Determination 700061

Adequacy of scope of works and cash settlement for storm water leak and ground movement damage

FirmAuto & General
Decided2020-09-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$29,359
Non-financial loss$2,500
Amount claimed$121,400
SourceAFCA PDF

Summary

A leaking storm water pipe damaged the home, and the insurer offered a cash settlement for the accepted scope. AFCA rejected the claim for underpinning and full repairs, required a 20% contingency uplift, and awarded $2,500 for delay in correcting the claim decision.

The complainants did not establish on the balance of probabilities that the leak caused the claimed underpinning and wider damage, and the insurer's expert evidence showed multiple causes.

Issues

Subjects and remedies

pay claimpay non financial loss

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination Case number 700061 Financial firm Auto & General Services Pty Ltd Determination | Case number: 700061 Page 2 of 16 Case number: 700061 4 September 2020 1 Determination overview 1.1 Complaint The complainants hold a home and contents insurance policy with the financial firm (insurer). The complainants submitted a claim for damage to their home involving cracking to the internal and external faces of the house. The insurer appointed a builder to inspect the damage, which was found to be the result of a leaking agricultural drain/storm water pipe. A quote and statement of work was provided for the amount of $24,466.20. A dispute has arisen as the complainants say the quote and scope of works are insufficient to repair the damage and that underpinning is required. Further, the complainants say they want the damage repaired rather than be cash settled. 1.2 Issues and key findings Is the quotation and scope of works provided by the insurer adequate to repair the damage? Yes, the scope of works is in line with the damage caused by the insured event. It is fair the insurer increases the cash settlement amount by a further 20% of that quoted amount to allow for unforeseen contingencies and the transfer of risk to the complainants. Are the complainants entitled to have the damage repaired as opposed to a cash settlement? No. Noting the issues of ground movement, the work cannot be warranted by the insurer’s builders. The insurer is therefore entitled to provide a cash s ettlement. Are the complainants entitled to compensation? The insurer took too long to resolve the complaint correctly. The delay in reaching the correct decision would have interfered with the complainants’ expectation of enjoyment and peace of mind. Determination | Case number: 700061 Page 3 of 16 1.3 Determination This determination is mainly in favour of the insurer. Should the complainants accept this determination, then within seven days of notification of acceptance, the insurer is to pay to the complainants:  $29,359.44, being the sum of $24,466.20 plus 20% contingency/transfer of risk, in full settlement of its liability pursuant to the claim, and  $2,500 compensation Otherwise, the insurer is not required to take any further action in relation to the claim or the complaint. Determination | Case number: 700061 Page 4 of 16 2 Reasons for determination 2.1 Is the quotation and scope of works provided by the insurer adequate to repair the damage? Complainants must establish claimed damage caused by insured event The complainants must establish, on the balance of probabilities, they have suffered a loss caused by an event to which the policy responds. This is known as a valid claim. It is not in dispute that the complainants ’ home was accidentally damaged because of a damaged agricultural drain/storm water pipe. The dispute relates to the extent of the damage caused by the event. The complainants must establish, on the balance of probabilities, all the claimed damage was caused by the event. Complainants instructed experts In support of their position, the complainants provided material from engineers and a builder. The insurer also obtained expert opinion. A summary of the expert opinion is set out in supporting section 3.3 of this determination. The complainants’ engineer RC concludes the damage is caused by the reactivity of the clay soil which has been exacerbated by the broken pipe/drain soaking the surrounding soil. RC says this has caused the clay soil to swell resulting in footing movement and building distress. A further report by RC suggests the house should be underpinned but does not provide any analysis as to how this conclusion was reached. RC attributes all the damage to the broken pipe, but the report does not provide persuasive and comprehensive information to support its conclusions. Similarly, neither the complainants’ builder (DG) or the other engineer (HC) explain why the leaking pipe has resulted in the need for the claimed underpinning. Insurer’s engineer says broken pipe is contributing factor, not sole cause The insurer obtained an engineer’s report from JH. JH agrees with RC in relation to the broken pipe causing the damage to the front of the property, but JH says this is not the sole cause of all the damage to the house. JH suggested the cause of damage may be attributed to several factors, such as ground movement, soil moisture variation, proximity to trees, environmental conditions and construction orientation. It says the combined effect of these factors over a period will eventually cause the separation of joints and cracking. JH also measured floor levels and says these do not establish severe swelling at the leak locations, supporting its contention multiple factors are the cause of the damage. Determination | Case number: 700061 Page 5 of 16 JH suggested the damage be apportioned 25% to the broken pipe and 75% due to the other factors for which cover is not provided by the policy. JH says all other damage is unrelated to the escape of liquid as it is too physically remote for the pipe fracture to be the cause of damage. JH goes on to say the broken pipe may be the result of the ground movement in the first instance. The report provided by JH is thorough and detailed, linking observations and evidence, rather than simply providing commentary. As such, it is a credible account of the probable cause of the damage. Insurer’s scope/quote sufficiently address repairs related to the damaged pipe Following the report from JH, the insurer initially offered 25% of its quote to the complainants. The insurer subsequently offered the full cost of repairs to the damage which could be attributed to the damaged pipe. There are items in the scope of works (SOW) provided by both parties which address similar repairs, and, in those instances, the quotes are relatively similar. Available information does not establish underpinning required because of leak The additional works provided by the complainants include underpinning of the house, replacement of the ground floor titling and some upstairs damage. There is no detail provided by RC as to why the underpinning relates to the leak. Further, the report supplied by JH addresses the damaged tiles and the upstairs damage. Based on the information provided the panel is satisfied these are unrelated to the insured event. JH was asked to provide specific commentary on the complainants’ requirement to underpin the property. JH reviewed the compl ainants’ expert reports, drawings and underpinning proposal. In the absence of any rebuttal material, the panel finds the opinion of JH persuasive. The panel accepts underpinning is not necessary based on the measured floor levels. The measured floor levels demonstrate a 44mm variance across the full width of the house. Normal surface movement for the complainants’ house would be 40mm. Therefore, on the available information, the panel accepts the footing movement cannot be described as severe and the footings are performing at or about the normal expected movements for any house constructed on the subject site. The panel considers the complainants have not provided persuasive evidence to show the insurer’s SOW and quote is not sufficient to repair the damage which has been accepted. Conversely, the insurer has been able to provide expert opinion explaining why the damages claimed are not all a result of the leak. Accordingly, the panel is satisfied the SOW provided by the insurer is sufficient save that the insurer is required to increase the cash settlement amount by a further 20% of that quoted amount. That is to ensure a fair settlement by allowing for unforeseen contingencies once repairs commence and the transfer of risk to the complainants. Determination | Case number: 700061 Page 6 of 16 2.2 Are the complainants entitled to have the damage repaired as opposed to a cash settlement? Insurer to pay to the complainants $29,359.44 The policy allows the insurer the discretion to repair an item, replace an item or pay a cash settlement to an insured. AFCA expects an insurer to exercise this discretion fairly in all the circumstances. The insurer is seeking to cash settle the claim, so it must be considered whether the insurer’s decision is fair and reasonable in the circumstances or whether the insurer should be required to repair the accepted damage. The report provided by JH suggests the evidence indicated long term ground movement damage and long tile expansion damage has occurred and the damage will be ongoing until effective remedial measures have been implemented. As a result, the builder says it cannot warrant the work. Therefore, the panel accepts it is reasonable a cash settlement has been offered by the insurer in these circumstances. Should the complainants accept this determination then within seve n days of notification of acceptance the insurer is to pay to the complainants $24,466.20 plus the 20% uplift of $4,893.24 making a total settlement due of $29,359.44. 2.3 Are the complainants entitled to compensation? Compensation paid in some circumstances The complainants are unhappy with the insurer’s claims management. They refer to delay tactics, not taking calls and deflection of responsibility and legal obligations. AFCA will award compensation (capped at $5,000) if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and anxiety. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. Insurer to pay to the complainants $2,500 compensation Not long after the claim was made, the insurer arranged for the damage to be inspected by a builder, and then an engineer and a plumber. In its final decision letter of 16 December 2019, it said it was unable to accept 75% of the damage. In March 2020, the insurer corrected this decision and accepted the full cost of repair to the damages attributable to the leaking pipe. Determination | Case number: 700061 Page 7 of 16 Having considered the available material, the panel considers the insurer took too long to resolve the claim correctly. The panel accepts the delay in reaching the correct decision would have interfered with the complainants’ expectation of enjoyment and peace of mind. The panel is satisfied it is fair in these circumstances for the insurer to pay the complainants $2,500 compensation. Determination | Case number: 700061 Page 8 of 16 3 Supporting information 3.1 Our Approach This complaint has not been the subject of a recommendation. Due to the nature of the complaint, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the AFCA Rules. The panel consists of an ombudsman and two representatives with consumer and insurance experience. The complaint has been determined based on what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance, good industry practice and previous relevant determinations of AFCA or predecessor schemes (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All the material provided by the parties has been reviewed and considered for the purposes of this determination. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. It is an accepted principle of general insurance law that the insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. 3.2 Relevant policy terms The relevant policy extracts are referred to in the correspondence between the parties and in the insurer’s Notice of Response . Both the policy document and the Notice have been exchanged with the complainant. 3.3 Policy Wording Reference Wording P. 11 Insured event Sudden and unexpected escape of liquid at the insured address from:  baths, sinks, toilets, basins or any fixed plumbing apparat us  fixed heating or cooling system or sealed portable unit  gutters and drainpipes attached to your home  pipes and taps  washing machines or dishwashers  water beds  water collection trays in any refrigerator or freezer. Determination | Case number: 700061 Page 9 of 16 Reference Wording We will also pay reasonable cost s incurred to locate the unknown source of a leaking pipe, but only if the leaking liquid is causing damage to your home and/or contents. We will not cover  the cost of repair or replacement of the pipe, tank, or container that the liquid escaped from, including the cost of repairs to a leaking shower floor, base, or walls  loss or damage caus ed by leaking shower floors or bases, tiled roman baths or shower recess walls  loss or damage caus ed by wat er splashing from baths, basins, recesses or tubs during u se  loss or damage caus ed by liquid that has escaped slowly over a period of time, unless it is reasonable that you could not have known about the liquid escaping. p. 29 – 32 General Exclusions Applying to the Whole Policy We will not cover Earth movem ent  loss or damage or the incurring of legal liability caused by erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement. But subject to the policy terms and conditions, we will cover loss or damage caus ed by earth movement that occurs within 72 hours and as a direct result of the following insured events:  Earthquake,  Explosion, or  Storm and rainwater Gradual deterioration  loss or damage caus ed by rust, corrosion, rot, mould, rising damp, mildew, gradual deterioration, wear, tear or fading Trees, shrubs or plants  loss or damage or the incurring or legal liability caused by the roots of trees, plants or shrubs. p. 36 How we settle claims If we agree to pay a claim for loss, theft or damage to your home, contents or personal effects, we will decide whether to:  repair the damaged property to the same standard, specification or quality as it was when it was new, or  replace the damaged property with the nearest equivalent property available, or  pay you the amount it would cost us to repair or replace the property to “as new” condition. The cost to us is:  the retail price of an item less any trade discount we are entitled to, or  the cost to us to repair or replace the property, allowing for any Determination | Case number: 700061 Page 10 of 16 Reference Wording trade discount we are entitled to. 3.4 Expert Reports Record Key points Insurer’s expert ( JP) builder’s report 2 8 .08. 2019  Inspected and photographed the property with the complainant 28 August 2019.  Noted small movement to the cornice and wall plaster in the lounge room and a large movement to the rendered brickwork at the front of the house starting at the ground level and reaching the top of the aluminium fascia.  Inspected the subfloor at the rear which showed no evidence of movement or moisture.  Possible damage to the front has been caused from leaking pipe or blocked drains at the front.  CCTV inspection be carried out to determine what exactly is causing the large amount of movement t o the front of the property and a specialist engineer to provide a repair method and scope of works for the cracks to the rendered brick work.  Provided a preliminary scope of works for the cornice and wall plaster in the lounge room.  P roperty is a double story brick veneer in excellent condition and very well looked after, an inspection throughout the property found no other movement or cracks it is only the front left - hand side that is affected. Insurer’s expert ( JH ) e ngineer r eport 10.10. 2019  Engineer ins pected and photographed 16 September 2019.  Rendered brickwork satisfactory to the east and south. Significant separation noted to the front brickwork on the left northern side of the front wall and rounded edge cracking in the render to the le ft nort hern side of the home.  Photographs show cracking to the northern elevation wall.  Inspected under the house noting large soil shrinkage cracks in the soils towards the northern elevation and water path noted coming from the front of the house under the external wall crack.  I nternal section of the residence displayed damage to limited plasterwork elements. Cracking was noted in the cornice and wall elements and appeared aged. Damage was pres ent to both levels adjacent to the front external wall crack. Cracked floor tiles noted but no tile expansion joints observed.  Conc rete separation gaps noted in the walls and cornices of garage.  Soil described as reactive: consistent with the observed soil shrinkage cracks present in sub floor void.  Level survey u ndertaken showing a 44mm variation falling towards the northern elevation. Peak not recorded at front external damage loc ation. Determination | Case number: 700061 Page 11 of 16 Record Key points  Observed damage and level variations are signific ant.  C aus e of movement on this site may be attributed to a number of factors:  Sub grade Movement  Soil Moisture Variation  Environmental Conditions  Trees wit hin Footing Influence Zone  Construction Orientation  combined effects of the above factors develop ov er an extended period of time. As a result, foundation and wall stress gra dually increases. Event ually the build - up of stress is relieved by the separation of articulation joints and/or the development of cracks.  causal mechanism and subsequent damage has gradually developed over a number of years as evidenced by rounded cra ck edges to the garage and Nort hern elevation wall. Moreover it is reasonable to conclude the damage will be ongoing until effective remedial measures have been implemented.  Level surveys do not indicate a large localised swelling at the location of dama ge although ground seepage was seen in the area under the house.  B reakage of the underground plumbing pipe could be contributing to the movement depending on the location of the drainage lines and location of a leak. Conversely the broken pipe may be the res ult of the generalised footing movement to the dwelling in the first instance. Requires plumbing investigation.  Re tiles: there are a number of factors which have contributed to the observed tile damage including: Tile Growt h. The effects of tile growt h (moisture abs orption) takes many years to develop. Hence the causal mec hanism has developed over a number of years. Absence of Expansion Joints.  A vailable evidence indicated long term ground movement damage and long term tile growth damage has occurred t o the subject dwelling. Specific causation factors have been included above in this report. Thus the available evidence indicates the damage is not due to a single event but we await the results of the plumbing investigation . Insurer’s expert ( PB ) p lumbing r eport 18.10. 2019  CTV inspections (18 October 2019) of the property's below ground storm water drainage system found the following defects  1 x Tree root affecting the aggy pipe across front elevation.  1 x Fracture affecting the rear of garage.  Fron t RHS pit backing up into aggy pipes across front elevation.  Stormwater can be seen back up into the pit at the front RHS of the dwelling and subs equently back through the Aggy drain across the front elevation of the dwelling due to the Determination | Case number: 700061 Page 12 of 16 Record Key points configuration of th e stormwater drains approx. 200mm from this stormwater pits outlet. This could be allowing water egress into sub surface soils across the front of the dwelling.  Large fractures can be seen affecting the stormwater drains underneat h the back RHS corner of t he garage. This is in the area and in line with the movement and cracking. Insurer’s expert ( JH ) supplementary report 06.11. 2019  Reviewed plumbing reports. Confirm findings of our original report as to damage causation including soil shrinkage as pipe fractures at the front and side of the house which correlate with a high slab levels and seepage parts observed in the subfloor.  This consistent with the liquid from the pipe causing some minor loc alised swelling in the founding soils evidenced by the cont ours and level variations.  Fractured pipes have contribut ed to the damage to the front of the house but are not the sole cause.  Significant soil shrinkage cracks noted in the subfloor.  Difficult to quantify the extent of damage due to the escape of liquid but say 20 to 25%.  All other damage is unrelated to the escape of liquid as it has occurred remote to the high section of level contours. Insurer’s expert ( JP) b uilders quote & SOW 21.11. 2019  Total quote value $24,466.20 (Includes builder’s margin of 20% and GST) for preliminaries, external front left corner of the house, internal bedroom first floor and family room.  [JP] are unable to warrant repairs .  we have provided a cost for the external damage and cracked brick work which is related to the escape of water as per the engineer ’ s report . We have provided a cost for a l l the damage that we believe is related and provided a full cost for this. Insurer’s expert ( JH ) s upplementary report 06.12. 2019  Reviewed the report from the complainant’s engineer whic h has identified reactive soils consistent with JH’s findings about multiple causation factors.  Pipe fractures to the front correlate with a high slab levels and seepage path seen under the floor. This is consistent with the liquid from the pipe causing so me/minor localised swelling in the founding soils. This is evidenced by the contours and level variations. Thus the available evidence indicat es the fractured pipework to the front of the dwelling has contributed to the damage to the front elevation of the dwelling, but is not the sole cause. Reiterated significa nt soil shrinkage cracks noted in the subfloor.  Difficult to quantify the extent of damage caused by the escape of liquid but say 20 to 25% attributable to the pipe fractures due to the other multiple causes contributing.  This relates to the damage to the front wall of the habitable section of the house external and internal (that is, external masonry articulation joint, front wall cornices to both levels).  A ll other damage about the dwelling may be considered as Determination | Case number: 700061 Page 13 of 16 Record Key points being unrelat ed to the escape of liquid as it has occurred remot e to the high section of the level contours.  Cracking has occurred to areas of the house remote from the storm water due to sub - grade movement, climatic soil moisture variation, environmental soil conditions, construction orientation a nd the effect of trees/ vegetation on reactive founding soils.  D amage to ot her areas of the dwelling are too physically remot e for the pipe fracture to be the causal mechanism of damage. Insurer’s expert ( JH ) s upplementary report 06.02. 2020  Reviewed complainant’s engineer’s report in relation to the unlevelled section of the upstairs.  Engineer referred to soil type as class M but does not contain measured levels which may be compared against the expected soil movement for class M site.  Class M sites have a defined expected ground movement up to 40mm as per Australian Standard.  Recorded floor levels determined a variation of 44mm to the habitable section of the house. Allowing for levelling tolerances this generally correlates with class M sit e expected ground movement and demonstrates g lobal footing movements substantially in excess of the normal expected movement has not occurred across the dwelling.  This furt her indicat es the influence of the pipe fractures have not resulted in severe movem ents.  A gree with the insured’s e ngineer’s findings that the pipe fractures would have resulted in the swelling of the clay soils. However, the measured floor levels do not establish severe swelling at the leak locations. This again supports the rational co nclusion that multiple factors are at play in the performance of the structure due to dispersion of damage around the dwelling (i.e. see 5 causal factors in orig. report)  In s implistic terms , the leak cannot rationally be held to have caused all the damage about the structure.  Upstairs damage: limited upstairs damage is relat ed to the leaks. This is reflected in the approved s cope of works.  Unlevelled upper floor: the upper level cannot move vertically in an independent manner from the lower level due to t he physical connection. Thus, ground floor levels are sufficient to establish the extent of vertical movement experienced by the dwelling due to ground movement.  S cope of works has been reviewed and is considered to allow for all the elements required for repair attributable to the leak. JH review 07.08. 2020  Reviewed complainant’s inspection report, drawings and underpinning proposal.  Underpinning not necessary based on measured floor levels and provisions of Australian Standard. Australian Standard provides underpinning should only be considered as a last Determination | Case number: 700061 Page 14 of 16 Record Key points report.  M easured levels demonstrated a 44mm variance across the full width of the habitable dwelling. Furthermore, the site is considered to be a Class M site as reported by the ins ured's engineer.  As detailed in our supplementary report dat ed 6 February 2020, the expected normal surface movement for a M class is up to 40mm as defined in Australian Standard. Thus the footings are performing closely with the normal expected movements for any house constructed on the subject site.  F ooting movement cannot rationally be described as being "severe", as it closely matches the normal expected movements. Hence any recommendation that underpinning is required is not consistent with the "last resort" provisions of the Australian Standard.  N oted multiple long - term causal mec hanisms are at play about the dwelling (as described in original report) and are subsequently driving 'global movement across the entire footing system'. As previously identified the global 44mm footing variation is the result of these long - term mechanisms . Owner maintenance of thes e causal mechanisms (which are unrelated to the leak) including trees and drying soil moisture to the Northern house elevation is required as per the Australian Standard. Complainants’ expert (RC ) engineer r eport 29.11. 2019  Documentation indicates soil with moderate reactivity which swells when moisture is absorbed and shrinks in dry weather.  Shrubs and small trees ab ut the front of the property with the balance of landscaping consisting of lawn and sparsely located small to medium trees. A row of neighbouring trees abut the property however are located at some distance.  Masonry wall cracking was predominat ely to the front of the dwelling (north end), the north wall of the dwelling abutting the garage and the east wall of the southern garage. Furthermore, the fir st floor to the bedroom 4/ rumpus area does not appear level. The wardrobe doors have become inoperable due to this floor movement. Hairline tile cracking was observed to the ground floor entry. The central pillar to the rear concrete stair has completely detached from the conc rete stair. There does not appear to be a physical tie present. The stair does appear to be in distress.  Reviewed plumbing report. A gricultural drain holds storm water resulting in uncontrolled disc harge to the surrounding soil. This uncontrolled storm wat er discharge would come into contact with the subsurface clay (foundation material) resulting in it to swell. The swelling of the clay would result in footing movement and cons equent wall and floor movement as evident on site.  M ajority of wall distress and floor movement is near where the storm water system is either broken or become ineffective.  O bserved distress to the building is caused by the reactivity of Determination | Case number: 700061 Page 15 of 16 Record Key points the clay soil and has been exac erbate d by the fractured storm water pipe and the agricultural drain releasing unc ontrolled storm water discharge to the surrounding soil. This has caused the clay soil to swell resulting in footing movement and building distress. Complainants ’ expert ( RC ) engi neer report 21.01. 2020  R ecommend to rectify the damage a n underpinning professional company be engaged to provide underpinning services alongside the wall that has failed.  R ectifications are to be structural and to address the items mention ed in the r eport dated 29 November 2019. Complainants ’ expert ( HC ) engineer report 21.01. 2020  Inspected and meas ured 20 January 2020.  Noted cracking in parts of the garage and in the north west side of the building next to the garage. Cracks indicate severe structural displac ement within the supporting footing network. Brief examination of Inside highlighted unevenness and cracking.  Rev iewed soil report structural footing plans and RC letter.  Note that a report prepared by plumber indicated damaged services within stormwater pipes within the building.  Abrupt and sudden moisture change in soil will facilitate abnormal soil reaction res ulting in potential heaving and shrinkage (as a process of moisture loss or evaporation) and will initiate movement within supported footings beyond the tolerance of design and hence eventuate potential cracking in brittle structures lead to further struct ural defects.  Significant abnormal moisture change over prolonged period of time may affect and the bearing capacity of underlying soil by potentially impacting soil composition and cohesion. While rectifying plumbing related issues will progressively red uce the effect of abnormal moisture change, future movement may be evident until a time for soil to regain its optimum moisture content. This process of rejuvenation may extend over multiple seasons and therefore movement shall still be tolerat ed within fo otings in the future.  To reduce the impact of this process, it may be advised to provide underpinning works to the existing footings affected by this process which may alleviat e (or reduce) further critical footing displacement in the short - term.  A pre liminary design has been provisioned as part of this report to provide indication of the extent of works whic h may be needed and therefore proposed. Complainants ’ expert ( DG ) rectification quot e 28.05. 2020  Reviewed material from engineer (HA) and quoted to carry out underpinning and rectification works following the building settlement along the northern half of building, resulting from the prolonged water egress.  R ectification works outlined cover repairs o f all damage affected by this occurrence, as well as subsequent works to ensure these repairs are not visible, and that the hous e is Determination | Case number: 700061 Page 16 of 16 Record Key points restored to it s original state prior to this occurrenc e .  W orks outlined are based on my site inspection conducted with you on the 13 May 2020, as well as the building and engineering reports you emailed to us.  Preliminary costs $17,120, underpinning 26 locations and subsequent reinstatement works ($53, 200), internal repairs ($21,024), façade repairs ($19, 020), total including GST $121,400.40. 3.5 Other relevant material considered and relied on  Parties’ submissions /emails and all attachments to all submissions/emails.  Parties’ expert reports .  Photographs and videos.  Scopes of work and quotations.  Underpinning proposal and layout 25 January 2020.  Correspondence between the parties.