Home / IAG / Determination 684945
Determination 684945
Delayed hail storm repairs and defective earlier repairs
Summary
A landlord's hail storm claim was accepted but repairs were defective and delayed about seventeen months. AFCA ordered the insurer to pay $5,000 for non-financial loss, after the insurer offered $500.
The insurer is responsible for its appointed repairers, and the unusual delay caused by its defective initial works supports non-financial loss compensation under the AFCA Rules.
Issues
- Delay primary · upheld“The time taken to finalise this claim is significantly unreasonable, approximately seventeen months after lodgement.”
- Repairs or contractors secondary · upheld“It is ultimately the responsibility of the insurer to manage its appointed repairers and contractors to ensure that works are done to the appropriate standards.”
Subjects and remedies
home or building damagenatural disasterpay non financial loss
Related
Text of the determination
Determination
Case number 684945
Financial firm Insurance Australia Limited
Determination | Case number: 684945 Page 2 of 6
Case number: 684945 20 May 2020
1 Determination overview
1.1 Complaint
The complainant holds a home building policy with the financial firm (insurer). On 21
December 2018, the complainant lodged a claim under the policy for hail and storm
damages to the insured property.
The insurer accepted the claim. However, the complainant is dissatisfied with the
repair quality and the delays to rectify the repairs.
1.2 Issues and key findings
Is the complainant entitled to compensation?
Based on the available material, the insurer’s handling of the claim has caused
significant inconvenience to the complainant and compensation is appropriate in the
circumstances.
1.3 Determination
This determination is in favour of the complainant.
The insurer is to arrange payment of $5,000 to the complainant by way of
compensation for non-financial loss, within 14 days of the complainant accepting this
determination.
Determination | Case number: 684945 Page 3 of 6
2 Reasons for determination
2.1 Is the complainant entitled to compensation?
Background to claim
On 21 December 2018, the complainant lodged a c laim with the insurer for hail and
storm damages to his rental property which had occurred the previous day. The
insurer accepted the claim.
The insurer appointed its labour hire company (T) to inspect and quote on the
damages. Following approval of a scope of works, T ’s subcontractor commenced
repairs on 29 March 2019 and completed repairs on 12 April 2019.
On 16 and 30 April 2019, the complainant raised concerns with the insurer about the
quality of repairs of the roof, damage to the wall paint and rendering from scaffolding,
and an awning which had not been replaced.
The insurer appointed an additional roofer (SM) to determine whether there were any
issues with the previous repairs. SM found rust marks to the roof sheetings, a skylight
that was too large for the opening, and flashings which were fitted incorrectly. SM said
the roof would need to be replaced with a full scaffold to commence works.
The insurer approved the replacement of the roof and resulting damages. In an email
to the insurer dated 2 August 2019, T explained that to rectify the works a scaffold
was required at the front and rear of the property, however due to the narrow footpath
and close proximity to powerlines, the installation of the scaffold required special
permits from the council and the electricity company (A). T said given the power lines
are the main network lines that service the whole street, application to A was a two to
three-month process.
On 6 August 2019, the complainant notified the insurer of moisture coming from the
roof flashing.
On 23 September 2019, the insurer advised the complainant that A was due to
disconnect the power on 20 November 2019, with scaffolding to go up the same day
and trades starting the first week of December 2019.
On 26 November 2019, the complainant called the insurer to advise that the scaffold
had not been installed and he had received no communication.
On 5 December 2019, T informed the insurer that A had attended but advised that the
entire street needed the power lines to be de-energised due to old cabling before
repairs could begin. It is understood that due to this unforeseen development, another
application was required to engage A’s attendance . T said it had spoken to the
complainant and advised that works to the home would commence in the second or
Determination | Case number: 684945 Page 4 of 6
third week of January 2020, with completion by the end of the first week of February
2020.
On 7 February 2020, the complainant says he received a call from the builder that
there would be a further delay of eight weeks due to A. The complainant advised that
water was continuing to leak and damage the property including the balcony.
On 11 May 2020, the complainant informed the Authority that he has not received a
commencement date for repairs.
The complainant says the ordeal has caused him significant stress, and that he is
dissatisfied with the lack of communication. He also says that he has attended the
property over forty times for building appointments and spent hours making calls and
sending follow up emails. Further, his tenants have been asking for a rent reduction
because of the state of the property and the tarps, ropes and sandbags that are
covering the property.
Insurer says delays outside of its control
The insurer has apologised to the complainant for any distress and inconvenience
experienced throughout the claims process.
The insurer acknowledges the delays in repairing the property and says that it has
offered to compensate the complainant for the previous faulty repairs by waiving the
claim excess of $300. It is understood this has been accepted by the complainant.
The insurer says that an initial waiting period of twenty-six weeks was enforced by A.
Nearing the end of this period, A pushed the date out a further eight weeks as it had
shut down due to an employee accident which resulted in a backlog of work.
The most recent update from A to T on file was on 15 April 2020. At this time, A
advised that it was yet to be given a scheduled date for the job and with Covid-19
there were changes with its staff resulting in delays.
The insurer says that the required safety measure of de -energising the power to the
property by A prior to carrying out the repairs is outside the control of the insurer and
T.
Under the policy, the insurer provides a lifetime guarantee when the home is repaired
by one of its preferred repairers.
The insurer says it has requested that T provided regular routine advice until the
satisfactory completion of repairs to the property.
The insurer says it has also offered a cash settlement so the complainant can engage
the repairer of his choice. It is unclear what this offer was.
Determination | Case number: 684945 Page 5 of 6
In its most recent correspondence to the Authority, the insurer offered $500 to the
complainant in a full and final effort to resolve the complaint.
AFCA may award compensation in certain circumstances
Under our Rules, AFCA may award compensation for non-financial loss (capped at
$5,000) where there has been an unusual amount of:
physical inconvenience
time taken to resolve the situation
interf erence with the complainant’s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to compensation and expects a complainant to
bear a normal degree of inconvenience during the course of the claim.
Insurer to pay compensation
I acknowledge that the complainant’s policy does not provide coverage for non-
financial loss or compensation for inconvenience.
I also acknowledge that some unforeseen circumstances have arisen with A.
However, I note that approximately seventeen months ha ve passed since the claim
was lodged. Having considered the available information, such as the claim file notes,
timelines, emails between the parties, the time it has taken to finalise this claim is
significantly unreasonable.
Further, there is no information to suggest that the original damage and associated
repairs were of a particularly complex nature. It is ultimately the responsibility of the
insurer to manage its appointed repairers and contractors to ensure that works are
done to the appropriate standards. If not for the initial defective works, it is likely the
delays experienced by the complainant would not have eventuated.
Accordingly, I consider it would be fair in all the circumstances for the insurer to pay
the complainant $5,000 in non-financial loss compensation under the claim.
The insurer is also requested to provide regular updates to the complainant regarding
a commencement date for repairs. The parties are asked to work cooperatively
together to agree as to the satisfactory completion of repairs, including resulting
damage, to the property.
If the parties are unable to reach agreement as to the satisfactory completion of
repairs, then the parties may return the matter to the Authority for further
determination.
Determination | Case number: 684945 Page 6 of 6
3 Supporting information
3.1 AFCA approach to this complaint
This complaint has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions of AFCA or its predecessor schemes (which are not binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised.
All of the provided material has been reviewed and considered. The parties have
raised numerous issues in their submissions to AFCA. However, commentary in this
determination is restricted only to those issues considered relevant to the outcome.
3.2 Relevant policy terms
Exclusions for all cover (page 53 of PDS)
These exclusions apply to all cover under your policy
What we don't cover
…
compensation for distress, inconvenience or other non financial loss,
except if covered under liability cover
consequential financial loss – for example, loss of profits, except if
covered under liability cover.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.