Determination 698734
Cash settlement offer and stopped storm repairs
Summary
The insurer stopped partly completed storm repairs after finding the cost would exceed the sum insured and offered a cash settlement of the balance. AFCA ordered the insurer to complete the repairs or cash settle, pay temporary accommodation, and pay $5,000 for non-financial loss.
Having chosen to repair and substantially progressed the works, the insurer could not fairly stop them and seek to cash settle the balance after more than two years.
Issues
- Claim amount dispute primary · upheld“No. The insurer has partially completed the repairs and spent a substantive proportion of the sum insured towards it.”
- Delay secondary · upheld“The insurer caused unreasonable delays in its claim handling that has impacted the complainant significantly.”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial lossrepair or rectify
Related
All Allianz Australia determinations · Find similar determinations
Text of the determination
Determination
Case number 698734
Financial firm Allianz Australia Insurance Limited
Determination | Case number: 698734 Page 2 of 17
Case number: 698734 30 October 2020
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm
(insurer).
The complainant lodged a claim for storm damage to the property. The claim was
accepted by the insurer and repairs authorised through a panel repairer. The insurer
has stopped repairs mid-way and now says:
the repairs cost exceeds the sum insured on the policy
it will pay for the outstanding repairs but only up to the sum insured on the policy.
The complainant disputes the insurer’s decision and is seeking for it to complete the
repairs or pay out the sum insured. The complainant is also seeking compensation for
inconvenience, stress and anxiety caused due to extended delays in claim handling.
1.2 Issues and key findings
Is the settlement offered fair and reasonable?
No. The insurer has partially completed the repairs and spent a substantive proportion
of the sum insured towards it. Further, the claim is almost three years old. It is not fair
in all these circumstances for the insurer to now stop the repairs and seek to pay out
the balance of the sum insured.
Therefore, the insurer should settle the claim as set out in section 2.1.
Should the insurer pay non-financial loss?
Yes. The insurer has caused unreasonable delays in its claim handling that has
impacted the complainant significantly. The insurer should pay $5,000 in non-financial
loss.
1.3 Determination
This determination is in favour of the complainant.
The insurer is to settle the claim as set out in section 2.1.
The insurer is to pay $5,000 in non-financial loss.
Determination | Case number: 698734 Page 3 of 17
2 Reasons for determination
2.1 Is the settlement offered is fair and reasonable?
Circumstances of the loss
The complainant has a home and contents policy with the insurer. The complainant
lodged a claim for storm damage to property on 6 February 2018.
The insurer engaged assessor C who attended the site on 12 February 2018. C
assessed the complainant’s property and acknowledged that the storm lifted the front
veranda. This landed on the roof and caused damage to the property. C organised a
make safe through a builder (D). D removed the veranda from the roof. Local SES
tarped the roof to prevent further rain water ingress and damage to internal property.
The policy provides cover for various insured events, including storm. The first report
from C confirms the complainant has established a claimable loss. C also engaged
two builders to provide a scope of works and quotations for repairs to storm damage
to the property.
Structural engineer report
C engaged a structural engineer (G) who provided a report in June 2018. The report
provides more information on the damage caused by the storm event to the roof and
the wall adjoining the uprooted veranda.
The report also provides images and shows damage to property which is not caused
by the storm event. This includes the ceiling as well as movement damage to the
concrete floor near the entry door.
G provided a scope of works and C requested two builders (D and F) to provide a
revised quote, including the additional work recommended by G. The quote received
from F was for $119,129.80 and D’s quote was for $87,436.02. F had highlighted the
possibility that further works may be required for the brickwork.
As the quote provided by D was lower, it was approved by the insurer. D started
coordinating with the council for approvals and prior to commencing the repairs,
noticed additional damage to the property from ground movement.
D withdrew its quote citing inability to warrant repairs
Assessor C organised the same engineer to assess the additional damage reported
by D. This engineer had moved to another company at the time (CSU).
CSU visited the property on 3 April 2019. The report advises that with the external
veranda missing, water flowed into the sub floor areas of the property causing
additional movements and cracks. CSU said this damage was a direct consequence
of the storm event and hence should be included in the scope of works.
Determination | Case number: 698734 Page 4 of 17
CSU also commented that delaying the repairs further will result in worsening of the
existing damage and advised for the repairs to be undertaken without any further
delays.
After reviewing this report, D communicated its decision to withdraw its quote due to
inability to warrant repairs.
Insurer engaged a second builder to carry out the repairs
After D withdrew its quote, and in an effort to speed up the repairs process, the
complainant engaged a heritage structure repairs expert CR who quoted $151,206 for
the repairs.
The complainant did not want a cash settlement and sought for the insurer to
authorise CR to undertake the work. This prompted C to engage another panel
builder J to provide a comparative quote. J appointed a heritage consultant and
provided a quote for $127,976.86. This was accepted by the insurer and J was
advised to proceed with repairs.
Original scope of works and two variations approved by insurer
The complainant requested the insurer to provide temporary accommodation due to
his wife’s health issues. This was accepted. The complainant was moved into
temporary accommodation and has not been able to get back to the property as
repairs are incomplete.
J commenced repairs in February 2020, about 24 months after the claim lodgement.
The original repairs quote $127,976.86 was approved by the insurer. The scope of
works included repairs to:
veranda
main roof
external brickwork
living room
front entry
sitting room.
The scope of works for the external brickwork included removal of bricks from the top
4-5 courses and replacement of the same.
The first variation requested by J was for $48,732.52. This was due to additional
damage being identified to the north facing roof and bull nose veranda, which were
also damaged during the storm event.
The second variation was for $3,682.80. This included replacing the main roof
guttering to bring uniformity to all external guttering as per heritage structure
requirements.
Determination | Case number: 698734 Page 5 of 17
Both the variations were approved.
Third variation for $136,481.40 has not been approved
A third variation request from the builder to the insurer was not approved. This is
because the cost of repairs will exceed the sum insured on the policy.
This variation was mainly because the brick wall needed to be completely removed
and replaced. This would include laying suitable foundations as the original brickwork
had none.
As a result, the insurer offered to settle the repairs in this way:
Settlement offered is not fair and reasonable
The insurer’s position and offer are unfair.
The policy provides the insurer with the discretion to settle the claim in one of these
ways:
At our option, we will:
a. repair or rebuild the damaged part of your building to the same condition
as when it was new; or
b. pay you the reasonable cost of repairing or rebuilding any damaged part
of your building to the same condition as when it was new; or
c. pay you up to the amount of the sum insured.
In most circumstances, once an insurer exercises its discretion, it is bound by it.
There is no dispute the insurer chose to repair the damage. In particular, the insurer
has progressed substantively in the repairs. The fact it has disco vered, more than two
years after the claim, that the cost is going to exceed the sum insured is not of itself a
fair or compelling reason to now stop the repairs and seek to cash settle the balance.
Further, in normal circumstances, when the cost of repairs exceed the sum insured,
the insurer can cash settle so that the complainant can make their own arrangements.
This may include taking any opportunities to mitigate the cost by either undertaking
certain works themselves, using mutual acquaintances, focusi ng on substantive
Determination | Case number: 698734 Page 6 of 17
issues (e.g. structural matters) or selling the property. These opportunities have been
lost as more than half the funds were spent by the insurer on contractors it chose to
engage and in arranging the repairs as it saw fit.
In addition, it would be impractical for the complainant to now have to engage other
contractors to finish the works. There will be legitimate issues as to which contractor
is responsible for what works. The complainant also says no contractor would be
prepared to warr ant the works given the property’s heritage status. This is likely given
both the heritage status and the fact the repairs have been left partially complete.
There are also legitimate concerns that the insurer has not mitigated the risk of further
damage to the property. CSU’s report noted that the removal of the veranda resulted
in water entering the foundations and causing movement and cracking issues. This
should have been a foreseeable risk given the veranda would be directing stormwater
away from the property. Therefore, at the least, any additional damage caused by this
should not be subject to the sum insured. This additional damage could include the
need to replace the brick wall, which has substantively increased the cost of repairs.
Given all this , the panel does not accept the insurer’s settlement is either fair,
reasonable or consistent with its obligations to the complainant.
How the claim should be settled
The complainant says the property should be a write-off.
The panel is not persuaded by this. Whilst the situation is complicated, it is not clear
from the available information that the damage cannot be repaired.
Given this, and the fact the insurer committed to repairing the property, it is fair for the
insurer to follow through with the repairs.
Therefore, the insurer should complete the property repairs and pay for temporary
accommodation until the property is repaired and habitable again. The payment of
temporary accommodation is not subject to the policy limits. This is because both the
repair period, and the extent of the repairs, has likely been substantively exacerbated
by the insurer’s conduct.
The panel acknowledges completing the repairs may be long and complicated. This
claim is almost three years old. The repairs are partially complete. There are
concerns further damage has occurred, which will need to be assessed and
considered. It is also not clear if J, or other contractors, are prepared to finish the
works.
Given this, and as an alternative, if the insurer wishes to cash settle the claim, then
the complainant’s option of declaring the property a total loss is a fair outcome. This is
because of the following.
Determination | Case number: 698734 Page 7 of 17
Based on J’s cost of repairs, and the amounts already paid by the insurer, there is
over $150,000 worth of repairs. This will not include additional costs that may be
discovered in the repairs. Given the parties experience to date, it is likely the costs will
continue to increase and possibly reach or exceed the sum insured.
This is putting aside the real issue of whether any of the parties can find a contractor
who is prepared to complete the repairs.
The panel also notes that if the complainants wanted to sell the property, it is unlikely
the partially complete repairs would add much value to the sale. This is particularly
the case if a purchaser identifies the property is heritage listed and a contractor is not
prepared to complete the works.
If the insurer does choose a cash settlement, it will have to pay the maximum benefits
under the policy associated with this claim. This would include the following:
the sum insured – this should include the automatic indexation benefit being
applied as at the date of the loss
the 10% additional benefit for temporary accommodation and ‘removal of debris,
professional fees and extra costs’ – this is in top of the sum insured
the fact GST is paid in addition to the sum insured (page 50 of the policy)
If the complainant accepts this determination, the insurer is to clarify if it wishes to
proceed with the repairs or cash settle the claim.
2.2 Should the insurer pay non-financial loss?
Compensation is awarded conservatively
Under the AFCA Rules, we may award compensation (capped at $5,000) for non-
financial loss where a complainant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
We take a conservative approach to compensation for non-financial loss. It is not
awarded when a person suffers the normal degree of inconvenience when a problem
occurs.
The insurer caused unreasonable delays
There is no dispute this claim has been substantively delayed.
The complainant and his wife are an elderly couple. Repairs did not commence until
about two years after the claim. This is too long. Whilst the panel appreciates the
situation is complicated given the heritage status, this timeframe is unreasonable. It is
also plain the impact of this experience to the complainant and his wife was
significant.
Determination | Case number: 698734 Page 8 of 17
The insurer’s proposed cash settle ment was unfair for reasons explained. Further,
even on its own position, the insurer’s allowance was inadequate as it did not include:
the GST portion which is meant to be paid in addition to the sum insured
an allowance for the automatic indexation of the sum insured
no allowance for interest despite the fact its attempt to cash settle the claim was
more than two years after the event
Additional damage also occurred due to the insurer failing to mitigate the risk of the
veranda removal. This would have increased the stress and inconvenience to the
complainant.
Therefore, the panel accepts the circumstances warrant the maximum amount of
compensation for non-financial loss. The insurer should pay $5,000 in non-financial
loss.
Determination | Case number: 698734 Page 9 of 17
3 Supporting information
3.1 Our approach
As advised to the parties, AFCA has considered it appropriate to expedite this
complaint in accordance with the Operational Guidelines to the AFCA Rules, due to
the nature of the complaint. Accordingly, this complaint has not been the subject of a
recommendation and has proceeded directly to determination.
This complaint has been determined based on what is fair in all the circumstances,
having regard to legal principles, applicable industry codes or guidance, good industry
practice and previous relevant determinations of AFCA or predecessor schemes
(which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All the material provided by the parties has been reviewed and
considered for the purposes of this determination.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
3.2 Extract from expert reports
Record Key points
Engineering report
10 April 2019 Page 2
In the corner inspected the ground below the floor was damp, though not
saturated. We note that there is a vent near the ground level on the outside of
the house. This is located such that significant flow over the ground would likely
result in some water flowing underneath the house. With the external veranda
now missing, the water from the hou se roof discharges directly onto the ground
next to the house and flows along beside the building, including some which
will flow into the ground level vent. There are flow marks in the soil indicating
significant surface flows in the recent past. We belie ve that during rain events
over the last year some wat er has flowed underneath the house, soaked int o
the soil and has caused some additional movement to the footings and caused
additional cracks. This is a direct result of the water from the roof being al lowed
to discharge onto the ground beside the house, rat her than controlled as it was
when the veranda was pres ent. Thus this damage is a direct consequence of
the storm event which removed the veranda.
Comparison of the photographs from the phot os of May 2018 show that the
cracks in this part of the house are clearly more severe than previously.
Existing cracks have increased in width and new related cracks have
Determination | Case number: 698734 Page 10 of 17
Record Key points
appeared.
The additional movement to this part of the house has also caused additional
damage t o the wall. We now recommend that the wall be deconstructed to the
top of the window level near the south west corner of the house, and the lintel
and brick arch reconstructed over 1 window (s ee photo)
When the veranda is repaired, the ground under it should be shaped so that
surface flows are kept away from the house and prevented from flowing under
it. Once the external veranda is repaired and water prevented from flowing
alongside and underneath the hous e, the ground under the house will stabilize
an d further movement will be minimal.
Because the soil is now wet under the house, it is likely that after the repairs,
some minor cracks may appear in the wall, as the soil under the house dries
out. If significant, these can be furt her repaired later. Howe ver they may be
minor, in which case they can be treated like the very large number of minor
cracks in the house and monitored for long term movement.
The worsening damage is a res ult of the missing veranda and associated poor
drainage and thus is a direct result of the storm event which removed the
veranda.
Delaying repairs further will res ult in on going and worsening damage to the
house. We recommend that the repairs be undertaken without further delay.
Engineering report
10 April 2019
Page 4
Determination | Case number: 698734 Page 11 of 17
Record Key points
Determination | Case number: 698734 Page 12 of 17
Record Key points
Determination | Case number: 698734 Page 13 of 17
Record Key points
Determination | Case number: 698734 Page 14 of 17
Record Key points
Determination | Case number: 698734 Page 15 of 17
Record Key points
Determination | Case number: 698734 Page 16 of 17
Record Key points
Determination | Case number: 698734 Page 17 of 17
Record Key points