The complainants said the bank released two progress payments to the builder based on inaccurate valuation reports, and the builder then abandoned an incomplete build. AFCA dismissed the complaint and ordered no compensation.

The complainants signed progress payment instructions authorising the payments, so the bank was contractually entitled to act on them and had no duty to share its valuation reports.

Issues

Subjects and remedies

no remedy

Related

All ANZ determinations · Find similar determinations

Text of the determination

Determination Case number 683935 Financial firm Australia and New Zealand Banking Group Limited Determination | Case number: 683935 Page 2 of 9 Case number: 683935 7 August 2020 1 Determination overview 1.1 Complaint In 2016, the financial firm (bank) provided the complainants with construction loan ending 342 (loan). The purpose of the loan was to refinance and existing loan and to provide funds for the complainants to construct a house at their L property. The loan was intended to be paid progressively to fund the construction works with the builder. The complainants say that the bank released the following progress payments to the builder upon receipt of an incorrect valuation reports:  brickwork stage (Brickwork) for $150,648.60 paid on 27 July 2017  lock up stage (Lock Up) for $150,648.60 paid on 25 November 2017 The builder abandoned the building site after receiving the Lock Up payment. The building remains incomplete and the complainants are seeking financial compensation. On 30 April 2020, an Australian Financial Complaints Authority (AFCA) case manager provided the parties with a recommendation on the issues in dispute. The recommendation was in favour of the bank and a copy of it has been attached to this determination. The complainants rejected the recommendation. 1.2 Issues and key findings Were the findings of the recommendation correct? The findings contained in the recommendation were correct and are adopted in this determination. Further submissions provided after the recommendation have been considered, but do not change the outcome for the reasons set out in section 2 below. Do the complainants’ further submissions change the outcome? For the reasons set out in section 2 below, the recommendation was fair in all of the circumstances and having regard to AFCA‟s approach and the information provided by both parties. The complain ants‟ further submissions do not change the outcome. The complainants provided the bank with signed progress payment instruction (PPI) forms for the release of the Brickwork and Lock Up progress payments. 1.3 Determination This determination is in favour of the bank. The bank is not required to pay any compensation to the complainants. Determination | Case number: 683935 Page 3 of 9 2 Reasons for determination 2.1 Were the findings in the recommendation correct? The recommendation was accurate I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous AFCA decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the case manager‟s recommendation contains an accurate summary of the complaint, the issues to be determined, any applicable paragraphs of the Rules and any relevant law. Based on all the available information, I am satisfied the recommendation was fair in all circumstances, having regard to our usual approach. As the recommendation adequately dealt with the issues the complainants raised, and I agree with its findings, it is adopted into this determination. The recommendation was in the bank’s favour The key findings in the attached recommendation include:  the bank paid the progress payments in accordance with the progress payment instruction (PPI) forms signed by the complainants  in completing and signing the PPI forms, the complainants instructed the bank to pay the builder  the PPIs also included an acknowledgement that the work completed by the builder was to the complainants‟ satisfaction, was in accordance with the building contract and sufficient work had been completed to cover the progress payment  the complainants had raised their concerns about the builder with their mortgage broker (PF), but did not tell the bank of any of these concerns  the bank ordered, and obtained, progress inspection valuations and was entitled to rely on their contents  the progress inspection valuations are conducted for the bank‟s own purposes, and  the available information did not support that the bank had breached the 2013 Code of Banking Practice (CBP). Determination | Case number: 683935 Page 4 of 9 The complainants rejected the recommendation The complainants have rejected the recommendation for several reasons including:  the recommendation did not accurately reflect the issues in their complaint  the bank relied on inaccurate progress inspection valuation reports to release the two payments to the builder  they are not satisfied that the valuer held the appropriate qualifications to complete the valuation reports  the recommendation did not address the external findings of the building inspection report and quantity surveyor report, and  the bank failed in the prudential obligations that it owed to them. After reviewing the available information from both the parties, I am satisfied the conclusions in the recommendation were accurate and fair. I agree with the findings in the recommendation and adopt them as part of this determination. As I have attached the recommendation to this determination, I have not repeated all of those findings here. However, I do have the following additional comments to make on the issues whi ch the complainants have raised which I hope will assist them to understand the reasons why I have not upheld their complaint. 2.2 Do the complainants ’ further submissions change the outcome? The complainants say the recommendation was not an accurate The complainants say:  the recommendation was not an accurate representation of their complaint  their complaint is about the conduct of the bank in requesting and conducting two inspection valuation reports, that can now be seen as being inaccurate and erroneous  those reports had an impact on the fixed price building contract. The complainants say that they were expecting AFCA to investigate, address and make a decision on the following:  inaccurate progress inspection valuation reports and the qualification and selection of the valuers  the actions taken by the bank after receiving the inaccurate valuation reports and the impact on their loan  the bank ‟ s procedures and conduct throughout the entire loan I will address these points in more detail below. Determination | Case number: 683935 Page 5 of 9 How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to contemporaneous documentary info rmation (that is, documents prepared at the time of the event). AFCA cannot rule on the valuation reports My determination of this complaint must be fair and impartial and within my powers under AFCA‟s operating Rules. As was explained in detail in the case manager‟s recommendation, the bank‟s valuation is for its own purposes. That is, a valuation is obtained to satisfy the bank that it has adequate security to secure the funds that it advances to a consumer. I cannot provide a ruling or issue a decision on the issue of the contents of the inspection valuation reports and the qualification and selection of the valuers because:  AFCA does not have the expertise to determine whether a valuation accurately reflected the value of the security property when it was valued. We do not have a team of valuers  AFCA‟s operating rules do not give me the power to review the bank‟s business decision and it was a business decision for the bank as to whether it accepted the inspection valuation reports  AFCA is not a regulator of the banking industry. I cannot review the bank‟s business operations and policies relating to the appointment and qualifications of bank-approved panel valuation firms. The complainants authorised the bank to release the payments The complainants provided the bank with the required signed PPI forms along with two builder invoices for the Brickwork and Lock Up payments. In signing the PPI forms, the complainants acknowledged that it was not the bank ‟ s responsibility to ensure that  the quality of the work is to the complainants‟ satisfaction  the work was done in accordance with the building contract  sufficient work had been done to cover the progress payments. If a person signs a document that they know contains contractual terms and which they understand will affect their legal relationship with the bank, then the person is legally bound by those terms. It is irrelevant whether or not the person read the document before signing it. Determination | Case number: 683935 Page 6 of 9 The bank has not made an error in releasing the Brickwork and Lock Up stage progress payment claims. The bank was contractually entitled to act in reliance on the PPI forms. The bank is not required to compensate the complainants. The bank requested progress inspection valuation reports The complainants say that the bank requested an extra inspection that was not included in the signed loan contract, and that makes the bank liable for its actions taken upon receiving the report. The complainants say the bank chose not to review it and allowed the payment process to be completed. The bank has provided its internal policy to AFCA describing when a progress inspection valuation is required. I have reviewed this information and I am of the view that the bank has followed its procedures correctly. In the case of a standard fixed price progress payment schedule, the bank determines that a progress inspection valuation report is required at frame and lock up stage. Historically these stages represent the greatest costs overall in the building contract. In the circumstances of this complaint, the complainant and the builder agreed to a non-standard progress payment schedule. This meant the building contract did not include a frame stage. The bank decided that a progress payment inspection would be required for the Brickwork and Lock up stages (each $150,648.60) as they represented the largest payments to be made within the contract. Valuations are for the bank ’ s purposes only A bank valuation is an assessment of the value of the property used as security for a debt in case it has to sell that property to recover the debt. When a bank is lending for a construction of a new home, it obtains two different types of valuation reports. At the time of assessing the loan application the bank obtains an “as -if complete ‟ valuation. The bank provides copies of the council- approved building plans and building contract to an approved panel valuation firm. The valuer considers all the information and provide the bank with an “as -if final ” valuation figure. The bank uses the valuation to confirm the lending margins involved in lending the money. The bank usually obtains progress payment inspection valuation reports during the construction of the property. These valuations are for the bank ‟ s purposes only. The bank was not under any obligation to disclose the findings of the valuation report to the complainants. Determination | Case number: 683935 Page 7 of 9 The complainants ’ broker provided them with incorrect information The complainants had engaged the services of PF to assist them with obtaining the loan. The available information shows that during the building process, the complainants relied heavily on the advice of PF. The recommendation found that the complainants had emailed photographs of the build and sought PF‟s advice whether they should make the brickwork payment. At the time, PF suggested that the complainants should seek the professional services and advice of an architect. This was to ensure that the building works were completed in accordance with the building plans and contract terms. By the time the Lock Up payment invoice was issued by the builder, the build date specified in the building contract had expired. It appears that the complainants acknowledged that the works to complete the Lock Up payment had not been completed satisfactorily, however the builder was placing pressure on them to make the payment. I acknowledge that this would have been a very stressful and unsettling time for the complainants. Instead of contacting the bank to advise of their situation, the complainants again sought advice from PF. PF advised that given the building works were delayed, the bank most likely would order a valuation report which would co nfirm the complainants‟ concerns and the bank would withhold the payment. PF was not an employee of the bank and was not aware of the bank ‟ s internal policy and procedures. PF provided the complainants with incorrect information on which they relied upon and forwarded the signed PPI form directly to the bank. The complainants did not raise any concerns directly to the bank after the payments were made On 27 July 2017 (Brickwork) and 27 November 2017 (Lock Up) payments were released by the bank and paid to the builder. The bank did not make an error in releasing these payments as the complainants had provided consent by signing the PPI form. The bank had not received any other instructions from the complainants to withhold payment from the builder. Because the complainants expected the bank to receive a valuation report confirming that the works were incomplete and withhold the payment, it would have been appropriate for the complainants to contact the bank immediately after the payment was made to complain. The complainants did contact the bank in March 2018, as they were concerned about the quality of the workmanship competed by the builder. The bank provided appropriate assistance to the complainants. This included providing the website details of the building dispute resolution services and suggested that the complainants should obtain an engineer‟s report to support any claims. Determination | Case number: 683935 Page 8 of 9 The independent professional reports were obtained in 2019 In rejecting the recommendation, the complainants say the case manager did not take into account the following professional reports  Quantity Surveyor Report (RV) dated 16 May 2019, and  Expert Evidence Report (IF) dated 16 July 2019. In assessing a complaint, AFCA can only review the available documentation at the time the event occurred. In this case the progress payments were released to the builder in 2017. I understand that the complainants have obtained the Expert Evidence Report to pursue a separate claim lodged with VCAT against the builder for defective building works. It is considered good industry practice for a bank to obtain an independent Quantity Surveyor (QS) Report when a building contract is terminated, and the build remains incomplete. The RV was commissioned by the Customer Advocate of the bank to enable him to complete his report to determine the costs required to complete the build of the L property. In 2020, the L property remains incomplete. The bank was not responsible for the quality and finish of the building works The complainants say the bank relied upon inaccurate inspection valuation reports when they released the Brickwork and Lock Up payments. The complainants may have wanted the bank to assume responsibility for ensuring that the building works were completed. However, at no time did the bank agree to do so. It was not the bank‟s role to project manage the build – its role was to lend the money to the complainants. The complainants were responsible to check on the progress of the building works at the L property. If they did not feel comfortable with the progress of the work or the workmanship, it was up to them to engage expert advice and to decline to sign progress payment requests . I have a lot of sympathy for the position the complainants now find themselves in. However, I am not satisfied this is not because of the bank‟s actions. The complainants failed to protect their own position when they signed and submitted the PPI forms to the bank to release the payment to the builder. The bank acted appropriately in releasing the progress payments. The complainants had an opportunity to discuss their concerns with the bank directly but chose not to do so. Determination | Case number: 683935 Page 9 of 9 3 Supporting information 3.1 AFCA approach to this complaint This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted only to those issues considered relevant to the outcome. Recommendation Case number 683935 Financial firm Australia and New Zealand Banking Group Limited Recommendation | Case number: 683935 Page 2 of 12 Case number: 683935 30 April 2020 4 Overview 4.1 Complaint This complaint is about the conduct of the financial firm (bank) in releasing two progress payments to a builder under a fixed price building contract. The payments were for:  brickwork stage (Brickwork) for $150,648.60 paid on 27 July 2017  lock up stage (Lock Up) for $150,648.60 paid on 25 November 2017 The complainants (Mr L and Mrs LA) say the bank relied upon inaccurate progress inspection valuation reports and released funds to the builder. The builder abandoned the building site after receiving the lock up stage payment. The building remains incomplete, and the complainants are seeking financial compensation. 4.2 Issues and key findings Did the bank breach any obligation it owed to the complainants when it paid the progress payments to the builder? The bank did not breach any obligation it owed to the complainants when it paid the progress payment claims to the builder. The bank:  paid the progress payment claims in accordance with the amounts identified on the fixed price building contract for the Brickwork and Lock Up stages  made the payment at the complainants‟ request  obtained a progress payment certificate from a suitably qualified valuer for the Lock Up payment who stated that all of the work to date had been completed satisfactorily. Did the bank comply with the Code of Banking Practice? The bank complied with the 2013 Code of Banking of Practice (Code), and its staff were adequately trained to provide financial services and products. The prudent and diligent banker test of the code did not extend to providing advice on the contents of the Building Contract. What is an appropriate outcome to this complaint? The bank is not required to compensate the complainants. Recommendation | Case number: 683935 Page 3 of 12 The bank has advised its previous offer of compensation totalling $25,000 and an extension of interest only terms is available to Mr L and Mrs LA. 4.3 Recommendation This recommendation is in favour of the bank. The bank is not required to compensate the complainants. If either party rejects this recommendation, the complaint will progress to the final stage of our process, where an ombudsman will issue a final Determination. Alternatively, given the findings of this recommendation, the complainants should consider the bank‟s offer of $25,000 and an extension of the interest only terms. Recommendation | Case number: 683935 Page 4 of 12 5 Reasons for recommendation 5.1 Did the bank breach any obligation it owed to the complainants when it paid the progress payments to the builder? The bank paid the progress payment claims correctly Based on the available information, the bank released the progress payments correctly as it:  received a signed progress payment instruction (PPI) form from the complainants  confirmed the progress payment matched the building contract  received an independent progress payment valuation report (Lock up) from a panel valuer that confirmed the amount of work completed matched the building contract. This is discussed in further detail below. The complainants signed the PPIs On 20 July 2016, the complainants signed a loan contract with the bank. It specified the loan amount as $931,000. The loan contract was subject to the bank‟s consumer lending terms and conditions (conditions). The conditions say progress payments will only be made where the request is accompanied by a completed PPI. The available information shows that on 26 July 2016 the bank issued a letter to the complainants congratulating them on starting their home construction. The letter outlined “things you need to know”. Included in this letter were instructions on how to complete and submit the progress payment instruction forms. This letter also provided information to the borrower about Progress Payments: If at any stage you do not want to make a payment to your builder, simply do not sign the Progress Payment Instruction form, and notify […] immediately by phon e and writing The available information shows the bank received signed PPI forms from the complainants with the builder‟s invoice attached for both the Brickworks and the Lock up progress payment claims. The PPI forms did not include any additional comments or instructions under section 4 from the complainants. In completing and submitting the PPI forms to the bank, the complainants instructed the bank to pay the builder. As set on the PPI forms, the complainants signed the forms acknowledging:  the quality of work had been done to their satisfaction  the work done is in accordance with the building contract Recommendation | Case number: 683935 Page 5 of 12  sufficient work has been done to cover the progress payments. The bank was entitled to rely on the signed PPI forms to release funds to the builder. The progress payments matched the building contract The building contract specified that the total cost for the building contract including GST was $502,162, but the contract included a warning that the fixed price may vary and provided some examples of when this may occur. The contract required the builder to be paid in six stages, also known as progress payments. The contract identified each of the six stages and provided a monetary amount for each. In addition, the contract provided a percentage allocation for each payment which was aligned to the total building costs. Mr L & Mrs LA and the builder agreed on a schedule 3 – method 2 payment structure. This differed from the standard fixed progress payment descriptions as under Section 40 of the Domestic Building Contracts Act 1995. The bank therefore had a fixed price building contract without a Frame or Final stage description. A copy of the schedule can be found at section 3.1 below. The available information shows the PPI forms received by the bank for the Brickwork and Lock up payments in 2017 matched the amount noted in the building contract of $150,648.60 for each stage. There were no discrepancies presented which would have raised a red flag for the bank to further investigate, before releasing the payments to the builder. The complainants did not disclose concerns about the works to the bank The available information shows the complainants had concerns during the construction about the builder and work completed on site. On 22 July 2017, the complainant s‟ mortgage broker (PF) replied via email to Mrs LA about the brickworks progress payment claim. In the email, PF says: If you feel the work hasn‟t been completed, then I wouldn‟t pay. However, if the brickwork is complete, then I think you should pay… So you sort have to trust that the builder is doing the right thing. This is where an Architect comes in very handy, as they would normally do these checks for you and give confidence that the works have been completed. On 24 July 2017, the complainants subm itted the builder‟s invoice along with a signed PPI form to the bank for payment. They did not share any concerns about the build with the bank. Recommendation | Case number: 683935 Page 6 of 12 On 2 November 2017, the builder issued its invoice for the Lock Up payment to Mr L and Mrs LA. The available information again shows the complainants did not feel the works had reached lock up stage. Mrs LA sought advice from PF as to what they should do regarding the payment. It appears the conclusion reached with PF was to send the signed PPI form and invoice to the bank. PF advised that given the building works were delayed, the bank most likely would order a valuation report which would confirm the comp lainants‟ concerns and the bank would withhold the payment. On 16 November 2017, the complainants forwarded a signed PPI form and attached the builder‟s invoice to the bank for the Lock Up payment. No other supporting notes were attached to this PPI form to alert or update the bank as to their concerns. The bank‟s contact notes for this time show PF made multiple calls to the bank on the complainants‟ behalf to enquire about the status of the valuation report and when the bank expected to receive it. The notes show PF spoke to multiple bank staff. However, the notes do not show PF indicated the urgency around the valuation report was due to the complainants‟ concerns with the works completed to date. Furthermore, the banks Consumer Lending terms and conditions say: Please note that you are responsible for making sure that specifications of the builder‟s contract are completed by the builder Aside from raising their concerns with PF, it does not appear that Mr L and Mrs LA shared their concerns with the bank or asked it to withhold the progress payment from the builder until the works were completed to their satisfaction. The bank ordered progress inspection valuations The bank‟s policy is when the amount of a building contract is between $300,000 and $800,000 progress payment inspections (valuation) are required at frame and final stage. In accordance with good industry practice, financial firms will request valuation reports at frame and final stage as they represent the larger value progress payments. The bank determined for the complainants, valuations would be completed at brickwork and lock up stages as each payment represented 30% of the total contract price. The available information shows the bank ordered valuations for the Brickworks and the Lock up stages. The bank had previously sent the valuer the building contract and approved building plans. The complainants say the bank engaged a valuer and relied upon the valuation reports to release funds to the builder incorrectly. The bank does not have to complete an inspection at each progress payment claim. When a financial firm does obtain a progress inspection valuation, it does so for its own benefit. The bank was not obligated to provide the valuation report to Mr L and Mrs LA. Recommendation | Case number: 683935 Page 7 of 12 The progress inspection valuation reports are for the bank’s own purposes The available information shows that the valuer completed an on-site inspection of the property on 24 November 2017. This can also be supported by the time stamped photographs attached to the valuation report. Contained within the valuation report were seven photographs taken by the valuer. Four photographs were of the outside of the building. These photographs showed that scaffolding was still in place and external doors (including the garage door) was missing. Three photographs were taken internally. These photographs showed that there were rooms with no plaster walls, no flooring and no fittings. The valuer in his report back to the bank confirmed that Lock Up stage has been completed. This was supported by the following statement: I can confirm that all building works up until this date of inspection are in accordance with the approved building plans provided The valuation also stated that the progress payment inspections are undertaken […] as valuers, not as building inspectors or building experts. The […] does not constitute a structural survey or building report. The complainants say that the bank relied on both (Brickworks and Lock Up) reports before releasing the payments, therefore they need to be held accountable for their actions. The complainants may have wanted the bank to assume responsibility for ensuring the building works were completed in November 2017. However, at no stage did the bank agree to do so. It was the complainants ‟ responsibility to check on the progress of the building works before authorising payment and submitting the PPI forms to the bank. If the complainants did not have the necessary experience to do so, the n it was up to them to obtain expert assistance or engage a building inspector to satisfy themselves that building was progressing satisfactorily. The bank obtained the valuation report for their own purposes. In the report, it was looking to satisfy its obligations as mortgagee to ensure the building works were council compliant and it held enough money to draw down the loan to complete the building contract. The bank was not under any further obligation to inspect the photographs and identify incomplete works. The bank was not obliged to disclose the findings of the valuation to Mr L and Mrs LA, or exercise of duty of care which extended beyond its obligations as a financial services provider. As the bank had been provided with signed PPI forms, they had M r L and Mrs LA‟s authority to release the progress payment amount to the builder. Recommendation | Case number: 683935 Page 8 of 12 The complainants did not raise concerns about the Lock Up payment until March 2018 The bank contact notes show on 15 March 2018, that Mrs LA contacted the bank. Mrs LA told the bank the builders were taking too long to finish the property. The bank confirmed that they do not get involved with builder disputes but could request a progress payment inspection to confirm status of the work done to date. The bank notes say that Mrs LA had no concerns regarding the quality of the works, only the time delays. The available information shows that a second call was made by Mrs LA to the bank on 27 March 2018. In that phone call Mrs LA says that she didn‟t believe the inspection report accurately reflected the Lock Up stage. Mrs LA says she believed that the valuer was related to the building company and works in general had slowed down since the payment was made in November 2017. Although Mr L and Mrs LA say that they had concerns with the Lock Up stage payment, they did not approach the bank until four months later. 5.2 Did the bank breach the 2013 Code of Banking Practice? The bank did not breach the 2013 code of banking practice When the progress payments were made in 2017, the 2013 Code of Banking Practice applied. Mrs LA says that the bank breached clause 9 of the code. Clause 9, Staff Training and Competency says: We will ensure our staff (and our authorised representatives) will be trained so that they: Can competently and efficiently discharge their functions and provide the banking services they are authorised to provide in compliance with this Code; and Have an adequate knowledge of the provisions of this Code and its application to banking services Mrs LA says the bank should ensure all conditions of the loan have been clearly shared and understood by the customer before they sign off on it. On the 20 July 2016, the complainants accepted the bank‟s offer of finance. In signing the loan contract, they acknowledged they had received:  a copy of the Letter of Offer marked “Copy to Keep”  a copy of ANZ‟s credit guide  a copy of the “Consumer Lending Terms and Conditions” (booklet V23), and Recommendation | Case number: 683935 Page 9 of 12  agreed to accept the terms set out in the consumer credit contract dated 19 July 2016. If a person signs a document that they know contains contractual terms and which they understand will affect their legal relationship with the financial firm, then the person is legally bound by those terms. It is irrelevant whether the person read the document before signing it. The only exception to this is if there are extenuating circumstances, for example if the person was misled into signing the document. The bank also received a PPI form for the deposit payment on 26 July 2016. I am therefore satisfied Mr L and Mrs LA understood the conditions of the loan and had been advised how to complete the PPI form to release payments to the builder. The building contract was acceptable to the bank for the loan purpose Mrs LA says the bank had a duty of care to request definitions of each building stage in the contract from the builder, before approving the payments. In general, a bank does not have a „fiduciary‟ duty or responsibility to its customer. This means it is not obliged to advise a customer that a service or product may not be in their interests. A fiduciary responsibility only arises where the role of the bank is seen to extend beyond that of a finance provider and into the area of advice or an agreement to make an exercise of judgement on the customer ‟s behalf. This happens if the bank provides advice or otherwise causes the customer to reasonably believe that the bank has assumed that responsibility. In this case there is no information to establish the bank provided the complainants with any advice about entering into a fixed price building contract. The parties to the building contract were the complainants and the building company. In providing finance for the construction of the property, the bank was only required to confirm the complainants held a fixed price building contract and council approved building plans. It was not the role of the bank to understand or seek descriptions of the building stages from the builder. The bank is there to provide banking services only. It was Mr L and Mrs LA‟s r esponsibility to understand each stage of the building contract. If they were unsure they could have sought independent advice or clarified with their builder. By signing the PPI forms and sending them to the bank, they failed to take reasonable steps to protect their own position. Recommendation | Case number: 683935 Page 10 of 12 5.3 What is an appropriate outcome to this complaint? The bank offer is available to accept as full resolution The bank made an offer to Mr L and Mrs LA to resolve their complaint. The details of the offer included:  $25,000 payment  an extension of 3 months interest only on both loans. The bank has also stated it would be willing to consider the extension of the interest only term to 12 months upon receipt of an updated Statement of Financial Position (SOFP). The bank‟s offer exceeds AFCA‟s findings which result in the bank not being required to provide compensation to the complainants. Recommendation | Case number: 683935 Page 11 of 12 6 Supporting information 6.1 Building contract – Progress payment Schedule Recommendation | Case number: 683935 Page 12 of 12 6.2 Complainants positions The complainants (Mr L and Mrs LA) say:  the bank engaged a valuer and relied upon the valuation reports to release funds to the builder incorrectly  the valuation reports were inaccurate and faulty, and photographic evidence confirms that the Brickworks payment was made before the second storey was in place  the builders abandoned the building site after receiving the lock up stage payment when only 65% of the words had been completed  the bank has released funds prematurely and enabled the builder to acquire funds they were not legally entitled to  they have had to engage lawyers to get the builders back on site to complete the contract, the builders ignored legal advice given and never returned to complete the remaining works  they terminated the builder on 31 May 2018  an independent building assessor has stated that to bring the building works back to Lock up stage as per the building contract is $204,627 6.3 Customer Service Issues Mrs LA raised a number of issues around the customer service they felt they did not receive from the specialised team at the bank. AFCA is a complaint resolution service. Our role is to consider specific types of complaints about financial firms and we can award compensation for loss or damage caused by a financial firm ‟s error. However, we do not have the power to consider complaints about the general level of service provided by a financial firm. Complaints relating to customer service are more appropriately dealt with by the financial firm itself. This is because the level of customer service is influenced by the financial firm ‟s policy on several issues such as staff levels and training. 6.4 Other matters not considered in this recommendation The complainants used the services of a broker The complainants used the services of a broker (PF) who assisted them in obtaining the loans from the bank. The complainants have not made any complaints about his conduct or that he was acting for the bank. The conduct of the broker has not been considered in this complaint.