Cyclone storm damage claim: scope of rectification works, delays, mould and compensation
Text of the determination
Determination
Case number 694823
Financial firm Westpac Ge neral Insurance Limited
Determination | Case number: 694823 Page 2 of 15
Case number: 694823 30 October 2020
1 Determination overview
1.1 Complaint
The complainants’ home sustained damage from Cyclone Debbie on 28 March 2017.
They lodged a claim with the financial firm (the insurer) on 10 April 2017. The insurer
accepted the claim and appointed a panel builder to rectify the damage.
The comp lainants say that the insurer’s first builder failed to complete the repairs
properly, and that the insurer’s rectification was inadequate. There have been mould
issues at the property. The complainants say that the insurer’s delay s in dealing with
the claim has resulted in further loss.
The complainants seek $500,000 to remedy the defective and outstanding works.
This is based on their builder (CR)’s second quote of $503,061.14 for a ‘totally re
done’ property, and the $500,000 maximum amount that represen ts the AFCA
compensation amount limit per claim.
The complainants also seek to be compensated for emergency accommodation, non-
financial loss and refund of expert fees.
1.2 Issues and key findings
What is the insurer’s liability regarding the outstanding property damage?
The panel considers that the insurer is responsible for the following:
Replacing the roof battens.
Remediating the impact marks on the lower roof sheets .
Re-attaching the clip to re-secure the gutter.
Replacing the particleboard to the whole upper floor, including the main bathroom
and WC (ensuring it extends below the bottom plate of the external wall) and
associated timber framing.
Remedying the sagging lintel and localised floor deflection over this area, along
with repairing the jamming door.
Project management fees of $10,000, if the matter is cash settled.
Expert reports.
The complainants are to obtain a quote for the repairs set out above. If the insurer
disputes the quote, it is to provide an actionable quote from a builder who ca n
commence within eight weeks of acceptance of the quote. Alternatively, the
complainants may choose to request a cash settlement of the insurer’s quote.
The insurer does not have any further liability for mould associated repairs.
Determination | Case number: 694823 Page 3 of 15
Is the insurer liable for temporary accommodation?
It is fair that the insurer maintains the offer of $6,000 towards temporary
accommodation.
Is the insurer obliged to pay compensation for non-financial loss?
The complainants have provided information to show they suffered undue stress, as a
result of the insurer’s processing of this claim. The insurer should the refore pay the
complainants $1,000 in compensation for non-financial loss.
1.3 Determination
This determination is substantially in favour of the complainants.
The insurer is to cash settle the complainants (subject to the process for a disputed
quote) for the cost of:
Replacing the roof battens.
Remediating the impact marks on the lower roof sheets .
Re-attaching the clip to re-secure the gutter.
Replacing the particleboard to the whole upper floor, including the main bathroom
and WC (ensuring it extends below the bottom plate of the external wall).
Remedying the sagging lintel and localised floor deflection over this area, along
with repairing the jamming door.
The insurer is to pay a 10% uplift on these costs, if the matter is cash settled.
The insurer is to also pay the complainants the following costs:
Project management fees ($10,000), if the matter is cash settled.
Pay the costs of the expert reports obtained by the complainants plus interest,
pursuant to section 57 of the Insurance Contracts Act 1984 (the Act). Interest is
payable from the date the complainant paid the invoice until the date payment is
made by the insurer. The complainants are to provide the invoices and proof of
payment, if they have not already done so.
Temporary accommodation costs ($6,000).
$1,000 in compensation for non-financial loss, on account of the excess stress
suffered by the complainants during the insurer’s processing of this claim.
Determination | Case number: 694823 Page 4 of 15
2 Reasons for determination
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
This decision has been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in the insurance industry and another
representative with extensive experience in consumer claims.
The decision follows consideration of all the material exchanged. It is based on what
is fair in all the circumstances having regard to the relevant legal principles, terms of
the policy, good industry practice including codes of practice and previous decisions
where applicable.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome.
2.1 What is the insurer’s liability regarding the outstanding property
damage?
1. Roof framing
The complainants say that they want confirmation from a structural engineer that the
roof framing members, connections and tie downs are compliant and functioning
correctly (as per the original scope of works (SOW) and report provided by the
complainants’ consultant (MB) ).
The insurer’s consultant (LC) advised that the contractor (TB) undertaking the works
confirmed that an engineer was engaged and had certified that the roof framing was
completete and adequate.
LC says the complainant did not provide any evidence to show that the roof had been
inadequately installed.
LC also noted the SOW provides for replacement of roof battens only and there was
no requirement to replace the roof rafters or trusses. He says the roof rafters and
trusses (i.e. roof framing members) were not damaged in the event and the insurer is
not responsible therefore to replace them to bring them up to current code.
The complainants’ builder (CR) advised the insurer, in an email dated 8 February
2019:
I've been in contact with my roofer and he will address the problem with the roof.
He agrees its probably a leak but doesn't think its much of a problem just
something small.
Determination | Case number: 694823 Page 5 of 15
On the information provided, on balance, the Panel is of the view that the insurer is
only responsible for replacement of the roof battens.
The cost of the roof battens has not been addressed in either the first CR quote
(dated 14 February 2019) or the TB quote (undated). CR included the item battens in
his second quote, although this was not individually quoted.
2. Impact marks on front roof sheets
CR noticed impact marks on the front roof sheets when completing his initial
inspection. The panel notes the property has a southern side elevation.
LC said he did not observe any damage to the roof sheeting consistent with impact
damage during the site inspection, and says no photographs were provided by the
complainants’ engineer ( GW).
However, GW also noticed impact marks. In its first report (dated 28 February 2019),
GW noted that the lower roof on the southern side of the residence, outside the upper
bedroom, showed signs of impact damage, which it noted was believed to have
occurred during removal of the damaged internal linings of the upper level.
The Panel is satisfied on the information provided that the impact marks to the roof
sheeting were likely to have occurred during the removal of the damaged internal
linings by the insurer’s builder.
3. Deformation of roof gutter
The complainant identified deformation of a roof gutter to the east side of the building.
LC said the complainant was concerned this was caused by a tree impact and was
not rectified by the contractor during repairs.
LC advised the SOW did not document replacement of the roof gutters to the upper
level of the building. He said an inspection confirmed that localised deformation of the
roof gutter occurred due to detachment of a gutter clip restraining the gutter.
LC noted this may have occurred due to inadequate reinstatement during repair
works, and that rectification required re-attachment of the clip to resecure the gutter;
replacement was not required.
The insurer is responsible for re-attaching the clip to re-secure the gutter. It is not
liable to pay for the replacement of the gutter.
4. Particleboard flooring was not replaced under bottom plate of external wall
The complainant seeks that the particleboard flooring is removed and replaced to the
entire upper floor.
LC initially said that in his investigations, he did not detect any evidence that the
particleboard flooring was not installed beneath the bottom plates.
Determination | Case number: 694823 Page 6 of 15
GW provided photos after his second inspection to show that the flooring does not
extend beneath the external bottom plate in some areas. GW noted in his report that
replacement of the particleboard flooring had not appeared to have been carried out
in numerous areas.
The insurer later acknowledged the gap upon the photos, however said it could not
determine whether the issue was widespread.
MB’s scope of works provided for the replacement of particleboard flooring to the
entire upper level, excluding the WC and bathroom.
CR included the last two areas in his quote, as he noted there was a risk that the
waterproof membrane and tiles could be damaged in these areas when replacing the
flooring underneath the external bottom plate.
On the information provided, the Panel is satisfied that the particleboard flooring has
not been correctly installed and that it is possible the waterproof membrane could be
damaged in the WC and bathroom.
The particleboard flooring to the entire upper level, including the main bathroom and
WC, is to be replaced.
5. Timber decay due to termite infestation
The MB report advised that termites had been present and most of the upstairs
frames were exposed, however visual inspection was not present to the downstairs
areas of the dwelling. It noted that the scope of works may need to be amended once
the specialist termite inspection report was complete.
LC said that:
the decay of the timber framing observed after the cyclone event was unrelated to
the one-off water ingress occurring during the cyclone
the reports evidence termite damage to the timber framing elements. He said these
reports indicated that the building has a termite issue, which is unrelated to the
cyclone
the damage to the timber framing was possibly due to termite infestation
damage to the timber framing could be a widespread issue that was as yet
unidentified, and due to termite infestation
this issue (amongst others) predated the cyclone event.
The insurer provided a termite treatment certificate after completion of treatment
works.
Conversely, GW said that the water ingress event and delay in remediation created
an environment conducive to termite infestation.
Determination | Case number: 694823 Page 7 of 15
There is insufficient evidence to show that termites caused the damage to the timber
framing before the cyclone.
The Panel therefore considers the insurer is liable for these repairs as part of the cost
of replacing the particleboard flooring .
6. Sagging lintel in family room and localised floor deflection
GW said that the sagging of the lintel in the family room may have occurred from
water ingress during the cyclone and failure to allow adequate drying.
Floor level survey results found that there was localised deflection in the flooring to
this area.
LC noted in its report:
Maximum floor differential of 20mm and 14mm recorded across lower and upper
levels of ground floor respectively.
Minor floor surface variations detected to ground floor – consistent with minor
differential footing movement or construction tolerances (in construction of the slab
or installation of floor coverings).
LC advised there was a maximum floor differential of 40mm recorded across
second floor of building.
A pattern of localised fall was detected to north side of second floor. ( This was
centred at the dividing wall between bedroom 2 and 3 , over the deflecting lintel of
the family room beneath.)
LC said that the sagging of the lintel was not caused by the cyclone event or water
ingress to the building. He noted that timber required prolonged periods of elevated
moisture content to undergo decay (up to 3 months without sustaining structural
damage), compromising the structural integrity of the timber. He advised that any
residual moisture after the event will dry with atmospheric exposure.
LC’s view was that the sagging was caused by the ina dequate size of the lintel
resulting in deflection, and/or termite damage to the lintel.
The insurer noted that saturation of the carpets was only estimated to increase load
by at most 0.1 to 0.2 KPa, which it said was well within the design limits of the lintel. It
refers to LC’s argument that the cause of the deflection was either due to inadequate
design and under sizing of the lintel causing deflection under load, or the decay of the
lintel due to termite damage or long-term moisture ingress through the balcony.
The insurer has not provided further evidence to support these possible causes.
In contrast to this view, the evidence shows that there was both elevated moisture
content and prolonged periods of moisture content:
Determination | Case number: 694823 Page 8 of 15
There was significant floor moisture content on the second floor (up to 210 and 230
in the second floor ensuite floor, and readings of 94 in the floor of the main
bathroom upstairs).
The complainants say that the insurer delayed removing soggy carpets upstairs for
months after the cyclone.
There was no potential for the flooring to be exposed to atmospheric exposure for
months after the event, given the delays with removing the soggy carpet.
Genera of mould were detected that are known to be associated with wood rot.
Fungal hyphae were detected with high levels in some samples. The presence of
fungal hyphae is indicative of recent active mould growth.
Notably, although the claim was lodged on 10 April 2017, the claim notes provided by
the insurer only begin on 2 November 2018, some seven months after the claim was
lodged.
The complainants had advised that the property was not properly remediated for
many months after Cyclone Debbie, with saturated carpets in place for an extended
period.
The complainants also noted that the contents settlement was made on October
2018, more than 18 months after the cyclone. They say that such was the extent of
the mould infestation, that all contents items were written off and paid out by the
insurer. This is further evidence that there were extensive delays with the claim
processing, and that mould contributed to the damage (as a result of the delays).
Conclusion – sagging lintel
Given this information, the mould report findings (discussed in more depth below),
and in the absence of claim notes surroundi ng the claim process and actions at the
beginning of the claim, the Panel considers that the damage to the lintel and the floor
levels was caused by the insurer’s delays in removing the soggy carpet upstairs and
drying the area, after Cyclone Debbie.
The insurer is responsible for the repairs to the lintel.
7. Jamming of door
LC advised that investigations confirmed that the jamming of the door was occurring
due to the deflection of the lintel.
The Panel is satisfied that the door should be rectified by the i nsurer and should be
included in the quote for the lintel repairs.
8. Mould
The complainants are concerned about mo uld growth within the property.
Determination | Case number: 694823 Page 9 of 15
Prior to remediation works
Prior to remediation works, ML (for ADE) found that:
The mould concentration in the outside air sample was elevated.
There were genera of mould detected in the indoor air samples that were not
detected in the outside air sample.
General of mould were detected that are known to be associated with wood rot.
Fungal hyphae were detected with high levels in some samples, and that the
presence of fungal hyphae is indicative of recent active mould growth and therefore
constitutes a potential health hazard.
Genera of mould were detected which include species that have been shown to be
either immune-compromising, allergenic and/or mycotoxin producers.
Post remediation works
Post remediation works, LC advised that:
He did not identify any mould growth during his inspection.
Moisture content testing of skirtings, walls and flooring was undertaken throughout
the house.
Moisture content testing indicated no anomalous elevation in moisture elevation to
the plaster walls or skirting boards, that would indicate water ingress from defective
roofing was contributing to mould growth.
Site investigations did not indicate any evidence of moisture staining to the walls or
ceiling, consistent with water ingress of the roof structure.
Roof cavity inspections did not identify any evidence of water ingress through the
roof, or moist ceiling insulation.
The species of timber used for the skirtings in the lounge room differed from the
skirtings used throughout the rest of the house.
Any ongoing mould growth was not due to water ingress of the building envelope
from defective repair works.
LC concluded that, in his opinion, there was no evidence of ongoing mould growth to
the building.
However, the complainants advised that LC did not climb into the roof space to
inspect the cavity. Further, moist insulation batts were found in the cavity above the
second floor and later removed by the insurer.
The complainants provided a report by B (an environmental assessment company). B
found that there was a significant airborne total mould count in the sample taken in
the upstairs hallway. This was consistent with a water damaged building and
consequent mould/fungal growth, and some insect activity. B said it was above that
Determination | Case number: 694823 Page 10 of 15
found in the normal outdoor air, and thus was more consistent with there having been
a significant water and mould event.
B’s view was that it was hi ghly likely that both the high natural humidity and the
significant water ingress event (Tropical Cyclone Debbie) may have wet building
materials in the upstairs sections, causing higher humidity in the roof space and
possible direct wetting of the roof-side insulation, leading to mould and insect growth
in the roof space.
B said there were signs the house sections were not repaired quite right, and that
there was likely to be some residual mould and other contaminating dusts (including
insect particles likely a consequence of water ingress some time ago).
B thought that the cause of the mould was incomplete physical removal methods and
physical containment of mould prior to repair works.
The insurer noted that B’s report says that that the property was in a high humidity
environment, which is expected given its location. The report noted that the high
humidity environment will produce high organism counts.
Although the panel notes the complainants ’ points regarding LC, the complainants
have not provided evidence to show that there is a roof leak that is causing continued
water ingress, which in turn is continuing to cause mould. The onus is on the
complainants to establish this
The panel notes that the onus is on the complainant to establish that the roof is
allowing water ingress, which in turn is causing more mould. The complainants have
not provided adequate evidence to satisfy this burden. The panel notes that the
property is in a humid environment and that this would be contributing to the mould.
In the circumstances, the Panel considers that the insurer is not required to do
anything further in relation to the mould claim.
Other issues
9. Earthquake (later submission)
The complainant advised in April 2020 that there was a 4.5 earthquake in the region,
and that some effects were felt at the property.
The complainant says he enlisted a builder to check the property, who demonstrated
that there was a dip in the corner. He could not confirm whether or not any damage
had been enhanced due to the earthquake but did not discount it.
The complainant wanted to highlight the occurrence in case the floors/walls gave way
due to structural damage.
Determination | Case number: 694823 Page 11 of 15
The insurer responded that LC had confirmed that the building had more than
adequate lateral stability provisions, to resist any earthquake loading.
The panel considers that the complainant has not provided adequate evidence to
establish that an earthquake caused any relevant damage to his property.
10. Project management fees
The insurer originally offered to pay an additional $10,000 for the costs of contracting
a project manager to oversee the works. This was based on works totalling
$74,143.18 in their original offer (or approximately 7.4% of the cost of these
remediation works).
The panel notes that it is difficult to provide a n estimate for project management
costs, given that some outstanding items still need to have quotes obtained.
In the circumstances, the panel considers the insurer is to uphold its original offer
regarding project managements costs and pay the complainants $10,000 for project
management fees.
11. Complainants’ expert report fees
The panel considers that the complainants ’ expert reports and advice have assisted it
in the investigation of this matter. These reports include those by MB, GW, CR and Dr
WB (from B).
The Panel considers that it is fair that the insurer should pay up to a maximum of
$5,000 for each expert report obtained by the complainants.
The insurer is pay interest on these sums under section 57 of the Act.
Interest is payable from the date the complainants paid the invoice, up until the date
of payment. The complainants are to provide to the insurer the invoices and proof of
payment.
12. Builder CR’s full scope of works and quote
The complainants’ builder expert CR noted his seco nd quote (undated; provided by
CR to the insurer on 9 July 2019) was based on the ‘worst possible case’, as
instructed by the insurer. Additionally, he advised that this further quote did not
include things for which he was waiting on an engineering opinio n and specifications;
for example, the sagging lintel.
During the complaint, AFCA requested that the complainants advise why they did not
agree with the insurer’s scopes of work and highlight what sections they believed
were insufficient. In response, the complainant s’ representative stated:
9. We refer AFCA to the report, commentary and scope supplied by [CR] and the report
and subsequent response supplied by [GW], as well as the report supplied by [Dr WB of B]
Determination | Case number: 694823 Page 12 of 15
which outline between them the full extent of the current issues [emphasis added] at
the property. We note in particular that there are suggestions from the inspections by
[CR] and [GW] that [TB] did not complete the scope as required by the [MB] scope of
works.
The Panel considers that the complaina nts and their representative have not provided
adequate information to support why CR’s full scope of works and quote should be
implemented. Indeed, the response notes that the complainants’ experts’ reports
outline between them the full extent of the current issues at the property, and it does
not account for the additional items included in CR’s second quote.
The complainants have not established that these items are either covered under the
policy or are the result of defective rectification works by the insurer’s panel builders.
13. Complainant says insurer’s engineer is not qualified and registered in QLD
The complaint said that the insurer’s engineer (LC) was not as qualified as its own
experts and that he is not a registered professional engineer in Qld.
The insurer noted that LC is able to assess and provide professional engineering
services in Qld. The insurer noted that LC was not required to have the registration
the complainants were referring to, as he was not certifying a job in Qld. The Board of
Professional Engineers Qld (BPEQ) had reportedly confirmed this was correct.
14. Settlement of the claim
Due to the effluxion of time, conflicting quotes and the breakdown of the relationship
between the parties, the Panel is of the view the most appropriate settle ment would
be by cash payment, if possible.
To achieve this outcome, the complainant is to obtain a quote for the works as set out
in this determination.
If the insurer disputes the quote, they are to obtain an actionable quote from a builder
who can commence the repairs within 8 weeks. The complainants may accept that
the works are carried out by the insurer’s builder. Alternatively, they may request that
the insurer cash settle the claim for that quoted amount.
The Panel considers that it is fair that any cash settlement should have an uplift of
10% to cover contingencies.
2.2 Is the insurer liable for temporary accommodation?
Insurer liable to pay for additional temporary accommodation, based on its
previous offer
The insurer had offered to place the complainants in an apartment during the repairs.
Determination | Case number: 694823 Page 13 of 15
However, the complainants moved back to their property, as the complainant’s
occupational therapist had advised that a home was more suitable (as compared to,
for example, a smaller apartment) for him to undertake his physical exercises, in
relation to his injuries.
The panel considers that the insurer is not liable for temporary accommodation, given
the complainants’ choice to return to their home. However , the insurer previously
made an offer of $6,000 for 3 weeks of temporary accommodation. The panel
considers it fair that the insurer upholds this offer.
The insurer is to pay the complainants $6,000 for temporary accommodation.
2.3 Is the insurer obliged to pay compensation for non-financial loss?
Complainants suffered excessive stress during claim processing
The delays have also caused the complainants significant stress and inconvenience.
The complainants noted that numerous people from the insurer and its
representatives attended at different inspections, and were in contact to try and
resolve the matter.
The panel considers the inconvenience to the complainants, although also
acknowledges the insurer’s view that it made efforts to try and bring the matte r to a
resolution.
The insurer says its claims team responded to the complainants’ requests in a timely
manner, actioned concerns immediately and made the required payments as soon as
possible.
While the panel notes this is a complicated matter and the ins urer was entitled to
spend time on obtaining expert reports and clarification, the matter has spanned
nearly three years, and caused significant stress and inconvenience to the
complainants.
The complainants have suffered various health issues, which they attribute in part to
the delays of the insurer.
Considering the claim processing, the length of time taken to resolve the complaint
overall, and the stress and health effects on the complainants, the panel considers
the insurer is to pay $1,000 in compensation for non-financial loss.
Determination | Case number: 694823 Page 14 of 15
3 Supporting information
3.1 Key references
Policy documents
Document Provi sion
Policy schedule
Amendment dat e:
11 October 2016
Type of policy
Home and Contents Insurance
Quality Care
…
Period of insurance
Effective date 11 Oct 2016
Expiry date 4pm on 16 Aug 2017
…
Cover
Sum insured
Buildings $350,000
…
Contents
General contents $115,900
Specified contents nil
Total contents $115,900
…
Personal Valuables
Specified nil
Unspecified $5,000 per claim
(max $1,000 per item)
…
Benefits included in your policy
Determination | Case number: 694823 Page 15 of 15
Document Provi sion
Comprehensive cover for sto rm, ✓
flood, fire, theft and more
…
You can upgrade your covera ge
Accidental loss and damage Not included
Product
Disclosure
Statement (PDS)
11 August 2015
Page 12
General exclusions.
Of course, insurance can’t cover absolutely everything. Here are the general
exclusions that apply to all cover described in this
PDS, other than:
…
Your po licy does not cover any loss or damage that is caused by or arises from:
…
Animals.
• vermin, insec ts or pests,
Page 29 Home and Contents Cover: Building additional benefits
Emer ge ncy accommodation
If your home is unliveable, we will cover the cost of similar alternativ e
accommodation for you and any other insureds.
This expense will onl y be paid if you actually incur costs for em ergency
accommodation, and only while your home remains unliveable.
Quality Care
✓
Up to 10% of the sum insured
or
the cost of accommodation for up to 12 months from the date of the event,
whichever is less