Home / QBE / Determination 685188
Determination 685188
Denial of water ingress damage claim relying on exclusions
Summary
A unit owner and beneficiary under a strata policy claimed for bathroom and bedroom damage from long-running water ingress, which the insurer denied under exclusions for corrosion and deterioration. AFCA found the insurer had not proven an exclusion and ordered the claim met, with interest if cash-settled.
The insurer bears the onus to prove an exclusion such as corrosion or gradual deterioration, and speculation about the cause does not discharge it.
Issues
- Claim denial primary · upheld“The insurer has not met its onus to establish it is entitled to rely upon exclusions within the policy to deny the complainant's claim.”
Subjects and remedies
home or building damagepay claimpay interest
Related
Text of the determination
Determination
Case number 685188
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 685188 Page 2 of 6
Case number: 685188 12 June 2020
1 Determination overview
1.1 Complaint
The complaint relates to a claim by the complainant under a Residential Strata
Insurance policy held with the financial firm (insurer) following damage to the
complainant’s home.
The complainant is not the insured but is a beneficiary under the insurance policy.
The insurer has denied the complainant’s claim and relies upo n exclusions from
coverage within the policy.
1.2 Issues and key findings
Is the insurer entitled to rely upon exclusions within the policy to deny the
complainant’s claim?
The insurer has not met its onus to establish it is entitled to rely upon exclusions
within the policy to deny the complainant’s claim.
1.3 Determination
This determination is in favour of the complainant.
The insurer is required to meet its obligations under the policy in relation to the
complainant’s claim.
The insurer’s obligations include reimbursement for the cost s associated with the
demolition and rebuilding of the complainant’s bathroom and attached bedroom.
If the insurer cash-settles the complaina nt’s claim, the insurer is required to pay
interest, in accordance with the Insurance Contracts Act 1984 (the Act), from the date
of denial of the claim to the date of payment.
Determination | Case number: 685188 Page 3 of 6
2 Reasons for determination
There has been a full exchange of all material information relied upon for the
purposes of this determination and each party has had the opportunity to address any
issues raised by the other. All the material provided by the parties has been reviewed
and considered.
The complaint has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions, where applicable.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
2.1 Is the insurer entitled to rely upon exclusions within the policy to deny
the complainant’s claim?
Coverage of the policy
The relevant Residential Strata Insurance policy provides coverage for accidental loss
or damage to the insured property that occurs during the period of insurance.
‘ Accidental ’ is not defined in the policy, but is taken to mean unforeseen, unintended
and unexpected.
The coverage provided by the policy is subject to exclusions which are detailed within
the policy documentation.
The exclusions detail that the insurer will not pay for loss or damage:
caused by lack of maintenance, rust, oxidation, corrosion, Wear, Tear,
…
gradual corrosion or gradual deterioration,
…
developing flaws,
…
or failure to maintain Your Insured Property in a reasonably good state of repair.
Further, the exclusions detail that the insurer will not pay for loss or damage:
caused by non-rectification of an Insured Property defect, error or omission that
You were aware of, or should reasonably have been aware of.
Determination | Case number: 685188 Page 4 of 6
It is accepted insurance law that the insured carries the initial onus to establish a loss
which is covered by the terms and conditions of the policy.
As stated, the policy covers accidental loss or damage to the insured property that
occurs during the period of insurance.
I am satisfied that the damage at the property was unforeseen, unintended and
unexpected and thus the complainant has met the onus to establish a loss which is
covered by the terms of the policy.
It is accepted insurance law that the insurer carries the onus to establish the
application of an exclusion on which it seeks to deny the complainant’s claim.
To deny the complainant’s claim, the insurer must esta blish that the loss and damage
to the property was due to corrosion, gradual deterioration, non-rectification of the
defect or defective workmanship.
Circumstances of the loss
The exchanged material confirms that from 2014 the complainant had noted severe
water ingress into his unit, originating from the unit 2 upstairs, after the owners of unit
2 renovated their bathroom.
The exchanged material includes several reports from plumbers and other experts
which, whilst offering opinions regarding the cause of the water ingress and the
source of the water ingress into the complainant’s unit, were unable to substantiate
either the cause or the source of the water ingress.
Given the exchanged material, I am satisfied that in March or April 2018, the
complainant was told to demolish the bathroom at his unit to find out where the water
was coming in and correct the problem.
Unfortunately, after completing this work, the water ingress into the complainant’s unit
continued.
In early 2019, the complainant and the plumber who carried out the 2018 renovations
to the complainant’s bathroom (LU), obtained permission to conduct invasive
investigation into the bathroom of Unit 2 , above the complainant’s unit.
LU advised:
Just wanted to confirm that the drainage pipe from Units 2 ’s bath and shower
which was embedded in the concrete has now been completely replaced. We
have made new connections to the PVC piping from bath and shower of unit 2
above and ran a new PVC drain outside with a new connection to the stack. We
ran all of the fixtures and the pipe is dry now. I will be looking forward to hearing
from you in the next weeks and confirming that all is dry and you can commence
the painting of your rooms.
Determination | Case number: 685188 Page 5 of 6
Based on all the exchanged material, I am satisfied that it was only at this time that
the source of the leak was discovered and repaired.
The insurer engaged a civil engineer (SA) to provide a report.
SA advised:
a) Based on the plumbing correspondence provided by (LU) the cause of the
water ingress to Unit 1 was a corroded cast iron waste pipe servicing the
shower and bath of Unit 2.
b) Corrosion of cast iron pipe fittings is a common occurrence of building of a
similar vintage and previously encountered by the writer.
c) Based on our moisture meter readings of the Bedroom wall, there is also
residual high moisture reading present adjacent to one of the external wall.
This is likely the result of a building defect, namely defective floor and/or
window flashing to around this area. No weep holes were identified to the
window above this area indicative of window flashing issue.
It is clear from the exchanged material that SA did not inspect the waste pipe which
SA says was corroded.
It is also clear from the correspondence from LU, that LU does not say that the pipe
was corroded, but simply that the pipe was replaced.
I accept that SA was unable to examine the pipe, as the repairs were completed by
LU and the pipe was not available to SA for its inspection.
However, having reviewed all the exchanged material and noting that the claim was
first lodged with the insurer well prior to the repair work being conducted by LU in
February 2019, I am satisfied that the complainant had kept the insurer advised of his
ongoing concerns and the fact there was a continuing ingress of water into his unit
and resultant damage.
Given that the ingress of water had been occurring for at least four years, it is neither
surprising nor unusual that the complainant would seek to continue to find a resolution
of the problem, particularly as it was contributing to health issues for himself and his
family.
Having reviewed all the exchanged material, I am satisfied that the complainant had
made the insurer aware of the ongoing repair effort.
As stated, the insurer carries the onus to establish the application of an exclusion to
deny the claim.
LU did not say that the piping was corroded.
Determination | Case number: 685188 Page 6 of 6
SA’s conclusion wa s speculation based upon what SA presumed to be the cause,
without knowing what the cause was, as it was not able to view the pipe question.
I consider that it is possible that when the owners of Unit 2 renovated their bathroom,
the pipe was defective at that point or the work at that time caused the fault.
I am satisfied that the actions of the complainant, in the circumstances, were
reasonable and could not have been avoided.
It is unclear to me as to why the insurer did not conduct its own invasive
investigations of the bathroom of Unit 2, to locate what it appears to be the source of
the problem as found by LU. But I accept that it is possible the owners of Unit 2 were
not prepared to allow invasive investigation at that time.
I am also satisfied that the complainant was unaware of any apparent defect. Indeed ,
the complainant had relied upon several plumbers and other experts who were also
unable to locate the cause of the problem.
This would extend to the absence of weep holes. There is no evidence that the
complainant was aware of, or a reasonable person in the circumstances would be
aware of, the absence of weep holes.
I am satisfied that the insurer has not met its obligation to establish the application of
an exclusion to deny the complainant’s claim.
The insurer is to meet the complainant’s claim under the terms and conditions of the
policy.
This would include the cost incurred by the complainant to demolish and rebuild the
bathroom and attached bedroom.
If the insurer cash-settles the claim, the insurer is to pay interest, in accordance with
the Act, from the date of denial of the claim to the date of payment.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.