Determination 697391
Cash settlement amount for storm damage to home and accommodation costs, and claim handling delays
Summary
Following a storm flood, the insurer offered a cash settlement of $115,787.23 and the complainant sought $160,000 and was unhappy with the claim handling. AFCA ordered $130,000 for house repairs, $12,200 for accommodation and storage, and $2,500 non-financial loss.
A cash settlement must reflect the real cost of repairs including contingencies and transferred risk, and the insurer's poor claim handling warranted modest non-financial loss compensation.
Issues
- Claim amount dispute primary · upheld“The insurer is required to increase its settlement and pay the complainant $130,000 for the damage sustained to her property as a result of the storm event.”
- Claim denial secondary · upheld“The insurer incorrectly declined the claim initially where it was evident the property had been flooded and had suffered some degree of damage.”
- Poor claim handling secondary · upheld“The available evidence shows the insurer has handled the claim poorly and caused unreasonable delays.”
- Delay secondary · upheld“The complainant has been significantly upset and inconvenienced by the protracted delays and uncertainties surrounding her claim.”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial loss
Related
Text of the determination
Determination
Case number 697391
Financial firm Insurance Australia Limited
Determination | Case number: 697391 Page 2 of 8
Case number: 697391 13 October 2020
1 Determination overview
1.1 Complaint
The complainant made a claim in December 2016 under her home and contents
insurance policy held with the financial firm (insurer), for damage to her property
following a storm event.th
The insurer has now accepted the claim; however the parties are in dispute regarding
the extent of the damage and cost of repairs. The insurer has offered to settle the
claim for $115,787.23 to cover repairs and temporary accommodation and storage
costs.
The complainant is seeking $160,000. She is also unhappy with the insurer’s handling
of the claim.
1.2 Issues and key findings
Is the insurer’s cash settlement offer fair in the circumstances?
The insurer is required to increase its settlement and pay the complainant $130,000
for the damage sustained to her property as a result of the storm event. The quote on
which the insurer’s offer is based has not been shown to be actionable by the
complainant and does not factor in all the likely repair costs, including catering for
unforeseen damage and the transfer of risk. The insurer is also liable for $12,200 for
temporary accommodation and storage costs.
Is the complainant entitled to compensation for non-financial loss?
The available evidence shows the insurer has handled the claim poorly and caused
unreasonable delays. The complainant has experienced a significant degree of upset
and inconvenience as a result. In the circumstances, she is entitled to $2,500
compensation for non-financial loss.
1.3 Determination
This determination is in favour of the complainant. The insurer is required to pay the
complainant:
$130,000 for the house repairs
$12,200 for temporary accommodation and storage
$2,500 compensation for non-financial loss.
It is not required to take any further action.
Determination | Case number: 697391 Page 3 of 8
2 Reasons for determination
There has been a full exchange of material between the parties, and each party has
had the opportunity to address the issues arising from that.
This determination follows consideration of all the information exchanged and is
based on what is fair in all the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice including codes of practice and
previous AFCA decisions where applicable.
2.1 Is the insurer’s cash settlement offer fair in the circumstances?
Extent of insurer’s liability is in dispute and cash settlement is appropriate
The parties are in disagreement about the extent of the storm damage sustained to
the property. The insurer has estimated its liability under the policy at:
$107,283.95 for the building repairs
$3,703.28 for the storage costs
$4,800 for the temporary accommodation.
The complainant says this figure is inadequate to repair the damage sustained to the
property. The complainant is seeking $160,000.
The insurer’s plumber (SL) concluded the flooding of the property during the storm
event was an odd incident and would not occur under normal conditions. The
exchanged evidence shows the parties engaged a number of experts. It is not in
dispute the damage has been progressive and evolving in nature. This is evident
through the constantly changing scope of works provided throughout the life of the
claim since 2016.
There has also now been a breakdown in communication between parties, and the
complainant says she has lost trust in the insurer and its representatives.
The insurer says it is willing to undertake repairs to the property and has been
prepared to do so since December 2017. However, the relationship between the
parties has deteriorated to the point where co-operation is difficult. I consider it is
appropriate in the circumstances that the claim be cash settled.
Tendered expert reports show extensive and ongoing claim-related damage
The complainant’s engineer (NH) says in his initial July 2017 report, that while there
was impact on the house contents, the flood water caused extensive damage to the
building, primarily as the result of the saturation of the soil beneath it.
In assessing the extent of the damage, NH notes:
cracking of internal masonry walls and separation of cornices
Determination | Case number: 697391 Page 4 of 8
cracking of external solid fencing, although some of that cracking is just render
crazing and would have been present before the flood event
moisture damage to the external rendering immediately in contact with the flood
waters (building perimeter)
moisture-affected floor boards (significant cupping)
dislocation of unit paving surrounding the garage and front of the house
cracking in the wall behind the garage, where the cracking is clearly more than
render crazing and has occurred recently in response to the disturbance of the soil
caused by inundation.
NH says the effect of the inundation on the soil profile is primarily saturation of the
sand layers with some consolidation and loss of bearing capacity, together with the
water not being able to seep away as it is trapped by the underlying clay soil.
NH asserts the ensuing damage is a result of foundation movement in response to
the saturation of the sand and would be very rapid; however the dissipation of the
water through the soil would be very slow, which is why there was still some retained
dampness when inspected.
I note NH compiled an initial scope of works in 2017 and the complainant ’s
representative obtained a quote from builder PRT for $32,224.50, based on that
scope. However, the complainant did not believe that quote would cover all repair
costs.
Given the on-going progression of the damage over time (the house was still
experiencing movement in January 2018, and the eastern side of the house was
getting worse), NH provided a more detailed scope in March 2018. The evidence
shows there had been a rising damp issue in the property due to the insured event,
and that was identified by NH in March 2018 where he reported that the soil was still
damp. NH did also say, however, that he believed given the time that has passed
since the storm event, that any resulting movement would have ceased.
The insurer has undertaken different onsite assessments by different experts. The
exchanged information shows the property has sustained some damage which is not
related to the subject storm event. Amongst other things, that includes:
pergola roof sheets: lifting due to incorrect fixings and timber shrinkage
cracking to garden walls: the cracking to the capping is a material movement issue
and not related to ground movement
undulation to roof plane: this damage has been evident since 2019 as shown in the
Google images.
The complainant has provided a number of photographs of the property where she
says the damage has deteriorated more, with further movement and cracking.
Determination | Case number: 697391 Page 5 of 8
I accept that given the nature and mechanism of damage, it is reasonable to conclude
the property has sustained further damage since the insured event and may continue
to do so until the underlying issues are thoroughly addressed. This is reflected in the
cumulative nature of the tendered scopes of work.
I nsurer’s January 2020 scope of works is a reasonable starting point
The insurer has provided a 17 January 2020 scope of works by builder BB, totalling
$107,283.95 for the resultant damage, and says it is willing to undertake the repairs to
the property based on that scope.
The complainant says this scope of works is inadequate to deal with the necessary
repairs. However, I note the complainant has not provided any evidence to justify her
requested figure of $160,000.
At some point the complainant suggested that, due to the extent of the damage, the
house requires total rebuilding. However, again, she has not provided any expert
evidence to substantiate that the house is not repairable. All the expert reports,
including the complainant’s engineer , conclude the property is repairable, but that it is
a question of cost.
Having carefully considered the parties ’ evidence and arguments, I accept the
insurer’s costed scope of works dated 17 January 2020 is a reasonable starting point
for determining a fair and reasonable cash settlement for the outstanding repairs. This
is the most comprehensive and relatively recent scope of works.
No evidence underpinning is required
The complainant has provided a separate quote (dated 7 April 2020) totalling
$12,670, from underpinning specialist SAU. It provides for two underpinning concrete
pads (one along the front footings and one outside the kitchen where the wall is
cracked); trenches and concrete/steel reinforcement; reinstating 3 paths; repairing the
bedroom 1 damp wall. SAU indicates the work would take seven days to complete.
SAU’s quote does not include various other cornice cracks or skirting repairs, or t he
roof sagging. SAU recommends the complainant obtains input from a structural
engineer on those issues.
Underpinning is not included in BB’s quote, NH’s scope of works or any of the
previous scopes.
I am not satisfied the complainant has established underpinning is strictly necessary
as part of the repairs required to be undertaken to address the event-related damage.
At the same time, however, I appreciate that the water inundation which led to the
claim did affect the integrity/stability of the soil be neath the building, and resulted in
foundation movement.
Determination | Case number: 697391 Page 6 of 8
Insurer must ensure the cash settlement is fair and appropriate
The insurer’s policy states the insurer can decide whether it will repair damage to the
building, or pay an insured the reasonable cost to repair or rebuild the property.
When the insurer repairs the building, it guarantees the quality of materials and
workmanship for the lifetime of the building. If a defect arises in the lifetime of the
building because of poor quality workmanship o r incorrect materials used by the
insurer, then the insurer is obliged to rectify the problem.
If, instead of the insurer undertaking the claim-related repairs, a cash settlement is to
be made, that cash settlement must reflect, as far as possible, the costs the
complainant will incur to repair the damage.
It must also be recognised that in having the claim cash settled, the complainant loses
the benefit of the insurer’s lifetime guarantee on repairs. The cash settlement
transfers from the insurer to the complainant all the risk of any unforeseen damage
and any additional work required once repairs commence.
T he insurer’s scope of works and attached quote from BB has not been shown to be
actionable by the complainant as a retail customer, and I am not satisfied it
reasonably caters for contingencies and the transfer of risk. It is fair in the
circumstances that the cash settlement amount be increased to allow for:
any volume discounts reflected in the insurer’s quote
project management/supervision costs
unforeseen damage that may only be discovered once repairs commence
the additional risk assumed by the complainant in undertaking the repairs herself
the passage of time, including any likely increase in costs, since the insurer ’s quote
was issued (given that a quote usually only has 30 day validity).
Insurer is required to increase its cash settlement to $130,000
Having carefully reviewed BB’s costed scope of works, I also note it does not factor
in:
engineering input
council approvals
replacement or repair to brickwork throughout the dwelling
repairing or replacement to any part of the subfloor or timber floor joists.
I also note that further assessment is required to inspect footings once the floors are
removed. I accept it is difficult to precisely establish the extent of the damage until
repairs commence.
For the reasons above, I consider it is fair in the particular circumstances that the
insurer increases its cash settlement to $130,000.
Determination | Case number: 697391 Page 7 of 8
Insurer is required to pay $12,200 towards accommodation and storage
The policy provides cover for the costs of temporary accommodation, including
storage, if a listed event causes loss or damage to the property and it cannot be lived
in during repairs.
The complainant is claiming $35,000 in accommodation for 12 to 18 months. The
complainant is basing this figure on the required period to rebuild her property. As
outlined above there is no evidence to establish the property needs a full rebuild.
I note BB has estimated the repairs to take between 10 to 12 weeks for the repairs.
There are no quotes to substantiate the $4,800 temporary accommodation offered by
the insurer (which was meant to cover an 8 week period of repairs). It is also unclear
how the insurer reached the $3,703.28 for the storage.
It is also worth noting that not all repairs will require the complainant to move out of
the home, so while the total repair work might take up to 12 weeks, that does not
necessarily mean she would need to be in alternative accommodation for that entire
period. However, in the circumstances and given the uncertainty about what other
work might need to be done once repairs start, I consider it fair that the insurer pay for
12 weeks of temporary accommodation, which (based on its own weekly estimate)
would be $7,200, together with $5,000 for storage. That is a total of $12,200.
2.2 Is the complainant entitled to compensation for non-financial loss?
The complainant is dissatisfied with the insurer’s handling of the claim
The complainant is dissatisfied with the insurer’s claims handling and says the insurer
has unreasonably delayed the claim.
AFCA may award compensation for non-financial loss where a complainant has
suffered an unusual degree or extent of physical inconvenience, time taken to resolve
the situation or interference with the complainant ’s expectation of enjoyment or peace
of mind.
However, AFCA adopts a conservative approach to the award of compensation, and
expects complainants to be moderately robust and bear the usual inconvenience
associated with an insurance claim.
The complainant is entitled to $2,500 compensation for the poor claim handling
The available evidence shows the insurer:
engaged a number of different builders, plumbers and engineers to assess the
cause and extent of the damage
considered the complain ant’s engineer’ s findings and reimbursed her for the cost
of their report
Determination | Case number: 697391 Page 8 of 8
continued to accommodate the complainant’s requests , including changing the
builder at her request
eventually accepted the claim and was ready to proceed with repairs back in
December 2017.
I accept that given the nature and extent of the damage, it was difficult to conclude a
final scope of works prior to the commencement of the repairs. It is reasonable to
expect that the scope of works would change and evolve over time due to several
factors, such as further damage being identified. It is clear the damage did not
manifest straight after the storm event. It took the rising damp and movement damage
over a year to become evident.
At the same time, however, the insurer’s assessor has acknowledged the claim was
handled ‘very poorly from the start’; he noted the insurer had failed to review all
relevant information and had reached ‘poor decisions’.
The complainant continuously raised concerns about the competence of the experts
involved, including her own. While she continued to express her dissatisfaction, I note
she has not provided any compelling evidence to advance her position or substantiate
her arguments and concerns.
In saying that, I note the insurer incorrectly declined the claim initially where it was
evident the property had been flooded and had suffered some degree of damage. The
insurer accepted the claim for the contents in the garage and incorrectly denied the
claim for the dwelling where it was evident through AJ ’s as sessment that the water
had reached the property.
The insurer’s early compiled scope of works missed damage identified by NH. As
well, the exchanged information shows despite the large loss, the claim was closed at
one point without any action.
It is clear the complainant has been significantly upset and inconvenienced by the
protracted delays and uncertainties surrounding her claim and the damage. It is also
understandable that she will have lost confidence in the insurer’s handling of the
matter. In the circumstances, it is fair the insurer pays the complainant $2,500 as a
compensation for non-financial loss.