Home / IAG / Determination 681153

Determination 681153

Garage ceiling collapse claim declined; water staining cash settled

FirmIAG
Decided2020-04-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$819
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed the full garage ceiling collapse after a storm, but the insurer declined that part as caused by moisture absorption and wear and tear. AFCA accepted the insurer's $744.74 cash settlement for water staining, ordering it paid with a 10% contingency.

The complainant did not show a covered storm cause, and the policy excludes wear, tear and deterioration, while cash settlement was reasonable.

Issues

Subjects and remedies

pay claim

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 681153 Financial firm Insurance Manufacturers of Australia Pty Ltd Determination | Case number: 681153 Page 2 of 8 Case number: 681153 17 April 2020 1 Determination overview 1.1 Complaint The complainant holds a home building policy underwritten by the financial firm (the insurer) covering her home address. On 3 October 2019, the complainant lodged a claim for a collapsing garage ceiling, which she stated occurred after a storm on or around 20 November 2018. After considering the claim, the insurer declined it on the basis the loss had not arisen as a result of any insured event covered by the policy. It later agreed to cover some water staining to the ceiling and offered a cash settlement of $744.74. This was based on a quotation and scope of works (SOW) prepared by its builder ‘UB’. The complainant disputes the insurer’s settlement and maintains the insurer is liable for the entirety of the claim. 1.2 Issue and key findings Was the insurer entitled to limit its liability for the claim? The insurer was entitled to limit its liability for the claim to the water staining damage to the plaster ceiling caused by water ingress. This is because the material shows the collapsed plaster ceiling was not caused by storm or any other event which would be covered by the policy. The insurer’s offer of $ 744.74 (less policy excess) for the resultant damage is reasonable and discharges its liability under the policy terms. 1.3 Determination This determination is in favour of the insurer. The insurer was entitled to limit its liability for the claim. If it has not already done so, it should remit payment for the water staining to the complainant. This should include a 10% contingency owing to the transfer of risk to the complainant. Determination | Case number: 681153 Page 3 of 8 2 Reasons for determination 2.1 Was the insurer entitled to limit its liability for the claim? Onus rests with the complainant to establish extent of loss There is no dispute that the complainant suffered a loss from a risk insured against for water staining damage to the ceiling due to rain water ingress, or that the insurer has accepted this aspect of the claim. However, a dispute has arisen between the parties as to the extent of th e insurer’s liability under the policy. Principally, the complainant says the insurer is liable for the repairs to the ceiling in its entirety, as it probably needs to be replaced. She says the storm event caused the water staining and also caused the ceiling to partially collapse. Therefore, as this is storm damage, her policy should respond. She has also raised concerns about the insurer’s c onduct when managing her claim, saying it breached both the General Insurance Code of Practice (the Code) and the Corporations Act 2001 (cth) (the Act). As the party seeking the benefit of additional cover under the policy, the onus rests with the complainant to show he is entitled to it. Policy is a defined events policy The insurer’s policy is a defined events policy. Therefore, the policy only responds where an incident caused by one or more of the listed events results in loss or damage, subject to any exclusions. ‘Storm’ is one of the listed events and is defined to include rainwater. It is established insurance law the complainant caries the initial onus to show that the loss claimed is covered by the terms and conditions of the relevant insurance policy. This is known as a prima facie claim. Establishing a prima facie claim includes showing both the cause and extent of the loss. There is no dispute that the complainant was provided with a copy of the policy documents at the relevant time, including the product disclosure statement (PDS) setting out the terms of cover. It is therefore fair in all the circumstances that the insurer is entitled to rely on those terms when assessing any claim made against the policy. To establish that the insurer is liable for repairs to the collapsed ceiling, the complainant must show that this arose due to the storm, or another covered event. In surer’s expert says ceiling collapse due to long term factors The insurer arranged for UB to inspect the property and report on the cause of the water ingress. Relevant details of the expert reports provided are contained in section 3.2 of this determination. Determination | Case number: 681153 Page 4 of 8 UB considered the cause of the ceiling collapse was due to moisture absorption into the plaster sheets, which has weakened the plaster. There was also a lack of perimeter fixings. This meant as the sheets absorbed more moisture, they stated to sag as the fixings were insufficient to support the increased weight. As each plaster sheet weakened, it created a cascade effect of failure on the adjacent sheets. UB did not attribute either of these issues a storm or any other covered event. Rather, this was due to a combination of factors such as wear and tear, deterioration, and the method of construction of the garage ceiling. I accept UB is suitably qualified and experienced to comment in this matter. In the absence of any contradictory information, the insurer is entitled to rely on their findings. Complainant’s evidence The complainant disagrees with the insurer’s findings, saying as there is clear evidence of water staining, this means the storm caused the plaster to fail. The complainant was invited to provide information in support of her position, such as a report from a suitably qualified person as to the cause of the damage to the roof. In support of her position, the complainant provided a property i nspection report from ‘RP’ and weather data from the Bureau of Meteorology (BoM). I have considered this information as part of my review. RP says the cause of the plasterboard failure is due to excessive gaps in the tiled roof, which is sufficient to allow water entry during periods of heavy or excessive rainfall. RP also noted there did not appear to be adequate fixings on either the plaster sheeting to the roof trusses or to the timber trims. Complainant has not presented sufficient contradictory expert evidence However, I do not consider RP’s report sufficiently challenges the insurer’s findings. Although RP considers that rainwater ingress is the source of the moisture which led to the collapse, as opposed to UB’s opinion that it was atmospheric moisture, crucially for the complainant, RP does not attribute this to a single event. Rather, RP says that water has been entering the garage roof space during periods of heavy or excessive rain, due to the excessive gapping in the roof tiles. This is an ongoing issue and may occur during each period of heavy rain. In addition to this, the BoM data shows the period when the loss is reported to have occurred did not experience any particularly heavy periods of rainfall. In my view, this tends to support U B’s conclusion as to the source of moisture, as does the RP’s comment that the timber trims are also moisture affected (but show no signs of visible water staining in the photographs provided). The pictures of the water staining also are not where the plaster has sagged. Determination | Case number: 681153 Page 5 of 8 Therefore, the insurer’s material is not sufficiently challenged. The onus to ensure the property is watertight and weatherproofed does not transfer to the insurer simply because it has insured the home. Cause of damage is specifically excluded from cover Even if it were accepted a prima facie claim was established (and I do not), the policy contains a number of exclusions from cover. Loss or damage from wear and tear and deterioration are specifically excluded from cover. Accordingly, I am not satisfied the complainant has discharged the onus on her to show, on balance, the ceiling collapse was due to a storm, or any other event which would be covered by the policy. Further, the exclusions from cover would be operative in the circumstances. The insurer is therefore entitled to decline this aspect of the claim. Insurer entitled to cash settle the claim UB prepared a SOW for the water stains to the ceiling that the insurer agreed to cover, in which it was estimated the repairs would cost $744.74 The complainant has not challenged this amount, nor provided any conflicting information such as an alternative quotation. Therefore, in the absence of any contradictory evidence, I accept UB’s view that $744.74 is a reasonable sum to remedy the resultant damage. The terms of the policy give the insurer the right to cash settle a claim in lieu of conducting repairs. Where an insurer has discretion as to how to settle a claim, AFCA expects an insurer to exercise this reasonably, as cash settlement may affect an entitlement to other benefits under the policy terms such as a repair guarantee. However, there is no evidence to suggest the insurer has not done so in this instance. In circumstances where there are maintenance works required to prevent the same issue occurring again, it is reasonable that the insurer discharges its liability by way of a cash settlement. The insurer is therefore to remit this amount to the complainant in settlement of his claim, within seven days of the date of her acceptance of this determination (if it has not already done so). As no repairs appear to have yet been conducted, it is not appropriate for an award of interest in the circumstances. However, owing to the risk of the repairs transferring to the complainant from the insurer, and the forfeiture of any repair guarantee, it is appropriate that a 10% contingency be added to the settlement amount. Determination | Case number: 681153 Page 6 of 8 Other matters The complainant asserts the insurer breached the Code and the Act with its management of the claim. However, determining whether the Code has been breached is not within the scope of AFCA’s jurisdiction when considering a general insurance complaint. Further, although the complaint asserts a breach of the Act, she has not detailed which specific section or how the insurer is alleged to have breached this. Whilst she does say the insurer used ‘high pressure sales tactics’ on her to accept the offer of settlement, I do not consider the situation as described by the complainant is reasonably analogous to the provisions contemplated by the Act in this regard. Accordingly, I am unable to consider these aspects further. The final matter for consideration is payment of RP’s invoice. However, as this did not advance the complainant’s position, I do not conside r it reasonable that the insurer be required to reimburse this cost to the complainant. 3 Supporting information 3.1 AFCA approach to this dispute This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted only to those issues considered relevant to the outcome. The complainant is represented in this complaint. For the sake of brevity, all references to ‘the complainant’ will inc lude those statements made by her representative (unless otherwise noted). 3.2 Relevant expert reports Record Key points Insurer’s ex pert (UB ) Builder’s r eport 9 October 2019  complainant stated that during a storm event damage had been sustained to garage ceiling  inspection revealed damage consistent with wear and tear over time  this has been caused by excessive moisture absorption into the Determination | Case number: 681153 Page 7 of 8 Record Key points plaster over time, especially during times of high humidity  the ceiling has been painted wit h a flat paint which is not a vapour barrier  there is no insulation in the garage ceiling  the plaster has been progressively weakening due to the moisture absorption to the point where the plasterboard has softened and pulled out the fixings  this issue has been exac erbated by the fact that the perimeter cornice is not supported by the plaster in the garage, so there is a lack of support a round the ceiling  as one section of the ceiling falls and pulls out the fixing, the additional weight is transferred to the adjacent fixings, causing a progressive collapse of the ceiling  plaster manufacturers reference this is their material  there are no storm created openings to allow water entry  there was minor det erioration to the capping and pointing and a couple of small chips to the roof tiles, however it is unlikely these would res ult in water entry , although the pointing does require replacement  timber prop s were used during the make safe to stop the ceiling from collapsing . Complainant’s ex pert (RP ) Building inspection r eport 20 January 2020  at the time of inspection, timber props were installed to prevent full collapse of the ceiling and to e nable safe access to the roof space  the gable end has a roof void wall vent correctly installed for ventilation of the garage roof space  the ceiling and cornices near the roller door are sagging significantly and full separation from the roof frame has occ urred  the ceiling fixings are visible  there is peaking of the plaster sheet joins due to sagging and moisture absorption  water staining was visible in the plaster sheets at the garage door in the mid - section  this is possibly due to a roof leak in the tiles above  sections of the timber trim are detached due to inadequate fixings and moisture absorption  there is no insulation installed over the garage ceiling  there was minimal visible evidence of plaster glue adhesive between the steel battens and the plaster sheeting  the roof framing showed no sign of mould or structural damage  the roof valley timber battens were dry at the time of inspection but showed signs of wat er staining  there are cracked tiles over the garage which require re - s ealing  some capping tiles require repointing on the mort ar  the hip and valley mortar has dislodged and there was a sign of a leak to the internal valley timber  the gap between the tiles is also excessive and is a likely source of water entry  the most likely cause of the damage is absorption of water in the plaster sheeting Determination | Case number: 681153 Page 8 of 8 Record Key points  the significant gap between the tiles is enough to allow water entry during excessive/heavy rainfall. 3.3 Relevant sections of policy The events we cover We cover your home or contents when certain things happen. These are known as 'listed events'. You can make a claim if a listed event takes place and causes loss or damage to your home or contents during the policy period. … Storm If loss or damage is caused by a storm. For example, hail damages your roof. Covered • violent wind, cyclone or tornado • rain, thunderstorm, hail or snow • landslide or subsidence that happens immediately as a result of a storm. … General exclusions for all cover The exclusions set out in this section apply to all cover under your policy. What we don’t cover Loss, damage, injury or death arising from: • rust, corrosion, gradual deterioration, depreciation, wear or tear

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.