Determination 697788

Development loans, progress payments to builder and financial difficulty response

FirmLa Trobe Financial Asset Management Limited
Decided2021-08-26
ProductCredit · Business lending
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A company and its guarantor complained about the adequacy of two development loans, progress payments made to the builder, and the lender's hardship response. AFCA found no lender error and ordered nothing except that, if accepted, the lender provide three months to repay or refinance.

The lender relied on a quantity surveyor's advice and the borrowers' knowledge and consent to progress payments, and AFCA cannot revisit the period covered by the forbearance deed.

Issues

Subjects and remedies

financial hardshipsmall businessloan or hardship variation

Related

All La Trobe Financial Asset Management Limited determinations · Find similar determinations

Text of the determination

Determination Case number 697788 Financial firm La Trobe Financial Asset Management Limited Determination | Case number: 697788 Page 2 of 6 Case number: 697788 22 July 2021 1 Determination overview 1.1 Complaint In May 2016, the financial firm (the lender) approved a business loan (Loan A) of $2,704,000 to the first complainant (S Company). The funds were provided to refinance a loan in the sum of $669,000, and to develop six residential units a nd two shops („the development‟ for $1,850,000 and cover $185,000 in interest repayments for the loan). In April 2018, the lender approved a further business loan (Loan B) of $369,000 to complete construction of the six residential units and two shops. S C ompany‟s director, Ms K, guaranteed its facilities and is the second complainant. Construction was undertaken by a separate building entity (M Company). The loan has been fully drawn by way of progress payments made by the lender to M Company and the development is incomplete. S Company and Ms K say:  The lender did not provide Loan A appropriately  The lender did not provide Loan B appropriately  Did not act appropriately by making progress payments to M Company  The lender did not comply with its financial difficulty obligations  S Company and Ms K are in financial difficulty An AFCA case manager provided the parties with a recommendation dated 22 April 2021 on the issues in dispute. A copy of the recommendation is attached to this determination. The recommendation was in favour of the lender. The complainants rejected the recommendation and reiterated their previous submissions to AFCA in their response. 1.2 Issues and key findings Were the findings in the recommendation correct? The findings in the recommendation were correct and are adopted in this determination. I have considered further submissions provided after the recommendation. The further submissions do not change the findings that the lender:  provided both loan A and loan B appropriately  was entitled to mak e progress payments to M Company for the complainant‟s benefit and with her knowledge and consent  complied with its financial difficulty obligations  should provide 3 months to the complainants to repay or finance the loans if this decision is accepted. Why is the outcome fair? The events the complainants have described are unfortunate and I understand that they have suffered financial hardship due to reasons beyond their control, namely construction cost overruns and other issues arising due to covid-19 and family law issues. But the lender met Determination | Case number: 697788 Page 3 of 6 its legal obligations, acted in line with good industry practice, and complied with applicable industry codes at all times, including when it provided Loan A and Loan B, managed the progress payments, and later responded to the complainants‟ financial difficulty . So it would not be fair to require the lender to compensate the complainants. However, as Ms K is a personal guarantor I consider it fair that she and S Company, which she solely owns and operates, should have 3 months in which to repay the debt. 1.3 Determination This determination is in favour of the lender. I agree with the reasons for the recommendation and the recommended outcome. Although this determination is in favour of the lender, if the complainants accept this decision within 30 days, then the lender should provide Ms K and S Company with 3 months from the date of acceptance to repay or refinance the debts owed on the terms outlined in section 2.5 of the recommendation. If, after the expiration of the 3-month period from the date of acceptance:  the debt is not repaid to the lender in full, or  an unconditional offer of finance from another financier, on terms that are reasonably acceptable to the lender, is not presented to the lender, with settlement to occur no later than a month after the expiration of the 3-month period, then S Company must voluntarily surrender B Property and any other relevant security to the lender upon request. If the property or properties are not surrendered, the lender is entitled to take recovery action in accordance with the terms and conditions of the loans. If the complainants do not accept this determination within 30 days, then the lender can take recovery action in accordance with the terms and conditions of the loans, once our file is closed. Determination | Case number: 697788 Page 4 of 6 2 Reasons for determination 2.1 Were the findings in the recommendation correct? The findings in the recommendation are correct Based on all the relevant information which I have independently reviewed, I am satisfied that the recommendation contains an accurate summary of the complaint, the issues to be determined, any applicable paragraphs of the rules and any relevant law. Based on my investigation, the findings in the recommendation are correct and are adopted in this determination. I have reviewed all the submissions received in response to the recommendation. For the reasons that follow, I am satisfied that:  The complainants ‟ submissions do not change findings and have not identified any error or breach of obligation by the lender that has caused any loss to the complainants  The submissions do not change the finding that the loans were appropriate for the reasons set out in the recommendation and below  The lender‟s submission highlights that the lending was appropriate, as it further clarified how it calculated and disbursed the funds it lent to S Company. T he complainants’ submissions do not change AFCA’s view The complainants have replied to the recommendation by essentially reiterating their previous submissions to AFCA. They have not provided any new information that would warrant a different finding or that establishes the lender made an error or breached an obligation to them . I am satisfied that AFCA‟s recommendation dated 22 April 2021 fully dealt with the complainants‟ submissions and I adopt the findings made therein. For completeness, I note the following:  One of t he complainants‟ main concern s is that the lender‟s decision to provide Loan A and Loan B was inappropriate because the loan amounts under-estimated the funds necessary to complete the development. In my view, the lender acted reasonably when it agreed to provide $2,035,000 on a „cost to complete basis‟ to cover the complainants‟ construction costs and any unanticipated contingencies. The lender acted based on advice from a quantity surveyor who advised that $1,840,000 was required to complete the development, inclusive of a $80,000 contingency. The fact that the complainants later experienced significant cost over-runs simply does not, in itself, show that the quantity surveyor‟s initial estimate was unreasonable or that the loans were inappropriate. It also does not show that the lender knew or ought to have known that the initial estimate was inaccurate or unreasonable. The lender acted on expert advice which it was entitled to do. It could not have been expected to do anything more at the time. The fact that the quantity surveyor reports and estimates change over time do not affect the finding that the provision of the loans was appropriate.  The complainants have also pointed out that some of the progress payments were made directly to the builder rather than to themselves. For reasons set out at section 2.3 of the recommendation, I accept that the payments occur red with the complainants‟ knowledge and consent, and that they benefited from it as Determination | Case number: 697788 Page 5 of 6 the builder actually undertook the works for which it was paid. Accordingly there is no loss established in this regard.  The complainants have also pointed out that the complaint was lodged on 31 January 2020 rather than 4 February 2021. The complainants are correct, but this does not change the outcome.  The complainants have indicated that the recommendation did not appropriately deal with the lender‟s response to finan cial difficulty issues in 2019 and into 2020 when covid issues affected their business. I confirm that AFCA is not able to review any aspect of this claim prior to the signed Deed of Forbearance. In addition, the complainants have had the benefit of 18 months of further forbearance while their case has been open at AFCA. During this time, the lender has sought to negotiate with the complainants over an extended period and has been prevented taking any action in relation to the expired facilities. That benefit has allowed the complainants to consider their position and explore options for completing the development or resolving the complaint if possible. Such a benefit is adequate recompense for any issues about the lender‟s hardship response that may have arisen before lodgement at AFCA and there is no information to show that the lender‟s r esponse to the complainants has caused any loss that would warrant an award of compensation in this regard. The lender ’ s clarification about Loan A indicates the lending was appropriate The lender has also provided further information to AFCA about how it estimated the amount of funds it deemed necessary to successfully finance the construction project to completion and refinance a loan the complainants owed to ano ther bank (the „existing loan‟) when it first provided Loan A. I note that th e complainants‟ key concerns included that the lender acted imprudently by severely under-estimating the funds necessary to complete the project, which I have addressed above. Se ction 2.1 of AFCA‟s recommendation noted that the letter of offer specifically broke down the amount of money the bank was lending to fund the project and warned the complainants that there would be a funding shortfall of „roughly $75,000‟ for which they w ould be responsible. The recommendation then concluded that the lender understated the estimated shortfall by about $51,500, but that this was not material as the use of the word „roughly‟ in the letter clearly put the complainants on notice that it was up to them to work out what the estimated shortfall might and come up with the remaining money themselves. The lender has now confirmed that the lending shortfall was less than this because the amount of the existing loan was not $665,000 as originally advi sed by the complainants‟ broker in their loan application, but $605,096 – a reduction in the loan amount of $59,904. This in turn reduced the estimated shortfall by that sum – meaning it stood at roughly $66,695. I am satisfied that the lender‟s further su bmission highlights that the letter of offer accurately broke down the estimated funding required to complete the project. 2.2 Why is the outcome fair? The outcome is fair The events the complainant has described are unfortunate and I understand the complainant has suffered financial hardship due to reasons beyond her control. But when it provided Loan Determination | Case number: 697788 Page 6 of 6 A and Loan B, managed the progress payments and responded to the complainants‟ financial difficulty, the financial firm met its legal obligations, acted in line with good industry practice, and complied with applicable industry codes. Therefore, it would not be fair to require it to compensate the complainants. However, as Ms K is a personal guarantor I consider it fair that she and S Company, which she solely owns and operates, should have 3 months in which to repay the debt as set out in section 1.3 above. Recommendation Case number 697788 Financial firm La Trobe Financial Asset Management Limited Recommendation | Case number: 697788 Page 1 of 14 Case number: 697788 22 April 2021 3 Overview 3.1 Complaint In May 2016, the financial firm (the lender) approved a business loan (Loan A) of $2,704,000 to the first complainant (S Company). The funds were provided to refinance a loan in the sum of $669,000, develop six residential units and two shops („the development‟ for $1,850,000 and cover $185,000 in interest repayments for the loan. In April 2018, the lender approved a further business loan (Loan B) of $369,000 to complete construction of the six residential units and two shops. S Company‟s director , Ms K, guaranteed its facilities and is the second complainant. Construction was completed by a separate building entity (M Company). The loan has been fully drawn by way of progress payments made by the lender directly to M Company and the development is incomplete. S Company and Ms K say:  The lender did not provide Loan A appropriately  The lender did not provide Loan B appropriately  Did not act appropriately by making progress payments directly to M Company  The lender did not comply with its financial difficulty obligations  S Company and Ms K are in financial difficulty 3.2 Issues and key findings Did the lender provide Loan A appropriately? The lender provided Loan A appropriately. The lender satisfied itself that S Company had the funds, including borrowed funds, necessary to pay M Company complete the development. Further, the lender investigated S Company‟s financial position and satisfied itself that S Company could service the loan. Did the lender provide Loan B appropriately? The lender provided Loan B appropriately. The lender satisfied itself that S Company had the funds, including borrowed funds, necessary to pay M Company complete the development. Further, the lender investigated S Company‟s financial position and satisfied itself that S Company could service the loan. Did the lender act appropriately by making progress payments directly to M Company? The lender acted appropriately when it made progress payments directly to M Company. The lender was only responsible for making the progress payments in line with the agreed method of authorisation, which it did. The responsibility for managing the development lay with S Company, not the lender. Recommendation | Case number: 697788 Page 2 of 14 Did the lender comply with its financial difficulty obligations? I cannot consider whether the lender complied with its financial difficulty obligations in the past because S Company and Ms K entered into a binding Deed of Forbearance (Deed) with the lender on or about 26 September 2019 concerning its financial difficulty. As a result, under paragraph C.2.1 of its Rules, AFCA will not consider any complaint concerning the lender‟s past financial difficulty response because the forbearance period in the Deed expired on 31 January 2020, noting that the complaint was lodged with AFCA 4 days later on 4 February 2020. Are S Company or Ms K in financial difficulty? I accept that S Company and Ms K are in financial difficulty because both Loan A and Loan B expired over a year ago, and the lender issued notices of demand to each of them in February 2019. As Ms K is a personal guarantor of both Loan A and Loan B and sole director of S Company, the lender should provide Ms K and S Company with 3 months to repay or refinance the debt on the terms set out in section 2.5. 3.3 Recommendation This recommendation is substantially in favour of the lender. If both parties accept the recommendation, the lender should provide Ms K and S Company with 3 months to repay or refinance the debt. Recommendation | Case number: 697788 Page 3 of 14 4 Reasons for recommendation 4.1 Did the lender provide the Loan A appropriately? The lender provided Loan A appropriately S Company says the lender did not provide Loan A appropriately because it significantly underestimated S Company‟s likely development costs. However, I am satisfied that the lender provided Loan A appropriately because:  The lender took reasonable steps to understand what Loan A was for  Loan A was affordable The lender took reasonable steps to understand what Loan A was for S Company says that the lender acted unreasonably by providing Loan A to it based on the estimate provided by M Company, even though its actual construction costs far exceeded that estimate. However, I am satisfied that the lender‟s decision to lend $2,704,000 was based on a diligent and prudent commercial assessment of S Company‟s reasonable construction costs because:  According to the broker‟s memo to the lender dated 3 February 2016, M Company had a record of previously constructing two similar successful developments, both of which were financed by the lender. The lender was entitled to rely upon M Company‟s es timate of what the construction costs would amount to given its previous successful dealings with M Company  The lender obtained a QS report dated 16 March 2016 prior to issuing the letter of offer. The QS confirmed that M Company‟s estimated construction c osts and the proposed contingency were reasonable. The lender was entitled to rely upon the QS report  The lender‟s letter of offer carefully broke down what the lender was and was not funding based on M Company‟s costs estimates, as relayed to it by S Company‟s broker by the broker‟s email to the lender dated 4 May 2016. The below table compares the broker‟s funding requests with the lender‟s funding breakdown. Sum requested Sum approved as per the letter of offer $665,000 to refinance an existing loan with another bank („existing loan‟) $669,000 to refinance the existing loan. Refer to page 12, special condition (g) $1,760,000 (including GST) for construction costs $1,750,000 (including GST) for construction costs. Refer to page 12, special condition (g) $80,000 for construction contingency costs $100,000 for construction contingency costs. While the letter only refers to $90,000, the loan balance of $2,035,000 was advanc ed as a whole on a „cost to complete basis‟. Refer to page 12, special condition (g) Recommendation | Case number: 697788 Page 4 of 14 $50,000 as a developer‟s contribution to Council („infrastructure contribution‟), noting that other planning and development costs had already been approved No provision for the developer‟s infrastructure contribution. $212,000 for capitalised interest $185,000 for capitalised interest. Refer to page 12, special condition (g) $63,500 in loan application fees No provision for loan application fees $2,830,500 in total funding sought $2,704,000 as per the letter of offer  The lender agreed to lend money to construct the building on a „on a „ cost to complete basis, progressively following [Quantity Surveyor] inspections . ‟ In other words, the lender was careful to ensure that the money it lent the borrower was used for the purpose for which it was intended  Special condition (h) of the letter, appearing at page 11, warns S Company that the lender believed they were liable for a shortfall of „roughly $75,000.‟ I accept that this warning put the borrower on notice that it was expected to privately fund any expected shortfall as a condition of accepting the letter of offer. While the warning appears to understate the estimated shortfall by about $51,500, I accept that the „roughly‟ put S Company on notice that it was up to S Company to calculate the shortfall. In these circumstances, I accept that if S Company considered the loan offer to be insufficient, it was up to S Company to reject the offer or renegotiate the loan terms  While the letter of offer made no provision for the developer‟s planning and compliance costs, the broker‟s email of 6 May 2016 says that S Company had already privately funded all costs save for an infrastructure contribution to the local council estimated at $50,000. I accept that it was clear to S Company that it was liable for this cost in the circumstances  The financial firm also obtained a valuation dated 6 October 2016 which indicated that the estimated construction budget appeared reasonable. The valuer says: „ The developers costs estimate provides a construction costs of $1,760,000 GST inclusive. Whilst we are not quantity surveyors, the builders contract price appears to lie within an acceptable cost range for a development of this size.‟  On 5 October 2016, the lender‟s Quantity Surveyor (QS) issued a further report stati ng that: > S Company‟s estimated construction costs of $1,600,000 as set out in the proposed construction contract of October 2015 were reasonable, though it may be an underestimate given the passage of time and changes in market conditions since that date > the likely construction cost was estimated at $1,707,878, to which a 5% contingency of $80,000 should be added or a total of $1,787,878. The QS suggested that construction Recommendation | Case number: 697788 Page 5 of 14 costs be revisited as a result to reflect this increased estimate. I note that this increased estimate broadly reflected the amount actually offered by the lender for construction costs by its letter of offer dated 10 May 2017 Loan A was affordable I am satisfied that Loan A was affordable because:  The lender has provided a serviceability assessment dating to May 2016 explaining how it calculated whether S Company could service Loan A. Based on the May 2016 serviceability assessment, the lender calculated S Company would have a net disposable income of $4,221 per month in May 2016  Because of a delay in settlement which occurred because necessary council and building permits had not yet been obtained, the lender asked for updated financial information in October 2016 prior to settlement. M Company‟s broker provided this information to the lender by email dated 7 October 2016, which attached: > Up-to-date account statements for the pre-existing loan to be refinanced. These evidenced that the complainant had paid down about $40,000 in respect of that loan since the time of her application > A low-doc declaration and statement of income, assets and liabilities, noting that their asset position had substantially improved since May 2016. Specifically: ‒ The broker noted that Ms K‟s loan with Ms K‟s loan with W Bank had increased from $630,000 to $700,000. This loan to W Bank was not being refinanced to the lender, and was secured by mortgage over an unrelated property (B Property). B Property was owned by Ms K and M Company‟s director Mr G, noting that they were then married ‒ Ms K and S Company‟s savings had increased substantially from $120,000 to $500,000 held with another bank (Z Bank)  the lender‟s serviceability assessment was conducted on the basis that payments were interest only, with full repayment of the loan balance to be made after completing the project and selling the development. This strategy was reasonable given the nature of the project  Serviceability is also supported by AFCA‟s independent assessment, which indicates that S Company could service the loan and achieve an annual surplus of $117,759. The key material included income figures supplied to the lender by the complainant‟s accountant. Details of AFCA‟s assessment are in section 3.1 below. 4.2 Did the lender provide Loan B appropriately? The lender provided Loan B appropriately S Company says the lender did not provide Loan B appropriately because it significantly underestimated S Company‟s likely development costs at that point in the development. However, I am satisfied that the lender provided Loan B appropriately because:  Loan B was in the sum of $369,000. Loan funds were carefully broken down to reflect S Company‟s requirements and the lender‟s credit risk appetite, as set out in special Recommendation | Case number: 697788 Page 6 of 14 condition (f), page 11 of the letter of offer dated 4 April 2018. The amounts sought broadly reflected a lending proposal set out by email dated 7 February 2018 from the lender to S Company‟s broker. Specifically: Sum suggested by the lender by email Sum approved as per the letter of offer, page 11 special condition (f) $ 9,880.00 for legal fees and loan set up costs $16,098.50 for legal fees and loan set up costs $ 49,995.00 for prepaid interest on Loan B $50,500 for prepaid interest on Loan B $ 71,330.32 top up for prepaid interest repayments on Loan A $44,568 top up for prepaid interest repayments on Loan A No provision for land tax $3,428 to pay outstanding land tax No provision for loan application fees $16,545 loan application fees $237,794.68 for the construction budget $237,800 for the construction budget  Loan B was proposed by the lender to S Company against the background of a QS report dated 31 January 2018. Significantly, the lender‟s decision to provide $237,800 to S Company reflected the advice it received from the QS to the effect that the project required a larger construction budget of at least another $216,176.98 to complete the development. The lender appears to have added a further contingency of $21623 to the construction budget which is roughly 10% on top of the QS‟ proposed budget  Specifically, the QS recommended to the lender not to release any more money to S Company unless more funds were allocated to the construction budget. In particular, the QS noted that the budgeted cost to complete the development at the time was $242,133.26, but that this „is insufficient to complete the project and, as such, [the QS] cannot recommend payment for this period. We [the QS] recommend a Construction Cost to Complete of approximately $450,000 complete the works (an additional $216,176.98 of funding).‟  The QS has clarified by email to the lender dated 18 December 2020 that they advised of the increase in required funding because M Company‟s director Mr G informed them that: Recommendation | Case number: 697788 Page 7 of 14 „…[he] believed there was not enough money in the budget remaining and estimated he would need $450k to complete the project. As such, we recommended no payment be made and that allowance for this figure as cost to complete was budgeted for. ‟  While interest repayments owing for Loan A fell into arrears on two occasions for three weeks each in March 2018 and April 2018 respectively, both repayments were eventually made before Loan B was approved.  the lender‟s contact notes indicate that between January 2018 to May 2018 S Company was in the process of applying for Loan B. I infer that S Company asked for the loan after it received a copy of the QS report, because it knew it did not have the money to privately complete the project as per the QS‟ recommendation  On 4 April 2018, the lender conducted a serviceability assessment in respect of Loan B. The assessment indicated that S Company would achieve a monthly surplus of $8043.71 if the loan were approved, based on the information available to it at the time  AFCA has conducted a serviceability assessment in respect of Loan B which indicates that Loan B was affordable. According to the assessment, S Company would achieve an annual surplus of $61,671. Details of the assessment are set out at section 3.1 below Cost over-runs were unanticipated I note that cost over-runs appear to have occurred for the following reasons:  According to an email dated 18 December 2020 from the QS, the QS‟ estimated shortfall as set out in their report of 31 January 2018 was prompted by advice from M Company that the project would take another $450,000 to complete. In other words, the builder was expecting cost over-runs as at that date which he had not anticipated earlier in the project  further cost-overruns are likely to be incurred if the project is completed because Ms K separated from Mr G in early 2019 , which is apparent from the lender‟s contact notes . As a result M Company, owned by Mr G, refused to complete the construction project as planned, causing substantial delays and requiring S Company to appoint a new builder to finish the development. These cost over-runs were entirely unanticipated at the time of loan approval. S Company‟s decision to initially appoint M Company as a builder was a commercial risk it chose to take, noting that it had the potential added benefit at the time of reducing project management costs because M Company was not charging project management fees. It was not the lender‟s role to prevent S Company from taking this commercial risk if it wished to do so. 4.3 Did the lender act appropriately by making progress payments directly to M Company? The lender acted appropriately by making progress payments directly to M Company S Company says that the lender acted imprudently and without its authority when it directly paid progress payments to M Company for the construction project instead of releasing the payments to S Company as the developer responsible for the project. However, I accept that the lender acted appropriately because: Recommendation | Case number: 697788 Page 8 of 14  General Condition 10 of the letters of offers for both Loan A and Loan B says that, following settlement “ further advances will be made payable to the Buil der”, that is, M Company, rather than S Company, the borrower  S Company was responsible for the development. Indeed, S Company, M Company and the lender all signed a Financier‟s Development Deed (FDD) which specifically required S Company to acknowledge that S Company was responsible for the development and that the lender was not assuming S Company‟s obligations in providing finance for the project. Key extracts from the Deed are set out at section 3.2 below  The FDD specifically stated that the lender would only pay M Company construction progress payments after it obtained QS reports confirming that construction was proceeding. The lender adopted this process when it released progress payments to M Company. As a result, I am satisfied that S Company benefited from the release of the payments to M Company even if they were unauthorised, because the payments were made to M Company for services that S Company genuinely received and was contractually bound to pay M Company for in any event  The fact that the lender obtained its own QS reports each time does not establish that the lender held out that it was overseeing and was endorsing the construction progress. A lender requiring regular QS reports is a common provision in development finance and is to assist the lender‟s ongoing assessment of its credit risk. Without more, it is not a promise to the developer that it will review each QS r eport with the developer‟s risk in mind  The lender was not a fiduciary to S Company, and did not owe a duty to act in S Company‟s best interests. Further information about AFCA‟s approach to a lender‟s duty to its customer is set out at section 3.3 below  As is apparent from the email correspondence between M Company, S Company and the lender, all payment claims were either prepared or submitted to the lender by S Company‟s accountant Ms S. Attached to these claims were copies of invoices from M Company as w ell as supporting invoices from what appear to be M Company‟s sub - contractors. I infer from these two facts that S Company was well aware that it was asking the lender to make payment to M Company on account of services genuinely rendered by M Company. I i nfer that S Company‟s accountant: > had authority to both sign the claims on S Company‟s behalf and direct the lender to make payment to M Company in so doing > would be able to advise S Company of its financial position and liaise with it about any construction budget shortfall it was experiencing  Ms K also personally signed progress claims dated 10 January 2017, 17 December 2017, 12 April 2018, and 4 June 2018, each of which directed payment to M Company‟s account  The lender sent letters to S Company shortly after it made each progress payment to M Company. The letters confirm the amounts paid and to whom they were paid (M Company). In doing so it put the complainant on notice of the payments. Similarly, S Company had access to loan account statements evidencing that payments were withdrawn from the loan to M Company. The available information does not show the complainant‟s director ever complained to the lender, shortly after those letters were sent, that she did not agree to the payments Recommendation | Case number: 697788 Page 9 of 14 4.4 Did the lender respo nd to S Company and Ms K’s financial difficulty appropriately in the past? AFCA cannot consider the lender’s past financial difficulty response For the following reasons, I accept that:  S Company and Ms K were in financial difficulty on and after 7 February 2019 at the latest  AFCA cannot consider whether the lender responded appropriately to the complainants‟ financial difficulty up to 31 January 2020 because it is the subject of a binding Deed of Forbearance  Even if AFCA could consider this aspect of the complaint, the lender responded appropriately to S Company and Ms K‟s in the past S Company and Ms K were in financial difficulty S Company and Ms K say they experienced financial difficulty because:  S Company could not complete the development as planned owing to construction delays and cost-overruns  Ms K is self-employed and runs an unrelated cosmetics business as director of an unrelated corporate entity (K Company). Since the coronavirus pandemic, K Company has been experiencing further financial difficulty as it was unable to complete international deliveries for some time, leading Ms K to suffer a loss of income I accept that S Company and Ms K were and are in financial difficulty because:  Loan A expired and the loan balance fell due for repayment in full on 17 December 2018, and it has not been repaid to date  Loan B expired and the loan balance fell due for repayment in full on 7 February 2019, and it has not been repaid to date  As a result, the lender issued notices of default to S Company and Ms K in or about 20 February 2019 S Company and Ms K signed a binding Deed of Forbearance AFCA cannot consider S Company and Ms K‟s claim for financial difficulty assistance because S Company and the lender signed counterpart copies of a Deed of Forbearance (Deed) on or about 26 September 2019. I am satisfied that the Deed was entered into in full and final settlement of any claim S Company might have concerning the lender‟s previous financial difficulty response up to and inclusive of 31 January 2020 being the expiry of the forbearance period set out therein because:  According to Recital K of the Deed‟s recitals, the Deed was intended to allow S Company an opportunity to complete and sell the development without the lender taking enforcement action or charging default interest  Under clause 3.1 of the Deed: > S Company was required to provide written reports on the progress of the development upon request Recommendation | Case number: 697788 Page 10 of 14 > S Company was required to ensure that an occupancy permit was issued and construction was completed by 31 January 2020 > Loan A and Loan B both had be repaid in full by 31 January 2020  Under clause 3.2 of the Deed, the lender agreed not to charge default interest or take enforcement action until 31 January 2020, provided S Company complied with the terms of the Deed. If the Deed was complied with the lender would also waive all default interest charged prior to the execution of the Deed  If S Company breached clause 3.1, S Company was obliged under clause 5 of the Deed to give the lender vacant possession of the development  Extracts of Recital K, and clauses 3 and 5 of the Deed appear at section 3.4 below AFCA has a discretion (under clause C.2.1 of our Rules) to not deal with an issue in a complaint, if we consider this to be appropriate. It is appropriate to not deal with any issues that were settled by the parties‟ entry into the deed of forbearance because a settlement represents the parties‟ intent to bring finality to the relevant issues. It is only appropriate to revisit settled issues in extraordinary circumstances. Extraordinary circumstances do not exist because S Company signed the Deed without being unduly influenced by the lender. S Company or its director Mrs S may have felt significant commercial pressure to sign because they owed the lender money, but this is not a reason to revisit the settlement. Even if AFCA could consider S Company and Ms K’s claim, the lender acted fairly Even if AFCA could consider this aspect of S Company and Ms K‟s claim, I consider that the lender acted fairly by offering the forbearance set out in the Deed because:  in respect of Loan A, the lender provided S Company with a period of over a year after it had expired, between 17 December 2018 to 31 January 2020, to repay or refinance the debt without taking enforcement action or charging default interest  in respect of Loan B, the lender provided S Company with a period of almost a year after it had expired, between 7 February 2019 and 31 January 2020, in which to repay or refinance the debt without taking enforcement action or charging default interest. 4.5 Are S Company and Ms K in financial difficulty? S Company and Ms K are in financial difficulty S Company and Ms K say they are in financial difficulty and require more time to complete and sell the development. I accept that S Company and Ms K are in financial difficulty because:  Loan A and B are both expired and unpaid  the lender issued notices of demand to each of S Company and Ms K in February 2019. I also accept that S Company and Ms K should receive 3 months from the date of acceptance of this recommendation in which to refinance or repay the debt owed by S Company Recommendation | Case number: 697788 Page 11 of 14 (including all amounts owing on account of Loan A and B as well as all interest and charges imposed by the lender) in full („the 3 - month period‟). That is because:  Ms K personally guaranteed Loan A and Loan B  Ms K and S Company are closely aligned entities, noting that Ms K is the sole director of S Company. Given the development appears to be unfinished to date, it might be in both parties‟ interests to see it completed and the parties may also use this period to negotiate an alternative agreement should they wish to do so. However, that is entirely a matter for the parties. If, after the expiration of the 3-month period:  the debt is not in repaid to the lender in full, or  an unconditional offer of finance from another financier, on terms that are reasonably acceptable to the lender, is not presented to the lender, with settlement to occur no later than a month after the expiration of the 3-month period, then S Company must voluntarily surrender B Property to the lender upon request. Recommendation | Case number: 697788 Page 12 of 14 5 Supporting information 5.1 AFCA’s serviceability assessment for Loan A and Loan B Details Loan A Loan B Annual income Director net wages Company net profit after tax Proposed rent Total annual income $ 229,618 $36,287 $42,486 $ 308,391 $229,618 $36,287 $42,486 $ 308,391 less annual expenses Loan A Loan B less Total annual expenses $ 190,632 N/A $ 190,632 $190,632 $56,088 $ 246 , 720 Surplus/(deficiency) $117,759 $61,671 Explanation of the figures adopted in the serviceability assessment  Annual income : > As declared in letters from the complainant‟s accountant to the lender dated 27 October 2015 (with respect to Loan A) and 23 March 2018 (with respect to Loan B). > According to a file note by Mr L of the lender dated 11 May 2016, he also spoke with the accountant by phone on 11 May 2016 and confirmed that the information set out in the accountant‟s letter dated 27 October 2015 was still accurate. > Note that separate items were noted in each letter as directors‟ wages (drawn from Ms K‟s unrelated cosmetics bu siness), and net company profits after tax > The proposed rental figure for the development, once completed, was drawn from a valuation report dating to March 2016  New loan repayments for Loan A and Loan B : The loans were approved over short to medium terms as bridging finance. Full repayment was to be effected from the sale of the completed development. Therefore, the loan repayments in the serviceability assessment are calculated on annual interest cost at the contracted interest rates  AFCA notes that Ms K and Mr G jointly owned a property (B Property) which was subject to a mortgage and loan with an unrelated bank at the time of loan approval. They also derived rent from B Property. However, as rent on B Property was not the income of S Company, and AFCA does not have details of the expenses associated with the rent, AFCA did not take account of it in assessing serviceability. Recommendation | Case number: 697788 Page 13 of 14 5.2 Key extracts from Financiers Development Deed (FDD) Clauses 10-11 of the FDD relevantly say: ‟ 10. ACKNOWLEDGEMENTS (a) the parties agree and acknowledge that: (i) The [lender] does not by the Facilities, the Securities this document or otherwise assume any of the obligations of the Developer [S Company] under, pursuant to or in connection with the [building contract]; (ii) … (iii) The [lender] does not by the Facilities, the Securities this document or otherwise assume any obligation to indemnify the Developer, the Architect or the Builder in respect of any liability incurred by either of them under, pursuant to or in connection with the [building contract] (b) … (c) …. (d) the parties acknowledge that no progress payment may be made under the [building contract] unless such progress payment is first approved in writing by a quantity surveyor appointed by the [lender] 11. COVENANTS TO OBSERVE (a) [S Company] covenants with the [lender] to perform and observe all the obligations of the developer under the [building contract] (b) [M Company] covenants with the [lender] to perform and observe all the obligations of the builder under the [building cont ract]‟ I accept that these clauses of the FDD, read together, indicate that:  According to clauses 11(a), 10(a)(i) and (iii) read together, the lender was not responsible or liable for completing the development – only S Company was  According to clauses 11(b) and 10(d) read together, M Company would only get paid if the lender‟s QS recommended it. This was done not because the lender was acting as a developer but rather, in order to protect is security position, noting that other clauses in the FDD enabled the lender to issue a Financier Notice which empowered to effectively take over and complete the development if either S Company or M Company, but only if either M Company or S Company breached the agreement 5.3 Lender not a fiduciary In general, a financial firm that is a bank or credit provider does not have a „fiduciary‟ duty or responsibility to its customer. This means that it is not obliged to advise a customer that a service or product is not in their interests or that there may be other services that would better suit their needs. A fiduciary responsibility arises only where the financial firm‟s role is seen to extend beyond that of finance provider and into the area of advice. This happens if the financial firm provides advice or otherwise causes the customer to reasonably believe that the financial firm has assumed that responsibility. The financial firm is otherwise in a position of lender, not adviser, and it does not have to tell a customer whether a particular product or s ervice is in the customer‟s interests. There can be Recommendation | Case number: 697788 Page 14 of 14 some exceptions to this: for example, if a customer specifically asks a question about a product or service, the financial firm is obliged to provide an accurate and complete response. 5.4 Extracts from Deed of Forbearance Recital K of the Deed says: „K. [S Company]…has requested that [the lender] forbear from enforcement action and charging default interest against [Loan A and Loan B] in order for [S Company] to complete the [development]…so as to sell the l ots on the [development] and repay the Amount Owed.‟ Clauses 3 and 4 of the Deed relevantly say: „3.1 [S Company] must: a) provide [the lender] with a written report in relation to the construction…of the [development] as requested by the [lender] from time to time; b) ensure that the construction…of the [development] is completed by 31 January 2020 and that the following must occur on or before 31 January 2020: i) the building certifications and occupancy permit are obtained by the above specified date ii) [S company] must pay [the lender] the Amount Owed in full. 3.2 Subject to [S company] complying with the terms of this [FDD], the mortgage and the Loan Agreements [for Loan A and Loan B]…[the lender] agrees to forbear from charging penalty or default interest on th e… [loan agreements for Loan A and Loan B]…until 31 January 2020‟ 4.1 [S Company] and [the lender] acknowledge and agree that: d) subject to [S Company] complying with the terms of this [FDD], that all penalty interest accrued during the Forbearance Period for both [Loan A and Loan B] will be irrevocably waived for the Forbearance Period.‟

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.