019  assessor and A1 are of the expert opinions that the pre - existing damages have been present and occurring over many years (highly likely to be 10+ years) which has not been maint ained to a satisfactory standard  due to the p oor deteriorating condition of this property Assessor is of the opinion that this customer has failed their ‘Duty Of Disclosure’ when taking out the policy with AAMI  customer’s son his father purchased the home approx. 4 - 5 years ago  there is clear evidence that this home was purchased with multiple defects and pre - existing damage throughout the home  there are only 3x external downpipes around the entire home (located on the LHS of the home) – insufficient downpipes installed to exist ing guttering  guttering is in poor condition and silicone has been used to seal up corner junction connections.  customer’s son advised there LHS front corner brickwork which has dropped and been patched up with mortar/silicone (cracked Determination | Case number: 710755 Page 11 of 21 Record Key points brickwork) was pres ent when they purchas ed the home.  customer’s son advised there is a blockage to the earthen ware pipes underground which they have not unblocked (and have been well aware of) and rather installed illegal stormwat er plumbing above ground to the existing 3x downpipes which discharges into the front yard  customer’s father has installed a risen section (py ramid style) of roughly installed concrete to the rear concrete path, to prevent water from flowing in under the subfloor area. This suggests there has been an ongoing issue of years of rainwat er run off getting in under the home into the subfloor area  insufficient grade / fall to the concrete path surrounding the home  there are multiple plumbing defects / issues present.  rotted timber fascia boards, cracked p anes of glass windows sealed with silicone, and cracking to external brickwork around the home, internal cracking to plaster walls, cornices.  customer’s son advised his father had the existing stumps ‘jacked & packed’ and relevelled approximately 2 - 3 year s ago.  •pre - existing poor attempt to repair rood ridge capping tiles evident in photos (long term damage). Roof is in poor condition.  the subfloor (soil / dirt) has turned into a wet area / very muddy due to a lot of dampness that has entered the subfloo r area (this all has not been caused by the leak in the bathroom).  client Manager to follow up with (Fraud & Intelligence this claim/policy  client Manager to forward entire claim and policy to (Fraud & Investigations) team to review, duty of disclosure is a concern.  client Manager to chase up with *** of A1 Building Group the following two reports to be obtained  roofing expert report  plumbing CCTV Camera inspection leak detection expert report Insurer Leak Detection ( LD ) Report 30 October 2019  a rrived on site to carry out a CCTV ins pectio n of the storm water and sewer  t he storm water runs along the west side of the house in PVC above the ground inadequat ely supported and discharges onto the front garde n  o ld earthenware downpipe entry points are still visible and filled w ith debris  t here is a surface drain to the rear of the property which is still connected to an ol d eart henware storm water line  t he PVC sewer line was inspected from the toilet and kitchen, a break was identified nearby as shown in the mud map  t he bathroom and laundry run to a gully which is under the extension. Unable to access the gully to inspect  i t appears a non - complaint horizontal extension of the gully outlet has been fit ted as shown in mud map  w hen running both bathroom and laund ry fixtures no water seen at I/O downstream rear of the property, instead water was seen discharging under the extension by the gully with wat er po oling Determination | Case number: 710755 Page 12 of 21 Record Key points likely due to a blockage  engage a licensed plumber to; ‒ run compliant storm water to the legal point of discharge ‒ connect the surface drain to the storm water ‒ blank old eart henware downpipe entries ‒ repair the break in the sewer ‒ gain access to the gully under the extension, clear blockage and address non - compliant installation Insurer Roofer ( RR ) Report 30 October 2019  conducted a roof report  located multiple cracked tiles  some tile are siliconed between joins  various repairs have been carried out previously to ridge capping, however cracks and gaps remain in mortar  maintenance issues – cracked tiles and m ortar Insurer Engineer (JHA) Report 9 January 2020  Conc erns were raised in relation to the condition of the dwelling following the recent discovery of a plumbing leak under the bathtub in the bat hroom.  Initially, during the inspection the insured pointed out the location at which the leak occurred in the bathroom. The insured explained that the leak had recently been identified by a plumber. It was advis ed that the bathtub had been removed to repair the damaged plumbing line.  The insured also pointed out cracking in the interior walls throughout the dwelling including cracking in the hallway and meals area during the inspection.  Furthermore, the ins ured explained that mould had recently grown on some of the ceilings throughout the dwelling.  During an inspection of the exterior the insured advised that the valley iron and rear guttering had been replaced. However, several significant structural issues were observed during the inspection.  Further enginee ring investigation of the structure was therefore required to determine their cause, influenc e on the structure and the resulting condition of the structure, and whether any of the damage may be attribut ed to the recent escape of liquid.  The following pho tos indicate the condition of the dwelling at the time of the inspection  A structural inspection of the dwelling was conducted in order to determine its condition as well as the cause and extent of any evident damage. Prior to the JHA inspection the bathtu b had been removed from the bathroom in order to repair the detected leak.  During the inspection the insured pointed out the location of the leak as well as some location of minor cracking, separation and mould throughout the interior. The insured also po inted out repairs conducted the roof including the replac ement of the valley iron and guttering.  The inspection noted that the dwelling was constructed on concrete stumps set into clay - based founding soils. The exposed Determination | Case number: 710755 Page 13 of 21 Record Key points subfloor soils founding the dwelling remained very moist indicating evidence that the recent leak may have caused structural damages. However, extensive pre - existing and long - term damages were noted all throughout the dwelling. Further investigation of the structure was therefore conducted  T he inspection of the dwelling interior observed the reported leak location in the bathroom. It was noted that the bat htub had been removed to repair the plumbing leak prior to the engineering inspection. Fibre cement sheeting had been installed over the fl ooring and walls as a temporary lining following the removal of the bathtub.  An inspection of the remaining floor and wall linings within and around the bathroom did not observe evidence of recent cracking or movement - related damage throughout this area. An inspection of the sunroom extension at the rear of the bathroom also did not note any furt her evidenc e of recent cracking or movement - related damage.  It is important to not e that when significant leaks occur, the reactive founding soils of the subfloor often swell at the leak location. This swelling can cause differential movement of the structure and cracking to the brittle materials lining the interior such as the floor tiles and plasterboard walls at the leak location. There was a noticeable lack of recent cracking observed throughout the bathroom and the surrounds.  During the inspection ot her areas of damage were obs erved throughout the dwelling. Cracking was observed through the plasterboard walls and ceilings in many locations. However, close insp ection at eac h location found that each of the cracks presented chipped and stained edges consistent with damage that had occurred many years prior to recent events.  Furthermore, the cracks were locat ed all throughout the dwelling. Typically, cacking caus es by a plumbing leak is contained to a localised area within close proximity to the leak. This is also known as a zone of influence. Damage was noted all throughout the dwelling and was not contained to a zone of influence .  The insured advised that there were concerns in relation to mould growth throughout the dwelling. The inspection observed mould across the cornice in the front bedroom. It was noted that while mould was evident in this location, it was more significant at the front corner of the dwellin g than it was at the location of the leak in the bathroom. There was also minimal mould growth in the hallway and rooms surrounding this location. The obs erved mould growth did not appear to be consistent with mould caused by the recent plumbing leak.  Fur ther inspection throughout the interior observed cracks that had been previously patched and painted. Patching was observed all throughout the dwelling. Some of the patched locations had since re - cracked. It was also observed that the bottom of the front e ntry door was damaged and had been planed off. The insured advised that the door had been misaligning for many years causing it to Determination | Case number: 710755 Page 14 of 21 Record Key points catch at the bottom. The inspection noted that these damages were consistent with damages that had occurred many years prior. The damages were also consistent with damages often attributed to long - t erm foundation movement.  The inspection conducted through the kitchen and meals room areas noted the bubbling of paint as well as poorly repaired cornices and walls. The evidence sug gested that repairs were not effectively conducted in this location following the reporting of the damages not ed in the 2016 claim.  An inspection of the subfloor was conducted through the floor hatch in the bedroom wardrobe. The inspection noted that the subfloor soil below the hatch was very wet. Elsewhere throughout the subfloor excessive moisture was also apparent.  An inspection of the dwelling exterior was then conducted. The inspection observed that the roof’s tiled hips had been re - bedded and re - poin t ed. The bedding and pointing however, was not repaired to a professional standard or a tradesman - like manner. The insured advised the previously - det eriorate valley iron and guttering had been replaced.  Further inspection of the exterior observed many iss ues. The downpipes on the left of the dwelling had been redirected to above - ground plumbing lines. The stormwater is then concentrated to an area in the front yard. This attempt to repair the dwelling’s stormwater system indicates a significant pre - existin g plumbing issue. The evidence indicates that significant amounts of water have leaked from the stormwater line into the subfloor prior to this repair being attempted.  Furthermore, the October 2019 Bay & Beyond plumbing report also indicated that a drain a t the rear of the property remains connected into this damaged stormwater line. It is likely that this is the source of the continued and significant moisture issue in the subfloor.  In addition to the redirected plumbing line, efforts have been made to co ntrol the flow of water from the backyard into the subfloor. The inspection noted that a crudely laid line of concrete had been installed on the pathway across the rear of the dwelling. This appears to be an attempt to prevent excessive wat er from flowing into the subfloor from the rear of the property. This repair attempt indicates a pre - existing and long - term subfloor moisture issue.  The evidence suggests that long - term and ongoing stormwat er and site drainage issues have caused a significant amount of water to build up under the dwelling over many years. The excessive moisture throughout the subfloor indicates that previous rectification attempts remain ineffective.  An inspection of the brickwork observed step cracking on both the left and right sides of the dwelling. The presence of step cracking may indicate that a dwelling has sustained structural movement from the foundation level.  Close inspection of the cracking on the right side of the dwelling revealed that the cracks presented smoothed and sta ined edges Determination | Case number: 710755 Page 15 of 21 Record Key points consistent with damage that had occurred many years prior.  The inspection of the cracking through the left side brickwork revealed that the cracking had been patched at a time prior to recent events. The patched step cracking had re - cracked due to this ineffective method of repair.  Separation was also observed bet ween the brick wall and the carport beam at the rear right corner of the dwelling indicating differential movement between the carport and dwelling. The evidence therefore suggests tha t foundation movement have occurred for many years prior to recent events.  During the inspection the insured also advised of the movement or separation of the middle control joint in the concret e driveway beside the dwelling. This was not considered a sig nificant issue; it does however indicate the likelihood that significant long - term moisture issues have caused the movement of the founding soils throughout the property.  The evidence suggested that the dwelling may have sustained movement - related crackin g prior to the recent leak incident. Further investigation was therefore required to det ermine whether the observed cracking and separation was related to the recent leak incident or whether it was caused by a long - term foundation movement issue.  Further assessment of the foundation was therefore conducted  The results of the hydraulic level survey indicated significant and wides pread foundation movement all throughout the dwelling. The location at which the gross movement was most significant was in the lo unge room, however areas of significant variance were detected all through the dwelling.  The difference in floor level across the dwelling was greater than 50mm. The greatest level variance was detected bet ween the rear sunroom and front lounge room. The flooring height in the front right corner of the lounge room was approximately 54mm lower than the highest recorded level. This was a similar level variance to the flooring at the front left corner of bedroom 1 which was 54mm lower than the highest recorde d level.  When a leak occurs, it increases the moisture content of the soil surrounding the leak location. In a reactive site the clay particles react by chemically absorbing wat er into the matrix of the particle. The absorption of the water int o the clay p article results in an increase in volume of the particle – the soil swells.  In reactive foundation soils a moisture - related volume increase will cause a localised ex pansion can occur. This is referred to as a doming effect. The extent of the expansion dim inishes over distance away from the broken pipe. When reviewing contour surveys, you may see the contours radiating out from the location of the break in the pipe. The high point is detected close to the break in the pipe where the expansion is the great es t.  In this case however, the contours at the bathroom on the level survey mud map did not indicate a localised expansion. There is no evident doming in this location. Determination | Case number: 710755 Page 16 of 21 Record Key points  An area of raised or expanded reactive soil foundation is observed when a leak impacts reactive founding soils. The evidence of the cause of damage is therefore not consistent with a recent leak from the bat hroom plumbing line.  This available evidence indicates that the foundation movement was not consistent with movement that has occurred as a res ult of a recent escape of liquid from the bathroom plumbing line.  The contours of the level survey indicate that localised subsidenc e has occurred in many areas of the dwelling. The level survey contours have detected areas of subsidence in these locations rather than the doming observed in zone of influence at the leak location.  The foundation movement in the loc ations outside of the zone of influence was attributed to poor foundation performance over a prolonged period. These areas foundation mov ement can be attributed to the following factors.  The Cause of the Foundation Movement  The cause of the movement is attributed to a number of factors:  1. Subgrade Movement – The soil in this area is mainly a clay - based soil which was estimated to have a site classification of S to H. Variation in the strength and content of the soil occurs in this area, hence some element of soil can provide a greater load bearing pressure t han others. With the construction of the building, additional weight is placed on the soil. This additional weight results in consolidation of the soil and over time, the soil settles under the weight.  The majority of this type of movement occurs in the f irst ten years following construction. After the consolidation occurs, further gross movement due to this effect dramatically diminishes. Subsoil movement is considered to be the main cause of the observed differential foundation movement.  2. Soil Type – The soil in this area is noted as being reactive. With cycling of moisture content, variations in volume of the soil occur. If the footings are not adequately constructed this variation in soil volume can result in movement of the footings. This is particu larly noticeable in the first three to seven years following construction. As this may occur unevenly, cracking and movement of the dwelling can occur.  3. Environmental Conditions – The type of soil on which the house is constructed is subject to swelling and shrinkage, dependent upon the amount of rainfall. Loss of moisture over depth has resulted in volumetric change in the soil, i.e. the soil shrinks and, as a result, foundational support is lost.  4. Site Drainage – Water can run under the subfloor are a and can pond/build - up against stump footings - uneven wetting of founding soils can cause unequal compression of founding soils and possible building movement.  5. Plumbing Lines - A PVC stormwater line has been installed above the ground along the west side of the property. The new stormwat er line is not adequately supported and discharges water Determination | Case number: 710755 Page 17 of 21 Record Key points to the surface of the garden at the front of the dwelling. The original earthenware plumbing lines that the new PVC lines replace are still visible and filled wi th debris. This indicates that significant pre - existing plumbing issues have not been suitably repaired.  Furthermore, a drain at the rear of the property was found to be still connected to the original disconnected and damaged stormwat er line. Water from the rear of the property is therefore channelled to the damaged plumbing lines around the dwelling during rainfall events.  Additionally, damage to the sewer line bet ween the toilet and kitchen was identified. A non - compliant plumbing line has been install ed to extend the rear gully outlet to below the rear dwelling extension. Water from the bathroom and laundry fixtures appeared to be discharging under the dwelling extension via the gully. Water pooling in the subfloor was likely to have occurred due to a blockage.  It is noted that the subfloor is uncharacteristically very wet and muddy. Each of these pre - existing plumbing issue appear to be contributing to the ongoing and long - term build - up of excessive moisture throughout the subfloor. The repeated and constant uneven wetting of founding soils is likely to cause the movement of founding soils and building movement.  The results of the hydraulic level survey detected widespread foundation movement consistent with pre - existing, long - term issues that have ca used differential movement and damage all throughout of the structure.  It is recommended that the insured engages a suitable structural engineer to further analyse the dwelling, monitor its movement and design an adequate design solution for rectification of the damage attributed to the significant differential movement throughout the dwelling.  It is also recommended that the insured engages a suitable plumbing specialist be engaged to repair and correct the many  significant plumbing issues around the dw elling including the repair of the stormwater, sewer and site drainage issues.  It is important to not e that the soil in the subfloor currently remains saturated. The soil will dry out over the 12 months following the repair of the plumbing lines and durin g this time the structure is likely to settle back down into its resting position. Further cracking may occur through the linings such as the floor tiles and plasterboard walls as the dwelling settles. It is therefore recommended that the insured delays ae sthetic repairs until after this time.  CONCLUSION  An engineering investigation of the dwelling was conducted following the discovery of several significant structural issues to the dwelling including foundation and roofing damage. There were concerns that a recent plumbing leak may have contributed to the damages. Determination | Case number: 710755 Page 18 of 21 Record Key points  In order to determine the condition of the dwelling and the cause of the damage, a review of past reports was conducted as well as a visual inspection and a hydraulic level survey. Further inves tigation was conducted to separate pre - existing damages from those that may have been attributed to the recent plumbing leak in the subfloor below the bathroom.  The available evidence indicates that the foundation of the dwelling has subsided over a prolo nged period causing differential movement throughout the structure. The build - up of stresses through the structure has caused cracking and separation of the interior and exterior.  The investigation found that the damage was not consistent with damage caus ed by a plumbing leak but was consistent with poor foundation performance over many years. The evidence indicates that the movement is a long - term issue caused by several contributing factors listed in the body of this report.  It is recommended that the i nsured engages a suitable structural engineer to further analyse the dwelling, monitor its movement and design an adequate design solution for rectification of the damage attributed to the significant differential movement throughout the dwelling.  It is r ecommended that the insured engages a suitable plumbing specialist to repair and correct the many significant plumbing issues around the dwelling including the repair of the stormwater, sewer and site drainage issues.  It is also recommended that the insur ed employs a 6 - 12 month dry out period following the repair of the plumbing issues prior to the commencement of aesthetic repairs due to the current saturated condition of the founding soils.  It should also be noted that proper site drainage be maintain ed at all times, so as to prevent any surface water ponding or laying near the foundations of the building.  The attached appendices A, B & C have been supplied to provide further information regarding the assessment of foundation performance, the classifi cation of damage and effective foundation maintenance. Insurer Builder (A1) Report 9 June 2019  Due to the recent heavy storm events that have passed in the area of the Insured’s property, the Insured had advised wat er has leaked through the kitchen and bedroom areas. As a result there is a small water stain affecting the kitchen ceiling close the entry to the living room. The paint is slightly  bubbling to the top right - hand side corner of the a rchitraves in the living room opening as well.  - Inspection of the roof directly above the affected rooms found that the pointing under the valley tiles  was cracked and allowing water to leak through. The valley iron directly above had rusted under the  til es and was allowing water to enter and damage the ceilings below. The valley iron requires Determination | Case number: 710755 Page 19 of 21 Record Key points  replacement prior to repairs proceeding.  - Pre - existing damage and patch up work was noticed to the ceiling plaster joins and a crack along the  wall join directly be low. It appears to the patch up was to a crack in the ceiling and the wall crack was  a result of the house movement, and not moisture from the recent event. The floor level beneath felt  uneven which also confirmed movement of the foundations.  - Inspection to the bedroom revealed water marks to the walls where the water was entering from  under the cornice. The patch up to the wall plaster join along the affected wall was finished uneven  and not from the effects of the event.  - Further inspection of the roof directly above revealed the gutters were rec ently cleared as the drain  had become blocked causing the water to overflow into the eaves and into the bedroom. No roof tile  damage was visible above the affected area.  - Other maintenance issues to the roof inc luded the remaining roof area had visible cracking to the  pointing under the ridge/hip capping tiles and roof valleys.  Debris was present within the gutters.  - The pointing under the valley tiles was cracked and allowing water to enter. The valley iron dir ectly  above had rusted under the tile and was allowing water to enter into the roof space to cause water  damage to the kitchen/meals area. The valley iron will need to be replaced to prevent furt her water  ingress.  - The remaining roof wit h the cracking of the pointing under the ridge/hip capping tiles and valleys  will lead to water ingress in the fut ure if not attended to.  Refer to insurer/ Due to maintenance issues with the roof. The Insured’s policy excess if far higher than the estimated repair cost, the refore the Ins ured may wish to withdraw their claim. Insurer Plumber (DPR) Report 25 October 2016  The roof has been observed to be approximately 25 years old  During our detailed inspection of the roof area we found that the roof was in good condition  We envisage the overall life expectancy of the existing roof, not taking into consideration insurance related damage to be 15+ years  Issues to the family home have come from several areas over the roof. First area was on the tile roof next to the skylight, wh ere a broken tile was staining the hallway ceiling. Second issue was over the kitchen area, where the tiles next to the valley have been silicone, creating issues around that area. The valley itself has rust. Third issue was the breakdown of the heater flu e cowl and decktite on the metal roof. Water has entered over the sunroom causing water problems. Fourth area in the bedroom we could not Determination | Case number: 710755 Page 20 of 21 Record Key points find water stains on the plaster inside of roof space. No issues on the roof above. The crack may have come from movem ent over time.  Overall the roof appears to be compliant to relevant Australia Standards  Issues to the family home have come from several areas over the roof. First area was on the tile roof next to the skylight, where a broken tile was staining the hallway ceiling. Replacing tiles around the hallway area is required. Second issue was over the kitchen area, where the tiles next to the valley have been silicone, creating issues around that area. The valley itself has rust. Valley to be replaced due to rust an d tiles that have been silicone to be replaced over kitchen area. Third issue was the breakdown of the heater flue cowl and decktite on the metal roof. Replacing dec k tite and replace rusted gas cowl is vital. Water has entered over the sunroom causing wate r problems. Fourth area in the bedroom we could not find water stains on the plaster inside of roof space. No issues on the roof above. The crack may have come from movement over time. Ceiling to be looked at. Addressing these issues on the roof is recomme nded before works inside of home Insurer Asse ssor Report 24 October 2016  On 24/10/2016 we attended the above residenc e in the presence of Mrs M to ascertain the damages  sustained to the property for the claimed storm.  Mrs M advised that on 17/10/2016 that during the storms her property was damaged. The Insured wife  claimed that they had lodged storm claim a few months ago. She then claimed that the insurance company  sent out a person at that time to siliconed the roof tiles, and placed bags on the roof .  The Insured then stated that no one had turned up to do anything further to her roof until she called again a  week ago. Insured said that she has owned this property for the past 9 months and that the property is approx.  55 years old. Insureds wife expla ined that she notes that water runs down the walls in the master bedroom  mainly the bed head wall. We have found that the roof report indicated no water entry to this room. This  would be condensation rather than wat er leaking.  The roof report indicated tha t the roof has leaking issues, the the valley rusted, cracked tiles silicone (Mrs  claimed done by insurance company). The hip has dislodged tiles. Water entry at the rear is non storm related  this is due to a poor heat er flu and boot flashing leaking.  The cause of water entry to this roof area is due to maintenance required to the insureds roof. No storm  related damage was found to this roof.  LEFT SIDE 1/2 SHARED FENCE  Insured also claimed that this has been damaged due to the recent strong winds. Determination | Case number: 710755 Page 21 of 21 Record Key points  We have f ound that the fence is leaning and loose not damaged due to recent storms requires also some  maintenance repairs to be done.  Yes as the roof report attached indicates many areas need repairs  Upon inspection of the residence there was found to be damages su stained to the as scoped internal minor  painting  Roof is maintenance related  As scoped 3.4 Other documentation  Insurer’s assessor reported dated 20 December 2019  FR Mould Remediation Scope of Works 31 December 2019  TRU underpinning quote 20 February 2020  JLG Scope of works 25 October 2016.