Home / NAB / Determination 697488

Determination 697488

Delays in construction loan application

FirmNAB
Decided2020-08-20
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$750
Amount claimed—
SourceAFCA PDF

Summary

The complainant said the bank misled her about the construction loan approval and delayed her application. AFCA found the misleading conduct claim not established but found the bank caused delay in several periods, and ordered $750 in non-financial loss compensation.

Misleading conduct requires evidence of a representation and reliance, and the absence of contemporaneous records meant it was not established, while unreasonable delay and poor updates warranted modest non-financial loss compensation.

Issues

Subjects and remedies

pay non financial loss

Related

All NAB determinations · Find similar determinations

Text of the determination

Determination Case number 697488 Financial firm National Australia Bank Limited Determination | Case number: 697488 Page 2 of 6 Case number: 697488 6 August 2020 1 Determination overview 1.1 Complaint The complaint is about the complainant ’s application for a construction loan with the financial firm (bank). In March 2019, the complainant approached the bank to apply for a loan to purchase some land (land loan), with the intention of obtaining a construction loan to build a property on the land later. There is no dispute in relation to the land loan, which settled in or about June 2019. The complainant says:  the bank misled her to believe that: > once the land loan was approved, the construction loan would definitely be approved > she needed to start building the property in order to start the application process for the construction loan, as she needed to provide the bank with building invoices to have the loan approved  the bank delayed the construction loan application by changing bankers and constantly requesting further information, which she had already provided. 1.2 Issues and key findings Did the bank mislead the complainant? No. There is insufficient information to show the bank misled the complainant. As a result, the complainant has not established this claim against the financial firm. Did the bank delay the complainant’s construction loan application? Yes, the bank caused some delay during application process for the construction loan. The bank’s conduct warrants compensation of $750. 1.3 Determination This determination is partially in favour of the complainant. Within 14 days of the complainant’s acceptance of this determination, the bank is to pay the complainant $750 into an account nominated by her. Determination | Case number: 697488 Page 3 of 6 2 Reasons for determination 2.1 Did the bank mislead the complainant? The bank must not engage in misleading conduct The bank must not engage in conduct which is misleading or likely to misled. To establish misleading conduct, a complainant must show:  the bank made a representation or omission that was likely to be misleading  the complainant reasonably acted in reliance on that representation  the complainant has suffered a loss as a result of relying on that representation. When assessing a complaint about misleading conduct, we will consider the available documents, the recollections of the parties, and all relevant circumstances. We give most weight to contemporaneous documentary information. That is, documents that were created at or around the time of the events giving rise to the complaint. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. Where there are conflicting recollections, and these are evenly weighted, we may find that a claim cannot be established. There is no evidence that the bank made a representation that was likely to be misleading On 5 March 2019, the complainant met with a branch manager to obtain information about an Owner Builder Loan and decided to apply for both the land loan and construction loan with the bank. The complainant says at this meeting the branch manager:  instructed her to begin construction in order to start the application process, as she would need to provide the bank with invoices to show the building costs she had incurred  assured her that the construction loan approval would take “a matter of weeks”. The bank’s file notes do not contain any entries for 5 March 2019 and as the bank has confirmed the branch manager is no longer employed by the bank, it was not possible to obtain a statement from her. In support of her claim, the complainant has provided AFCA with a photograph she took during her meeting with the branch manager, which shows the bottom right corner of a bank document with some hand-written calculations they discussed in relation to a construction and land loan. Determination | Case number: 697488 Page 4 of 6 Based on the available information, I am unable to find that complainant was misled by the bank, as:  the only words in the photograph either refer to the calculations or list the five stages of drawdowns for a construction loan  there is no evidence that the branch manager told the complainant to start building before applying for the construction loan or that she needed to do so in order to start the application process  there is no evidence the branch manager told the complainant that the construction loan would definitely be approved, that it would be approved at all or in any timeframe  the calculations in the photograph are not misleading. As there is simply no information available as to what the branch manager said to the complainant on 5 March 2019, the complainant has not established that she was misled by the bank. 2.2 Did the bank delay the complainant’s construction loan application? The complainant says the bank caused an unreasonable delay with her construction loan application by:  only contacting her once a fortnight  requesting documents from her that she had already provided  changing the banker dealing with her application. I have reviewed the information provided to me by the parties. Based on the information provided, I am satisfied that the bank caused some delay during the application process for the construction loan at the following times:  from 13 November 2019, when the complainant provided invoices and payslips and asked who she could contact about her application, until 19 December 2019, when the bank apologised to the complainant as it was aware it had not been a good experience for her. Although her application was not complete, the complainant was not provided with any update during this period, the banker dealing with her application changed twice, and she was just referred to a third banker on 24 December 2019  between 31 December 2019 – 24 January 2020, the complainant received no response from the bank. While I appreciate this was between the New Year’s Eve and Australia Day holidays, the complainant should have received some update or acknowledgment of her emails  between 15 March 2020 – 24 March 2020. On 15 March 2020, the complainant sent the banker some requested documents. On 24 March 2020, the complainant had to re-send the documents as the banker said she had not received them, however the documents were originally sent to the banker’s correct email address Determination | Case number: 697488 Page 5 of 6  between 5 April 2020 – 21 April 2020. On 5 April 2020, the complainant asked the banker to send her the application, so she could check it and send back. On 15 April 2020, the complainant was unable to contact the banker and requested a call back. She did not receive any further contact from that banker and a fourth banker was assigned on 21 April 2020. I consider it appropriate for the bank to pay the complainant compensation of $750 for the stress and inconvenience caused during the periods above. However, I am not satisfied that the bank caused any further delay during the application process, as:  on 31 December 2019, the complainant acknowledged that her loan application would not be straightforward as she had already begun construction  communications between the complainant and the bank were quite regular and not only once every fortnight, expect during the periods of delay above  the bank responded to the complainant’s questions promptly and advised her what documents it needed from her to progress her application  on 24 January 2020, the bank requested a Quantity Surveyor’s ( QS) report. On 6 February 2020, the complainant said she had already provided it, however when she emailed the QS report to the bank on 15 March 2020, the report was dated 13 March 2020. As such, the QS report could not have been provided to the bank any earlier than 13 March 2020  it appears the complainant may have been asked to provide the plans on two occasions and was asked to provide her payslips again as they were too old due to the time she had taken to arrange the QS report. However, overall, I am satisfied the bank did not ask the complainant to provide documents she had already provided  the complainant did not provide all the documents the bank required to order a valuation until approximately 18 May 2020  the application process was complicated as the complainant: > had already started building the property > did not have a Fixed Price Building Contract, which made it more difficult for the bank to assess the value of the proposed security. Determination | Case number: 697488 Page 6 of 6 3 Supporting information 3.1 The determination is made under the AFCA Rules This complaint has been determined based on what is fair in all the circumstances, having regard to factors such as legal principles, good industry practice, codes of practice and previous decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All material provided has been reviewed and considered.