Determination 693198

Insurer declined render damage claim as workmanship, wear and rust

FirmQBE
Decided2020-07-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$22,000
SourceAFCA PDF

Summary

The complainant, represented by lawyers, claimed $22,000 for render damage he attributed to storms on 21 November 2019, one day after the policy started. AFCA found the damage was caused by poor workmanship, rust and gradual deterioration, which are excluded, so the insurer could decline the claim.

The complainant must first establish loss within an insured event, and the expert evidence showed the render damage was excluded workmanship, corrosion and wear.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 693198 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 693198 Page 2 of 7 Case number: 693198 10 July 2020 1 Determination overview 1.1 Complaint The complainant holds a home insurance policy which is underwritten by the financial firm (insurer). On 22 November 2019, the complainant lodged a claim under the policy for damage to the render of the insured property which he says was caused by strong winds and storms. The insurer has declined the claim and says the proximate cause of the damage falls within the policy exclusions. 1.2 Issues and key findings Is the insurer entitled to decline the claim? The evidence provided does not establish that the complainant‟s property sustained damage caused by an insured event under the policy. Even if the damage was caused by storms or winds, the material provided establishes that the cause of damage to the render was poor workmanship, in combination with rust, wear and tear and gradual deterioration. As these causes of damage are excluded from cover, the insurer is entitled to decline the claim. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to decline the claim. Determination | Case number: 693198 Page 3 of 7 2 Reasons for determination 2.1 Is the insurer entitled to decline the claim? Complainant has onus to establish a valid claim It is established insurance law that the complainant carries the initial onus to show that the terms and conditions of the relevant insurance policy cover the loss. This is known as a valid claim. Once the complainant establishes a valid claim, the onus then shifts to the insurer to demonstrate the loss is not covered, either by way of one o f the policy exclusions or on some other basis. Policy covers insured events The complainant‟s home policy commenced at 4.00pm on 21 November 2019 providing cover for buildings. It is understood that the complainant attended a branch of the insurer between 3.30pm and 4.00pm on 21 November 2019 to take out cover. The complainant lodged the claim on 22 November 2019. The complainant‟s policy is a n „ insured events‟ policy. This means that not all loss and damage is automatically covered. Rather, only loss or damage caused by one or more of the listed events and subject to the exclusions, is covered. One of the insured events is loss or damage as a result of storm, rainwater, flood or wind. Accordingly, the onus is on the complainant to establish that the buildings suffered loss or damage as a result of an insured event under the policy. Complainant says render damage due to strong winds and storms In the complaint lodgement form to AFCA, the complainant states: Our issue is we bought the house not knowing what was done properly (to Australian standard) and what wasn‟t done properly. Our render has come off after strong winds and thunderstorm on the day we lodged the claim, I strongly believe that it is unfair for this not to be repaired at insurance cost because it was not our fault that this happened. I believe it was the builders fault for not following the right procedures, all though the builders warranty has expired (house being 10 years old). If something else was to happen to the house that we had no intentions off, how are we meant to know if it was done properly before an accident happens. We brought in a qualified renderer (A Rendering) and in his professional opinion he stated that “the right product wasn‟t used to stick on top of the foam & mesh from the beginning, that is what caused the cracks, bubbling and for the render to peel off. [sic] Determination | Case number: 693198 Page 4 of 7 No report from A Rendering has been provided, only a quotation which lists the repairs required and states “these repairs need to be done due to storm damag e on the property which has damaged the previous render work. ” The complainant subsequently engaged lawyers on his behalf. The complainant says that there were storms and strong winds on 21 November 2019 and that the damage could have occurred sometime after commencement of the policy at 4.00pm on 21 November 2019 and 11.59pm on 21 November 2019. The complainant only noticed the damage on 22 November 2019. The complainant says the main cause of damage to the render was due to the strong winds and storms, and prior to this the render was in a satisfactory condition. The complainant also says the insurer‟s investigations are defective as they focused primarily on the workmanship of the building as opposed to the bad weather. The complainant seeks the sum of $22,000 based on another quotation from a renderer. Insurer says policy exclusions apply The insurer confirms that Melbourne and surrounding areas experienced high wind speeds on 21 November 2019. The insurer has provided a report from the Bureau of Meteorology (BOM) from the weather station closest to the insured property. The BOM report indicates that maximum wind speed on 21 November 2019 was 96km/hr at 8.49am, and that at about 3.00pm the wind speed was 39km/hr. The insurer also appointed a builder (P) to assess the damage. P inspected the insured property on 25 November 2019 and produced a report dated 29 November 2019. P was of the view that:  there were copious amounts of cracked damages to the render of the insured property and believes the damages had been present for a period of up to six to twelve months;  damages were caused by poor installation methodology - there is no visible base coat or joint tape installed under the render. Only a top coat appears to be installed which is not a suitable method of installation as there is little bonding between the foam sub straight and external render. This has resulted in the delamination of the external render. If there was a basecoat of render installed, then he would not expect the resultant damages to this extent;  at the front elevation of the property, a majority of the corners have cracked, there are bubbles and a majority of the steel external angle is rusting, causing bubbling in the render. The bubbles/cracking to the external render would result in water ingress behind the render assisting in the delamination of the render to the property; Determination | Case number: 693198 Page 5 of 7  the delamination, bubbling and rust to the render would not have been from a one- off event but over a period of time. P‟s report is supported by photog raphs of the damage. The insurer says that the damages are attributable to the exclusions for rust, gradual deterioration, structural defects and faulty workmanship or design, and that the claimed damages were occurring prior to policy inception. The wording of these exclusions is outlined in section 3.2 of this determination. Insurer is entitled to decline the claim I have carefully considered the information provided by the parties. I accept that there were strong winds and thunderstorms on 21 November 2019. However, I am not satisfied that the complainant has established that the insured property sustained damage caused by the winds and/or storms. As stated above, it is a well-established legal principle of insurance law that the onus rests with the insured to establish the loss falls within the provisions of the contract. Simply advising of a claim for loss or damage does not, of itself, satisfy this onus. Even if I were to accept that the insured property had incurred wind/storm damage, P‟ s report establishes, on the balance of probabilities, that the render had significant issues with workmanship, together with rust, corrosion, gradual deterioration and wear or tear. These are factors which are excluded under the policy. Although the complainant had some criticism of the insurer‟s report, I am satisfied the photographs support the opinions proffered by the insurer‟s expert in relation to the nature and cause/s of damage. Further, the complainant has not provided any compelling evidence to refute the insurer‟s position, or to establish that the loss occurred within the period of insurance. Therefore, the insurer is entitled to decline the claim. Determination | Case number: 693198 Page 6 of 7 3 Supporting information 3.1 AFCA approach to this complaint This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted only to those issues considered relevant to the outcome. 3.2 Relevant policy terms When your buildings are protected (pages 7 to 13 of PDS) The insured events that your buildings will be covered for are listed in the table below. This cover is subject to the exclusions outlined on Page 38 to 39. Insured event Storm, rainwater, flood or wind We will cover Loss or damage as a result of:  storm (including named cyclone)  rainwater  flood, or  wind We won’t cover Water entering your buildings:  through an opening made for any building, renovation or repair work  because of a structural defect, faulty design or faulty workmanship … General exclusions (Page 38 of PDS) We will not pay for any loss or damage, or liability caused directly by or arising from:  any event that does not occur within your period of insurance … Buildings and contents cover exclusions (page 39 of PDS) We will not pay for any loss or damage which is caused directly or indirectly by:  erosion, rust, corrosion, gradual deterioration, depreciation, wear or tear … Determination | Case number: 693198 Page 7 of 7  a defect in an item, structural defects, faulty or poor workmanship or design