Home / Allianz Australia / Determination 691032

Determination 691032

Storm water damage claim not accepted pending information

FirmAllianz Australia
Decided2020-06-05
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$250
Amount claimed—
SourceAFCA PDF

Summary

A homeowner claiming storm-related water damage disputed the insurer's request for further inspection and rental history information, and sought lost rent. AFCA held the claim need not be accepted until he provided the information, that the insurer must decide within 14 days of receipt, and ordered $250 for non-financial loss from the unreasonable file closure.

The policy requires the insured to assist with information the insurer reasonably requires, and an unreasonable closure of the claim without warning justifies modest non-financial loss compensation.

Issues

Subjects and remedies

home or building damagepay non financial lossreassess claim

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 691032 Financial firm Allianz Australia Insurance Limited Determination | Case number: 691032 Page 2 of 6 Case number: 691032 19 May 2020 1 Determination overview 1.1 Complaint The complainant lodged a claim for water damage to his property with his home insurer, the financial firm (insurer). The insurer has not accepted the claim because it is seeking additional information. The complainant disputes this as he says the damage was caused by storm and has provided the relevant information. He is also seeking compensation for lost rent due to the delay and for his claims experience. 1.2 Issues and key findings Is the insurer required to accept the claim? The insurer is not required to accept the claim because the complainant has not provided all the relevant information. The complainant must provide the relevant information set out in section 2.1. Once the complainant does, the insurer is to make a claim decision within 14 days of receiving all the relevant documents. Should the insurer pay compensation? The insurer should pay $250 in non- financial loss due to the complainant’s claims experience. 1.3 Determination This determination is substantially in favour of the insurer. The insurer is not required to accept the claim at this stage. The complainant is to provide the information set out in section 2.1. Once he does, the insurer is to make a claim decision within 14 days or receiving all the relevant documents. The insurer should pay $250 in non-financial loss. Determination | Case number: 691032 Page 3 of 6 2 Reasons for determination 2.1 Is the insurer required to accept the claim? Insurer requires more information The insurer is seeking more information from the complainant before making a claim decision. In doing so, the insurer is relying on the following policy provision: 1. Assist us with your claim You must assist us with your claim. This means you give us all the information and assistance with your claim which we may reasonably require. If you do not we may not pay your claim or provide cover Complainant must facilitate another inspection The complainant lodged a claim for storm damage to his property on 20 July 2019. This property is not his principal place of residence. Delays occurred in inspecting the property. Upon inspecting the property, the insurer’s contractors conducted some testing. The latest report from P said: A spray test of external wall and window on the affected side revealed an immediate leak through the window. The property is built into the side of the hill with no spoon drains along the edge of the concrete The insurer wants to do another inspection to clarify the cause. The complainant had initially refused. He later agreed but had provided a time with limited notice, which the insurer could not meet. He also disagrees about these potential causes. I agree another inspection is appropriate. The cause of damage is unclear. The testing conducted indicates it was not due to storm. It is reasonable for the insurer to engage at least one other expert to attend the property and identify the cause of damage to ensure the policy responds. Therefore, the complainant should assist in arranging this. In doing so, he should provide seven business days ’ notice for any inspection and ensure either he, or an authorised representative, is available to meet the insurer’s contractor /s. Complainant must provide more information about property’s rental The insurer says the complainant indicated he has been renting the property at various times for the last three years. The insurer provided evidence of the property being advertised. The insurer also provided notes of a conversation the complainant had with it on 10 October 2019 indicating he may start using the property for ‘AirBnB’. The insurer is therefore seeking the following information: Determination | Case number: 691032 Page 4 of 6  Confirmation of when the property was first listed on any holiday rental accommodation service  A copy of the initial listing application and registration confirmation for each of Airbnb, Bookabach and Stayz  Full booking records from all listings from the date the property was first listed. The complainant says the property has not been listed on Airbnb or Bookabach. He has provided information about bookings through Stayz. Having carefully considered the available information, I note the following. The insurer provided copies of advertisements through Bookabach and Stayz showing the complainant’s propert y. This is inconsistent with the complainant’s information that the property has not been listed through these websites. The complainant is seeking lost rent from July 2019. However, according to the information he provided on Stayz, he received no bookings at all in 2019 and only received secured reservations in 2020. This is inconsistent with his evidence that he has lost rent due to the delays. The information he provided from Stayz is limited. He provided a statement of income from 2020. However, this document does not clarify that this represents all the monies he received through this provider. The registration he provided simply shows when the property was available to be viewed by the public at a certain time. He has provided calendars for only 2019 and 2020 of previous reservations. This does not include previous years. Given this, I am not satisfied the complainant has complied with the insurer’s requests. I am also satisfied the insurer’s request is reasonable. The policy was issued as an owner occupied one. If it was rented, this changes the nature of the risk. The insurer is entitled to investigate and clarify when this change occurred and to what extent it would have affected its assessment of the risk. Complainant must provide the following information After careful consideration of all the available information, I accept the insurer is not required to accept the claim until the complainant does the following:  arrange for either himself, or an agent, to attend an inspection with the insurer’s contractor/s so that the insurer can determine the cause of damage – in doing so, the complainant should provide at least seven business days ’ notice  provide the information about his rental history – alternatively, he can provide an authority to the insurer so that the insurer can access this information Until these have been complied with, the insurer is not required to accept the claim. If the complainant does comply with these requests, then the insurer is to make a Determination | Case number: 691032 Page 5 of 6 claims decision within 14 days of receiving the contractor’s report and all the documents for the property’s rental history. 2.2 Should the insurer pay compensation? Insurer not required to pay for lost rent The complainant is dissatisfied with the claim delay, the insurer’s conduct (which includes closing the claim) and issues he experienced with attending an inspection. The complainant is seeking compensation due to his claims experience. This includes lost rent due to the claim delay. In terms of his lost rent, there is no basis to award this. As stated previously, the complainant has provided no evidence to show the property was receiving any rent at the relevant time or could have received rent during the whole period he is seeking. Further, for reasons later explained, I am not satisfied the insurer has caused the claim delay. Insurer should pay $250 in non-financial loss AFCA may award compensation for non-financial loss up to a maximum of $5,000. AFCA takes a conservative approach to awarding this type of compensation. It is only awarded where the complainant has suffered from an unusual amount of physical inconvenience or stress or the financial firm’s con duct has meant the time taken to resolve the situation has been unusually excessive. The insurer says the delay in arranging an assessment was because the complainant refused to attend. He has not provided evidence to the contrary. The texts he provided simply show he was prepared to give access to the property but not attend. He has not provided evidence to show that in 2019, he had made times available to attend with the insurer which the insurer refused. A case analyst issued a preliminary assessment noting the insurer’s loss adjuster (C) missed an assessment on 3 February 2020 and awarded $250 compensation for this. In reading the contemporaneous correspondence though, there was confusion about the appointment. The complainant believed the appointment was between 12-2 whereas C believed it was between 12 -4 and arrived closer to 4. It is not clear if the misunderstanding was due to the complainant or C. The complainant was dissatisfied with the insurer closing his claim. I note the insurer did so on or around 27 August 2019. There was some information exchanged between the insurer’s first loss adjuster (S) and the complainant about facilitating an inspection. The last email appears to have been sent by C on 7 August 2019 about this. The insurer’s claim notes do not show any calls with the complainant after this and before it sent an email saying it would close the claim. It appeared it did so without Determination | Case number: 691032 Page 6 of 6 having a conversation with him. It is not clear if S had warned the complainant of this possibility. Based on this, it appears the insurer’s closing of the file was unreasonable and would have caused interference and inconvenience. I do not accept the complainant’s evidence that the insurer’s representative (NJ) was acting inappropriately. The correspondence provided does not show NJ was acting unreasonably or placing undue pressure. Given all this, and considering our conservative approach, an award of $250 for non- financial loss is fair in all the circumstances.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.