Home / Suncorp Group / Determination 708996

Determination 708996

Water pipe leak claim: exploratory works paid, internal and external damage and repairs declined

FirmSuncorp Group
Decided2020-11-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$42,361
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

After two water pipes burst, the complainant carried out extensive works and sought the full cost of repairs from the insurer. AFCA ordered the insurer to pay $42,361 with interest for locating the leak and repairing the exploratory damage, but refused the internal and external damage and repair costs.

The policy covers exploratory costs of locating an escape of liquid, but excludes gradual deterioration and rising damp, and the insured's unapproved repairs prejudiced the insurer's assessment.

Issues

Subjects and remedies

home or building damagepay claimpay interest

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 708996 Financial firm AAI Limited Determination | Case number: 708996 Page 1 of 15 Case number: 708996 30 October 2020 1 Determination overview 1.1 Complaint The complainant held home building and contents insurance policy with the financial firm (insurer). A claim was lodged on 11 February 2019 for water damage after two water pipes burst a few weeks apart in January and February 2019. The insurer ’s engineer found no structural damage but recommended a further assessment after the soil dried out for 12 months. The complainant despite acknowledging this advice proceeded with exploratory works and internal and external damage repairs. The complainant says this was necessary for health reasons. He says he was given the impression the insurer would reimburse him for his costs and kept the insurer updated. The insurer has declined the claim. It says at no time did it accept liability and the complainant’s actions have prejudiced its ability to determine liability. 1.2 Issues and key findings Has the complainant established a valid claim within the terms of the policy? The complainant has established a valid claim for the costs of locating the source of the escaped liquid and to repair the damage caused by the exploratory work. Is the insurer liable for the internal and structural damage? The complainant has prejudiced the assessment of any potential structural damage as set out under section 2.2 of this determination. The panel is further satisfied the balance of the internal and external damage is not covered under the terms of the policy. Did the insurer promise to cover the complainant’s repair costs? The panel is satisfied the insurer did not mislead the complainant to believe it would accept liability for the claim or the costs of repairs. 1.3 Determination This determination is partially in favour of the complainant. Within 14 business days of the complainant’s acceptance of this determination, the insurer is to pay the complainant a total of $42,361 with interest in line with section 57 of the Insurance Contracts Act 1958 (Cth) from 5 December 2019 until the date of payment. Determination | Case number: 708996 Page 2 of 15 2 Reasons for determination There has been a full exchange of material between the parties, and each party has had the opportunity to address the issues arising from that. Due to the complexities involved in this dispute, it has been referred to a panel for determination. The panel is comprised of the Lead Ombudsman, a member with considerable industry experience and a member with extensive experience as a consumer representative. While the parties raised various issues in their submissions, for the purposes of this determination, the panel has restricted its commentary to those issues which it considers directly relevant to the outcome. This determination follows consideration of all e information exchanged. It is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and previous decisions where applicable. 2.1 Has the complainant established a valid claim within the terms of the policy? Complainant bears onus to establish claim falls within terms of policy It is established insurance law that an insured has the onus to establish on the balance of probabilities (that is, more likely than not) that a claim falls within the terms of a policy. This is commonly called a prima facie claim. The complainant ’ s home and contents policy provides cover for a series of insured events including the escape of liquid from fixed drains and pipes. The relevant policy section is set out at 3.1 of this determination. The complainant says a crushed stormwater pipe leaked a large amount of water into the foundation soils which caused erosion and ground movement which, in turn, caused the water supply pipe to burst at the back and front of the property. He says this resulted in further soil saturation and both internal and external damage. Evidence establishes multiple leaks from supply and crushed stormwater pipes The insurer appointed several assessors to inspect the damage, including : builders (A, P and C), plumbers (BB), and an engineer (IL). The complainant also provided reports from a plumber (JN) and an engineer (ZC). The key reports are summarised at section 3 of this determination. Determination | Case number: 708996 Page 3 of 15 The assessors initially found two leaks from a supply pipe. In addition, the complainant’s plumber, JN, and engineer, ZC, reported a crushed stormwater pipe; they suggest the pipe seeped water over years until it finally burst, flooding the foundation soils and causing ground movement which burst the supply pipe. The insurer does not acknowledge the issue with the stormwater pipe. As noted below, its plumbers, BB, did not comprehensively inspect the pipe. During the review of the claim the building co -ordinator, C, declared there was no evidence of a crushed or broken pipe. Based on the complainant’s reports and photographs (which show the broken pipe in-situ), and in the absence of a compelling submission from the insurer to the contrary, the panel is satisfied that the stormwater pipe was crushed and a source of the escape of liquid. IL reported a significant increase in water usage based on the water rate notice for the period October 2018 to January 2019 consistent with the burst pipes. The panel is satisfied that the volume was significant (and its ultimate extent unknown), based on the reports of JN, ZC and IL. The panel is satisfied the complainant has established a valid claim for loss and damage arising from the escape of liquid. Insurer is liable for the exploratory costs and to repair damage caused by exploratory work The policy provides cover for the reasonable costs of locating the source of the escaped liquid and the cost to repair the building damage caused by the exploratory work. Building is defined in the policy and includes pathways and driveways. The invoice provided by the complaina nt for work performed includes costs of locating the burst pipes and crushed stormwater drain as follows: 1. Cutting the concrete paths …. $2,161 2. Demolition and excavation of side path …. $15,000 3. Rear path manual excavation ……. $4,500 4. Removal of debris ……. $6,700 5. Remove and replace front driveway …. $14,000 Total …… $42,361 A identified the leaking pipes had undermined the driveway and the storm water had been blocked. The complainant’s plumber JN a nd engineer ZC confirm the leaking pipes had undermined the driveway and pathway. Plumber BB, the Determination | Case number: 708996 Page 4 of 15 assessor and engineer IL did not address the issue or the need to repair the damage caused by the exploratory work or leaking pipes to the pathways or driveway. In the absence of information to dispute the findings of JN and ZC, the panel accepts that the insurer should meet to costs as identified and pay the complainant $42,361. 2.2 Is the insurer liable for the internal damage or external damage? No structural damage to house established There is no evidence of structural damage. The complainant has not established any structural damage to the house itself arose as a result of an insured event. Neither JN nor ZC reported structural damage to the dwelling. At best they find that soil movement may have affected the pipework. IL observed no cracking or other evidence of structural damage to the house. The panel accepts IL’s conclusions in this regard. There was movement, but this did not result in damage to the house itself. IL is suitably qualified, and the report is detailed. IL supported the observations with photographs and floor level measurements, which recorded only slightly elevated levels in the south eastern corner of the house near the stormwater pipe leak. Complainant prejudiced the insurer’s asse ssment of the structural damage IL acknowledged that a large amount of water had entered the subfloor and it would not be unusual for movement to occur as the soil dried out. IL considered it necessary to allow a drying out period of 12 months to determine the extent if any of movement. The panel accepts IL was suitably qualified to make such a recommendation. This is not unreasonable and a common requirement where there has been significant inundation of a property. The insurer was willing to reassess the presence of any resultant structural damage after the drying out period. The complainant disagreed with IL’s soil drying recommendation and decided to press ahead with exploratory works and repairs. The policy says the insured must allow the insurer to assess damage and must not conduct repairs without the insurer’s consent, failing which the insurer may be entitled to reduce its liability. The complainant says ZC observed a degree of moveme nt sufficient to affect the pipework, which shows the movement needed to be addressed immediately. This assertion is not supported by expert evidence . The comments by ZC do not in the panel ’s view undermine the merit of IL’s recommendation. Determination | Case number: 708996 Page 5 of 15 The complainant says that IL failed to address the stormwater pipe. The panel agrees but the complainant has provided no evidence to explain how this would undermine the correctness of the recommendation. IL proceeded on the assumption that a significant amount of water entered the founding soils, and this assumption would not likely be altered by the presence of an additional leak. The complainant says he had to undertake all repairs to mitigate the risk of mould re-occurring. The panel notes that the mould was remediated relatively early in the claim process. The panel accepts this was necessary, as were the repairs to the pipes. However, beyond this it is not entirely clear how the complainant’s works would have mitigated the risk of mould re-occurring given the water had already saturated the soil. To the extent there may have been developing damage as the soil dried out, the insurer has been prejudiced by the complainant’s actions. It is now not possible to determine the extent, if any, of structural damage attributable to the insured event. Renovations, improvements, preventative, unrelated works – not covered Once the leaks were discovered and repaired, the complainant took the opportunity to complete repairs, renovations, improvements, preventative and other works not directly related to the insured events. Without being exhaustive, the additional/unrelated works include:  the renovation of/upgrades to the laundry and bathroom. Whilst the complainant suggests the bathroom works were necessary to dry out the soil, this is not supported by expert evidence  the repair/installation of the retaining wall  other improvements and preventative measures, including to the foundations and front of the property and garden area  the neighbour’s driveway. The panel is satisfied such work was not required because of the insured events. Other damage not related to leaking pipes IL and the other assessors noted internal damage including swollen joinery/architraves to the doors on the eastern side of the building, as well as corrosion to the base of the laundry cabinet trough. Other assessors, including ZC and the builders, variously observed the external damage, including damage to the archway, garden and efflorescence to the brickwork. Determination | Case number: 708996 Page 6 of 15 IL found the house had an absent/deficient vapour barrier under the slab which facilitated rising damp which in turn resulted in the efflorescence to the brick walls, the swelling of the joinery, the corrosion of the laundry tub and, presumably, the mould. The panel notes that IL does not actually prove an absent/defective vapour barrier by invasive testing. Damage most likely long term The panel accepts that the leaking pipes occurred in the period between October 2018 and January 2019. This is supported by the water rate notice that shows a significant increase in water usage in that period compared to the three previous quarters. The photographs of the damage to the doors, joinery, architraves and laundry cabinet show extensive damage. The panel accepts that it is unlikely such extensive damage occurred in the short period (i.e. between October 2018 and January 2019) prior to the leaking pipes being identified. The panel accepts that most likely the efflorescence and corrosion and swelling was due to gradual deterioration from the rising damp over several years. The panel notes in support of this the complainant’s comments that the efflorescence had been observed for a few years. The policy excludes cover for gradual deterioration, corrosion, wear and tear, rising damp and the like. The panel accepts the insurer is entitled to rely on the terms of the policy to refuse payment of the additional damage. 2.3 Did the insurer promise to cover the complainant’s repair costs? Evidence does not establish insurer promised to cover the repairs There is no dispute that the complainant had received the policy documents. The documents clearly set out the complainant’s obligations. The policy clearly sets out “What you must do” and what happens if you do not comply. The complainant says the insurer should be liable for his repair costs because:  he put the insurer on notice that he would go ahead with the works  he kept the insurer updated as the works progressed  the insurer failed to inspect the site when invited to do so by the complainant  the insurer neglected to instruct the complainant to cease works  the insurer, by its conduct, promised to cover the costs / did not say he should not go ahead, thereby giving him the impression the costs would be covered. The complainant relies on the principle of estoppel to seek reimbursement from the insurer and bears the onus to establish his allegations. Determination | Case number: 708996 Page 7 of 15 Based on the available information, the panel is satisfied that:  the complainant was advised that no repairs (other than to the pipes) should commence for 12 months to allow the soil to dry out  the complainant made a conscious choice to proceed with the repairs regardless of the position on coverage  at no stage did the insurer say it would accept liability for the repairs  the insurer offered no indication to the complainant to lead him to assume the repairs would be covered  the complainant has proceeded with the repairs on his belief that the insurer would be liable  it was not reasonable for the complainant to adopt the assumption as to coverage and incur costs in reliance on this assumption. In these circumstances, the available information is not sufficient to establish estoppel or misleading conduct by the insurer. The insurer is not liable to pay the repair costs. Determination | Case number: 708996 Page 8 of 15 3 Supporting information 3.1 Key policy provisions Insuring provision Determination | Case number: 708996 Page 9 of 15 The insured’s obligations Determination | Case number: 708996 Page 10 of 15 3.2 Key reports and events The table below contains a summary of key reports and events. It does not record every report or instance of contact between the parties. Unless text is put in “quotation marks”, it has been paraphrased to some extent. Abbreviations: Com = the complainant or his representative FF = the insurer Date / document Event / details Com’ s expert (JN) Plumbing asse ssment Date of assessments: 18 Jan and 12 Feb 2019 Date of report: 16 Jun 2019 [some of the works referred to appear to have been undertaken bet ween February and June 2019]  on 18 January I found and repaired a leak to a water supply line at the rear of the property, adjacent to the south wall of the bathroom, which had apparently been cracked by ground movement  on 12 February 2019 I repaired another leak to the same pipe at the front of the property under the driveway adjacent to the south west corner of the property. I also found a crus hed stormwat er pipe beneath the pa th surfac e near the first leak  the escapes of liquid caused int ernal damage (including to the walls, rust to the laundry tub, swelling/rotting of skirtings and doors, mould) as well as external damage (including to brickwork, the settlement of the driveway and front path , garden bed and the falling away of the side path archway)  I undertook extensive exploratory work, repaired some of the damage, treated the mould and brickwork (which in some instances required replacement ), replaced the pipework in the lau ndry and refitted a new bathroom  the stormwater pipe at the rear was badly crushed which would have allowed water to build up there over a long time  the pipework along the side of the hous e may be unstable  the water pipes feeding the laundry and upper back yard were in bad condition and I temporarily repaired them, but note they will need replacement  all the stormwater and regular water pipes need replacement, all the walls require new render or acid washing. FF’s expert (A) Building asse ssment 14 Feb 20 19 Initial review  “A was appointed to inspect a possible escape of liquid claim at this property.  Upon inspection of the customers, front A has advised a copper pipe under the customer's pavement had burst last week.  Previous to this, one month ago there was a burst to the backyard furt her up the conc rete path. There is cracking for brick archway bet ween these areas. Inside is showing signs of Efflorescence. Determination | Case number: 708996 Page 11 of 15 Date / document Event / details  Customer advised there are damages to rooms inside however A was unable to inspect as people were sleeping in the rooms at the time of inspection. As A was unable to inspect all the property SOW is hard to determine  A has organised a leak detection to confirm if there is any more leaks and conduct thermal imaging. O nce the leak det ection is performed, we will have a clearer idea where the water has travelled.  Please be advised an engineer may be needed for this claim. TBC with the leak detection findings.” Leak detection  “Arrived on site to assess damage and conduct a leak detection.  The Insured has had two burst pipes repaired at the front and rear right hand side of the property, he believes they had been leaking for a while as the water bills have been high.”  A pressure test was performed and passed indicating no further leaks to the mains pipe work.  Damage was not ed with movement to the archway near the burst. The laundry cabinetry has rusted, the laundry door frame has swollen and there is efflorescence staining and damage to walls.  Not all downstairs rooms could be inspected at the time of attendance due to people sleeping in them.  Inspected and tested bot h the laundry and toilet wit h no issues found.  Inspected the shower, found the screen to be leaking and some grout missing around the drain. However, water did not appear to be escaping underneath the tiles. The shower walls are in a good condition. FF’s expert (BB) Plumbing report 21 Feb 2019 Second FF leak detection:  the complainant repaired a burst pipe at the front and a burst pipe at the rear  a pressure test showed no further leaks to the mains pipe work  the laundry tub is rusted, the laundry door frame is swollen and there is efflorescence staining and damage to walls  there are no issues with the laundry and toilet or the shower. FF’s exper t (IL) Engineering asse ssment 19 Mar 2019  the average daily water usage at the property bet ween October 2018 and January 2019 was nearly 5 times greater than the average daily water usage at the same time in the preceding year  there was no significant ext ernal damage to the property  efflorescence was widespread in the lower level walls of the dwelling, with no discernible pattern  we saw several instanc es of swollen joinery/architraves to the doors on the eastern side of the building, as well as corrosion to Determination | Case number: 708996 Page 12 of 15 Date / document Event / details the base of the laundry tub. No other internal damage was sighted or report ed during our inspection  we measured the hy drostatic floor levels, whic h showed the levels in the south eastern area of the dwelling (ensuit e and bathroom) were slightly higher t han the rest of the dwelling. Apart from this area, the levels throughout the rest of the dwelling were generally relatively level, with no discernible pattern of movement  we do not believe the escape of liquid caused any structural damage to the dwelling. Otherwise one would expect non - uniform movement, in the area of the leak. Although the floor levels at the sout h east near the leak were slightly higher, no damage (for example cracks) was seen  however, given a large amount of water has entered soils bene ath the subfloor, it would not be unusual for movement to occur as the soil dries out  the efflorescence to the brick walls was likely caused by rising damp due to a defective / absent vapour barrier underneat h the concrete slab. Damage was not localised bu t was rather wides pread throughout the lower level, which shows it was not caused by an escape of liquid. The rising damp caused the damage to the brick walls and the swelling of the joinery and the corrosion of the laundry tub  as a large volume of water h as entered the founding soils, we recommend a 12 - mont h soil drying out period to allow the soils to return to a relatively stable moisture profile. The insured should monitor the dwelling during the drying out period and report any new cracking or foundati on movement to us. Should the dwelling remain relatively stable with no further cracking reported, no further action will be required and no structu ral repairs would be nec essary. FF’s expert (BB) Plumbing report 1 Apr 2019 BB plumbing attended again on 1 April 2019 and found:  the sewer line is clear and runs to the east of the property  the bathroom to the south - east is currently being renovated  it is difficult to clearly see the stormwater pipes running east and west of the property due to debris  ther e is some root intrusion to the pipes in the front garden  waste pipes from the Jacuzzi room to the nort h east of the property are connected to the stormwat er line which is against regulations. 18 Apr 2019 FF claim decision ba sed on IL engineer report  advis ed of 12 month drying period to see any resultant damage but at the moment there’s nothing. Com’ s expert ( ZC )  I was told there was a leak near the rear of the bathroom in the south west corner of the property which lasted at least a week  the footings rest on shallow rock. This means any movement Determination | Case number: 708996 Page 13 of 15 Date / document Event / details Engineering asse ssment Date of assessment: 27 May 2019 Date of report: 16 Jun 2019 was not caused by normal settlement of the foundations  the brickwork, door frames and skirtings have been water damaged over t ime, as has the laundry tub attached to the damp wall  the stormwater pipe under the path at the rear of the property was crushed and did not discharge water through. This means it would cause water to build up in the area over time. It is also the most likely cause of the rupture in the water supply line  the damaged stormwater pipe is right outside the laundry wall, which explains how the most severe dampness and mould have affected the nearby walls in the centre and rear end of the house  the leak happen ed near the downpipe. The stormwater line trench can easily become a channel for water to mak e its way to the front of the building, contributing to the movement of the driveway  the water leak at the rear of the property is the sole cause of the movement t o the front driveway. FF’s expert (PA) Internal asse ssment report 27 Jun 2019 FF asse ssor PA attends si te of Com’ s works “ On attending onsite, I was advised by the customer that he has begun repairing damage from what he believes is a result of the leaking pipes at the property. The customer has begun extensive repairs to the property. The paving at the southern and eastern s ide of the house has been removed. A new retaining wall has been installed along the southern boundary. The customer has replaced several steel internal door frames and has replaced cabinetry at the rear laundry. Skirting boards in the home have also been replaced. The customer also believes that the front driveway has dropped due to the leak and is going to have this section of the driveway replaced. The customer advised me that he will spend over 100k in completing thes e repairs and is continuing with re pairs regardless. The Engineers report provided by [our builders] advised that there is no visible resulting damage from the leaks at the property. The customer disagrees with these findings and believes that the works completed to date are all related to the leak and should be covered as part of the claim. The customer has provided his own Engineers report which outlines both internal and external damage. A Plumbers report has also been provided . … It is my opinion that the customer has prejudiced the cla im by proceeding with repairs prior to the drying out period elapsing and before [the FF] were able to properly identify all result ant damage. ” FF’s expert ( C ) Determination | Case number: 708996 Page 14 of 15 Date / document Event / details Building co - ordinator report 25 Nov 2019  “ 1/ The front driveway. There are photos showing an approx displacement of 20mm on one concret e panel only, near the entrance. As the mandatory drying time was not adhered to, we cannot determine if this panel would have returned to its original position. As such we cannot cover any cost associated with thi s.  Also additional concrete works have been done to the front yard that were not there prior to the event.  2/ There is no evidence to support the claim that the storm water pipe was broken or crushed. The supplied photos only show a pile of broken pipes wi th no evidence of the pipes insitu in a broken state. Our CCTV shows a blockage only and as such this could have been cleaned with a jetting service.  3/ The retaining wall: we have been given no structural engineering reports to confirm the side parting w all was displaced by any event. The insured had a duty of disclosure to inform FF if additional works were required. As FF were not given any evidence or any opportunity to inspect, these works are not covered.  To that point we will not cover any works on the neighbouring property.  4/ Bathroom: The leak detection was done on the 21/02/2019 and found that the bathroom renovations had already begun. There is no scientific evidence to support the claim for damage to this room. It is fair and reasonable to con clude this room was not affected by any of t he burst pipe events as listed.  In conclusion, I note: the insureds plumber and Engineer have not supplied any scientific evidence to support their “opinion” based reports. Where’s all of the [the insurer’s builders’] reports, the IL reports and the leak detection reports have substantial photographs supporting the position of the events.  I agree with IL’s report to the fact that no damage has been sustained to the dwelling from a bust pipe eve nt. My reasoning for this is confirmed by the full dept h corrosion to the Laundry trough, the full depth corroding to the solid steel door jambs. This kind of corrosion t akes at least 10 years to rise to a height of 200mm above finished floor heights, not from a burst pipe for 2 - 3 months.  As the insured has diminished our ability to accurately assess all damage, refused to accept the mandatory 12 month drying period and commence renovations before we could complete our investigations, it is my recommendati on these claims be declined on the grounds that I cannot scientifically attribute any damage to the burst wat er pipe as described.  It is however fair and reasonable to conclude that there is no vapour barrier under the house as described in the independent link report which would explain the level of corrosion and the effervesce to the brickwork.” Determination | Case number: 708996 Page 15 of 15

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.