Home / NAB / Determination 697488
Determination 697488
Delays in construction loan application
Summary
The complainant said the bank misled her about the construction loan approval and delayed her application. AFCA found the misleading conduct claim not established but found the bank caused delay in several periods, and ordered $750 in non-financial loss compensation.
Misleading conduct requires evidence of a representation and reliance, and the absence of contemporaneous records meant it was not established, while unreasonable delay and poor updates warranted modest non-financial loss compensation.
Issues
- Delay primary · upheld“The bank caused some delay during the construction loan application at several periods, warranting compensation of $750.”
- Misleading conduct secondary · not upheld“There is no evidence the branch manager said the construction loan would definitely be approved or that building was needed to start the application.”
Subjects and remedies
pay non financial loss
Related
Text of the determination
Determination
Case number 697488
Financial firm National Australia Bank Limited
Determination | Case number: 697488 Page 2 of 6
Case number: 697488 6 August 2020
1 Determination overview
1.1 Complaint
The complaint is about the complainant ’s application for a construction loan with the
financial firm (bank).
In March 2019, the complainant approached the bank to apply for a loan to purchase
some land (land loan), with the intention of obtaining a construction loan to build a
property on the land later. There is no dispute in relation to the land loan, which
settled in or about June 2019.
The complainant says:
the bank misled her to believe that:
> once the land loan was approved, the construction loan would definitely be
approved
> she needed to start building the property in order to start the application process
for the construction loan, as she needed to provide the bank with building
invoices to have the loan approved
the bank delayed the construction loan application by changing bankers and
constantly requesting further information, which she had already provided.
1.2 Issues and key findings
Did the bank mislead the complainant?
No. There is insufficient information to show the bank misled the complainant. As a
result, the complainant has not established this claim against the financial firm.
Did the bank delay the complainant’s construction loan application?
Yes, the bank caused some delay during application process for the construction
loan. The bank’s conduct warrants compensation of $750.
1.3 Determination
This determination is partially in favour of the complainant.
Within 14 days of the complainant’s acceptance of this determination, the bank is to
pay the complainant $750 into an account nominated by her.
Determination | Case number: 697488 Page 3 of 6
2 Reasons for determination
2.1 Did the bank mislead the complainant?
The bank must not engage in misleading conduct
The bank must not engage in conduct which is misleading or likely to misled. To
establish misleading conduct, a complainant must show:
the bank made a representation or omission that was likely to be misleading
the complainant reasonably acted in reliance on that representation
the complainant has suffered a loss as a result of relying on that representation.
When assessing a complaint about misleading conduct, we will consider the available
documents, the recollections of the parties, and all relevant circumstances. We give
most weight to contemporaneous documentary information. That is, documents that
were created at or around the time of the events giving rise to the complaint.
If there is no relevant documentation, we will decide what is most likely to have
occurred based on the information provided to us. Where there are conflicting
recollections, and these are evenly weighted, we may find that a claim cannot be
established.
There is no evidence that the bank made a representation that was likely to be
misleading
On 5 March 2019, the complainant met with a branch manager to obtain information
about an Owner Builder Loan and decided to apply for both the land loan and
construction loan with the bank.
The complainant says at this meeting the branch manager:
instructed her to begin construction in order to start the application process, as she
would need to provide the bank with invoices to show the building costs she had
incurred
assured her that the construction loan approval would take “a matter of weeks”.
The bank’s file notes do not contain any entries for 5 March 2019 and as the bank has
confirmed the branch manager is no longer employed by the bank, it was not possible
to obtain a statement from her.
In support of her claim, the complainant has provided AFCA with a photograph she
took during her meeting with the branch manager, which shows the bottom right
corner of a bank document with some hand-written calculations they discussed in
relation to a construction and land loan.
Determination | Case number: 697488 Page 4 of 6
Based on the available information, I am unable to find that complainant was misled
by the bank, as:
the only words in the photograph either refer to the calculations or list the five
stages of drawdowns for a construction loan
there is no evidence that the branch manager told the complainant to start building
before applying for the construction loan or that she needed to do so in order to
start the application process
there is no evidence the branch manager told the complainant that the construction
loan would definitely be approved, that it would be approved at all or in any
timeframe
the calculations in the photograph are not misleading.
As there is simply no information available as to what the branch manager said to the
complainant on 5 March 2019, the complainant has not established that she was
misled by the bank.
2.2 Did the bank delay the complainant’s construction loan application?
The complainant says the bank caused an unreasonable delay with her construction
loan application by:
only contacting her once a fortnight
requesting documents from her that she had already provided
changing the banker dealing with her application.
I have reviewed the information provided to me by the parties. Based on the
information provided, I am satisfied that the bank caused some delay during the
application process for the construction loan at the following times:
from 13 November 2019, when the complainant provided invoices and payslips
and asked who she could contact about her application, until 19 December 2019,
when the bank apologised to the complainant as it was aware it had not been a
good experience for her. Although her application was not complete, the
complainant was not provided with any update during this period, the banker
dealing with her application changed twice, and she was just referred to a third
banker on 24 December 2019
between 31 December 2019 – 24 January 2020, the complainant received no
response from the bank. While I appreciate this was between the New Year’s Eve
and Australia Day holidays, the complainant should have received some update or
acknowledgment of her emails
between 15 March 2020 – 24 March 2020. On 15 March 2020, the complainant
sent the banker some requested documents. On 24 March 2020, the complainant
had to re-send the documents as the banker said she had not received them,
however the documents were originally sent to the banker’s correct email address
Determination | Case number: 697488 Page 5 of 6
between 5 April 2020 – 21 April 2020. On 5 April 2020, the complainant asked the
banker to send her the application, so she could check it and send back. On 15
April 2020, the complainant was unable to contact the banker and requested a call
back. She did not receive any further contact from that banker and a fourth banker
was assigned on 21 April 2020.
I consider it appropriate for the bank to pay the complainant compensation of $750 for
the stress and inconvenience caused during the periods above.
However, I am not satisfied that the bank caused any further delay during the
application process, as:
on 31 December 2019, the complainant acknowledged that her loan application
would not be straightforward as she had already begun construction
communications between the complainant and the bank were quite regular and not
only once every fortnight, expect during the periods of delay above
the bank responded to the complainant’s questions promptly and advised her what
documents it needed from her to progress her application
on 24 January 2020, the bank requested a Quantity Surveyor’s ( QS) report. On 6
February 2020, the complainant said she had already provided it, however when
she emailed the QS report to the bank on 15 March 2020, the report was dated 13
March 2020. As such, the QS report could not have been provided to the bank any
earlier than 13 March 2020
it appears the complainant may have been asked to provide the plans on two
occasions and was asked to provide her payslips again as they were too old due to
the time she had taken to arrange the QS report. However, overall, I am satisfied
the bank did not ask the complainant to provide documents she had already
provided
the complainant did not provide all the documents the bank required to order a
valuation until approximately 18 May 2020
the application process was complicated as the complainant:
> had already started building the property
> did not have a Fixed Price Building Contract, which made it more difficult for the
bank to assess the value of the proposed security.
Determination | Case number: 697488 Page 6 of 6
3 Supporting information
3.1 The determination is made under the AFCA Rules
This complaint has been determined based on what is fair in all the circumstances,
having regard to factors such as legal principles, good industry practice, codes of
practice and previous decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All material provided has been reviewed and considered.