Text of the determination
Determination
Case number 686882
Financial firm Insurance Australia Limited
Determination | Case number: 686882 Page 1 of 15
Case number: 686882 3 December 2020
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm
(insurer).
He lodged a claim on 25 April 2015 after his property was water damaged on that
day. The insurer accepted the claim and undertook repairs to the property. The
complainant raised concerns regarding the adequacy of repairs after noticing visible
cracking sometime after the repairs were completed.
The insurer assessed the damage and found that the repairs were not undertaken
correctly and offered to cash settle the cost of the required repair rectification.
The complainant says the amount offered to repair the storm related damage and the
inadequate repairs by the insurer’s builder is insufficient.
To resolve the complaint, he requests the insurer provides settlement based on the
repair quotes he has obtained.
1.2 Issues and key findings
What is the extent of the insurer’s liability for rectification repairs?
The complainant provided a recent quote which he says accurately reflects the
rectification repair work required.
This quote and email was exchanged with the insurer on 25 September 2020. The
insurer has not disputed the complainant’s quote or provided a quote of its own.
Therefore, on balance, the panel is satisfied the quote provided by the complainant is
an accurate assessment of rectification works required as it is not challenged by the
insurer and it is based on the insurer’s own scope of works.
The insurer must cash settle the complainant the amount of $127,000 plus a
contingency of 10% to allow for potential variations and the transfer of risk.
Is the insurer required to make other payments to the complainant?
Yes: the insurer is required to provide temporary accommodation costs from the date
of repairs commencing until the date of completion. As the home is undergoing
extensive repairs, the panel is satisfied the home will be uninhabitable during this
period.
Upon satisfactory proof, the insurer is to indemnify the complainant for the cost to
remove and store contents and then return them to the home after repairs.
Determination | Case number: 686882 Page 2 of 15
The available information establishes it is fair the insurer contributes to expert report
costs because the claim was complex and the complainant needed expert opinion to
make his case.
While the panel accepts the property cannot be lived in while it is being repaired, the
panel does not accept the property is presently unliveable so the insurer is not
required to pay the complainant any amount for rent paid by the complainant.
Is the complainant entitled to compensation?
Yes: the available information establishes there has been an unusual degree or
extent of physical inconvenience and time taken to resolve the complaint which would
have interfered with the complainant’s expectation of enjoyment or peace of mind.
The complainant has not provided sufficient evidence to show the handling of the
claim by the insurer has caused him indirect financial loss and so the complainant is
not entitled to compensation for indirect financial loss due to the handling of his claim
by the insurer.
1.3 Determination
This determination is mainly in favour of the complainant.
Should the complainant accept this determination then within seven days of
notification of acceptance, the insurer is required to pay the complainant the following:
$139,700 for rectification repairs
$3,760 for temporary accommodation during repairs
$1,870 for expert report fees
$3,500 compensation for non-financial loss.
If the complainant has paid for the expert reports, the insurer is also to pay interest
pursuant to section 57 of the Insurance Contracts Act on $1,870 from the date of
payment for the reports until the date of settlement.
Should the complainant accept this determination then within seven days of
notification of acceptance, the complainant is to provide the insurer with a quotation
for the cost to remove and store contents and then return them to the home during the
rectification repairs. Upon receipt, the insurer is to assess this aspect of the claim and
cash settle the complainant.
Determination | Case number: 686882 Page 3 of 15
2 Reasons for determination
2.1 What is the extent of the insurer’s liability for rectification repairs?
Valid claim has been established
This has been some lack of clarity as to the exact mechanism leading to the initial
damage, however, irrespective of this the panel is satisfied that the complainant’s
property suffered water damage on 25 April 2015.
The claim was accepted, and repairs we re undertaken by the insurer’s builder (M).
Sometime after the repairs were completed, the complainant raised concerns
regarding the adequacy of these repairs upon noticing cracking and gaps in the
ceiling. After further investigation by the insurer, it accepted the works undertaken by
M were inadequate and required rectification.
On the available information, the panel is satisfied a valid claim has been established
as the insurer has accepted the claim and confirmed rectification issues are evident
based on its post repair inspection.
Complainant says insurer’s offer insufficient to rectify repairs
The claim file was reopened in January 2018. The insurer arranged for an inspection
by a builder (AG) and an engineer (CD). Both agreed rectification work was required.
The insurer consulted with M. As the roof is under pitched, M was not willing to
warrant the repairs and said a cash settlement of $14,037.27 was adequate.
Relying on repair quotations obtained from KG ($74,250), AH ($120,000 plus GST)
and PP ($111,692.76) the complainant said the offer was inadequate.
In its final decision letter on 23 September 2019 the insurer agreed the repair work
conducted by M was insufficient and rectification work was required. It said a further
assessment would be carried out to report on additional repairs required.
Due to a miscommunication no builder was allocated. By letter dated 21 February
2020 the insurer said an independent engineering company (CFT) was allocated to
the claim.
CFT finally inspected the property on 12 August 2020. Upon the complainant
receiving an updated scope of works from CFT the complainant provided quotes from
his nominated trades (KP) ($127,000 including GST) and (EW) ($142,000 including
GST). The quotes for rectification repairs were provided to the insurer.
A summary of the material relied on by the parties is set out in supporting section 3.3
of this determination.
Determination | Case number: 686882 Page 4 of 15
In view of the large discrepancy between the amount offered by the insurer and the
quotations obtained by the complainant, the complainant rejected the offer made by
the insurer. The complainant requested the insurer provide settlement for the amount
quoted by his experts.
Insurer has not disputed the complainant’s costings
The complainant provided the quote from KP on 22 September 2020 for the
rectification works. The quote, along with the complainant’s email was exchanged
with the insurer on 25 September 2020.
The complainant provided the quote from EW on 6 October 2020. The quote was
exchanged with the insurer on 12 October 2020.
On 14 October 2020, the complainant advised the case manager his builder advised
him it would take about 6 to 8 weeks for repairs to be undertaken. This information
was exchanged with the insurer in a letter dated 18 November 2020.
By letter dated 27 November 2020 the insurer said it had no further information to
add.
The insurer confirmed through discussions with AFCA it would provide a quote from
its nominated trades on or by 14 September 2020. In its further notice of response of
8 September 2020, the insurer said it had requested a quotation for the rectification
costs based on CFT’s scope of works. On receipt of the quotation it said it would
provide a cash settlement offer based on the quotation with a 10% variation.
To date the insurer has not provided any further submissions disputing the
complainant’s quotes nor has it provided a quote of its own.
It is fair the claim is cash settled
The insurer’s policy states it can choose to settle a claim by either arranging for
repairers to repair the home or by paying the reasonable cost to repair the home.
The insurer has confirmed it wishes to cash settle this claim on the basis that there
are maintenance and defects issues which are likely to affect the rectification works.
The panel generally prefers for rectification repairs to be undertaken by the insurer,
but in all the circumstances of this claim, the panel is satisfied it is fair for the insurer
to cash settle the claim.
This is because considerable time has passed since the initial repairs by M, the
available evidence shows there are some maintenance and defects issues with the
property and because of the state of the relationship which are now exists between
the parties.
The panel has considered the quotations provided by the complainant. Both
quotations appear to include items which were not on the CFT scope of works. The
Determination | Case number: 686882 Page 5 of 15
panel prefers the quotation provided by KP as it is clearly sets out the reasons why
these extra items have been included. The panel finds the quotation provided b y EW
lacks the same particularity.
The insurer has not commented on the quotations provided by the complainant. The
insurer has not provided its own quotation of the cost of rectification based on CFT’s
scope of work.
Insurer to pay to the complainant $139,700 for rectification repairs
Based on the information provided and in the absence of any further responses from
the insurer, the panel is satisfied the quote provided by KP is fair and is actionable.
KP’s quote addr esses concerns raised by the complainant including issues with
asbestos and electrical issues.
In circumstances where a cash settlement takes place an insurer should consider any
contingencies and variations which may occur once repairs commence.
Additio nally, the insurer’s policy provides a lifetime guarantee if the insurer
undertakes repairs and it is fair the complainant is compensated for giving up this
lifetime guarantee on repairs.
In view of the earlier comments made about KP’s quote and that it is actionable and
relatively recent, the panel is satisfied an uplift of 10% is fair in all the circumstances
and that no interest is payable.
The insurer is therefore required to pay to the complainant for rectification repairs in
the sum of $127,000 plus a 10% contingency for transfer of risk and potential
variations.
Should the complainant accept this determination then within seven days of
notification of acceptance the insurer is to pay to the complainant $139,700 for
rectification repairs.
2.2 Is the insurer required to make other payments to the complainant?
Upon proof, the insurer is to pay the cost to remove and store contents
The complainant claims for the cost of relocation of household items during repairs.
Although EW refers to this item in his quotation the amount allocated is not specified.
The insurer has not addressed this issue.
Included in the cover under building insurance is the cost to remove and store
contents and then return them to the home.
Should the complainant accept this determination then within seven days of
notification of acceptance, the complainant is to provide the insurer with a quotation to
remove and store contents and then return them to the home during the rectification
Determination | Case number: 686882 Page 6 of 15
repairs. Upon receipt, the insurer is to assess this aspect of the claim and cash settle
the complainant.
The insurer is to pay $3,760 for temporary accommodation during repairs
The complainant’s policy provides cover for temporary accommodation when the
home has been damaged because of an insured event and the insurer agrees the
insured cannot live in the home whilst these repairs are being undertaken.
The policy confirms this amount is paid over and above the sum insured noted on the
certificate of insurance (COI).
The insurer’s policy does not defin e the concept of the property being unliveable nor
does it set out the criteria required for the premises to be considered unliveable.
AFCA generally considers that consideration of the fitness of the premises for
habitation is usually limited to factors such as being secure to the elements, access to
electricity, gas and water at the premises, as well as kitchen and bathroom facilities,
and the absence of contaminants or other safety hazards.
The repairs required to the property include damage to the ceili ngs in multiple areas.
In some areas of the property, ceilings require complete replacement.
Upon review of the scope of works, the panel is satisfied works required are extensive
as the home requires major works to be undertaken. The panel has considered all the
available material and is satisfied, on balance, the property could not reasonably be
considered liveable whilst the rectification works are undertaken.
The complainant has confirmed the repair timeframe will be approximately 6 to 8
weeks. The insurer has not challenged this assertion.
The complainant says he is living in rented accommodation paying $470 a week.
While he has provided no proof of this outgoing, the panel is satisfied this is a
reasonable amount for temporary accommodation in the co mplainant’s area.
Should the complainant accept this determination then within seven days of
acceptance of the determination, the insurer is to pay to the complainant 8 weeks
temporary accommodation in the amount of $470 per week ($3,760).
The insurer is to pay $1,870 for expert reports
The complainant claims for the cost of reports from his expert engineer (PP). The
panel has considered the reports provided by PP and PP’s invoices which total
$1,870.
Pursuant to AFCA Rules (D5) AFCA may decide an insurer is to contribute to the
complainant’s costs. The panel is satisfied it is fair the insurer contributes to these
costs because the claim was complex, and the complainant needed expert opinion to
make his case.
Determination | Case number: 686882 Page 7 of 15
Should the complainant accept this determination then within seven days of
notification of acceptance the insurer is to pay to the complainant $1,870 for the
reports.
If the complainant has paid for the reports, the insurer is also to pay interest pursuant
to section 57 of the Insurance Contracts Act on $1,870 from the date of payment for
the reports until settlement.
The insurer is not required to pay the complainant for rent
The complainant claims around $36,660 for rent. Due to serious health and safety
hazards present in the property (especially for his young daughter who has high care
needs) he says he had to rent elsewhere since November 2019. He also says due to
the marriage breakdown since November 2018, his wife and daughter have lived
elsewhere.
The complainant says the property has many health and safety issues, like mould and
dust and pests invading the interiors through cracks in the ceilings and walls and
electrical safety concerns.
The panel notes some of these issues were raised when the file was reopened in
2018. The claim file notes show the insurer conducted a minor make safe at the
complainant’s request at this time.
The panel has carefully reviewed all the material provided including recent
photographs and PP’s report which refers to these issues.
Taking all matters into account and particularly the recent photographs, while the
panel accepts the property cannot be lived in while it is being repaired, the panel does
not accept the property is presently unliveable.
In the circumstances, on the available information, the panel is satisfied the insurer is
not required to pay the complainant any amount for rent paid by the complainant.
2.3 Is the complainant entitled to compensation?
Compensation paid in some circumstances.
The complainant makes several complaints about the way the claim was handled,
and delays occasioned by the insurer.
AFCA will award compensation (capped at $5,000) if there has been an unusual
degree or extent of physical inconvenience, time taken to resolve a complaint or
interference with the complainant’s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to awarding compensation. We do not award
compensation because the complainant has suffered some inconvenience and
anxiety. AFCA expects complainants to be moderately robust and to bear the normal
Determination | Case number: 686882 Page 8 of 15
degree of inconvenience experienced when a problem occurs and to take reasonable
steps to manage the situation.
Insurer to pay to the complainant $3,500 compensation for non-financial loss
Having reviewed the available information, the panel is satisfied that the complainant
is entitled to compensation for non-financial loss.
The complainant has shown the wor ks undertaken by the insurer’s builder in the first
instance were inadequate. This is not disputed by the insurer and it accepts the home
requires rectification works.
The complainant’s claim has also experienced multiple delays of many months at a
time due to the insurer failing to arrange the attendance of trades and provide a quote
for rectification works. The insurer was also followed up by AFCA on several
instances for an updated quote and significant delays were experienced in obtaining
this information.
The panel notes the insurer’s apology. The panel accepts the insurer’s claims
handling was untimely and caused significant stress and inconvenience to the
complainant.
Taking all matters into account the panel is satisfied it is fair the insurer pays to the
complainant $3,500 compensation for non-financial loss.
Complainant is not entitled to compensation for indirect financial loss
The complainant claims his take-home earnings have dropped significantly because
he has been unable to take up overtime shifts or attend to call for certain
assignments.
AFCA may award compensation for indirect financial loss up to a maximum of $5,000.
Where a general insurance policy excludes liability for consequential (indirect
financial) loss, AFCA may still make such an award of compensation if indirect
financial loss has been caused by the unreasonable handling of the claim by the
insurer.
On the available information, the panel is not satisfied the complainant has provided
sufficient evidence to show the handling of the claim by the insurer has caused him
indirect financial loss.
In the circumstances, on the available information, the panel is not satisfied the
complainant is entitled to compensation for indirect financial loss due to the handling
of his claim by the insurer.
Determination | Case number: 686882 Page 9 of 15
3 Supporting information
3.1 Our Approach
This complaint has not been the subject of a recommendation. Due to the nature of
the complaint, it has been referred directly to a panel for determination, in line with the
Operational Guidelines to the AFCA Rules. The panel consists of an Ombudsman
and two representatives with consumer and insurance experience.
The panel has decided this complaint based on what is fair in all the circumstances,
having regard to legal principles, applicable industry codes or guidance, good industry
practice and previous relevant determinations of AFCA or predecessor schemes
(which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all the material provided by the parties. While
the parties have raised numerous issues in their submissions, for the purposes of this
determination the panel has restricted its commentary to those issues that it considers
directly relevant to the outcome only.
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie or valid claim.
Once so established, the onus shifts to the insurer to prove on the balance of
probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Relevant policy terms
Relevant policy extracts are referred to in the correspondence between the parties
and in the insurer’s Notice of Response . Both the policy document and the Notice
have been exchanged with the complainant.
Page Key points
Page 35 Temporary accommodation for home owners
If a listed event causes loss or damage to your home and we agree
you can’t live in it and you need to move out so it can be repaired or
rebuilt.
Covered under Buildings Insurance
costs for temporary accommodation that we agree are reasonable
and appropriate for you, your family and your pets that you normally
keep at your site any additional living expenses that we agree are
Determination | Case number: 686882 Page 10 of 15
Page Key points
appropriate costs to remove and store your cont ents and then return
them to your home.
Page 53 What we don't cover
[…]
compens ation for distress, inconvenience or ot her non - financial
loss, except if covered under liability cover
consequential financial loss - for example, loss of profits, except if
covered under liability cover.
Page 58 How we settle your buildings claim
[…]
2. Pay you the reasonable cost to repair or rebuild your home.
We can choose to:
pay you
pay your nominated repairer, supplier or builder, or
provide you with store credits from one of our nominat ed suppliers.
3.3 Extracts from material relied on by the parties
Date Action
Scope of repair works by
insurer’s builder (M)
25 May 2015
Scope describes work to be done in bedroom1,
garage, living room, and roof.
Note from complainant
regarding scope of works
Required amendment of scope and confirmation
i n sul ation will be removed and replace d as became
wet during and after the storm.
Has weakened the integrity of the existing ceiling s .
Water coming through damag i ng carpet and bedding .
Conc erned further storm damage to rear perimeter of
property.
Insurer’s report (AG)
18 January 2018
Inspected and photographed as since repairs were
completed storm damage cracks appeared in ceilings
in the hall, kitchen, lounge ro om and garage.
D amage to the ceiling in the hall, kitchen & lounge
(small impact area) was related to the event.
C racks in the ceiling of the garage is faulty
workmanship and the cornic e repair was overlooked.
M ajority of the ceiling in the lounge room ap pears to be
within tolerance but further investigation would be
required to confirm due to the extent of insulation
required to be moved to inspect.
Estimated cost of repairs $5,319.78.
Determination | Case number: 686882 Page 11 of 15
Date Action
Insurer’s report (CD)
8 May 2018
Inspected and photographed 27 April 2018 with
complainant.
Ceiling to the garage has been repaired and the joints
are visible and of a poor finish with joints easily visible.
The joints to the plasterboard ceiling of the garage
have also cracked due to poor workmanship.
1.2 The mark to the cornice in the living room is due to
the bottom cord of the truss slightly bowing down over
the wall plate and causing the cornice to deflect.
1.3 The cracks to the living room ceiling around the fan
is due to the ceil ing being repaired there previously
and as a result of additional weight and moisture to the
ceiling. The Insulation to the ceilings in the living room,
the hallway and the main bedroom were not replaced
at the time of the repairs and the moisture to the
c eiling and insulation would have been trapped.
1.4 This is also the cause of the fixings to the ceilings
to have bled through the paint work.
1.5 The caus e of the cracking to the ceiling in the
hallway is also a combination of moisture to the ceiling
being left and the gradual time for the plasterboard
timber and insulation to dry out would have been at
different rate causing added stress to the plasterboard
and expansion and shrinkage to the timber roof
trusses.
1.6 The plasterboard to the hallway has also had wat er
ingress through the tiles and the valleys caused by
heavy debris and this has also contributed to the
cracking of the ceilings.
1.7 The roof pitch to the front balcony roof is under
pitched at 11 degrees with the minimum pitch for tiles
being 15 degrees. This section of the roof is sarked but
the sarking is breaking down due to age and this would
have been a contributing factor for the wat er ingress
during the hailstorm due to then flat pitch allowing
water to ingress into the roof cavity. We also witnessed
watermarks to the battens and the insulation at the
time of the inspection but we are unable to determine if
they are from the event or more recent due to the
insulation not being replaced.
1.8 The water damages to the cornice to the front of
th e garage are due to the single skin brick work and
the barge pointing breaking down allowing water to
enter the wall and flow through the flashing to the
internal of the wall and out on to the cornice below.
Due to the cornices being blackened and deterior ated
this has been happening for a period of time before the
hail event.
1.9 Cracking to the ceiling in hallway is a combination
of not replacing the insulation and the debris to the
Determination | Case number: 686882 Page 12 of 15
Date Action
roof allowing moisture to penetrate the ceiling cavity.
1.10 Downlights h ave stopped working due to them
being covered by the insulation and overheating.
Recommended complainant clean the roof and re -
point roof tiles.
Recommended repairer return and replace the
insulation to the front section of the roof and repair the
cracked and uneven finish to the garage plasterboard.
Complainant’s repair costs
(KG)
26 February 2019
Removing and placing ceiling, insulation and wiring,
replacing timber wall, wall lining in lounge and hallway
main room wall lining, bathroom timber wall damage,
painting, pest control: $74,250 including GST.
Complainant’s repair costs
(AH)
3 March 2019
Repairs to ceiling, external walls, internal walls, work in
bathroom, pest control, painting: $120,000 plus GST.
Some work excluded.
Duration of project minimum six weeks from practical
start.
Complainant’s structural
engineer’s report (PP)
12 April 2019
On 16 March 2019, over 2 hours, this structural
engineer inspected the property with the complainant
to assess its integrity and adequacy after recent
cracks, movements, defects found resulting from the
hail storm which occurred April 2015 and failure to
rectify by insurer’s builder.
Provided supporting documents including photographs
and a diagram of defects.
1. I nspection revealed several defects at the properly
resulting from the non - standard repair works of the
insurer’s contractor after the hail storm in April 2015.
2. Insurer’s repairer had not been taking care enough
for the remedial works that they had carried out. Th ere
had not been any method to strengthen the roof
structure implement ed from the hailstorm impact. The
roof has been deformed and the integrity of the roof
structure (or truss system) has additional deflection of
minimum 10mm in compared to the original s tate.
3. A ‘Band Aid’ solution was implemented to the repair
works carried out by the repairer such that the ceiling
was cut and joint out of the cornices which were
supposed to be replaced as a whole.
4. Wall plasterboards and stud wall had not been
inves tigated carefully in such that moisture was
trapped inside the stud walls and the plasterboards
have been absorbing and swollen causing cracking
and loosen joints.
5. Moisture had also trapped in roof space causing
smell and damages to anti - insect barrier of the ceiling.
We found dust, moisturized insulation, insects,
Determination | Case number: 686882 Page 13 of 15
Date Action
cockroaches, spiders, ... within roof space. Apparently,
the insects, mouldy dusts invading the rooms through
cracks have put threats to health and safety of the
occupants.
6. The roof pitch f ound 11 degrees that is non -
standard for this kind of tile roof to the front area of the
property should have been rectified or suggested to
rectified after the hail storm as a call of builder’s and
insurer’s due diligence.
7. Electrical hazards including blown - out downlights
and broken - down electricity have raised a big concern
to the owner. Light tube was blown out and felt over
head of the owner wife. The insurer had not
investigated the whole system after the hail storm as
required. Wiring was found eve ry where within the roof
cavity.
8. The whole building was put into dangerous situation
due to the unthorough repair works of the contractor
that have developed the hazards and threatened
health and life of the occupants.
9. We are of the opinion that thoro ugh rectification
should be carried out by the insurer. This includes but
not limited to 9.1. Repair/ replace ceilings of the Living
rooms, Garage, Bedroom 1, Hallway, Kitchen, Dining
Room, Family Room, Bathroom and Toilet. Check
other ceiling areas. 9.2. Check/ Measure moisture,
structural integrity of roof trusses and rectify for long
term capacity. 9.3. Replace thorough insulations of the
entire ceiling 9.4. Replace wall plasterboards of Living
room, Kitchen, Hallway, Bedroom 1. 9.5. Replace
cornices and all left over compromised ceilings 9.6.
Seal leakages to ceiling, Bay windows and windows
9.7. Check and rectify stud walls.9.8. Check and
rectify/ replace the whole building electrical system.
9.9. Carry out all necessary checking/rectification
works to reinstate habit ability to the building
Complainant’s rectification
quote (PP)
3 May 2019
Provided a cost estimate as per its defects report in
the sum of $111,692.76 including GST.
Insurer’ s building inspection
report (CFT)
21 August 2020
After an inspection and review of earlier reports from
the insurer, the report details information to determine
causation and identified damage as a result of the
storm in 2015 and building defects and maintenance
related issues.
Inspection took place 12 August 2020 with the
complainant.
Described the storm related damage and work
required in the garage, laundry, living room, hallway,
Determination | Case number: 686882 Page 14 of 15
Date Action
bedroom 1, kitchen, family room and painting and
replacement of light fittings.
Described some maintenance relat ed work a nd a
building defect in relation to the under pitched skillion
roof to the front of the house.
Highly probable materials containing asbestos at site
and this should be attended to before repairs.
Concluded the initial damage to the ceilings in 2015
was d ue to water ingress caused by the low roof pitch
and the choking of valley gutters with debris but these
issues were not identified as the cause of the water
ingress, nor were they attended to and repaired prior
to the ceiling repairs been complet ed.
Damp ceiling insulation was never removed and a
combination of the damp ceiling insulation and ongoing
water ingress due to the low roof pitch and choked
valley gutters continues to contribut e to the ongoing
water damage to the internal area of the house.
Ini tial water damage due to the storm in 2015 was not
repaired in compliance with relevant Australian
standards.
Provided a scope of works for the repair of the
resultant damage.
Insurer’s scope of works
storm (CFT)
21 August 2020
Scope compiled following a site inspection by insurer’s
licensed qualified builder following information
provided on site by the complainant for the purpose of
reinstating the building to a condition similar to that
prior to the event.
Provided a scope which included comments in relation
to electrical works and asbestos. The scope describes
work required to be done generally, in bedroom 1,
living room, family/kitchen, hallway, garage/laundry,
and general prot ection and clean - up.
Complainant’s rectification
quote (KP)
21 September 2020
KP quote (applicable for 30 days) based on scope of
works developed by CFT, discussion with complainant
and site inspection.
Describes work to carpentry and roof exterior, plaster
and paint work and electrical: $127,000 including GST.
E xcludes any unforeseen circumstances throughout
building.
Complainant’s rectification
quote (EW)
3 October 2020
Quote to correct defective repair consequences –
scope comprises engineers list and on - site inspection
evaluation $142,000 GST included.
3.4 Other relevant material considered and relied on
Parties’ submissions /emails and all attachments to all submissions/emails.
Determination | Case number: 686882 Page 15 of 15
Parties’ expert reports.
Photographs, invoices and quotations
Claim file notes.
Correspondence between the parties.