Home / Suncorp Group / Determination 702418
Determination 702418
Break cost charged on early refinance of fixed-rate business loan
Summary
Business complainants refinanced a fixed-rate business facility early and were charged a $35,933 break cost, which they sought refunded, alleging the bank forced the refinance by cutting a facility limit. AFCA found the bank was not obliged to lend further, the refinance was the complainants' own decision, and the break cost was a reasonable estimate of loss, so the bank was not required to refund it.
The bank had no obligation to provide further finance or renew facilities, the complainants had committed to refinancing before the limit reduction, and the break cost approximated the bank's loss under the loan terms.
Issues
- Incorrect fees or charges primary · not upheld
“the bank is not required to refund the break costs (in whole or in part)”
- Other secondary · not upheld
“The bank did not force the complainants to refinance early”
- Poor communication secondary · unclear
“The available information does not establish whether the bank gave the complainants prior notice of the facility limit reduction”
Subjects and remedies
small businessno remedy
Text of the determination
Determination
Case number 702418
Financial firm Suncorp - Metway Limited
Determination | Case number: 702418 Page 1 of 7
Case number: 702418 19 August 2020
1 Determination overview
1.1 Complaint
The complainants had a business facility with the financial firm (bank) with a total limit
of $2.85 million. The facility was made up of a term loan facility of $1.35 million and a
cash advance facility of $1.5 million, with both facilities expiring on 30 November
2011. In 2007, the complainants agreed that a fixed interest rate would apply to the
term loan facility for the last four years of the term.
In 2010, the complainants refinanced the business facilities with another lender. The
bank charged them a break cost of $35,933 because they had terminated the fixed
interest rate period early.
The complainants say:
in late 2009, the bank informed them it had changed its lending policy on
development finance
in March 2010, the bank reduced the limit of the cash advance facility without
notifying them;
the bank’s actions forced them to refinance (and pay the break cost) because the
bank would not provide the additional development funds they needed; and
the b reak cost was payable because of the bank’s actions and therefore the bank
should refund the break cost.
1.2 Issues and key findings
Did the bank inappropriately force the complainants to refinance?
No. The bank was entitled to make its own commercial decision not to advance
further funds and had the right under the terms of the loan facilities to reduce the cash
advance facility limit and decide not to renew the facility when it expired in November
2011.
The bank did not force the complainants to refinance the facilities before they expired
and gave them reasonable notice that it would not be providing further lending. It was
the complainants’ need for further finance to undertake a new development which
caused them to refinance the facilities in 2010 before the fixed interest rate ended.
The bank was entitled to reduce the cash advance facility limit under the terms and
conditions of the loan contract. There is insufficient information available to confirm
whether the bank provided notice of the reduction..
Determination | Case number: 702418 Page 2 of 7
However, the reduction in the facility limit did not cause the break cost to become
payable. The complainants had decided to refinance the facilities when they
committed to their development plans, which occurred before the reduction in the
facility limit.
Was the break cost reasonable?
AFCA has independently confirmed that the break cost charged by the bank was a
reasonable estimate of the loss the bank suffered as a result of the complainants
breaking the fixed rate period early.
1.3 Determination
The determination is in favour of the bank.
The bank is not required to refund the break cost or to take any other action.
Determination | Case number: 702418 Page 3 of 7
2 Reasons for determination
2.1 Did the bank inappropriately force the complainants to refinance?
The bank was not obliged to provide additional lending or renew the facility
The complainants had been customers of the bank since 2004. In December 2006,
the bank agreed to increase the complainants ’ existing business facilities by $650,000
to a total of $2.85 m illion ‘ to assist [them] with future investment opportunities and
extend current facilities to 30 November 2011’ .
In late 2009, the bank informed the complainants it was divesting itself of its property
development portfolio and therefore would not be providing further loans to this
sector. This meant the bank would not renew the complainants’ loans after November
2011.
The complainants had an upcoming development opportunity and needed additional
funding. They say the bank had moral and ethical obligations to them as long-term
customers with a good record, which it failed to take into account when it decided not
to renew their facilities or provide further finance.
I appreciate that the complainants feel they were worthy of the bank’s further support,
but the bank was not obliged to provide the additional funding the complainants were
seeking or to renew their facilities when they expired. Even so, the bank should act
fairly and not arbitrarily when managing the end of its banking relationship with the
complainants.
The bank did not force the complainants to refinance early
The complainants say the bank forced them to refinance during the fixed rate period
and before the facility expired, meaning they had to pay the $35,933 break cost.
The bank says it did not require the complainants to repay the facilities before they
were due to expire on 30 November 2011.
However, in March 2010, the bank reduced the cash advance facility limit from $1.5
million to $900,000. The complainants say the reduction was made without prior
notice and they only became aware of this in July 2010, when the bank apologised for
failing to advise them earlier.
The available information does not establish whether the bank gave the complainants
prior notice of the facility limit reduction. It would have been appropriate and
reasonable for the bank do so.
However, the facility limit reduction (and any failure by the bank to provide notice) did
not cause the break cost to become payable. The complainants had already decided
to refinance the facilities when they committed to a new property development. As set
out below, this occurred before the reduction in the facility limit which means the
Determination | Case number: 702418 Page 4 of 7
break cost would have been payable regardless of whether the limit was retained at
the original level or reduced.
The complainants say:
in January 2010, they provided information the bank required to complete an
annual review which had been delayed. They also signed a heads of agreement to
undertake a new property development. The complainants say they had
discussions with the bank about the proposed development, refinancing the
facilities to another lender and whether security could be provided by a related
entity;
in February 2010, they contacted the bank to discuss funding options as they had
received indications that the bank’s lending policy may have changed to once
again allow development funding, but the bank did not respond;
in March 2010, the bank reduced the cash advance facility limit;
they further progressed the new development and in July 2010 obtained an offer of
refinance from another financial firm and discussed the termination of their existing
facilities with the bank but the bank would not agree to waive the break cost;
on 21 October 2010, the facilities were paid out.
between January and June 2011, they completed the new development.
The available information, including the complainants ’ recollection of events, does not
show that the bank unduly forced the complainants to refinance in October 2010. This
is because:
the bank did not have any obligation to provide the additional finance and/or renew
the loan facilities and the complainants were on notice that it did not intend to do so
in late 2009;
when the complainants signed the heads of agreement for the new development,
they were already aware that the bank would not be providing the funding and that
there would be a break cost if they terminated the facilities early;
as the development was progressed between January and June 2011, the
complainants needed the additional funding before their existing facilities were due
to expire;
there is no information to show that the complainants would have been able to
obtain standalone finance for the new development project without refinancing the
existing facilities.
while it was open to the complainants to wait for the existing fixed interest rate term
to expire before refinancing the facilities, this would have potentially delayed the
development.
I am satisfied that the complainants refinanced because they had committed to the
development by January 2010, were aware the bank would not provide the necessary
Determination | Case number: 702418 Page 5 of 7
funding and wished to proceed with the development before the facilities expired in
November 2011.
The bank is not required to reimburse the break cost
For the reasons set out above, I am satisfied the bank is not required to reimburse the
break cost because:
the complainants refinanced the facility to take advantage of a development
opportunity, not because they were unduly forced to by the bank; and
the complainants were aware the term loan had a fixed interest rate period and
there would be a break cost if they terminated the fixed rate period early. They
made their own decision to refinance before the fixed interest rate term ended.
2.2 Was the break cost reasonable?
The break cost charged wa s a reasonable estimate of the bank’s loss
The method of calculation of break costs is complicated and each financial firm uses
its own methodology. The bank says it provided the complainants with a fact sheet in
2006 or 2007 setting out its methodology for calculating break costs. However, the
bank says it is unable to provide a copy of the fact sheet because of the time which
has passed.
In the absence of this information, an AFCA industry adviser has estimated the loss
the bank is likely to have suffered due to the complainants terminating the fixed rate
period early. The industry adviser has extensive experience in the banking and
financial services industry and regularly undertakes break cost calculations.
The industry adviser has estimated the bank’s loss based on the movement in
wholesale market fixed interest rates between the date the fixed rate period was
entered into and the date the fixed rate period was terminated. I am satisfied this
approach provides a reasonable estimate of the loss the bank is likely to have
suffered.
The industry adviser has estimated the bank’s loss from the complainants terminating
the fixed interest rate period early at $35,933. This is only $5 less than the amount
charged by the bank and is not material. On this basis, I am satisfied that the break
cost charged by the bank reflected a reasonable estimate of its loss.
Whilst I appreciate this is not the outcome the complainants are seeking, the bank is
not required to refund the break costs (in whole or in part).
Determination | Case number: 702418 Page 6 of 7
3 Supporting information
3.1 Our approach to this complaint
This complaint was the subject of a written preliminary assessment provided by the
AFCA case manager on 9 June 2020 that was in favour of the bank. The bank
rejected the preliminary assessment and the complainants failed to respond.
I have determined this complaint based on what is fair in all the circumstances, having
regard to the legal principles, good industry practice, codes of practice and previous
decisions of AFCA and predecessor schemes (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All material provided has been reviewed and considered.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, I have limited commentary to those issues I consider to be
directly relevant to the outcome.
AFCA cannot review the bank’s decision not to approve finance
AFCA has Rules , approved by the Australian Securities and Investment Commission,
which set out our jurisdiction to consider complaints.
Under our Rules, AFCA must exclude complaints about a financial firm’s assessment
of the credit risk posed by a borrower unless the complaint is about a breach of a duty
or obligation in relation to lending, loan management or security matters (Rule C.1.3).
A financial firm does not have a duty or obligation to provide finance to a customer.
This means we cannot consider complaints solely about a financial firm’s decision not
to approve finance.
Further, AFCA is not a regulator of the financial services industry and we will not
review complaints solely about a policy decision by a financial firm which does not
breach any duty or obligation owed to the complainant. This means we will not review
a complaint solely about the type of facilities a financial firm is prepared to offer or the
purposes for which it is willing to lend, as these are commercial matters for the
financial firm to determine.
3.2 Relevant sections from the bank’s letter dated 19 December 2006
Facility review
The continuation of the Facility(s) is to be subject to annual reviews that will commence on
30 November 2007, or as requested by the bank…
the bank reserves the right to terminate any Facility following a review of the Facility(s) or
impose such other conditions as it considers appropriate for the continuation of the Facility.
Determination | Case number: 702418 Page 7 of 7
Break costs
If the Borrower requests to fix the rate there may be break costs applicable to terminate
any fixed rate…
If a fixed rate period is applicable at the time of any early repayment the Borrower will
pay any applicable break costs for the following:
• Repaying the loan in full; or
• Payments greater than those provided for in the Repayment section above …
If the Borrower requests to switch to a variable rate or a different fixed rate period there
may be break costs applicable to terminate any existing fixed rate.
The Bank does not represent or warrant that fixing the rate of interest is suitable to the
Borrower or the financial circumstances of the Borrower … The Borrower should obtain
independent legal and financial advice on this matter.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.