Determination 680304

Cash settlement amount for water damage to transportable home

FirmRAA
Decided2020-12-09
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$300,000
SourceAFCA PDF

Summary

The complainant disputed the $49,075.33 cash settlement for water damage to his transportable home and sought $300,000 for rebuild, contents and stress. AFCA found the property repairable but the settlement inadequate, so the insurer must reassess the damage and settle the claim, with no non-financial compensation.

Expert evidence shows the home is repairable, but the insurer must have the damage from both events reassessed and costed because its own settlement did not reflect further damage it acknowledged.

Issues

Subjects and remedies

home or building damagepay claimreassess claim

Related

All RAA determinations · Find similar determinations

Text of the determination

Determination Case number 680304 Financial firm RAA Insurance Limited Determination | Case number: 680304 Page 2 of 9 Case number: 680304 2 November 2020 1 Determination overview 1.1 Complaint The complainant held a home and contents policy with the financial firm (insurer) and lodged a claim on 10 January 2019 following the discovery of water damage to his transportable home caused by burst pipes. The financial firm (insurer) accepted the claim and settled the complainant $49,075.33 for repairs. The complainant disagrees with the settlement amount and seeks the sum of $300,000 for demolition and replacement of the property, replacement of furnishings and compensation for undue stress and inconvenience. 1.2 Issues and key findings Is the insurer ’ s offer of settlement fair in all the circumstances? The panel is not satisfied given the information exchanged that the settlement amount of $49,075.33 is fair in all the circumstances. The insurer should appoint an independent engineer to attend the complainant ’s property, assess the extent of the claim related damage and prepare a full scope of works. Any affected contents should also be assessed in line with the policy. The insurer may then settle the claim as set out in section 2.1 of this determination. Is the complainant entitled to non-financial compensation for service issues? The circumstances of the claim suggest an award of compensation is not warranted. 1.3 Determination This determination is partially in favour of the complainant. The insurer is to appoint an independent engineer to reassess the damage to the property and contents and prepare an appropriate scope of works (SOW). The insurer is to then settle the claim as set out in section 2.1 of this determination. The insurer is not required to pay non-financial compensation for service related issues. Determination | Case number: 680304 Page 3 of 9 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues arising from the information. Due to the complexity of the issues involved this complaint has been referred to a panel for determination. The panel comprises the Lead ombudsman, a member with considerable experience as a consumer representative a nd a member with significant industry experience. This determination follows consideration by the panel of all relevant information. It is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. 2.1 Is the insurer ’ s offer of settlement fair in all the circumstances? Policy covers damage caused by burst pipes The complainant ’ s home building and contents policy insured the home building for $249,245 and contents for $60,862 for loss or damage from a series of listed events. Included in the listed events is loss or damage as a result of bursting, leaking, discharging or overflowing water or liquid from amongst other thing drainage and sewerage systems at the home or pipes or plumbing apparatus fixed to pipes There is now no dispute that the property was damaged initially by liquid from the drainage and sewerage system and then from the discharge of water from a b urst flexi hose under a vanity unit. The issue in dispute is the extent of liability. Complainant seeks for the property to be rebuilt The complainant says the property must be demolished and rebuilt due to damage and movement caused by the water. They also seek the full contents sum insured to replace furnishings. The complainant submitted a quote for the property to be demolished and rebuilt by builder AS in the amount of $162,686. The insurer maintains the property did not require complete replaceme nt. It says it is liable only for the cost to repair damage to building and contents caused by the claimed event. It says it has accurately assessed the full extent of its liability with respect to building and contents items. Initial expert reports identified issues The insurer engaged several experts to determine the cause and extent of the damage. No expert reports have been provided by the complainant to date. The insurer’s loss adjuster Y attended in early January 2019 and reported significant cracks to internal and external walls as well as concrete path ways that it attributed to Determination | Case number: 680304 Page 4 of 9 movement. It also said the bathroom was severely deteriorated with mould and water damaged walls. Y appointed plumber RP who attended in mid-January 2019. RP investigated the leak and found the hot water flexi hose under the vanity had burst. It noted the cold-water flexi hose was also in poor condition. On conducting various leak detection tests RP also found issues with the shower recess, breecher pipe, toilet waste pipe head, sewer drain head and hot water lines as well as observing deterioration to the shower and bathroom. Further to this, RP said the concrete path and pylons holding up the house had dropped significantly, and sewer drains were visibly broken in several areas. Finally, RP said the sewer drain under the house was completely blocked and broken in several areas, and this had likely caused the concrete pathway to sink. RP replaced the basin flexi hoses while on site . It recommended replacement of the entire sewer drain and shower breecher as well as retiling and waterproofing of the shower alcove. On 1 February engineer MB attended the property and in addition to the damage already noted, observed cracking and partial separation of the WC riser pipe, cracking to the slab, damp soil, water staining and a sticking patio door. Diagonal cracking to weatherboard cladding was found to coincide with the WC and bathroom windows. These locations are where the leaks were discovered. Water staining was observed to the floor joists directly below the shower area. It was also noted the soil beneath the bathroom was damp and covered in effluent. MB conducted a floor level survey using bedroom 2 as the datum point due to it being located furthest away from the leak location. The level survey gave level readings that varied between plus 22 and minus 44 with the lowest levels occurring around the leak location and around drains and wet areas. MB concluded the leaks had been occurring over an extended period of time given the extensive nature of water staining under the shower recess. An influx of moisture would have caused soils to swell and movement leading to the waste pipe shearing off, which would have exacerbated the process and caused further swelling and movement to the down slope of the drain. This process would have led to soil collapsing and washing away leaving voids under the slab. Complainant disputed the insurer’s scope and quote The insurer appointed engineer GP who attended on 4 June 2019 to reassess the damage. GP reported observing significant water staining caused primarily by long term water loss from deficiencies in the shower base. It also noted the burst flexi hose would have caused damage to the bathroom beneath the tiled surface, as well as the WC Determination | Case number: 680304 Page 5 of 9 and laundry. A second flooring level survey revealed long term movement across the floorplate with the lowest points recorded near the broken WC waste pipe. These findings were consistent with the level survey conducted by MB. GP also noted a drummy sound under the rear patio slab where supporting soils had washed away. GP provided a scope of works it believed sufficient to reinstate the property and described it as ...reasonable and conservative in the Member’s favour. The insurer provided a quote from builder AT in the amount of $51,077.13 which was based on a scope of works prepared by GP. The complainant was dissatisfied with the scope and say the hot water system and vanity should be included. He also raised concerns about asbestos. The latter was addressed by Y who said asbestos was removed from sale in the mid 1980's, and the complainant’s property was built in 1989. GP reviewed the quote and advised an additional $600 was to be added for a vanity cabinet and another $6,000 for work to the stump bases and footings in the wet areas. Available information indicates property is repairable Although the complainant’s view was that the property needed to be rebuilt due to movement, GP said categorically that the property was repairable as the scope allowed for the entire home to be relevelled and replacement of stump bases in the wet areas to be done. Plumber DS later assessed the hot water system and observed it to be in working order. DS said the complainant had raised concerns that due to a burst hot flexi hose, excessive water had run through the unit and would possibly affect its life span. DS concluded this would have little to no effect on the unit and concluded it did not require replacement. In the absence of expert reports from the complainant to refute the insurer’s findings, the panel accepts the material shows the property is repairable. Insurer acknowledged further damage was likely present In October 2019 the insurer sent the complaina nt a cheque for $49,075.33 representing the estimated cost of repair less a $200 excess. It is unclear how this figure was reached as the quote based on GP’s scope of works plus additional items recommended by GP totals $57,677.13. In its communications, the insurer acknowledged further cracking and movement would have occurred. It agreed to arrange and pay for repairs to the broken waste pipes, and to reassess the damage to determine the current cost of repair. It also agreed to provide temporary accommodation for the duration of repairs. Determination | Case number: 680304 Page 6 of 9 The insurer says the complainant would not allow it to reattend the property and insists the entire structure must be demolished and rebuilt. While the panel understands the complainant ’ s concern about a significant volume of water entering the building, the expert reports do not support the complainant ’ s position. Insurer has not assessed the full extent of its liability in relation to the claim All available expert reports agree the property is repairable. In the absence of expert reports from the complainant to refute this position, the panel is not satisfied the complainant has shown the property requires demolition and rebuilding. However, g iven the insurer’s agreement the property would have suffered further damage and the discrepancy between the expert reports and the cash settlement put forward by the insurer, the panel is satisfied the insurer should have the damage reassessed. In the panel ’ s view in order to finalise this dispute the insurer must appoint an independent engineer to attend the property, assess the damage arising from the two events and prepare a detailed SOW. The insurer must then have the SOW costed by a builder prepared to complete the works. The complainant must cooperate with the independent engineer and builder and allow whatever necessary access is reasonably requested. If the insurer is prepared to carry out the work it may do so, or it can cash settle the claim based on the costed SOW plus a 10% margin to account for contingencies, transference of risk and the loss of workmanship guarantees. Portable bathroom facilities The insurer provided the complainant with portable bathroom facilities, and says it is using the complainant’s entitlement for temporary accommodation for this purpos e. The insurer says this entitlement will be exhausted on 4 October 2020. The insurer has previously said it will provide temporary accommodation for the duration of repairs. On review of the policy, it says the insurer will provide temporary accommodation for a maximum of 10% of the sum insured for any one event. The panel notes the complaint relates to two separate events. One for a burst flexi hose in the bathroom, and one for a broken waste pipe. The insurer accepted both claims and acknowledges each event contributed to the property damage. Given the above and the insurer’s previous position on accommodation which made no reference to policy limits, the panel considers it fair in the circumstances for the insurer to continue providing portable bathroom facilities, temporary accommodation or a cash settlement for the estimated duration of repairs once a new scope of work has been agreed upon. Determination | Case number: 680304 Page 7 of 9 2.2 Is the complainant entitled to non-financial compensation? Compensation only paid in some circumstances AFCA can award up to $5,000 compensation where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensatio n. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. The complainant says the insurer was biased in its reporting and took many months to overturn the decision to decline the claim, leading to further damage at the property. Given the complainant has not provided any independent reports to support his position that the home must be completely rebuilt, the panel is not satisfied he has shown the insurer’s reports were biased. With regard to delays, where an insurer identifies an error has been made it must immediately take steps to remedy that error. In this case, the insurer originally denied the claim at an IDR level on 10 April 2019 based on expert reports. The decision to decline the claim was overturned in writing on 16 May 2019 based on information provided by the complainant during the IDR process, and advice from GP which the insurer received on 15 May 2019. The panel does not consider this to be an unreasonable delay in the insurer’s review of GP’s advice and the subsequent overturn. On careful review of the claim file notes in conjunction with the attendance dates of the insurer’s experts which give an overall in dication of the insurer’s service, it appears the insurer remained engaged with the complainant throughout the life of the claim. The available information establishes the claim was appropriately managed and a decision made in a timely fashion on receipt of relevant information. For this reason, the panel is not satisfied the insurer’s conduct warrants an award of compensation. Determination | Case number: 680304 Page 8 of 9 3 Supporting information Record Key points Product Di sclosure Statement ( PDS ) Temporary accommodation If Home and/or Cont ents is shown on your Certificate of insur ance and they are damaged by an insured event an d : • we agree that the home is unfit for you to live in as a res ult of this loss or damage, then we will cover you for: • the cost of temporary accomm odation for you and any person permanently living in the home who is covered by th is insurance during: - the time it takes to replace or repair the home or cont ents, or - the peri od that the home remains unfit to live in for a m aximum of 12 mo nths. The cost of temporary accommodation will be based on the rentable value of your ho me immediately prior to the loss or damage. W e pay this benefit in addition to the sum insured for the home or contents. The maximum we wil l cover you for Temporary accommodation is 10% of the sum insured for any one event. Insurer’s expert ( GP ) Report 19 June 2019  …we believe that there has been long term water loss from the bathroom due to the deficiencies in the shower base.  We also note that the failed wat er pip e was within the vanity cupboard and it is likely that water has affected the flooring within the bathroom beneat h the tile surface. Similarly, we cannot deny that the flooring in the W.C and laundry has been damaged. A level survey was taken through the home which showed that there had been long term movement across the entire floorplate however, the worst settlement was to the eastern elevation around the Laundry/W.C.  The Member, whilst outside, gave his opinion on the movement to the home and opined tha t the structure had both settled and moved laterally towards the east. His opinion is based on the crippling to some of the roof sheets to the veranda  We do concur that it is likely that some settlement of the structure had occurred as a result of the wate r inundation however, it is obvious that long term and differential settlement has occurred elsewhere to the floorplate which is remote from the wet areas and this is not unusual in a home of its age. However, we emphatically disagree that any horizontal m ovement has occurred to the home as a result of the events. Given that no damage was present anywhere in the home that would suggest lateral movement, the Determination | Case number: 680304 Page 9 of 9 Record Key points entire home would need to move up the natural slope of the property and this is unfeasible.  We rather advise that the damage to the sheets, which is found to random locations, is due to a local failure of the sheet under foot loading.  Based on the observation made during our attendance, we have provided a scope of works which we believe addresses all dama ge caused by the water leak events. We believe the scope is both reasonable and conservative in the Members favour. Insurer’s expert ( AT ) Quote 10 July 2019  We confirm that in accordance with the documents provided we have included Prime Costs sums as li sted are for the following works: 1. Wall frame repairs to the bathroom 2. Floor joist repairs to the bathroom 3. Wall frame repairs to the laundry/we 4. Floor joist repairs to the laundry/we 5. Re - levelling of the building. Total (I nc GST ) $51,077.13 Insurer’s expert ( GP ) Further respons e 20 November 2019  The quotation provided by AT substantially follows the scope of works provided by this office with the exception of the following: • Provision of a vanity cabinet to the main bathroom. We suggest an additional sum of $600.00 be added to the quoted sum to cover for this. • No allowance made for the replac ement of stump bases/footings in the wet areas as noted in the scope of works. An additional allowance should be made for the removal of the existing bases, compaction and replacement with new. We suggest that an additional sum of $6000.00 be added to the quoted sum.  The damage is purely confined locally to the wet areas in the south west quadrant of the home and the scope of works reaso nably addresses all of the damage present in this area. We see no reason why the repairs should extend outside this area given that the home is performing well despite its age and categoric ally disagree that the home should be demolished.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.