Text of the determination
Determination
Case number 679588
Financial firm Commonwealth Insurance Limited
Determination | Case number: 679588 Page 1 of 13
Case number: 679588 14 July 2020
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm
(insurer).
On 31 May 2019 the complainant contacted the insurer and submitted a claim for
storm water damage to her home.
The insurer has accepted the claim for damage to the ducted heating and resultant
mould and paid the complainant‟s temporary accommodation until 21 June 2020.
However, it denied the portion of the claim relating to cracking and movement as it
says this was not the result of an insured event and was not consistent with the
accepted event.
The complainant disputes the partial denial. The complainant is seeking cover for all
the damage and her home returned to a habitable state.
The complainant also says there was a substantial delay before any action was taken
by the insurer and this delay contributed to mould developing. The complainant says
the delays in the handling of the claim caused her considerable distress.
1.2 Issues and key findings
Is the insurer liable for the damage caused by the inundation of the property?
I am satisfied the movement of the property is associated with the inundation of the
property following the storm. The insurer is liable to meet the claim for the damage as
set out under section 2.1 of this determination.
What is the extent of the insurers liability regarding mould?
The insurer is liable to remediate mould, disconnect and replace the existing heating
and under floor ducting. Further the insurer is liable for the replacement of certain
contents affected by mould.
Is the complainant entitled to compensation?
The complainant is entitled to compensation as set out in section 2.3 of this
determination for professional costs incurred and for the unusual degree of
inconvenience caused by the insurers handling of this claim.
1.3 Determination
This determination is in favour of the complainant.
Determination | Case number: 679588 Page 2 of 13
The insurer is to:
complete the mould remediation and to meet the costs of replacing the heating
unit and heating ducts and repairs to the flooring as required
inspect the complainant‟s contents and either restore or replace any contaminated
contents identified
extend the allowance for temporary accommodation to cover any such costs
incurred until the mould has been remediated and the house declared habitable
complete the drying of the subfloor and remove any contaminated sub floor soil
continue to cover the complainant‟s utility bills incurred during the drying process
obtain a detailed scope of work from KMA as set out under Section 2.1 of this
determination. The insurer can then either completed the repairs or cash settle the
claim for the repairs subject to agreement between the parties
pay the complainants professional costs of $3080 for E and $3799.40 and
$2,299.00 for KMA pursuant to AFCA Rule D.5.1 and D.5.2
pay the complainant $5,000 in compensation for non-financial loss pursuant to
AFCA Rule D.3.3.
Determination | Case number: 679588 Page 3 of 13
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
This determination follows consideration of all the available information. It is based on
what is fair in all the circumstances, having regard to the relevant legal pri nciples,
terms of the policy, good industry practice, including codes of practice and prior
determinations where applicable.
2.1 Is the insurer liable for damage caused by the inundation of the
property?
The complainant has the onus to establish a claim within the terms of the policy
It is established insurance law that an insured person has the initial onus to establish
on the balance of probabilities, that is more likely than not, that the loss or damage
claimed falls within the terms of the policy. This is commonly called a prima facie
claim.
The complainant‟s policy is a Home and Contents policy insuring the property for a
series of insured events including damage caused by the escape of liquid, flood, and
storm damage.
There is no dispute that on or about 18 May 2019, the complainant‟s property was
damaged following a storm. There is no dispute that a blocked council stormwater
drain directed the storm water under the complainant‟s property.
Exactly when the stormwater flooded underneath the complainant‟s p roperty is
unclear. There may have been further episodes of inundation because of the blocked
drain. According to the complainant, it is likely that water accumulated under the
house over many months.
According to the insurer‟s claim system, the complainan t reported the damage on
31 May 2019 as follows:
Storm damage timber stumped house water build up under house damaging
gas/elec heater. Request from insured elec & plumber report.
The insurer‟s assessor, AB, reported water underneath the house, with water having
entered the heating ducts and the possibility of mould. AB advised that the issue was
urgent and necessary to prevent any further damage.
Reports subsequently provided by AB and SR confirm damage to the ducted heating
system, movement of the timber flooring and cracking to the ceiling and cornicing.
Determination | Case number: 679588 Page 4 of 13
I accept based on the available information that the complainant has established on
the balance of probabilities that is more likely than not, that the property has been
inundated because of a storm event.
I am satisfied that the complainant has established a prima facie claim within the
terms of the policy.
Insurer to complete drying of the sub-floor area
I note work did not commence to dry the sub-floor or treat the mould until 39 days
after the incident was reported.
According to a report from the insurer‟s restoration company MR dated 1 July 2019,
the ducting under the house was wet as it was sitting on the soil and required
replacement. The clay soil had already shifted, causing the splash back and bench
top in the kitchen to crack, cornices shift and plaster cracking.
The insurer‟s expert L believes the abnormal site moisture conditions are due largely
to inadequate site and sub-floor drainage which is trapping moisture under the floor.
The compla inant‟s expert KMA believes the water from the storm event has inundated
the building with stormwater settling in low lying areas of the sub-floor and being
trapped behind the front wall of the lounge with resultant swelling occurring. KMA
accepts there was minor pre-existing movement due to the age of the footings and
therefore some pre-event cracking, consistent with seasonal moisture variations. KMA
does not believe the current variations are consistent with this.
I accept that the sub-floor area was extensively flooded during the insured event. In
the circumstances, the insurer is required to complete the drying of the sub-floor area
to achieve a uniform moisture content. All engineers have identified contaminated sub
-floor soil following the event. The insurer should insure that any contaminated sub-
floor soil is removed.
Differing expert reports as to cause of movement and cracking
The insurer and the complainant have both obtained their own engineer‟s reports to
establish the cause of the movement and cracking damage to the house.
The insurer‟s expert L says the building damage has been caused by a combination
of differential footing movement arising from abnormal site moisture conditions due to:
the large and medium trees in close proximity to the property
inadequate site and subfloor drainage
inadequately designed footings
inadequate installation of the plaster ceiling causing failure of the fixings
the inflexible construction methodology for the building and failure to articulate the
brickwork
Determination | Case number: 679588 Page 5 of 13
evidence of past repairs and cracking.
The complainants claim is not for the minor, long-term cracking which has occurred to
the rear areas of the house. This is conceded. The claim is for the significant damage
which appeared after the storm damage and inundation of the subfloor.
KMA provides compelling reasons to refute the findings of L‟s report. KMA says the
general issue regarding movement is water from the storm event entering under the
building and affecting the internal footings.
Supplementary reports have been provided by both KMA and L. Whilst both reports
reached different conclusions, I am persuaded by the report from KMA.
I accept the findings of KMA that the pre-event cracking to the house was consistent
with normal seasonal moisture variations and consistent with the nature of the
footings provided in a house built in the sixties and eighties. I accept however that the
current floor levels observed by KMA are not consistent with normal seasonal drying
or the impact of vegetation causing that drying as suggested by L.
Given the only known change in circumstances is the flooding, then I accept that the
flooding of the sub-floor area can reasonably be said to have significantly contributed
to the movement and cracking damage.
Exclusion does not apply
The insurer also says the exclusion for loss or damage was caused by:
water including rainwater after it has disappeared beneath the surface of the land
at your insured address
should apply.
The insurer says this exclusion should apply to the inundation of the property by
stormwater. I do not agree. If the exclusion were to apply to damage resulting from
stormwater inundation, then it would also apply in circumstances where the property
was inundated by flood or by the escape of liquid.
I do not believe that the exclusion is intended to apply to that extent. In my view, the
exclusion would apply normal seasonal events not flood or storm or circumstances an
insured event that has resulted in an abnormal level of inundation of the property.
Inundation of a property through a storm or flood is likely affect the soils low bearing
capacity with the resultant damage. If it was the intention of the policy to exclude such
damage, then this should be clearly spelt out in the insuring clause as it would
significantly limit the cover provided.
Determination | Case number: 679588 Page 6 of 13
Insurer to obtain a scope of works
I am satisfied the complainant has established a valid claim for damage caused by
movement of the house following the storm water inundation. The insurer is liable to
meet this aspect of the claim.
KMA provided a detailed report and explanation with respect to the damage identified
at the property. The complainant scope of works provided by the complainant
includes such as the repair of a chimney which is not consistent with the damage
identified by KMA. According to KMA, the lean on the chimney had developed at
some stage between March 2015 and March 2017, nearly two years prior to the
inundation of the property. The repairs of the chimney and any associated damage
are not reasonably claimable.
In my view, it is fair that once the insurer has completed the drying of the sub-floor
and the mould remediation that a scope of works be obtained from KMA to allow for
the damage caused by the sub-floor inundation, including any re-levelling of the
property, repair, replacement or sanding of the floors and any necessary internal
repairs. To be clear, the scope of works is not to include the cost to repair pre -existing
damage to the property.
2.2 What is the extent of the insurers liability for the mould remediation?
Insurer has accepted the claim for mould remediation
The insurer has accepted the claim for mould remediation, although the remediation
work and removal of the ducts has not commenced.
The insurer advised the complainant that until works such as correcti ve surface
drainage and removal of the trees to prevent ponding/surface water at the site are
completed, the contractor will not complete the works as they cannot be warranted.
The alternative was an offer of $35,874.80 for the heating and flooring repairs to
finalise the accepted component of this claim. It has recently increase this offer to
$43,049.76 to allow for contingencies.
The insurer’s delays caused further loss
The drying did not commence until 39 days after the event. The insurer has confirmed
t hat drying works commenced on 5 July 2019. The complainant‟s engineer, KMA,
says that this delay, combined with the use of the contaminated ducted heating
system to dry the area under the property has contributed to the current mould issues.
The assessment report by AB indicates the house was habitable. However, a later
report by the insurer‟s mould expert MR says the house is uninhabitable and the
complainant was moved to temporary accommodation.
Determination | Case number: 679588 Page 7 of 13
In October 2019, MR advised the mould and humidity has inc reased. The available
information suggests the delays have contributed to the continued development and
spread of mould.
Insurer is to pay for replacement of contaminated contents
The complainant‟s expert E says the heating ducts and most likely the heati ng unit of
the ducted central heating system are contaminated and require replacement. The
use of a contaminated ducting system to facilitate the drying has been confirmed by
several of the commissioned experts and the complainant.
The complainant and com plainant‟s expert KMA have also referenced the Victorian
Government recommendation in relation to mould contamination of central heating:
Air conditioning or central heating should not be used unless they are undamaged
and uncontaminated by the floodwater. If you suspect contamination with mould
or floodwater, do not use until these systems have been cleaned and checked by
a qualified person.
With the development of mould and the home being uninhabitable and contents
exposed, the complainant made a request under the contents insurance for the
removal of all home contents, cleaned/replaced and stored until such time that the
home was deemed to be habitable.
Given the available information, I am satisfied the insurer is liable to meet the costs of
replacing the heating unit and heating ducts and repairs to the flooring as required. I
am also satisfied based on the reports from the complainant‟s experts E and KMA
that it is reasonable for the insurer to inspect and replace any of the contaminated
contents identified.
Insurer to pay further amount for temporary accommodation
The policy provides compensation for temporary accommodation for a period of 52
weeks and that has now been exhausted. The delays caused by the insurers handling
of this complaint have caused an unreasonable delay in the completion of the mould
remediation. This has led to the temporary accommodation allowance being
exhausted. In my view, the complainant should not be disadvantaged by the insurers
poor claims management.
My understanding is that the complainant has now returned to live with her parents.
As such, she may not be incurring temporary accommodation costs. However, should
she incur any temporary accommodation costs, then the insurer must reimburse
those costs until the mould remediation is completed and the home is habitable.
Once the property is certified as being habitable the insurer is entitled to cease
payment of temporary accommodation benefits.
Determination | Case number: 679588 Page 8 of 13
2.3 Is the complainant entitled to compensation?
Insurer must cover complai nant’s mould expert costs
AFCA may award the professional costs incurred by the complainants during the
dispute. Normally, this would be awarded if the professional costs were reasonably
incurred and assisted the complainant‟s position.
The complainant engaged E to report in relation to the mould. The report has assisted
resolving this complaint. The insurer must reimburse the report fee of $3,080.00.
The complainant engaged structural engineer KMA who provided two detailed reports
that have substantially assisted in the resolution of this dispute. The insurer is
required to reimburse the cost of KMA‟s reports of $3,799.40 and $2,299 respectively.
Insu rer to cover complainant’s utility costs when the house was uninhabited
The complainant is still residing in temporary accommodation and says the gas
ducted heating relies upon electrical power to operate the electric fan which is still
operating, distributing the contaminated air through the subfloor of the home. To date
she has provided utility bills, which I believe have now all been paid. As these are a
consequence of the electricity and gas still being used to dry the damp areas, the
insurer is required to continue to cover these costs until it is no longer using the
complainants gas and electricity as part of the remediation process.
Complainant is entitled to compensation for non-financial loss
AFCA may award an amount of compensation (capped at $5,000) for non-financial
loss where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind by the insurer.
The handling of this complaint by the insurer has caused unnecessary stress and
inconvenience to the complainant and her children, over and above that which would
reasonable be expected.
The complainant and her family have been living in temporary accommodation during
the period since the house was declared uninhabitable. Temporary accommodation
has been approved for short duration (usually two weeks but as short as 4 days). The
requests for extensions to temporary accommodation have been due to the
complainant phoning the insurer (she says with durations of 2 to 4 hours on the
telephone) seeking approval.
The approvals were given usually the day before expiry and with the temporary
accommodation management advising the complainant to vacate, causing her great
stress and anxiety.
It is fair in the circumstances that the insurer pays the complainant $5,000 in
compensation for non-financial loss.
Determination | Case number: 679588 Page 9 of 13
3 Supporting information
3.1 Key references
Policy wording
PDS ref Wording
General exclusions
(p 75)
Under this policy there is no cover provided for any loss, damage or
liability caused directly or indirectly by or in any way connected with:
5. water, including rainwater, after it has disappeared beneath the
surface of the land at your insured address;
9. the vibration, settling, shrinking or expanding of earth or any
building, foundation, wall, pavement or path (except in the case of
the Insured Events “Lightning” and “Earthquake” claims);
12. the actions of trees, plants or their roots that occur slowly and
gradually over time;
We will also not cover:
35. gradual loss or damage of any kind;”
How we settle a claim
Building claims
(p 82)
If we agree to pay your claim, we will decide whet her to:
Repair or rebuild the lost or damaged part of your building
Replace your building
Pay you the amount we determine to be the reasonable cost of
repairing or rebuilding the lost or damaged part of your building up
to the sum insured stated on your Certificate of Insurance.
Expert reports
Report Key points
Insurer’s expert (AB)
Asse ssor amended report
undated
The water under the house has resulted from a single storm event
where the council drain was blocked which caused water to flood
the rear yard and under the house.
Insurer’s expert (D)
Electrician report
21 - 06 - 2019
Whole subfloor had been flooded, approx. 300mm of wat er had
been confined in the subfloor area with still visible pools of water
and floor joists being wet. All underfloor duct is laying on the
ground and will require replacem ent due to being water
contaminated.
Floor joists are still wet and dripping and underfloor area still wet.
Windows are fogging up as the sub floor tries to dry; the building is
very damp throughout. Mechanical ventilation is required to assist
in drying t he subfloor area and it was noted that there are visible
signs of mould present at the rear of house.
Heat er unit has been compromised by water and in our opinion will
need to be replac ed.
A possible solution is to have a replacement heater and duct
installed in the roof space, however the floor duct outlets and
Determination | Case number: 679588 Page 10 of 13
Report Key points
Return Air compartment would require covering over.
Insurer’s expert (MR)
Mould expert report
01 - 07 - 2019
The clay soil underneath the house has already shifted. The glass
splashback and benc htop in the kitchen has cracked, cornices
have shift ed, and plaster has cracked in places.
Moisture readings of plaster surfaces throughout ranged from
16% - 17%. Relative humidity indoors was 79% at the time of our
attendance (outside RH was 61%).
Power will be required to the premises to run drying equipment.
Insurer’s expert (FE)
Expert email
20 - 08 - 2019
Tech noted on 8/ 8/19 that there was a lot of standing water around
the outside of the house.
It does not appear that the ground around house drains freely -
may be possible for wat er to seep through under the hous e
depending on condition of the damp - course.
Insurer’s expert (ML)
Mycologi st Report
10 - 10 - 2019
High levels of fungal hyphae with low levels of active hyphae
present were detected in sample 1 and therefore constitutes a
potential health hazard
Types and levels of mould detected have been shown to be either:
Immuno - compromising; and/or
Allergenic; and/or
Mycotoxin producers.
Continued occupancy is ill advis ed until remediated.
Following remediation, retesting to confirm post - remediation
verification should be performed.
Insurer’s expert (M)
Mould expert
email
13 - 09 - 2019
Attended 2/9/19. There was slight mould on the rumpus room
ceiling, so our technician cleaned and treat this as a courtesy.
Relative humidity inside was 62% and outside was 59%. The
damage in the rumpus room appears to be a gutter overflow.
Monitored drying on our last inspection 9/9/ 19. There is an
ongoing recurring issue with seepage from storm water going
under the house. It is our opinion that this is an ongoing issue at
this property.
Insurer’s expert (MR)
Mould expert report
17 - 10 - 2019
Visual mould sighted to the ceiling in rear family room. This is not
consistent with the claim incident – indicative of a r oof/gutter leak
to the corner of this room.
Relative humidity indoors 68% (RH out doors 56%). A relative
humidity of 63% or higher is ideal for mould growt h.
house is not currently habitable. Mould will need to be
professionally remediat ed and structure dr ied to a dry standard
before regarded as “habitable”.
The visual mould sighted on 4/10/19 was not present during our
previous attendances to this property (on behalf of [insurer]),
except for the mould in the rear family room which we do not
believe is cla im relat ed.
The humidity levels recorded indoors on 4/10/19 have risen since
our last attendance on behalf of [insurer].
It is our professional opinion current conditions (based upon which
Determination | Case number: 679588 Page 11 of 13
Report Key points
we recommend that the house is not habitable) are due to ongoing
moisture issues which are not related to the original claim incident
(one - off water from storm wat er blockage).
Insurer’s expert (L)
Engineer‟s report
25 October 2019
Water ingress of the subfloor will be a long - term and ongoing
issue from normal precipit ation due to inadequate site drainage
provisions.
Long term differential footing movement due to differential
moisture content variation in the reactive foundations because of
one or more of the following contributing factors:
Tree root drying effects due to the presence of groups of
large and medium sized trees within close proximity to
the structure.
Construction of an extension over virgin soils.
Inadequate site drainage of the building perimeter and
subfloor contributing to ponding adjacent the footings
and variation in the moisture content of the reactive clay
foundation.
Changes in soil moisture content due to seasonal and
climatic effects.
The „drought‟ conditions in Victoria bet ween 1997 and
2010, followed by the return of „normal‟ rainfall patterns.
Long term consolidation of the clay foundations
Escape of water from the reported stormwater leak from the
council drainage and reported water ingress and flash flooding of
the property is not the cause of the detected building movement or
observed buildi ng damage.
Insurer’ Expert (L) Report
14 April 2020
Initial damage claim was for wide spread damage. The
complainant has changed the nature of the claim.
KMA‟s report based on what KMA was told by the owner as
opposed to objective independent engineering analysis.
KMA ignores evidence of significant past and ongoing building
movement.
KMA fails to refer that the back to the building footing system is
inadequate.
KMA ignores the fact that the building has inadequate site and
sub - floor drainage.
KMA does no t satisfactorily address why no damage has occurred
to the brittle tile floor and wall finishes in the recently renovated
bathroom and laundry.
Photographs evidence exists of rotation movement and damage to
the chimney prior to the claim flooding event.
On the balance of probabilities, there is overwhelming evidence to
suggest building movement and damage has been a long term
ongoing issue due to differential footing movement caused by
normal soil movement, abnormal soil moisture conditions, created
by grou ps of large trees and inadequate site and sub - floor
drainage and inadequat ely designed footings for the site
conditions.
Determination | Case number: 679588 Page 12 of 13
Report Key points
Complainant’s expert E
Mould Asse ssment
19 - 02 - 2020
The soil beneath the property has evidence of significant
inundation of water as it has the appearanc e of dried mud and
high levels of visible efflorescence on the soil surface.
Significant amount of general organic debris on the soil of the
subfloor whic h is most likely a source of microbial contamination.
No significant visible mould growth was identified on any inspected
materials wit hin the property or subfloor with exception to some
dust and mould growth in the return air duct.
One of the eight surfac es sampled had “elevated” levels of settled
mould (Bed 3 - Bed Head) and another had “high” levels of settled
mould (Rumpus – Table).
Property did not have an unaccept ed indoor mould ecology.
The ducts and most likely the heating unit of the ducted cent ra l
heating system are contaminated and require replacement.
Complainant’s expert (KMA)
Structural Engineer report
The change in moisture content under the kitchen area of the
building can only have occurred during a flooding event such as
that which occurred.
Once the water entered under this building there were only limited
options for its escape … Once the water level dropped below the
level of the ventilation openings the water could only exit from
under the building by soaking into the soil or out by soaking
through the bricks...
Once water was trapped under the building, it would pond in the
lowest areas for the longest period of time, causing the soil in
these areas whic h had been drying since being enclosed, to
become hydrated and swell.
While d rying of the area under the building has reportedly been
undertaken, mould is visible to the rear of pictures as well as to the
ceiling in the rear of the house.
KMA report dated
31 May 2020
L appears to be attempting to connect the dots for many items th at
are not relat ed or just don‟t make any sense.
L are trying to connect events from 20 years plus ago and say the
flooding event has had no effect on the property.
Complainant is not claiming for damage that has occurred as a
result of normal movement but rather claiming for the severe
damage to the kitchen and living room that is associated with the
flooding event.
Complainant is not trying to change claimable items but has
presented information in what a laymen‟s opinion constituted
possible damage becau se of the flooding.
Damage that has occurred is clearly and obviously much more
significant than previous minor cracking from seasonal moisture
change to the soil and is clearly as a result of some form of event.
The only event that has occurred is the flo oding the site because
of the blockage of the council pipe.
L‟s statement that the timing of the damage to the kitchen is simply
based on the owner‟s comments makes no sense as the previous
Determination | Case number: 679588 Page 13 of 13
Report Key points
actions of the ins ured would indicate.
A holistic view is taken of the movement to the building, except the
building like many other throughout Melbourne and rest of
Australia has previously suffered minor movement related to
damages with previous work undertaken for underpinning and
packing sometime between 20 and 40 ye ars ago.
Our opinion remains unchanged in regard to the caus e of
significant movement around the kitchen and living room.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.