Home / Lloyd's / Determination 678538

Determination 678538

Cyclone damage cash settlement and repair scope

FirmLloyd's
Decided2020-11-13
ProductGeneral Insurance · Strata
OutcomeFor the complainant in part
Amount awarded$57,953
Non-financial loss—
Amount claimed$79,786
SourceAFCA PDF

Summary

After cyclone damage, the insurer made a cash settlement that the owner disputed as too low. AFCA accepted the insurer's repair scope but ordered additional payments for a roof calculation error, contingencies, a shed, expert costs and tenant accommodation on proof, with interest, and rejected the larger repair claim.

The panel preferred the insurer's assessment of pre-existing and non-cyclone damage, but found the settlement calculation erred and that the policy extra benefits apply.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Lloyd's determinations · Find similar determinations

Text of the determination

Determination Case number 678538 Financial firm Lloyd's Australia Limited Determination | Case number: 678538 Page 1 of 8 Case number: 678538 13 November 2020 1 Determination overview 1.1 Complaint The complainant holds a Commercial Strata Policy over its property damaged by Cyclone Debbie in March 2017. The policy is underwritten by the financial firm. (Reference to the financial firm will also include reference to the insurer) A claim was submitted to the financial firm and accepted but a dispute has arisen over the extent of the cash settlement offered by the financial firm to resolve the claim. The financial firm has indicated it has not allowed for all damage claimed because areas were not damaged by the cyclone including areas subject to pre-existing damage or wear, tear and gradual deterioration. The complainant is seeking an increased financial settlement from the financial firm. 1.2 Issues and key findings Has the financial firm met its obligations under the claim? No. The financial firm is required to pay the complainant a further sum in settlement of its claim. 1.3 Determination This determination is substantially in favour of the financial firm. The financial firm is required to pay to the complainant the sum of:  $26,147.93 as an additional amount for contingencies,  $10,519.46 for the roof,  $6,285.84 for the replacement shed,  Up to $15,000 towards the costs incurred by the complainant for expert reports and assistance and  Interest on the amounts not already paid, in accordance with section 57 of the Insurance Contracts Act, from 4 November 2019, to the date of payment The complainant is to provide proof to the financial firm of amounts paid for expert reports and assistance. The interest on this amount is to be calculated from the date the payment was made by the complainant. The financial firm is to review its obligations to the complainant for tenant accommodation costs upon proof of loss by the complainant. Determination | Case number: 678538 Page 2 of 8 2 Reasons for determination 2.1 Has the financial firm met its obligations under the claim? The complainant and financial firm do not agree on the covered loss The complainant’s property is covered for accidental damage from any occurrence, subject to general exclusions including wear and tear, gradual deterioration and lack of maintenance. The financial firm arranged for assessor (A) to advise it on the loss sustained because of the cyclone. A arranged a building consultant (M) to provide a scope of works of repairs required. Initial concerns were raised by A as to the extent of the cyclone damage. A reported there was evidence of general wear and tear, and a lack of maintenance. M also held similar concerns and the scope of works reflected this. The financial firm accepted its assessor’s opinion that damage to the paintwork could not be attributed to by the cyclone. It also accepted its assessor’s opinion that the doors and windows had been leaking water with every rainstorm due to maintenance issues and that only a small portion of the tiled roof needed repair. The financial firm also concluded that most of the internal damage was primarily a product of wear and tear and the existence of the property in a tropical environment rather than the cyclone. Builders (T) and (Q) provided quotes on the accepted scope of works. The financial firm preferred T’s quote over Q and authorised repairs. The complainant would not sign the Scope of Works contract presented by T, largely because it disputed the extent of the scope of works. The financial firm facilitated multiple attendances by M and T at the insured premises to attempt to resolve the differences between it and the complainant over the scope of works. The complainant arranged for an engineer (E) to assess the damage from the cyclone. E provide reports from inspections undertaken in October 2018, April 2019 and August 2019. E did not agree that M made sufficient allowance for repairs to damaged areas in the scope of works. E provided a list of the areas in which no allowance had been made in the scope of works where it should have been. An agreement could not be reached on the settlement. The complainant maintains there was no evidence of any wear and tear damage or a lack of maintenance before the cyclone. The complainant also maintains it was entitled to seek a full replacement Determination | Case number: 678538 Page 3 of 8 for the roof and the estimate of costs to repair the premises by the insurer are unrealistic. The financial firm has made a cash settlement The financial firm offered a financial settlement for the roof over the building containing the retail store on the ground floor and residential dwelling upstairs. This settlement was reduced with the reduction of the excess and GST. The settlement paid was $1,788.08. The financial firm made two other payments for incidental expenses in the sum of $1,918.82 and $307.10 before making a final payment of $287,627.19, in November 2019. This sum included an allowance of 10% for contingencies ($26,147.93) and 20% for builders mark up. It should be noted that from the sum of $1,918.82, a sum of money deducted for the excess which the insurer alleged was underpaid in the settlement of $1,788.08. The complainant has disputed the settlement sum The complainant has disputed the cash settlement and the following items remain in dispute: Overall repair costs The complainant and the financial firm remain in dispute as to the overall repair costs. The complainant has produced quotes indicating the repairs to the roof alone would cost over $190,000. Therefore, it submits the scope of works and offers from the financial firm’s repairers are not realistic. The complainant also notes the quotes from the financial firm are very old and do not accurately reflect the current repair costs. Finally, the complainant also notes the f inancial firm’s ch osen repairer is now refusing to complete the work so additional allowances needs to be made for contingencies. The key differences in the sums quoted for the repairs arise from the dispute as to the actual loss and damage caused by the cyclone. The Panel has assessed the reports provided. The Panel prefers M’s assessment of loss over E’s assessment. A & M attended the complainant’s premises very quickly after the financial firm was notified of the claim in May 2017. With T, they have attended the premises on multiple occasions to consider and re-consider the loss and damage flowing from the cyclone. On multiple occasions they have reviewed the loss following observations from the complainant and conducted further assessments to consider these observations. Such attendances have led to variations of the scope of works, and in the panel’s view, fairly so. Determination | Case number: 678538 Page 4 of 8 E attended the premises in October 2018, April 2019 and August 2019. The first attendance occurred almost 18 months after the cyclone. E concedes there were maintenance issues with the premises but does not attach much significance to these issues. E refers to water ingress at multiple points of the premises but does not accept such ingress was caused by any wear and tear or gradual deterioration before the cyclone. E refers to foundation movement contributed to cracking throughout the premises but does not concede such foundation movement could have occurred over time. E attributes the crack to load forces provided by the cyclonic winds. E accepts the assertion of the complainant on the structural state of the premises without any obvious evidence to support such assertions. On balance, the Panel accepts the age and location of the premises lends to the conclusion there was likely to be some evidence of wear a nd tear and deterioration. The Panel accepts the assessments of A and M that much of the repairs claimed by the complainant were pre-existing and not caused by the cyclone. As such, save for a couple of variations, the Panel accepts that the quotation upon which the financial firm based its cash settlement is a fair and reasonable quotation to reflect the loss caused by the cyclone. On the other hand, the panel is concerned that the q uotation used for the cash settlement was not actionable. Whilst the financial firm has allowed a 10% uplift for contingencies ($26,147.19), given the transfer of risk of repairs that occurs when a cash settlement is made, the panel is satisfied it is fair that the financial firm pays an additional 10% for contingencies. This means that the financial firm is to pay the complainant the additional amount of $26,147.93, for contingencies. As noted above, the financial firm made an allowance for roof repairs over the building containing the retail store on the ground floor and residential dwelling upstairs. Such a settlement was reduced with the payment of the excess and GST. The settlement paid was $1,788.08. The financial firm has erred in its calculation of this settlement. The initial quote for this section of the roof was $15,898.08 for repairs as opposed to the complainant’s quote for $29,693.33 for replacement. The insurer then added a variation agreed by T in the sum of $10,890. The accepted sum for repairs was therefore amended to $26,788.08. After further review the financial firm agreed that this should be increased to $41,191.36 but sent a release to the complainant with the sum of $26,788.08. The Determination | Case number: 678538 Page 5 of 8 sum was reduced by the excess of $25,000 and the release signed by the complainant allowed for a payment of $1,788.08 which was duly paid. The financial firm noted there was an error, however, in the settlement proposal as GST was not deducted from the loss, as it should have been. The financial firm therefore concluded that, after the deduction of GST, the complainant was required to pay an extra $647.23 for the excess. This was as opposed to being paid $1,788.08. The financial firm later deducted this $647.23 from a further payment made to the complainant. What the financial firm should have paid was $41,191.36, less GST of $4,531.05 and an excess of $25,000. The sum of which is $11,660.31. Taking away the $1,788.08 it did pay and adding in the $647.23 it deducted from another payment, the financial firm is required to pay the complainant an extra sum of $10.519.46. Accommodation for tenant house 2 nd bedroom @ $77.00/ day (2yrs) $ 56,000.00 The complainant is seeking the costs of having to relocate a tenant for two years because the room was uninhabitable. The financial firm says such loss is not covered by the policy, however, it would be expected that loss of rent from the tenant would have occurred. The Panel does not agree with the financial firm that such a claimed loss is not contemplated by the policy. It is clearly contemplated by section two of the policy. However, there is a shortage of information to calculate the extent of the loss. Upon provision by the complainant of evidence to support this loss, the financial firm is to make additional payment, under the terms of the policy, for the amount proven. Replacement of garden shed (insurers quote) $ 6,285.84 The complainant says it agreed to the cost of the replacement of the garden shed. There is no dispute as to whether the shed should be replaced. It has been replaced but the complainant is alleging that the sum agreed has not been paid. The Panel has seen no evidence that the financial firm has paid the agreed sum for the replacement of the garden shed. As such, the loss is payable by the financial firm unless it can provide proof it has done so previously. Allowance for mental stress of owner including pain and suffering over this insurance issue now almost 3 years of disagreements The financial firm says the complainant is not entitled to such an award under the policy. The financial firm may be correct, but such loss can be contemplated by AFCA in circumstances where AFCA consider that financial firm has conducted itself in a manner that has provided undue delay or aggravation to a complainant. Determination | Case number: 678538 Page 6 of 8 Given the long history of the claim it is often the case such an award may be made. The Panel is not inclined to make such an award in this instance. The delay has primarily been caused by the fundamental differences in the opinion of the complainant and the financial firm in relation to the loss and damage caused by the cyclone. The Panel accepts the complainant has not actively assisted the financial firm in facilitating an earlier agreement. As the Panel agrees with the assessment of the loss by the financial firm, and the Panel considers that the financial firm has made every effort to try and commence repairs on the property, the Panel is not inclined to make such an award. Work involved by owner in complying with insurance requests The financial firm says the complainant is not entitled to such an award under the policy. The Panel notes that such an allowance is contemplated as an extra benefit under section 1 and 2 of the policy. The benefit is capped at $25,000 under section 2. The complainant has not provided evidence of how such a loss is calculated. The Panel also notes that the complainant has been provided with assistance by an experienced claims manager and the allowance is to include such costs. The Panel is therefore not prepared to make an allowance to the complainant under this section. Accommodation for owners whilst house repaired 4wks $2,500.00 The financial firm says the premises are not deemed to be uninhabitable nor will they be rendered as being uninhabitable during the period of reinstatement. As the complainant has not provided sufficient evidence to support such an assertion, the Panel is not inclined to make an award for this claim. Engineers expenses and travel up to $15,000.00 The financial firm says the complainant is not entitled to such expenses as the complainant chose to engage the services of additional parties despite the financial firm absorbing the cost of multiple (independent) Engineering, Loss Adjusting and Building inspections over the course of 3 years. The Panel does not agree that this is the required test. As noted above, the policy does allow such an extra benefit under section 1 and 2 for costs incurred by the complainant in providing evidence the financial firm needs to assess the claim. The panel also recognises the special circumstances of this claim and the assistance provided to the complainant by his experts. Determination | Case number: 678538 Page 7 of 8 Subject to appropriate receipts, the Panel is prepared to allow a contribution of $15,000, towards the cost incurred by the complainant in arranging for the engineer to attend and report on multiple occasions. The complainant has established it is entitled to a further cash settlement The complainant is therefore entitled to receive additional sums for the following: Additional payment for contingencies $26,147.93 Cash settlement for the building $10,519.46 Replacement of garden shed $6,285.84 Engineers expenses $15,000.00 The financial firm should pay interest on the sums in accordance with s57 of the Insurance Contracts Act from the date the complainant submitted the complainant to AFCA, being 4 November 2019. The financial firm is also required to pay the costs incurred for tenant accommodation, upon proof by the complainant of the loss incurred. The financial firm should pay interest on the amount incurred, from the date it was incurred by the complainant. Cancellation of insurance The financial firm denied the complainant ongoing insurance coverage as the property had not been repaired for a lengthy period. The financial firm subsequently agreed to a six-month extension until October 2019. Given the time that has passed, and the repairs not completed, together with the extension offered, the Panel accepts that the financial firm is entitled reconsider its underwriting conditions and has acted fairly in the circumstances. Determination | Case number: 678538 Page 8 of 8 3 Supporting information 3.1 Key references EXTRA BENEFITS 2. Claim preparation costs - We will pay You for those reasonable costs that You incur in providing the claim details that We need.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.