Determination 684756

Cash settlement after fire: sum insured adequacy and additional benefits

FirmAuto & General
Decided2020-08-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,664
Non-financial loss—
Amount claimed$482,452
SourceAFCA PDF

Summary

A homeowner whose home was damaged by fire disputed the cash settlement, which was based on a $250,000 sum insured after she relied on an online estimator. AFCA accepted the sum insured limited liability but ordered payment of the debris benefit shortfall, temporary accommodation and an asbestos test invoice.

The insurer may rely on the sum insured where the complainant cannot show the estimator produced the underinsurance, but additional benefits and reimbursable costs are payable.

Issues

Subjects and remedies

home or building damagepay claimpay compensation

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination Case number 684756 Financial firm Auto & General Services Pty Ltd Determination | Case number: 684756 Page 2 of 7 Case number: 684756 6 July 2020 1 Determination overview 1.1 Complaint The complainant took out a home insurance policy with the financial firm (the insurer) online in August 2019. She says she used the estimator tool offered by the insurer to calculate how much it would cost to rebuild her home. This said $250,000. Therefore, she nominated a sum insured of $250,000. The complainant lodged a claim with the insurer after her home was substantively damaged by fire in October 2019. The insurer accepted her claim and calculated the cost to rebuild her home at $482,452. Given this, the insurer decided to cash settle the complainant the full sum insured of $250,000, plus $30,482.91 for other costs covered by her policy. The complainant disputes the settlement amount. She says the insurer should pay the full cost to rebuild her home because its estimator misled her into underinsuring. The complainant also says the insurer’s allowance for temporary accommodation was insufficient and the insurer should reimburse her the cost of an asbestos test. 1.2 Issues and key findings Is the insurer’ s offer fair? The insurer is not required to pay more than the sum insured for the building repairs. This is because the available information does not show that the reason the lower sum insured was placed on the policy was due to an error made by the estimator tool. The insurer should pay for the additional benefits of removal of debris and temporary accommodation as set out in section 2.1. Further, the insurer should reimburse an asbestos test paid for by the complainant subject to the production of a n invoice. 1.3 Determination This determination is partially in favour of the complainant. The insurer is to settle the claim as set out in section 2.1. Determination | Case number: 684756 Page 3 of 7 2 Reasons for determination 2.1 Is the insurer’s offer fair? Complainant took out her policy online The complainant took out her policy online in August 2019. The complainant says that when she set the sum insured, she relied upon an estimator that was available through the insurer’s website. When selecting to use the estimator, the customer is taken to a separate website owned by a separate company. The estimator requires the customer to:  type in their address so it can display any data it has for their house  agree to the terms of use  manually enter the original year built  update mandatory and optional pre-filled questions about the construction of their home. The estimated cost to rebuild the customer’s home appears at the end of the webpage. The page also gives them an option to download or email themselves a copy of the estimation, including the data they entered. The customer is then required to go back to the insurer’s website to manually enter a sum insured. Insurer can rely on the sum insured The complainant was asked for a copy of the report when she took out the po licy. However, she unfortunately did not save it at the time. The complainant attempted to recreate the report on 16 April 2020. This does not support her position as that report provided an estimate of $603,913. Given this, the panel has no document or o ther evidence to show:  the complainant used the estimator at the time of arranging the policy, and  if she did > that she entered the correct data into the estimator, and > based on this correct data, the estimator provided an estimate of $250,000 Therefore, the panel does not accept there is sufficient basis to conclude that the reason the complainant underinsured the home was due to an error made by the estimator. Accordingly, this argument does not assist the complainant. The insurer is entitled to rely on the policy sum insured of $250,000. Determination | Case number: 684756 Page 4 of 7 Insurer to pay the maximum removal of debris benefit The insurer’s settlement email dated 27 March 2020 set out what it would pay. This included the sum insured for the building repairs as well as the following:  $21,951.60 for the demotion quote  $ 857.05 for ‘Remaining removal of debris benefit’  $2,144.26 for temporary accommodation from 18 February 2020 to 27 March 2020  $5,530 for 14 weeks temporary accommodation The insurer then deducted the excess, remaining premiums and payments already made from the total. There is no dispute the insurer is entitled to make these deductions. The panel will deal with temporary accommodation below. The policy provides an additional benefit for ‘Remova l of debris and extra costs of rebuilding’. This benefit includes removing home debris, demolition of the home, securing the home, reasonable fees for the services of an architect, surveyor or engineer and building application fees. The maximum amount payable is 10% of the sum insured. In this case, that is $25,000. This is payable in addition to the sum insured. The amount allowed by the insurer’s settlement is short of this total by $2,191.35. The insurer has not clarified if other costs were paid under this benefit. This may include the installation of temporary fencing. If the insurer can show that it has spent this shortfall already, then no further amount is payable. Otherwise, the insurer should pay the shortfall. This is because it is likely the complainant will incur professional fees and a building application fee that would exceed this shortfall. How temporary accommodation should be paid The policy provides temporary accommodation up to a maximum of 10% of the sum insured, being $25,000. This benefit is in addition to the sum insured. The insurer has recently agreed to pay 26 weeks temporary accommodation. This is presumably from 27 March 2020, being when the insurer offered to pay the sum insured. The complainant is concerned rebuilding her home may take more than six months in the current circumstances with Covid-19. At this point, the panel does not consider it necessary to increase the amount given there is no clear indication that the repairs will take longer than this. Determination | Case number: 684756 Page 5 of 7 If, however, the home is not rebuilt within the allowable timeframe, then it is fair for the insurer to continue to cover the complainant’s reasonable additional temporary accommodation costs. The insurer must do so until the earliest of the following:  the $25,000 sum insured is exhausted,  12 months has passed from the date of settlement, or  the home has been rebuilt. This is subject to the complainant ensuring she is making reasonable attempts to progress the repairs. The panel notes this benefit includes a 12 month limit from when the damage occurred. This would be reached on 16 October 2020. The panel does not accept it is fair or reasonable for the insurer to rely upon this provision given the building sum insured was not paid until more than five months after the claimed event. This meant the complainant had no opportunity to begin repairs before then. Instead, it is fair for the 12 months to begin from when payment was issued. Similarly, the panel does not accept the sum insured should include any payment made before the cash settlement was issued. This is because:  payment was not made until more than five months after the loss,  there is no dispute the complainant had no means to begin repairs until settlement was made,  if the insurer could deduct any payments already made under this benefit from the sum insured, this could result in the complainant exhausting her sum insured well before the repairs are complete This cannot be fair or consistent with the intent of this cover. Instead, the panel considers it is fair in all the circumstances the sum insured should be based on the temporary accommodation paid from the time the insurer cash settled the claim. Insurer should reimburse asbestos test invoice In an email dated 30 March 2020, the complainant noted she had to pay for an asbestos test ($472.56). She says this did not need to be incurred as it was already done. The insurer has not responded to this or disputed her position. Given it appears this was a cost the complainant did not need to incur, then this should be reimbursed by the insurer. This is subject to the complainant producing an invoice. Determination | Case number: 684756 Page 6 of 7 3 Supporting information 3.1 Policy wording Sum insured Temporary accommodation Determination | Case number: 684756 Page 7 of 7 3.2 Other evidence Screenshot of insurer offering estimator from complainant (de-identified)