Home / Endeavour Securities (Australia) Limited (In Liquidation) / Determination 696103

Determination 696103

Refusal to process redemption request during minimum term and fund illiquidity

FirmEndeavour Securities (Australia) Limited (In Liquidation)
Decided2020-04-08
ProductInvestments · Managed investment
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Trustees of an SMSF invested $20,000 in a commercial property fund and later sought redemption. The firm refused because the 12-month minimum term had not lapsed and the fund was illiquid. AFCA found the firm acted in line with the PDS and the determination is in favour of the firm.

The redemption obligation under the PDS was conditional on the minimum investment period and fund liquidity, both of which were unmet and disclosed.

Issues

Subjects and remedies

smsfno remedy

Related

All Endeavour Securities (Australia) Limited (In Liquidation) determinations · Find similar determinations

Text of the determination

Determination Case number 696103 Financial firm Endeavour Securities (Australia) Limited (In Liquidation) Determination | Case number: 696103 Page 2 of 6 Case number: 696103 8 April 2020 1 Determination overview 1.1 Complaint The complaint is about a $20,000 investment in a managed commercial property income fund (fund). The Product Disclosure Statement (PDS) identifies the financial firm as the Responsible Entity and the issuer of the units for the fund. The PDS also states the financial firm appointed a corporate authorised representative as the investment manager of the fund. The complainants say:  they submitted an online enquiry in relation to the fund  Mr H, a director of the corporate authorised representative, responded to their enquiry  Mr H promised the complainants a guaranteed return of 12% per annum to be paid monthly  Mr H further promised the complainants an additional 2% per annum for the first 12 months, to be paid monthly  they received a one-off payment of $2,838.36 in May 2019 but have not received any further returns on his investment  they requested a withdrawal of the investment in January 2019  the withdrawal request has not been processed and they have received no further payments. 1.2 Issues and key findings Should the financial firm comply with the complainants’ withdrawal request? The PDS states the financial firm’s obligation to process the complainants’ redemption request arises after the 12-month minimum investment period has lapsed. It is also dependent on the liquidity of the fund’s assets. As the fund is currently facing liquidity issues, the financial firm is not obligated to process the complainants’ redemption request. 1.3 Determination This determination is in favour of the financial firm. No compensation is payable to the complainant. Determination | Case number: 696103 Page 3 of 6 2 Reasons for determination 2.1 Should the financial firm honour the complainants’ redemption request? The complainants entered into a contract with the financial firm On 24 June 2018, the complainants completed and signed an application to invest $20,000 in the fund on behalf of their self-managed superannuation fund (SMSF). As part of the initial application process, the complainants acknowledged they had received a copy of the Product Disclosure Statement (PDS) dated 7 May 2018 and agreed to be bound to the terms of the PDS. This investment was subject to the 7 May 2018 PDS. The complainants lodged a redemption request In their submissions, the complainants state they decided not to continue wit h the investment in January 2019 due to the financial firm failing to pay them the agreed monthly distribution rate. They advised the financial firm of their decision and were provided with a redemption request form. The complainants requested a withdrawal of their funds on 22 January 2019 by lodging the completed redemption request form with supporting documentation. The financial firm confirmed it received the redemption request on 27 February 2019. The complainants say they were advised the deposit and the interest owed would be paid within seven days. The complainants say the financial firm has not complied with their request. There was a 12-month minimum investment period that applied to the fund The PDS specified there was a minimum investment term of 12 months from the date of initial application before a redemption request could be made. The minimum investment period was restated in the financial firm’s email to the complainants dated 2 May 2019. It stated the financial firm was not required to proces s the complainants’ withdrawal request as it was made before the 12-month minimum investment period had lapsed. The email further states the complainants’ redemption request would be actioned at the end of the 12-month minimum investment period. Section 2.2 of the PDS provides the processing of withdrawal requests after the minimum investment period is also dependent on whether or not the fund is liquid. Overall, I am satisfied the financial firm’s obligation to process the complainants’ redemption request could only arise after 25 June 2019. This satisfied the minimum investment period specified in the PDS and was subject to the liquidity of the fund’s assets. Determination | Case number: 696103 Page 4 of 6 The complainants were aware the fund was not liquid Section 601KA of the Corporations Act 2001 (Corporations Act) provides that a registered scheme is considered liquid if liquid assets account for at least 80% of the value of the scheme ’s property. Liquid assets include cash, bank bills and market securities. The Corporations Act also says property can be classified as a liquid asset if the Responsible Entity reasonably expects that the property can be realised for its market value within the period specified in the f und’s constitution for satisfying withdrawal requests while the scheme is liquid. Section 2.2 of the PDS highlights that the fund is not liquid as defined in the Corporations Act and as such may affect the financial firm’s ability to action withdrawal requests submitted by investors. In addition, section 4 of the PDS notes the fund may be susceptible to liquidity risks. It states: Under abnormal or difficult market conditions, some normal liquid assets may become illiquid, restricting our ability to sell them and to make withdrawal payments for Investors without a potentially significant delay. Having considered the PDS, I am satisfied the complainants should have been reasonably aware that the fund was not liquid, and this may affect the processing of their redemption request. The complainants were notified of the temporary suspension Contemporaneous emails provided by the complainants show that from September 2018 to March 2020, the corporate authorised representative regularly informed the complainants the fund was temporarily suspended due to liquidity issues. These emails also outline the financial firm’s efforts to raise the capital required to lift the temporary suspension and process the withdrawal requests. Based on the evidence available to me, I am satisfied the financial firm provided the complainants with regular updates in relation to the investments and projects being undertaken to address the fund’s liquidity issues. The correspondence provided also suggests there will be funds available for redemption after the required capital has been raised by the financial firm. The financial firm is not required to comply with the redemption request The complainants allege the financial firm’s failure to comply with the redemption request is a breach of the financial firm’s obligation to the complainants. Determination | Case number: 696103 Page 5 of 6 I have reviewed the terms outlined in section 2.2 of the PDS and the contemporaneous emails sent by the financial firm, I am satisfied the financial firm’s obligation to action the redemption requests was dependent on the lapsing of the minimum investment period and the fund’s liquidity. As the fund is facing liquidity issues, I am persuaded the financial firm has acted in line with the PDS and is not required to comply with the complainants’ redemption request. Determination | Case number: 696103 Page 6 of 6 3 Supporting information 3.1 Process The Australian Financial Complaints Authority (AFCA) has decided this complain based on what it considers is fair in all the circumstances, having regard to:  the relevant law  good industry practice  previous decisions of the Financial Ombudsman Service (FOS) and AFCA. AFCA is satisfied that the material it has relied on in making this decision has been exchanged with the parties. 3.2 The complaint has been expedited AFCA was notified the financial firm was in liquidation on 2 October 2019. Taking this into considera tion it is AFCA’s position that it would be in the interest of all parties involved to have this matter resolved in a timely manner. Hence, this complaint was expedited to the final (decision) stage of the AFCA process.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.