Home / IAG / Determination 697391

Determination 697391

Cash settlement amount for storm damage to home and accommodation costs, and claim handling delays

FirmIAG
Decided2020-10-26
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$142,200
Non-financial loss$2,500
Amount claimed$160,000
SourceAFCA PDF

Summary

Following a storm flood, the insurer offered a cash settlement of $115,787.23 and the complainant sought $160,000 and was unhappy with the claim handling. AFCA ordered $130,000 for house repairs, $12,200 for accommodation and storage, and $2,500 non-financial loss.

A cash settlement must reflect the real cost of repairs including contingencies and transferred risk, and the insurer's poor claim handling warranted modest non-financial loss compensation.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 697391 Financial firm Insurance Australia Limited Determination | Case number: 697391 Page 2 of 8 Case number: 697391 13 October 2020 1 Determination overview 1.1 Complaint The complainant made a claim in December 2016 under her home and contents insurance policy held with the financial firm (insurer), for damage to her property following a storm event.th The insurer has now accepted the claim; however the parties are in dispute regarding the extent of the damage and cost of repairs. The insurer has offered to settle the claim for $115,787.23 to cover repairs and temporary accommodation and storage costs. The complainant is seeking $160,000. She is also unhappy with the insurer’s handling of the claim. 1.2 Issues and key findings Is the insurer’s cash settlement offer fair in the circumstances? The insurer is required to increase its settlement and pay the complainant $130,000 for the damage sustained to her property as a result of the storm event. The quote on which the insurer’s offer is based has not been shown to be actionable by the complainant and does not factor in all the likely repair costs, including catering for unforeseen damage and the transfer of risk. The insurer is also liable for $12,200 for temporary accommodation and storage costs. Is the complainant entitled to compensation for non-financial loss? The available evidence shows the insurer has handled the claim poorly and caused unreasonable delays. The complainant has experienced a significant degree of upset and inconvenience as a result. In the circumstances, she is entitled to $2,500 compensation for non-financial loss. 1.3 Determination This determination is in favour of the complainant. The insurer is required to pay the complainant:  $130,000 for the house repairs  $12,200 for temporary accommodation and storage  $2,500 compensation for non-financial loss. It is not required to take any further action. Determination | Case number: 697391 Page 3 of 8 2 Reasons for determination There has been a full exchange of material between the parties, and each party has had the opportunity to address the issues arising from that. This determination follows consideration of all the information exchanged and is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and previous AFCA decisions where applicable. 2.1 Is the insurer’s cash settlement offer fair in the circumstances? Extent of insurer’s liability is in dispute and cash settlement is appropriate The parties are in disagreement about the extent of the storm damage sustained to the property. The insurer has estimated its liability under the policy at:  $107,283.95 for the building repairs  $3,703.28 for the storage costs  $4,800 for the temporary accommodation. The complainant says this figure is inadequate to repair the damage sustained to the property. The complainant is seeking $160,000. The insurer’s plumber (SL) concluded the flooding of the property during the storm event was an odd incident and would not occur under normal conditions. The exchanged evidence shows the parties engaged a number of experts. It is not in dispute the damage has been progressive and evolving in nature. This is evident through the constantly changing scope of works provided throughout the life of the claim since 2016. There has also now been a breakdown in communication between parties, and the complainant says she has lost trust in the insurer and its representatives. The insurer says it is willing to undertake repairs to the property and has been prepared to do so since December 2017. However, the relationship between the parties has deteriorated to the point where co-operation is difficult. I consider it is appropriate in the circumstances that the claim be cash settled. Tendered expert reports show extensive and ongoing claim-related damage The complainant’s engineer (NH) says in his initial July 2017 report, that while there was impact on the house contents, the flood water caused extensive damage to the building, primarily as the result of the saturation of the soil beneath it. In assessing the extent of the damage, NH notes:  cracking of internal masonry walls and separation of cornices Determination | Case number: 697391 Page 4 of 8  cracking of external solid fencing, although some of that cracking is just render crazing and would have been present before the flood event  moisture damage to the external rendering immediately in contact with the flood waters (building perimeter)  moisture-affected floor boards (significant cupping)  dislocation of unit paving surrounding the garage and front of the house  cracking in the wall behind the garage, where the cracking is clearly more than render crazing and has occurred recently in response to the disturbance of the soil caused by inundation. NH says the effect of the inundation on the soil profile is primarily saturation of the sand layers with some consolidation and loss of bearing capacity, together with the water not being able to seep away as it is trapped by the underlying clay soil. NH asserts the ensuing damage is a result of foundation movement in response to the saturation of the sand and would be very rapid; however the dissipation of the water through the soil would be very slow, which is why there was still some retained dampness when inspected. I note NH compiled an initial scope of works in 2017 and the complainant ’s representative obtained a quote from builder PRT for $32,224.50, based on that scope. However, the complainant did not believe that quote would cover all repair costs. Given the on-going progression of the damage over time (the house was still experiencing movement in January 2018, and the eastern side of the house was getting worse), NH provided a more detailed scope in March 2018. The evidence shows there had been a rising damp issue in the property due to the insured event, and that was identified by NH in March 2018 where he reported that the soil was still damp. NH did also say, however, that he believed given the time that has passed since the storm event, that any resulting movement would have ceased. The insurer has undertaken different onsite assessments by different experts. The exchanged information shows the property has sustained some damage which is not related to the subject storm event. Amongst other things, that includes:  pergola roof sheets: lifting due to incorrect fixings and timber shrinkage  cracking to garden walls: the cracking to the capping is a material movement issue and not related to ground movement  undulation to roof plane: this damage has been evident since 2019 as shown in the Google images. The complainant has provided a number of photographs of the property where she says the damage has deteriorated more, with further movement and cracking. Determination | Case number: 697391 Page 5 of 8 I accept that given the nature and mechanism of damage, it is reasonable to conclude the property has sustained further damage since the insured event and may continue to do so until the underlying issues are thoroughly addressed. This is reflected in the cumulative nature of the tendered scopes of work. I nsurer’s January 2020 scope of works is a reasonable starting point The insurer has provided a 17 January 2020 scope of works by builder BB, totalling $107,283.95 for the resultant damage, and says it is willing to undertake the repairs to the property based on that scope. The complainant says this scope of works is inadequate to deal with the necessary repairs. However, I note the complainant has not provided any evidence to justify her requested figure of $160,000. At some point the complainant suggested that, due to the extent of the damage, the house requires total rebuilding. However, again, she has not provided any expert evidence to substantiate that the house is not repairable. All the expert reports, including the complainant’s engineer , conclude the property is repairable, but that it is a question of cost. Having carefully considered the parties ’ evidence and arguments, I accept the insurer’s costed scope of works dated 17 January 2020 is a reasonable starting point for determining a fair and reasonable cash settlement for the outstanding repairs. This is the most comprehensive and relatively recent scope of works. No evidence underpinning is required The complainant has provided a separate quote (dated 7 April 2020) totalling $12,670, from underpinning specialist SAU. It provides for two underpinning concrete pads (one along the front footings and one outside the kitchen where the wall is cracked); trenches and concrete/steel reinforcement; reinstating 3 paths; repairing the bedroom 1 damp wall. SAU indicates the work would take seven days to complete. SAU’s quote does not include various other cornice cracks or skirting repairs, or t he roof sagging. SAU recommends the complainant obtains input from a structural engineer on those issues. Underpinning is not included in BB’s quote, NH’s scope of works or any of the previous scopes. I am not satisfied the complainant has established underpinning is strictly necessary as part of the repairs required to be undertaken to address the event-related damage. At the same time, however, I appreciate that the water inundation which led to the claim did affect the integrity/stability of the soil be neath the building, and resulted in foundation movement. Determination | Case number: 697391 Page 6 of 8 Insurer must ensure the cash settlement is fair and appropriate The insurer’s policy states the insurer can decide whether it will repair damage to the building, or pay an insured the reasonable cost to repair or rebuild the property. When the insurer repairs the building, it guarantees the quality of materials and workmanship for the lifetime of the building. If a defect arises in the lifetime of the building because of poor quality workmanship o r incorrect materials used by the insurer, then the insurer is obliged to rectify the problem. If, instead of the insurer undertaking the claim-related repairs, a cash settlement is to be made, that cash settlement must reflect, as far as possible, the costs the complainant will incur to repair the damage. It must also be recognised that in having the claim cash settled, the complainant loses the benefit of the insurer’s lifetime guarantee on repairs. The cash settlement transfers from the insurer to the complainant all the risk of any unforeseen damage and any additional work required once repairs commence. T he insurer’s scope of works and attached quote from BB has not been shown to be actionable by the complainant as a retail customer, and I am not satisfied it reasonably caters for contingencies and the transfer of risk. It is fair in the circumstances that the cash settlement amount be increased to allow for:  any volume discounts reflected in the insurer’s quote  project management/supervision costs  unforeseen damage that may only be discovered once repairs commence  the additional risk assumed by the complainant in undertaking the repairs herself  the passage of time, including any likely increase in costs, since the insurer ’s quote was issued (given that a quote usually only has 30 day validity). Insurer is required to increase its cash settlement to $130,000 Having carefully reviewed BB’s costed scope of works, I also note it does not factor in:  engineering input  council approvals  replacement or repair to brickwork throughout the dwelling  repairing or replacement to any part of the subfloor or timber floor joists. I also note that further assessment is required to inspect footings once the floors are removed. I accept it is difficult to precisely establish the extent of the damage until repairs commence. For the reasons above, I consider it is fair in the particular circumstances that the insurer increases its cash settlement to $130,000. Determination | Case number: 697391 Page 7 of 8 Insurer is required to pay $12,200 towards accommodation and storage The policy provides cover for the costs of temporary accommodation, including storage, if a listed event causes loss or damage to the property and it cannot be lived in during repairs. The complainant is claiming $35,000 in accommodation for 12 to 18 months. The complainant is basing this figure on the required period to rebuild her property. As outlined above there is no evidence to establish the property needs a full rebuild. I note BB has estimated the repairs to take between 10 to 12 weeks for the repairs. There are no quotes to substantiate the $4,800 temporary accommodation offered by the insurer (which was meant to cover an 8 week period of repairs). It is also unclear how the insurer reached the $3,703.28 for the storage. It is also worth noting that not all repairs will require the complainant to move out of the home, so while the total repair work might take up to 12 weeks, that does not necessarily mean she would need to be in alternative accommodation for that entire period. However, in the circumstances and given the uncertainty about what other work might need to be done once repairs start, I consider it fair that the insurer pay for 12 weeks of temporary accommodation, which (based on its own weekly estimate) would be $7,200, together with $5,000 for storage. That is a total of $12,200. 2.2 Is the complainant entitled to compensation for non-financial loss? The complainant is dissatisfied with the insurer’s handling of the claim The complainant is dissatisfied with the insurer’s claims handling and says the insurer has unreasonably delayed the claim. AFCA may award compensation for non-financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the complainant ’s expectation of enjoyment or peace of mind. However, AFCA adopts a conservative approach to the award of compensation, and expects complainants to be moderately robust and bear the usual inconvenience associated with an insurance claim. The complainant is entitled to $2,500 compensation for the poor claim handling The available evidence shows the insurer:  engaged a number of different builders, plumbers and engineers to assess the cause and extent of the damage  considered the complain ant’s engineer’ s findings and reimbursed her for the cost of their report Determination | Case number: 697391 Page 8 of 8  continued to accommodate the complainant’s requests , including changing the builder at her request  eventually accepted the claim and was ready to proceed with repairs back in December 2017. I accept that given the nature and extent of the damage, it was difficult to conclude a final scope of works prior to the commencement of the repairs. It is reasonable to expect that the scope of works would change and evolve over time due to several factors, such as further damage being identified. It is clear the damage did not manifest straight after the storm event. It took the rising damp and movement damage over a year to become evident. At the same time, however, the insurer’s assessor has acknowledged the claim was handled ‘very poorly from the start’; he noted the insurer had failed to review all relevant information and had reached ‘poor decisions’. The complainant continuously raised concerns about the competence of the experts involved, including her own. While she continued to express her dissatisfaction, I note she has not provided any compelling evidence to advance her position or substantiate her arguments and concerns. In saying that, I note the insurer incorrectly declined the claim initially where it was evident the property had been flooded and had suffered some degree of damage. The insurer accepted the claim for the contents in the garage and incorrectly denied the claim for the dwelling where it was evident through AJ ’s as sessment that the water had reached the property. The insurer’s early compiled scope of works missed damage identified by NH. As well, the exchanged information shows despite the large loss, the claim was closed at one point without any action. It is clear the complainant has been significantly upset and inconvenienced by the protracted delays and uncertainties surrounding her claim and the damage. It is also understandable that she will have lost confidence in the insurer’s handling of the matter. In the circumstances, it is fair the insurer pays the complainant $2,500 as a compensation for non-financial loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.