Determination 684756
Cash settlement after fire: sum insured adequacy and additional benefits
Summary
A homeowner whose home was damaged by fire disputed the cash settlement, which was based on a $250,000 sum insured after she relied on an online estimator. AFCA accepted the sum insured limited liability but ordered payment of the debris benefit shortfall, temporary accommodation and an asbestos test invoice.
The insurer may rely on the sum insured where the complainant cannot show the estimator produced the underinsurance, but additional benefits and reimbursable costs are payable.
Issues
- Claim amount dispute primary · upheld
“The insurer should pay the shortfall in the removal of debris benefit, continue temporary accommodation and reimburse the asbestos test subject to an invoice.”
- Misleading conduct secondary · not upheld
“The panel does not accept there is sufficient basis to conclude that the reason the complainant underinsured the home was due to an error made by the estimator tool.”
Subjects and remedies
home or building damagepay claimpay compensation
Text of the determination
Determination
Case number 684756
Financial firm Auto & General Services Pty Ltd
Determination | Case number: 684756 Page 2 of 7
Case number: 684756 6 July 2020
1 Determination overview
1.1 Complaint
The complainant took out a home insurance policy with the financial firm (the insurer)
online in August 2019. She says she used the estimator tool offered by the insurer to
calculate how much it would cost to rebuild her home. This said $250,000. Therefore,
she nominated a sum insured of $250,000.
The complainant lodged a claim with the insurer after her home was substantively
damaged by fire in October 2019. The insurer accepted her claim and calculated the
cost to rebuild her home at $482,452. Given this, the insurer decided to cash settle
the complainant the full sum insured of $250,000, plus $30,482.91 for other costs
covered by her policy.
The complainant disputes the settlement amount. She says the insurer should pay the
full cost to rebuild her home because its estimator misled her into underinsuring. The
complainant also says the insurer’s allowance for temporary accommodation was
insufficient and the insurer should reimburse her the cost of an asbestos test.
1.2 Issues and key findings
Is the insurer’ s offer fair?
The insurer is not required to pay more than the sum insured for the building repairs.
This is because the available information does not show that the reason the lower
sum insured was placed on the policy was due to an error made by the estimator tool.
The insurer should pay for the additional benefits of removal of debris and temporary
accommodation as set out in section 2.1. Further, the insurer should reimburse an
asbestos test paid for by the complainant subject to the production of a n invoice.
1.3 Determination
This determination is partially in favour of the complainant.
The insurer is to settle the claim as set out in section 2.1.
Determination | Case number: 684756 Page 3 of 7
2 Reasons for determination
2.1 Is the insurer’s offer fair?
Complainant took out her policy online
The complainant took out her policy online in August 2019. The complainant says that
when she set the sum insured, she relied upon an estimator that was available
through the insurer’s website.
When selecting to use the estimator, the customer is taken to a separate website
owned by a separate company. The estimator requires the customer to:
type in their address so it can display any data it has for their house
agree to the terms of use
manually enter the original year built
update mandatory and optional pre-filled questions about the construction of their
home.
The estimated cost to rebuild the customer’s home appears at the end of the
webpage. The page also gives them an option to download or email themselves a
copy of the estimation, including the data they entered. The customer is then required
to go back to the insurer’s website to manually enter a sum insured.
Insurer can rely on the sum insured
The complainant was asked for a copy of the report when she took out the po licy.
However, she unfortunately did not save it at the time.
The complainant attempted to recreate the report on 16 April 2020. This does not
support her position as that report provided an estimate of $603,913.
Given this, the panel has no document or o ther evidence to show:
the complainant used the estimator at the time of arranging the policy, and
if she did
> that she entered the correct data into the estimator, and
> based on this correct data, the estimator provided an estimate of $250,000
Therefore, the panel does not accept there is sufficient basis to conclude that the
reason the complainant underinsured the home was due to an error made by the
estimator.
Accordingly, this argument does not assist the complainant. The insurer is entitled to
rely on the policy sum insured of $250,000.
Determination | Case number: 684756 Page 4 of 7
Insurer to pay the maximum removal of debris benefit
The insurer’s settlement email dated 27 March 2020 set out what it would pay. This
included the sum insured for the building repairs as well as the following:
$21,951.60 for the demotion quote
$ 857.05 for ‘Remaining removal of debris benefit’
$2,144.26 for temporary accommodation from 18 February 2020 to 27 March 2020
$5,530 for 14 weeks temporary accommodation
The insurer then deducted the excess, remaining premiums and payments already
made from the total. There is no dispute the insurer is entitled to make these
deductions.
The panel will deal with temporary accommodation below.
The policy provides an additional benefit for ‘Remova l of debris and extra costs of
rebuilding’. This benefit includes removing home debris, demolition of the home,
securing the home, reasonable fees for the services of an architect, surveyor or
engineer and building application fees.
The maximum amount payable is 10% of the sum insured. In this case, that is
$25,000. This is payable in addition to the sum insured.
The amount allowed by the insurer’s settlement is short of this total by $2,191.35. The
insurer has not clarified if other costs were paid under this benefit. This may include
the installation of temporary fencing.
If the insurer can show that it has spent this shortfall already, then no further amount
is payable. Otherwise, the insurer should pay the shortfall. This is because it is likely
the complainant will incur professional fees and a building application fee that would
exceed this shortfall.
How temporary accommodation should be paid
The policy provides temporary accommodation up to a maximum of 10% of the sum
insured, being $25,000. This benefit is in addition to the sum insured.
The insurer has recently agreed to pay 26 weeks temporary accommodation. This is
presumably from 27 March 2020, being when the insurer offered to pay the sum
insured.
The complainant is concerned rebuilding her home may take more than six months in
the current circumstances with Covid-19.
At this point, the panel does not consider it necessary to increase the amount given
there is no clear indication that the repairs will take longer than this.
Determination | Case number: 684756 Page 5 of 7
If, however, the home is not rebuilt within the allowable timeframe, then it is fair for the
insurer to continue to cover the complainant’s reasonable additional temporary
accommodation costs. The insurer must do so until the earliest of the following:
the $25,000 sum insured is exhausted,
12 months has passed from the date of settlement, or
the home has been rebuilt.
This is subject to the complainant ensuring she is making reasonable attempts to
progress the repairs.
The panel notes this benefit includes a 12 month limit from when the damage
occurred. This would be reached on 16 October 2020. The panel does not accept it is
fair or reasonable for the insurer to rely upon this provision given the building sum
insured was not paid until more than five months after the claimed event. This meant
the complainant had no opportunity to begin repairs before then.
Instead, it is fair for the 12 months to begin from when payment was issued.
Similarly, the panel does not accept the sum insured should include any payment
made before the cash settlement was issued. This is because:
payment was not made until more than five months after the loss,
there is no dispute the complainant had no means to begin repairs until settlement
was made,
if the insurer could deduct any payments already made under this benefit from the
sum insured, this could result in the complainant exhausting her sum insured well
before the repairs are complete
This cannot be fair or consistent with the intent of this cover.
Instead, the panel considers it is fair in all the circumstances the sum insured should
be based on the temporary accommodation paid from the time the insurer cash
settled the claim.
Insurer should reimburse asbestos test invoice
In an email dated 30 March 2020, the complainant noted she had to pay for an
asbestos test ($472.56). She says this did not need to be incurred as it was already
done.
The insurer has not responded to this or disputed her position.
Given it appears this was a cost the complainant did not need to incur, then this
should be reimbursed by the insurer. This is subject to the complainant producing an
invoice.
Determination | Case number: 684756 Page 6 of 7
3 Supporting information
3.1 Policy wording
Sum insured
Temporary accommodation
Determination | Case number: 684756 Page 7 of 7
3.2 Other evidence
Screenshot of insurer offering estimator from complainant (de-identified)