The insured's flood-damaged home was cash settled, and she disputed the amount. AFCA ordered a further $51,000 for building repairs and $1,250 for non-financial loss, but declined the fence claim.
The cash settlement had to allow for the complainant's rebuild risk and contingencies, and the insurer's excessive claim processing time warranted non-financial loss compensation.
Issues
- Claim amount dispute primary · upheld“The insurer is to increase its offer of settlement by $51,000.”
- Claim denial secondary · not upheld“The insurer is entitled to decline the claim to replace the fence.”
- Delay secondary · upheld“The time between obtaining the first quote and the final quote was excessive.”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial loss
Related
All Suncorp Group determinations · Find similar determinations
Text of the determination
Determination
Case number 686094
Financial firm AAI Limited
Determination | Case number: 686094 Page 2 of 9
Case number: 686094 20 August 2020
1 Determination overview
1.1 Complaint
The complainant held a home and contents insurance policy with the financial firm
(insurer) for her property in Townsville. The property was impacted by catastrophic
flooding in early February 2019.
Following the flooding, the complainant lodged a claim with the insurer for property
damage. After multiple on-site assessments, the insurer accepted the claim and has
paid $325,323.57, to settle the building aspect of the claim.
The complainant says the settlement offered by the insurer is inadequate. She wants
the insurer to settle as per the quote obtained by her amounting to $376,351.
Furthermore, she wants the insurer to increase the temporary accommodation
allowance.
1.2 Issues and key findings
Is the insurer required to increase its offer of settlement?
The insurer is to increase its offer of settlement by $51,000.
The insurer’s offer to provide an additional six months accommodation is fair and
reasonable in the circumstances.
Is the insurer entitled to decline the fence damage?
The Panel is satisfied, on balance, the fence was not damaged by flood or any other
insured event. Accordingly, the insurer is entitled to decline the claim to replace the
fence.
Is the complainant entitled to any compensation?
The insurer must pay the complainant $1,250, for non-financial loss compensation.
1.3 Determination
This determination is substantially in favour of the complainant.
The insurer is to increase its offer to $51,000 as set out under section 2.1 of the
determination.
The insurer is to pay $1,250 as non-financial loss to the complainant.
Determination | Case number: 686094 Page 3 of 9
2 Reasons for determination
We have considered it appropriate to expedite this complaint in accordance with the
Operational Guidelines to the AFCA Rules, due to the nature of the complaint.
Accordingly, this complaint has not been the subject of a preliminary assessment and
has proceeded directly to determination.
This determination is made by a panel consisting of the Panel Chair Ombudsman,
together with a Panel member with extensive experience in the insurance industry
and a Panel member with extensive experience in consumer claims.
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address the issues
raised. While the parties have raised various issues in their submissions, for this
determination the panel has restricted its commentary to those issues it considers
directly relevant to the outcome only.
This determination follows consideration of all the available material. It is based on
what is fair in all the circumstances having regard to the relevant law, terms of the
policy, good industry practice including codes of practice and prior determinations,
where appropriate.
2.1 Is the insurer required to increase its offer of settlement?
Damage falls within the terms of the policy
The policy is an insured events policy that provides cover for a series of insured
events including flood.
There is no dispute the property sustained damage resulting from flood waters
inundating the property. The damage clearly falls within the terms of the policy.
Following the claim lodgement on 4 February 2019, the insurer appointed its assessor
to attend the insured property with a builder (JG) and a restorer (RX) to assess the
damage. An assessment was undertaken on 9 February 2019, when the assessor
authorised JG to complete a strip out of the property.
Parties decided cash settlement is the best method to settle the claim
Following the initial assessment, it was mutually agreed between the parties that the
strip out will be completed by the complainant’s specialist (RJ).
The assessor attended with JG on 19 July 2019. He reported there was termite
damage throughout the study and noted JG would not be able to warrant any repairs
if the termites remained active.
Determination | Case number: 686094 Page 4 of 9
The assessor also reported the strip out was not completed to an acceptable standard
by RJ. On 21 August 2019, the assessor confirmed JG would not be able to complete
repairs as it did not complete the strip out.
The complainant advised she does not want JG to undertake the repairs. The
complainant states her house was custom built and it was built by a master builder.
She believes JG would not be able to rebuild the house like it was before. She
obtained quotations from two independent builders and requested a cash settlement.
JG provided a quotation in August 2019, amounting to $253,432.51. Five
amendments were submitted and approved by the insurer.
The Panel notes that five amendments to the quotation is a significant number but
accepts these were a result of negotiations between the complainant and builder and
items disputed by the complainant.
The Panel is satisfied the insurer approved a number of these amendments to move
the claim forward. It is also satisfied the number of variations approved by the insurer
shows it was not likely to place the complainant in the position of having to pay for
variations that were within reason or justifiable.
Policy allows for cash settlement
It is clear from the terms of the policy that the insurer has the discretion to decide
which settlement method to adopt. However, AFCA expects an insurer to act
reasonably, fairly and consistently with utmost good faith in exercising its discretion,
having regard to the circumstances of the claim.
As the complainant wanted to use a private builder and JG was not able to warrant
the repairs, the Panel is satisfied it is fair and reasonable for the insurer to cash settle
the claim.
Complainant says cash settlement offer is not adequate
The complainant says the insurer has used predatory pricing in determining its
liability. The complainant says the insurer has relationships with its industrial partners,
such as JG, which allows it to get better pricing that is lower than the market prices.
The insurer acknowledges that it negotiates prices and can receive large discounts
due to its relationship with its vendors.
In cash settling, the insurer must ensure the settlement amount is reasonable and
sufficient for the complainant to complete the necessary work herself. That is, the
amount must be arrived at having regard to all relevant factors, including the fact that
the risk is passing to the complainant, since she will lose the lifetime guarantee on the
work and there may be as yet unknowns in the repair process.
Determination | Case number: 686094 Page 5 of 9
The complainant says there was a sliding door and two bifold doors along with 18
other doors at her property. She says JG has accounted for the sliding and bifold
doors, however, it has only accounted 15 doors. Furthermore, the complainant says
the cost allowance for the tiles in the property including the bathroom needs to be
increased by JG.
JG provided a final scope of works and a quotation of $322,472.57 . The insurer says
JG ’s scope of works covers all the claim related damage. The insurer believes it has
settled the claim in a fair and reasonable manner by adding $2,851 to the quoted
amount. Accordingly, it paid a total of $325,323.57 for the building damage.
The panel notes that the builder’s margin on the JG quote is 13.9%.
The panel does not accept that this is consistent with industry standards and 18% is
more appropriate.
The complainant has obtained two quotations from independent builders, DP and TC,
amounting to $397,794.67 and $376,351 respectively. The complainant says she is
not able to obtain the same prices as the insurer due to the insurer’s better buying
power.
The P anel is satisfied the complainant’s cost to rebuild the house may be higher than
the settled amount. Due to the significant repairs that are required and to allow for
contingencies, the Panel determines the insurer should add 15% to the cash
settlement, in addition to the increase in the builder’s margin on the JG quote.
Accordingly, the insurer should pay an additional $51,000 (rounded out) for the
building repairs as full and final settlement of the claim.
Insurer offer for additional temporary accommodation is fair
The complainant had to evacuate the property after it was flooded. The complainant
initially stayed in short term rentals which the insurer approved. Afterwards, due to the
scarcity of accommodation in Townsville, it was mutually agreed between the
complainant and the insurer that the complainant would be able to stay at her
investment property. The insurer settled the complainant as per the rental amount she
would have received had the property been tenanted.
The policy limit for temporary accommodation is 10% of the sum insured for up to 12
months. The insurer has paid the complainant temporary accommodation for 52
weeks. The insurer has also agreed to cover a further six months to allow for the
repairs to the property.
The complainant says it will take a further six weeks in addition to the six months
allowance for the repairs to complete. The Panel is satisfied the insurer’s off er of
providing a further six months accommodation in addition to the policy limit is fair and
reasonable in the circumstances. Accordingly, the insurer is not required to pay
anything further for the temporary accommodation.
Determination | Case number: 686094 Page 6 of 9
2.2 Is the insurer entitled to decline the fence damage?
Insurer is entitled to decline the fence damage
DP reports the structural integrity of the fence has been compromised by the flood. It
reports the posts have become loose in the ground by the water force and the fence
shows signs of wood rot. The complainant says there was no wood rot prior to the
flood and wants the insurer to replace the fence .
The insurer’s assessor says the photograph provided by DP shows mould growth
which is pre-existing. The photograph does not show the fence has been structurally
affected. The insurer says the cash settlement for the building repairs includes $2,500
for a full external pressure clean and sanitise which it considers to be sufficient for the
mould treatment.
There is no dispute the area received a catastrophic flood. However, after careful
consideration of all the available information, the Panel is not persuaded that the
reason the fence is failing is due to the flood damage. Accordingly, the insurer can
decline the claim to replace the fence.
2.3 Is the complainant entitled to any compensation?
Compensation payable in some circumstances
AFCA may award compensation (capped at $5,000) if there has been an unusual
degree or extent of physical inconvenience, time taken to resolve a complaint or
interference with the complainant’s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to awarding compensation. We do not award
compensation because the complainant has suffered some inconvenience . AFCA
expects the complainant to be moderately robust and to bear the normal degree of
inconvenience experienced when a problem occurs and to take reasonable steps to
manage the situation.
The claim was made on 4 February 2019. The insurer responded quickly by
appointing a builder, a restorer and an assessor to assess the damage and undertake
the remediation works. The insurer had several opportunities to ascertain its liability.
The Panel considers the time between obtaining the first quote and the final quote, 13
August 2019 and 6 May 2020 respectively, was excessive.
The complainant says there were unnecessary delays and staff were unprofessional.
The complainant says she had to send the photographs and documents , regarding
the building fixtures, multiple times to the insurer.
In the circumstances, the Panel agrees there has been an unusual degree of physical
inconvenience caused by the claims process. Further, the claim ’ s decisions have
resulted in an unusual amount of time taken to resolve the situation which would have
interfered with the complainant’s expectation of enjoyment or peace of mind.
Determination | Case number: 686094 Page 7 of 9
Taking all matters into account, the Panel is satisfied it is fair the insurer pays the
complainant $1,250 for non-financial loss compensation.
Determination | Case number: 686094 Page 8 of 9
3 Supporting information
3.1 AFCA’s approach
A full exchange of the relevant information has taken place between the parties and
each party has had the opportunity of addressing any issue raised.
All the provided material has been read and considered. The parties have raised
numerous issues in their submissions. For this determination, commentary is
restricted to only those issues considered relevant to the outcome.
3.2 Key policy terms
Product Disclosure Statement
Pages Wording
26 - 28
Additional features
Temporary accommodation when you have home cover
We cover
When an insured event damages your home to the extent you cannot
live there, and we agree, we will pay for your reasonable temporary
accommodation costs for the time it will take to repair or rebuild your
home to a liveable condition. We will also pay for temporary
accommodation for your domestic pets in a commercial boarding
establishment for the same period that w e pay for your temporary
accommodation.
The most we will pay for is:
up to 4 weeks in short term accommodation agreed to by us
(e.g. standard rates for a hotel, motel or serviced apartment),
then if necessary up to another:
48 weeks in residential accommodation of a similar standard to
your home if you have Classic or Classic Extras cover
….
69
How we settle your claim
If we agree to pay a claim for loss, theft or damage to your home, we
will decide if we will:
Determination | Case number: 686094 Page 9 of 9
Pages Wording
repair damage to your home;
rebuild your home;
pay you what it would cost us to repair or rebuild your home;
pay you the sum insured for your home.
If we rebuild (or pay you what it would cost us to rebuild), we will do so
on a ‘new for old’ basis.
If we repair (or pay you what it would cost us to repair), we will at our
option do so on a ‘new for old’ basis or to a similar condition to what
your home was in before the loss or damage occurred.
We may offer you a voucher, store credit or stored value card for the
amount it would cost us to rep air or rebuild an item.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.