Home / Auto & General / Determination 710534
Determination 710534
Dispute over building claim scope and cash settlement for storm damage, with temporary accommodation, costs and non-financial loss
Summary
The complainant disputed the insurer's $90,037.17 building settlement after a storm, and sought a rebuild, shed damage, temporary accommodation and costs. AFCA rejected both parties' positions, ordered an engineer-led scope and cash settlement, temporary accommodation, reimbursement of up to $5,000 legal costs, a possible $1,500 reimbursement and $5,000 non-financial loss.
Neither the insurer's unactionable quote nor the complainant's unsupported rebuild case was persuasive, so AFCA ordered an independent engineer scope and cash settlement based on actionable quotes.
Issues
- Claim amount dispute primary · upheld
“The insurer's offer is not based on an actionable quote.”
- Poor claim handling secondary · upheld
“The insurer's handling of the claim has caused an unusual degree of stress, inconvenience, or delay.”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay non financial lossreassess claim
Text of the determination
Determination
Case number 710534
Financial firm Auto & General Services Pty Ltd
Determination | Case number: 710534 Page 2 of 9
Case number: 710534 16 December 2020
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm
(insurer). The complainant lodged a claim on her home and contents insurance policy
following a storm on or around 9 February 2020.
The insurer accepted the claim. The insurer has offered to pay $90,037.17 for the
building works.
The complainant says the scope of works, and the amount provided, is insufficient.
She is also claiming for damage to her shed and other costs associated with the
building. Further, she is seeking reimbursement of payments made earlier that have
been deducted from her contents sum insured. She is also seeking compensation for
her legal costs and non-financial loss.
1.2 Issues and key findings
How should the building claim be settled?
Neither p arty’s position is preferred. The insurer’s position does not appear to be
based on an actionable quote. The complainant’s builders have not provided sufficient
reasoning to support their position that the house needs to be demolished and rebuilt.
Therefore, the claim should be settled as set out in section 2.1.
Should the insurer pay other costs?
Yes. The insurer should pay additional accommodation in the manner set out in
section 2.2. The insurer should also pay the complainant’s legal costs up to $5,000
and subject to the production of invoices. Further, the insurer should reimburse the
$1,500 it deducted from the complainant’s contents payment if this amount was
already deducted from the $50,000 temporary accommodation benefit.
Is the complainant entitled to compensation for non-financial loss?
Yes. The insurer’s handling of the claim has caused an unusual degree of stress,
inconvenience, or delay. The insurer should pay $5,000.
1.3 Determination
This determination is mostly in favour of the complainant.
The insurer is required to do the following:
settle the claim as set out in section 2.1
pay additional temporary accommodation as set out in section 2.2
Determination | Case number: 710534 Page 3 of 9
pay $1,500 – this is only payable if this amount had also been deducted from the
temporary accommodation benefit previously paid by the insurer
pay the complainant’s legal fees, up to $5,000, and subject to the production of
invoices
pay $5,000 for non-financial loss
Determination | Case number: 710534 Page 4 of 9
2 Reasons for determination
This determination is based on information submitted by the parties. Each party has
had an opportunity to review and respond to the other party’s submissions.
The panel has considered all of the parties’ submissions. However, in this
determination, the panel has only commented on submissions directly relevant to the
outcome.
This determination is based on what is fair in the circumstances, having regard to any
relevant legal principles, industry codes or guidance, good industry practice, and prior
determinations of AFCA or its predecessors.
2.1 How should the building claim be settled?
There was an accepted insured event and liability was accepted by the insurer
The complainant’s home sustained loss and damage on or about 9 February 2020
following a significant storm.
The complainant holds a home and contents insurance policy with the financial firm
which covers ‘insured events’.
The insurer has accepted an insured event caused damage to the complainant’s
home and contents.
There is no dispute the house has suffered substantive damage from the claimed
event. There is also no dispute this situation has been exacerbated by the presence
of unsafe asbestos. The issue is the extent of works necessary to repair the house.
The experts disagree on the scope of works to restore the complainant’s home
The insurer is relying on a scope of works that has been costed by R totalling
$90,037.17. The insurer says this reflects a fair settlement of the works. Alternatively,
the insurer has offered to arrange an independent loss adjuster to attend with the
complainant and representatives of the parties to determine what is required to repair
the home.
The complainant says the home should be demolished and rebuilt. In support, she
has provided reports from builders J and A. The reasons they provided for this course
of actions are mainly due to the following:
the existing electrical, plumbing, structural framing and termite barriers are not up
to building code and will require significant rectification works – this would exceed
the cost to demolish and rebuild the property
without this course of action, they are unable to warrant the works
Determination | Case number: 710534 Page 5 of 9
This is relatively consistent with the evidence of another contractor (RH) engaged by
the complainant. RH said the home is beyond repair and required extensive
renovations.
The insurer has made the following arg uments against the complainants’ evidence:
they have not provided any specifics as to why, or what code, the building is not up
to and what requires rectification
they make no references to the National Construction Code (NCC), the Building
Act 1975, Australian Standards or other documents to support their assertion that
the insurer's scope of works is non-warrantable or non-compliant
NCC is performance-based and provides a choice of compliance pathways – this
means there can be a myriad of solutions to correct suggested issues that is both
less invasive and more cost effective
Neither party’s position is persuasive
The panel is not persuaded by either party’s position.
The insurer’s offer is not based on an actionable quote. Whilst the insurer says it is
based on an accurate scope of works, there is nothing to indicate its contractor is
prepared to do the works for the complainant for the price quoted.
Further, the complainant has provided evidence from several independent builders
who were not prepared to do the works proposed. They say it is uneconomical to
repair the home. In addition, if they were to attempt to repair the home, they would not
be able to warrant the works.
However, as the insurer pointed out, the complainant’s builders provided minimal
detail to support their position that the home is uneconomical to repair. They
reference the fact that various items need to be brought up to code to justify a
complete rebuilding but they do not:
identify which relevant code, standard or legislation applies,
what would be required to bring these items up to code,
a full scope of works that sets all this out, and
a fair costing of these scope of works to justify the rebuild of the property.
Claim should be resolved this way
The panel considers it is fair in all the circumstances the dispute be resolved in the
following way.
The parties are to engage an independent structural engineer to inspect the property
and provide a full scope of works for all the required repairs. This should include the
shed and the septic tank.
Determination | Case number: 710534 Page 6 of 9
The engineer should be one agreed to by the parties. This can be done by the insurer
providing a list of three engineers that the complainant can choose one from.
Alternatively, the complainant can provide three choices for the insurer to choose one.
The engineer’s costs are to be borne by the insurer.
Once this engineer has been engaged and has completed the scope of works, each
party can obtain at least one, and no more than two, actionable quotes based on that
scope of works. To clarify, an actionable quote is one where the builder is prepared to
do the works for the complainant.
If only one actionable quote is obtained, then the insurer is to cash settle the claim
based on that quote plus a 20% contingency. If more than one actionable quote is
obtained, then the insurer is to cash settle based on the average of those quotations
with a 20% contingency.
The contingency is to address the likely variances that may arise in a complicated job
like this and the fact the risks of the works are passing to the complainant.
Any amount payable by the insurer is limited by the relevant sum insured. No interest
is payable given payment should be based on current rates.
If the parties are unable to agree on the final quantum, they can return to AFCA for a
decision on this point.
2.2 Should the insurer pay other costs?
Temporary accommodation
The policy provides this benefit for temporary accommodation:
Sometimes damage to your home and contents can mean you can’t stay living at
your insured address. If your home becomes unliveable and we agree to pay your
claim, we pay up to 10% of your home or contents sums insured for temporary
accommodation
The insurer has paid $50,000, which is 10% of the building sum insured. The
complainant said it should be 10% of the combined sum insured for buildings and
contents.
This is incorrect. The wording says ‘we will pay up to 10% of your home or contents’.
The use of the word ‘or’ makes it clear it is not the combined total. Therefore, the
payment of $50,000 represents the maximum and this has been paid.
The complainant is seeking additional payment beyond that. It is not clear if her costs
have exceeded the amount paid by the insurer.
Determination | Case number: 710534 Page 7 of 9
AFCA can award additional accommodation if these will be incurred due to the
insurer’s acti ons.
In this case, the panel accepts the insurer’s settlement would not have been sufficient
to allow the complainant to repair the damage. Further, it is clear the complainant did
not have the financial capacity to do so. As a result, she has not been in a position to
do the claim related repairs for almost 12 months.
The relevant benefit is based on a time limit of 12 months. However, it is not fair for
this time to include any period where:
the insurer has yet to fairly cash settle the claim
the complainant cannot reasonably be expected to repair the damage
she has been unable to live in the property during the whole time
Therefore, the panel considers it is fair for the 12-month period to begin from the time
the insurer has fairly cash settled the claim. This means that up to the point the claim
is cash settled, the insurer should be paying temporary accommodation. This is
subject to the complainant providing reasonable co -operation with the insurer
regarding the implementation of this determination (for example, allowing reasonable
access to the property for the engineer and the builders who are providing actionable
quotes).
Once the claim is cash settled, then the insurer should pay for temporary
accommodation for the estimated time it will take for the builders to complete the
engineer’s scope of works. For instance, if the builders estimate the works will take
six months to complete from the time they are engaged, then the insurer should pay
up to six months of temporary accommodation and subject to the $50,000 limit.
Payment of an additional $2,000
The complainant notes food spoilage ($500) and an emergency payment ($1,500)
were deducted from her cash settlement.
She seeks reimbursement for this. She says the food spoilage is an additional benefit.
She says the $1,500 was deducted from the temporary accommodation payments.
Regarding the food spoilage, it does not appear this is a benefit in addition to the sum
insured. When reviewing this section of the policy, it sets out various additional
benefits. Some, such as removal of debris and temporary accommodation, expressly
note the benefit is paid in addition to the sum insured. The food spoilage contains no
such reference.
Therefore, the panel does not accept this is a benefit paid on top of the sum insured.
The insurer was entitled to deduct this.
Determination | Case number: 710534 Page 8 of 9
For the emergency payment of $1,500, if the insurer deducted this from the $50,000
payments allowed for temporary accommodation, then it should be reimbursed.
Otherwise, the insurer is not required to repay this amount.
Possible vehicle damage to be pursued against the vehicle’s insurer
The complainant says her vehicle may have been damaged by having clothing with
asbestos in it. No evidence has been provided to show the vehicle has damage.
The vehicle is not covered by this policy. Given this, the panel considers any such
claim should be pursued under the complainant’s vehicle policy.
Legal costs
Under Rule D.5, AFCA may decide a financial firm contribute to the professional costs
incurred by a complainant in the course of a complaint. These costs can be awarded
if the complainant needed an expert to understand or establish their claim. These
costs are normally capped at $5,000 unless exceptional circumstances apply.
The panel accepts the complainant required assistance. It is clear she had been
adversely affected by her claims experience and had health issues. Her solicitors
assisted in identifying the issues in dispute and provided cogent submissions in
support.
The panel does not accept there is sufficient basis to say there are exceptional
circumstances to warrant an award over $5,000.
Therefore, the insurer is to reimburse the complainant’s legal costs, subject to the
complainant providing invoices in support. The total amount payable is not to exceed
$5,000.
2.3 Is the complainant entitled to compensation for non-financial loss?
Compensation is awarded conservatively
Under the AFCA Rules, we may award compensation (capped at $5,000) for non-
financial loss where a complainant has suffered a n unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
We take a conservative approach to compensation for non-financial loss. It is not
awarded when a person suffers the normal degree of inconvenience when a problem
occurs.
The complainant is entitled to compensation for non-financial loss
It is clear the complainant has experienced an unusual degree of stress and
inconvenience due to the insurer’s clai ms handling. This has included the following
factors:
Determination | Case number: 710534 Page 9 of 9
the accidental disruption of asbestos in the complainant’s home that were likely
caused by the insurer’s trades – this substantively complicated the claims
experience
the likely cross-contamination of the asbestos and the loss of most, if not all, her
contents
the complainant’s inability to repair the claim related damage
As such, the panel is satisfied that the complainant is entitled to the maximum sum
available, being $5,000.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.