Complainants claimed for cracking damage to their home from ground movement, which they attributed to a leaking stormwater pipe. AFCA found the insurer entitled to decline the claim.

Complainants must establish a valid claim under the escape-of-liquid cover, and the expert evidence showed long-term foundation movement rather than a leak.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination Case number 706923 Financial firm Westpac General Insurance Limited Determination | Case number: 706923 Page 2 of 8 Case number: 706923 31 March 2021 1 Determination overview 1.1 Complaint The complainants hold a building and contents policy with the financial firm (insurer). A claim was lodged for ground movement that has caused movement and cracking damage, mostly to the rear left-hand side of the property. The complainants believe this was caused by a leaking pipe. The insurer declined the claim on the basis that damage was caused by long term and ongoing natural foundation movement. It says this is attributable to the consolidation of clay foundations, seasonal movement in the soils and the effects of tree root drying. The complainants dispute this and is seeking for the insurer to pay for repairs to the property. 1.2 Issues and key findings Have the complainants established a valid claim? No. This is because the available information does not show the leaking pipe caused the movement and cracking damage. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to deny the claim. Determination | Case number: 706923 Page 3 of 8 2 Reasons for determination 2.1 Have the complainants established a valid claim? Complainants have an onus to establish a valid claim The complainants are required to show, on the balance of probabilities, they suffered a loss caused by an event insured for under the policy. This is known as establishing a valid claim. If established, the onus shifts to the insurer to show, on the balance of probabilities:  the policy does not cover the loss or damage or  the insurer is otherwise entitled to deny the claim. Policy provides cover under specific circumstances The product disclosure statement (PDS) outlines the circumstances under which the policy provides cover. The policy covers a series of insured events, with no optional cover for accidental damage. Under the insured event ‘escape of liquid’, the policy provides cover f or loss or damage caused by accidental escape of liquid from any fixed pipe, fixed tank, waterbed or fish tank or fixed item used to hold the liquid. Parties disagree as to whether the leak caused the damage The complainants lodged a claim on 1 October 2018 for damage sustained to their property from a leaking stormwater pipe. The complainants also lodged a similar claim in 2014. The complainants maintain all this damage was caused by a leaking pipe. They are mainly relying upon engineer TE to support their position. The insurer assessed the damage. In doing so, it engaged two engineers, H and L. The insurer is mainly relying upon engineer L in support of its position as it submits L’s report is more compelling. Evidence establishes proximate cause of damage is ground movement The relevant expert evidence has been summarised in section 3. Therefore, the panel does not propose to set them out in detail. Having carefully reviewed all of the available information, the panel notes the following. L’s report is persuasive. L concluded the damage was not due to the leak. In support of this conclusion, L provided a detailed report that made several compelling observations and reasons. These included the following: Determination | Case number: 706923 Page 4 of 8  there were previous repairs evident in various parts of the house – this indicates pre-existing movement and cracking issues  evidence of restumping to the north side of the building – the complainant confirmed this was done before both claims and is near the area of the greatest damage  evidence of significant relevelling works throughout the building  measured floor levels showed movement across the entire building footprint – this is inconsistent with a leak being the cause as you would expect localised and isolated footing heave or anomalous footing move ment in the vicinity of the leak  no abnormal soil moisture or saturation was detected at a bore hole near the area of greatest damage – this indicates settlement has not occurred due to soil bearing failure The other engineers were not persuasive. For instance, neither H nor TE:  measured the floor levels to identify the fact the movement is widespread and inconsistent with the damage being caused by a leak  identified there has been previous repairs  identified there has been extensive relevelling works and restumping These are substantive factors that support L’s conclusion. They show a pre -existing issue in the footing movement. H’s report included a geotechnical report from HC. HC noted that calcrete lenses were identified in the two boreholes they dug. These show water can travel laterally across the site. L noted this but said it was unlikely given the highly impermeable nature of the stiff to the very stiff clay and the depth of the calcrete lenses. This is plausible. Also, this is not refuted by HC. HC simply said it is possible water could travel laterally, not that it did. Complainants arguments do not assist them The complainants have made various arguments to dispute L’s report. These include the following:  L failed to consider the 2014 claim  the presence of the leak could have existed from 2014 given the insurer had not done sufficient testing of the stormwater pipe  L visited the property about nine months after the leak was repaired – this would explain the dry nature of the soil The panel does not accept these arguments assist the complainant. The insurer provided evidence to show the relevant pipe was tested in 2015. This was found to be break free. Therefore, it could not have been leaking from before 2014. Determination | Case number: 706923 Page 5 of 8 Further, the 2014 claim was not covered. The previous engineer noted site drainage issues and other factors. This is consistent with L’s evidence that the site has general footing movement issues that are widespread and inconsistent with being caused by a leaking pipe. The panel accepts L inspected the property around nine months after the leak was repaired. However, it is not clear the soils would have completely dried if they were meant to be wet enough to cause the footing to lose its bearing pressure. Regardless, L’s other factors are of themselves compelling. Insurer can deny the claim Accordingly, after careful consideration of all the available information and arguments, the panel finds the following. The available information does not show the cause of the movement and cracking damage is the leaking pipe. This is because the panel is persuaded by L’s report. This means the complainant has not established a valid claim for the damage being claimed. Given this, the insurer is entitled to deny liability for the claim. Determination | Case number: 706923 Page 6 of 8 3 Supporting information 3.1 Relevant policy sections: Section Insured events (Building and Contents) Escape of liquid Covered  Loss or damage caused by accidental escape of liquid from any fixed pipe, fixed tank, waterbed or fish tank or fixed item used to hold the liquid.  We will also pay reasonable ex ploratory costs in locating the source of the damage, provided we have agreed to pay for the loss or damage caus ed by the escape of liquid. Not covered  loss or damage to the item from which the liquid escaped, and if the liquid escaped from a  shower recess, the cost of re - tiling the walls or floor of the shower recess  repair or replacement of undamaged parts of your contents to match property that has been repaired or replaced  loss or damage caus ed by gradual escape of liquid which is evident and which you fail to rectify. General exclusions Maintenance and building  defects in design, structure, materials, workmans hip and construction Wear and tear, and environmental conditions  wear and tear, gradual deterioration, or fading […]  earth or soil movement (other than earthquake) including landslide, subsidenc e, or erosion  settlement, expansion, shrinkage or vibration  hydrostatic pressure  tree roots 3.2 Expert reports Report Findings Determination | Case number: 706923 Page 7 of 8 Report Findings Building consultant (P) report 02 - 10 - 2018  Blocked sewer line under garage identified as a pre - existing ongoing m maintenance issue  Recommendations made for leak detection expert and engineer to attend Plumber (TB) report 01 - 10 - 2018  Damage attributable to age, deterioration and movement  CCTV inspection of stormwater system confirmed blockage and break at front left of the garage  Sewer is suspended under dwelling and installed away from area of subsidence and damages.  Recommendations made to engage plumber to clear stormwater, repair drai nage system and CCTV inspect left side once complete. Engineer (H) report 18 - 01 - 2019  The boreholes and testing at the site confirm that the Geology is Quaternary Basalt — CLAYS. These are highly reactive soils.  The owner would not allow Borehole 1 be complet ed close to the house.  The owner insisted that Borehole 1 was completed close to the front boundary.  During the excavation of the boreholes calcrete lenses were encountered. These calcrete lenses can allow wa t er to travel laterally across a site.  The thickness and permeability of these lenses can vary over a short distance.  The travel path of water would be dictated by the depth, thickness and permeability of these calcrete layers.  The fall of land in conjun ction with the angles of the calcrete layers would also determine water flow.  extreme changes in the moisture content of the foundation material due to the problems with the stormwater system. absence of control joints.  footings not being compliant to current standards. Complainant’s engineer (TE) report 28 - 05 - 2019  Damage to property caused by swelling due to egress of water from leaking stormwater pipes within the property  There are no leaks coming from on - site pipes at the property on the day of ins pection  Documentation and report by P has been provided relating to internal pipe leaks within this property.  Works have been completed by the appointed drainage contractors (AB) to rectify the wat er leaks within the stormwater pipes.  Rectification of all pipes along the northern side of the property was complet ed via pipe re - sleeving.  No further leaks have been detected.  Cracking has occurred in multiple mas onry walls  Articulation joint in mas onry has separated wider than the allowance  Cracking under eav es due to separation of articulation joint Determination | Case number: 706923 Page 8 of 8 Report Findings  Bowing of masonry wall due to movement in footings  All internal walls separating and cracking (nort h walls & walls joining to nort h walls)  Calcrete lenses were encountered from 800mm to 1200mm by geotechnical  engineers, causing the drainage issue  Due to abnormal moisture conditions differential movement has caused the footings to sink and or heave and or experience uplift  Due to the footings having differential movement the subfloor beams have moved and caused cracking and separation in the flooring  It is highly likely that cracking and movement may occur when the subgrade soil dries and stabilizes  Conc rete paving around the property has been compromised (sinking and movement occurring) Engineer (L) report 29 - 0 8 - 2019  The pattern of detected settlement is not localised and isolat ed to indicate an escape of water is the cause.  Tree root drying effects due to the presence of existing small and large size trees within the proximity of the structure  The removal of trees within close proximity of the structure  Changes in soil moisture content due to seasonal and climactic effects  The drought conditions in Victoria between 1997 and 2019, followed by the return of normal rainfall patterns  Long term consolidation of the clay foundations  Building survey results and preliminary soil investigations indicate the escape of water from the stormwater leak to the northwest corner of the building is not the cause of building movement or damage.  No anomalous pattern of building mo vement was detected in the vicinity of the leak consistent with an increase in foundation moisture.  L disagrees with the suggestion that calcrete lenses in the soil have allowed water to migrate to the rear of the property.  Building survey results and soi l tests to the rear corner indicate no anomalous movement to the rear to indicate water has migrated and caus ed movement.  Site investigations confirm widespread restumping of the property and significant relevelling.  Widespread crack repairs were also obs erved confirming damages have been long - term.  Investigations confirm widespread differential footing movement. The footing system adopted in construction is inadequate for this site and very susceptible to movement.  Foundation reactivity and inadequate f ootings is the cause of movement and has been happening for a long period of time.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.