Home / Stewart Title Limited / Determination 701126

Determination 701126

Unreasonable delay in assessing and settling a title insurance claim

FirmStewart Title Limited
Decided2021-01-18
ProductGeneral Insurance · Other general
OutcomeFor the complainant
Amount awarded$110,000
Non-financial loss$5,000
Amount claimed$160,000
SourceAFCA PDF

Summary

The insurer accepted a title insurance claim but delayed over 300 days in completing the scope of works and settling it, and its offers were based on an incomplete scope. AFCA determined in favour of the complainant, ordering payment of $110,000 plus interest, $5,000 for non-financial loss, and a complete scope of works.

Unjustifiable and excessive delay by the insurer in resolving an accepted claim, with no adequate justification provided.

Issues

Subjects and remedies

home or building damagepay claimpay interestpay non financial lossreassess claim

Related

All Stewart Title Limited determinations · Find similar determinations

Text of the determination

Determination Case number 701126 Financial firm Stewart Title Limited Determination | Case number: 701126 Page 2 of 7 Case number: 701126 12 January 2021 1 Determination overview 1.1 Complaint This complaint is in relation to delays by the insurer, in settling a claim under the complainant’s title insurance policy. The claim was accepted by the insurer on 30 January 2020. The complainant has made this complaint due to lengthy delays in assessing the loss and paying or resolving the claim. During this time, the complainant has received ongoing warning letters from their local council, threatening large fines due to non-compliance with Council building regulations. The complainant is seeking the maximum payment under their policy, being $160,000 to resolve the complaint. 1.2 Issues and key findings Has the insurer unreasonably delayed resolution of the claim? Yes. The claim was accepted by the insurer on 30 January 2020. To date, no complete scope of works has been prepared, there has been limited contact from the insurer to the complainant and that contact often lacks information. The insurer has not been able to adequately justify ongoing delays. What loss was suffered because of this delay? The complainant has suffered a large amount of stress and inconvenience because of the delays. She has also spent a significant amount of time corresponding in detail with the insurer and chasing the insurer up after missed deadlines and ongoing delays. Additionally, the complainant’s property has been in an extended state of disrepair, while housing a child with a compromised autoimmune system. Further, the complainant has been and remains under significant pressure from the local Council and its threat of fines. What is the extent of the insurer ’ s liability in this claim? The complainant estimates the repairs will be above the maximum amount covered under the policy. The insurer has not prepared a complete scope of works to date. Because of the insurer’s failure to obtain a complete scope of works and adequately justify a lesser value payout, the insurer should, upon acceptance of this Determination | Case number: 701126 Page 3 of 7 determination by the complainant, immediately pay the complainant the offered amount of $110,000, and a further amount of $5,000 for non-financial loss. The insurer is also to immediately obtain a scope of works and an actionable quotation from an engineer, to ascertain the full extent of rectification required. The complainant may also obtain her own scope of works if she wishes. The insurer is to meet its obligations to the complainant in accordance with the scope of works and actionable quotation and under the terms of the policy. If either scope of works indicates that there are further repairs required because of the insurer’s failure to resolve the claim and complaint, which would exceed the policy coverage limit, the complainant my return to AFCA for further orders . If the complainant chooses to obtain her own scope of works and actionable quotation, the insurer is required to reimburse the associated costs. 1.3 Determination This determination is in favour of the complainant. The insurer is to arrange immediate payment to the complainant of $110,000 under the policy. The insurer is to pay interest, in accordance with the Insurance Contracts Act, 1984, on this amount, from 10 November 2020, until the amount is paid. The insurer is also to pay the additional amount of $5,000 for non-financial loss. Additionally, the insurer is to arrange a complete scope of works and actionable quotation to be completed within 14 days of the date of this determination. In relation to the threatened Council fine, I am satisfied that this problem has arisen due to the conduct by the insurer and in the event the Council levies a fine, the complainant is entitled to return to AFCA to seek further orders. Determination | Case number: 701126 Page 4 of 7 2 Reasons for determination 2.1 Has the insurer unreasonably delayed resolution the claim? Claim duration The claim was lodged by the complainant on 19 November 2019 and the insurer acknowledged receipt of the claim on 25 November 2019. On 30 January 2020, the claim was accepted by the insurer. The complainant lodged a complaint with AFCA on 19 February 2020, following two missed deadlines from the insurer. On 13 March 2020, the insurer contacted AFCA to advise building consultants (MC) had attended the property on 27 February 2020, to complete an inspection. The insurer said it believed the complaint was resolved as a result. The complainant responded to AFCA on 26 March 2020 , to advise the complaint was not resolved. The complainant advised that on 26 Feb 2020, MC attended the property and did not have all the appropriate issues from the local Council in his letter of directions from the insurer. The complainant was advised to obtain an updated letter from the local Council and have the insurer send the assessor out again to prepare one scope of works for all the issues. On 25 June 2020, the local Council sent the complainant an updated letter clarifying all the outstanding issues that need to be rectified. The updated letter was sent to the insurer on 26 June 2020, with a request for an updated assessment. On 8 July 2020, the assessor from MC came back to assess the property in accordance with the updated letter. He could not complete the job and attended the site again on 18 July 2020, to finalise his assessment. The assessor advised the report would take two weeks for him to provide to his boss, another two weeks for his boss to review and possibly another two weeks with the insurer before being delivered. The insurer advised the complainant on 14 August 2020, that it accepts indemnity for the new issues in the letter from the local Council, provided on 26 June 2020. On 9 September 2020, an AFCA case analyst, sent an initial letter to the insurer, requesting a response by no later than 30 September 2020. This timeframe was not met, and no response was received. The case analyst then sent a request for overdue response letter to the insurer on 7 October 2020, requesting the outstanding information, in addition to confirmation of attendance at the conciliation on 12 October 2020. The requested information was not received before the conciliation. On 9 October 2020, the insurer made an offer of $75,792.56 as a cash settlement figure, being the amount advised by WA Builders as a quote for repairs. The complainant rejected this offer and the complaint went to conciliation on 12 October 2020. No agreement was reached during the conciliation, however, the insurer promised to obtain an updated offer based upon two valuations of the property and Determination | Case number: 701126 Page 5 of 7 demolition works for the unauthorised build. The insurer missed its own deadlines conveyed to the complainant and AFCA on multiple occasions. On 10 November 2020, the insurer provided a revised settlement offer of $110,000. The complainant noted that the revised offer was relying on an incomplete scope of works, and that parts of the quotation for repairs were made without been viewed by the relevant contractors. The insurer disagreed, however, has not adequately addressed the issues raised by the complainant, and maintains adding information to the initial scope of works is acceptable. The insurer provided a builder’s (BC) scope of works dated 7 September 2020. The complainant responded to the scope of works on 09 September 2020, with detailed mark-up and notes on the PDF provided by BC. The complainant detailed concerns with water/electrical risk; temporary repairs; structural issues with the wardrobe and lintel, amongst other items. Apart from the insurer again accepting indemnity for the claim, the complainant did not receive a response to many of these questions and concerns. Having viewed all the exchanged material I agree with the complainant’s submission that BC’s scope of works does not factor in all rectification issues and is incomplete. I also agree with the complainant that the insurer’s 10 November 2020 offer, is not based upon a complete scope of works and some items have not been properly costed as costing are based upon estimates and not site attendance. Further, the complainant says that the offer made by the insurer, includes a miscalculation, to the complainant’s disadvantage. The insurer does not appea r to have responded and needs to do so. On 19 November 2020, AFCA sent the insurer a 14-day notice to provide a complete, up to date, scope of works in addition to an engineer ’ s report. This was not obtained. Considering the claim was accepted on 30 January 2020, that means the insurer has had over 300 days to provide a complete scope of works and an engineer ’ s report, which they have failed to do. I consider the delays by the insurer in resolving this claim to be unjustifiable and excessive. At no point has the insurer been able to adequately provide evidence as to why the delays were necessary. Given what has occurred I am satisfied that it is fair that upon acceptance of this determination by the complainant, the insurer immediately pays to the complainant the offered amount of $110,000. The insurer is also to pay interest on this amount from 10 November 2020, until the amount is paid. Determination | Case number: 701126 Page 6 of 7 The insurer is also to immediately obtain a scope of works and an actionable quotation from an engineer, to ascertain the full extent of rectification required. The complainant may also obtain her own scope of works if she wishes. The insurer is to meet its obligations to the complainant in accordance with the scope of works and actionable quotation and under the terms of the policy and to attend to any miscalculations.. If either scope of works indicates that there are further repairs required because of the insurer’s failure to resolve the claim and complaint, which would exceed the policy coverage limit, the complainant my return to AFCA for further orders. If the complainant chooses to obtain her own scope of works and actionable quotation, the insurer is required to reimburse the associated costs. 2.2 Non-financial loss compensation Under the AFCA Rules, we may award compensation (capped at $5,000) for non- financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. We take a conservative approach to compensation for non-financial loss. It is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. The complainant has provided AFCA with an extensive amount of correspondence which shows ongoing and lengthy delays in contact by the insurer. The complainant also provided a detailed timeline of events up until 10 September 2020. After this time, AFCA was copied into most correspondence with the insurer. In one instance, the complainant did not receive any contact from the insurer from 19 February 2020 to 29 June 2020. AFCA has also had issues in corresponding with the insurer and has had to follow up regularly to receive adequate responses. The numerous attempts at contact between the complainant and the insurer have been exchanged with both parties. The insurer has failed to handle this claim appropriately and its conduct in ensuring adequate responses were provided to the complainant, has fallen well below an acceptable standard. Since the in volvement of AFCA, the insurer failed to respond to AFCA’s initial request for information, nor did it provide the requested information following the request for overdue information. The insurer also failed to meet its obligations when providing AFCA and the complainant with multiple promises regarding providing an updated settlement offer after the conciliation. Determination | Case number: 701126 Page 7 of 7 The insurer has been aware of the considerable threat facing the complainant due to their breach of the local Council building requirements. The Insurer was made aware of this threat at the commencement of the claim and allowed the initial extension of time to lapse, without contacting the local Council. The complainant has again been advised that within 60 days from 25 November 2020, the breach will be handed to the local Council’s legal team to pursue further action. It is evident from the significant amount of communication and detail provided by the complainant, the insurer has not met its obligations under its own complaint ’ s policies, nor the expectations of the complainant and AFCA. I consider the way the insurer contacted the complainant, and at times AFCA, to fall well below the professional standards expected of a financial firm, and to have contributed to an extreme amount of inconvenience for the complainant. The claim was lodged with the insurer in November 2019. The insurer accepted the claim on 30 January 2020. I consider that 308 days to provide an accurate scope of works is not acceptable, and multiple make safes were required throughout this period. In addition to this, the insurer is aware the complainant has a child with an autoimmune condition and is also aware the property has been in a state of disrepair for many months. Given these concerns I am satisfied that it is fair in all the circumstances that the insurer pays the complainant, the additional amount of $5,000 for non-financial loss compensation.