Home / IAG / Determination 678404

Determination 678404

Flood exclusion applied to water inundation damage at veterinary clinic

FirmIAG
Decided2020-03-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer refused most of a flood-related claim for water damage to a veterinary clinic building under the flood exclusion. AFCA found the exclusion not established for the initial stormwater inundation, ordered cover up to 50mm above floor level and roof ingress damage subject to a scope of works, and upheld the exclusion for later floodwater.

The insurer bears the onus to prove the flood exclusion, and stormwater that could not drain into a full river is not water that escaped from the river's normal confines.

Issues

Subjects and remedies

home or building damagenatural disastersmall businesspay claimpay interestreassess claim

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 678404 Financial firm Insurance Australia Limited Determination | Case number: 678404 Page 2 of 8 Case number: 678404 17 March 2020 1 Determination overview 1.1 Complaint The complainant holds an office insurance policy with the financial firm (insurer). The insured property is a building from which the complainant operates a veterinary business located in Rosslea, Queensland. A claim was lodged under the policy after the insured property was inundated with water on or about 3 February 2019. The insurer accepted a portion of the claim, for damage as a result of stormwater ingress via the roof. However, it maintains the remainder of the damage at floor level was caused by flood, which is excluded from cover under the terms of the policy. 1.2 Issues and key findings Is the damage covered under the terms of the policy? Based on the available material, the panel is not satisfied that the insurer has established the initial inundation at floor level was definitely caused by flood as opposed to ponded stormwater runoff. 1.3 Determination This determination is partially in favo ur of the complainant. The insurer is required to meet its liability for damage sustained up to a height of 50mm above floor level in accordance with the policy and as set out under section 2.1 of this determination. The insurer is also required to cover the damage caused as a result of stormwater ingress via the roof. The insurer is otherwise entitled to refuse payment of the balance of the complainant‟s claim on the grounds that the damage caused by ground -water over 50mm above floor level was caused as a result of flood. Determination | Case number: 678404 Page 3 of 8 2 Reasons for determination 2.1 Is the damage covered under the terms of the policy? The complainant holds an office insurance policy with the insurer providing cover for damage to the building and contents, known as „property‟, occurring du ring the period of insurance, subject to the terms, conditions, exclusions and limitations of the policy. The policy specifically excludes damage caused by, or as a consequence of, flood. Flood is defined on page 3 of the product disclosure statement (PDS) as: Flood means the covering of normally dry land by water that has escaped or been released from the normal confines of: a) a lake (whether or not it has been altered or modified); b) a river (whether or not it has been altered or modified); c) a creek (whether or not it has been altered or modified); d) another natural watercourse (whether or not it has been altered or modified); e) a reservoir; f) a canal; g) a dam. The exchanged material confirms the complainant was aware the policy did not provide cover for loss and damage caused by flood. It is accepted insurance law that the insurer carries the onus to establish the application of its policy exclusion for damage caused by flood. Circumstances of the loss In late January and early February 2019, the city of Townsville and surrounding areas of north Queensland experienced a significant weather event. Heavy rainfall occurred in the Townsville catchment over several days and at or around the complainant‟s pro perty. The insured property is a single storey building which operates as a veterinary business. The insurer has provided a report from a hydrologist (BM) dated March 2019, which was prepared following a site inspection on 13 February 2019. BM says the floor level of the building is at a similar elevation to the crest level of B Road in front of the site and the surrounding paving slopes „slightly‟ up towards the floor level of building. It is noted there are stormwater pit inlets directly in front of the property and across the opposite side of B Road. Determination | Case number: 678404 Page 4 of 8 Following the site inspection and review of data from the Bureau of Meteorology and Townsville City Council, BM concluded that the initial and maximum depth of inundation at the insured property was caused by floodwater overflowing from the Ross River. BM is of the view local stormwater runoff would not have inundated the building above floor level. Complainant says initial inundation was caused by stormwater While the complainant concedes that floodwater entered the property at some stage, it considers stormwater runoff entered the insured property prior to riverine flooding. The complainant provided reports from experts including civil engineer SM and water engineer PW. Both SM and PW were of the view that BM did not give adequate consideration to the sheer volume of rainfall that occurred during the 13-day event, nor did it analyse the local stormwater drainage network. BM responded to this via a supplementary reported dated 7 June 2019. BM says that these factors are irrelevant. Regarding the magnitude of the 13-day rainfall event, BM says peak stormwater level near the insured property would typically be generated by storm durations up to three hours. The parties agree that initial inundation at the property occurred at approximately 10:00AM on Sunday 3 February 2019 and BM is of the view the three hours of rainfall immediately prior was insufficient to cause stormwater inundation. Regarding the local stormwater drainage network, BM says this is irre levant because even if the drainage network was overwhelmed by the sheer volume of water, the topography of the area is such that the water could freely drain away down IS Street and L Street towards the golf course and Ross River. Further, BM considers that if there was surcharge from stormwater drains this would be due to high tailwater levels in the Ross River preventing stormwater drainage and causing backflow. BM is of the view that in this scenario the root cause of inundation would be considered flood. The complainant disputes this and provided multiple photos from Saturday 2 February and the morning of Sunday 3 February 2019, showing significant amounts of water pooled in the streets, on the footpaths, nature strips and paving surrounding the building and ultimately entering into the building. The complainant notes the water is clear (as opposed to the brown colour that would usually be expected with floodwater). The complainant says there was simply so much rain over a number of days that the stormwater drainage system was unable to cope and the water was pooling in the streets as it had nowhere to go. The complainant says this ultimately led to stormwater ingress into the building at approximately 10:00AM on Sunday 3 February Determination | Case number: 678404 Page 5 of 8 2019. It accepts that later that night floodwater from Ross River arrived and inundated the property, but says this was after the initial stormwater inundation. Available evidence does not rule out ponded stormwater causing inundation The panel is not persuaded by BM‟s assertio n that the sheer volume of pooled water in the streets due to the 13-day rainfall event and nature of the local stormwater drainage system, can be discounted as relevant factors. While BM says that regardless of the volume of stormwater collecting in the street gutters, it would be able to freely drain away from the property given local topography, the photographs supplied by the complainant clearly show this was not the case. The photographs show large amounts of water pooling in the streets, on the footpaths and nature strips and on the paving surrounding the building as early as the morning of Saturday 2 February 2019. By the morning of Sunday 3 February 2019, this water had entered the building. The Ross River Dam spillway gates were not fully opened until later that night at approximately 8:30pm, according to BM‟s report, though the material supplied by the complainant suggests the gates may have opened automatically at around 5:00PM. In any case, this was subsequent to the initial inundation of the building earlier that morning. BM‟s report indicates that peak water levels in the Ross River occurred late on the evening of Sunday 3 February 2019 and in the early hours of the morning of Monday 4 February 2019. BM says that at the peak of the event, the Ross River “ would ” have overtopped its banks in the vicinity of B Bridge and inundated the complainant‟s building. BM offers no opinion as to whether Ross River likely overtopped its banks prior to this, such as on the morning of 3 February 2019, when initial inundation of the complainant‟s building occurred. The panel notes the photographs show the paving around the building and the surrounding nature strips and streets are all quite flat and at a similar elevation to the floor level of the building. Any sloping of the paving surrounding the building is very slight at most. It is clear from the photographic evidence provided by the complainant that significant levels of stormwater had accumulated and were unable to drain away from the property. Given BM did not initially undertake any analysis of local stormwater drainage systems, the panel considers BM was not in an optimal position to comment on whether the water pooling in the streets inundated the building prior to the arrival of floodwater. Further, the panel notes BM in subsequent reports was also of the view that if stormwater was unable to drain via the local stormwater drainage network due to elevated tailwater levels in Ross River, then the root cause of stormwater inundation could be considered flood. The panel disagrees with this. Determination | Case number: 678404 Page 6 of 8 The policy definition of flood refers to „…. water that has escaped or been released from the normal confines of…. a river….‟ The panel does not accept that water which cannot enter the Ross River through the drains and other infrastructure due to the amount of water already in that river, is water which has escaped or is released from the Ross River. In other words, the panel does not consider that water which could not enter the river because the river level was high, meets the definition of flood. On balance, the panel cannot be satisfied the insurer has established that the exclusion for damage caused by flood applies in respect of initial above floor level inundation at the insured property. It is entirely possible tha t ponded stormwater runoff caused the initial above floor level inundation of the insured property, in which case the policy responds. Conclusions The complainant is seeking for the insurer to agree to the appointment of its preferred engineering expert FM to complete a scope of works for the repair of all damage associated with the stormwater ingress via the roof and the ground level stormwater inundation. Without precise information on which to determine the level of the inundation by stormwater, the panel can only do what is fair in all the circumstances. The panel notes the insurer‟s assessor (S) provided a report dated 8 March 2019, however, S did not provide an estimate of the extent of the insurer‟s liability. Further, the available material does not allow the panel to assess the extent of the damage caused as a result of the initial inundation of stormwater, as opposed to damage caused by the later arrival of floodwater. Having reviewed all of the exchanged material, the panel is satisfied that the insurer is responsible for damage to the property caused by inundation up to a height of 50mm above floor level. In the circumstances, the panel also believes it is fair and reasonable that the insurer be given the opportunity to provide a scope of works and estimate as to the likely costs associated with repairs and damage sustained as a result of the inundation of the insured property to the height of 50mm above floor level, together with the damage caused by water ingress via the roof. The scope of wo rks must be prepared within 14 days of the complainant‟s acceptance of the Determination, subject to the availability of an appropriate person(s) to conduct the assessment. Upon receipt of the scope of works, the parties are asked to work cooperatively together to agree as to the extent of damage sustained as a result of such inundation and in accordance with the terms of the policy. Determination | Case number: 678404 Page 7 of 8 If the insurer cash settles the claim, then the insurer is to pay interest in accordance with Section 57 of the Insurance Contracts Act 1984 (the Act) from 2 May 2019 (date of insurer‟s denial letter) to the date of payment of the claim. If the complainant has already completed the repairs, the insurer is to pay interest from the date the complainant paid for the repairs. If the parties are unable to reach agreement as to any cash settlement, then the parties may return the matter to the Authority for determination as to quantum. Peak inundation caused by flood Having reviewed the exchanged material and considered numerous flood complaints, the panel is satisfied, on balance, that subsequent to the initial inundation the property was inundated by flood. The panel accepts the water would have become flood water when the river overtopped its banks and mixed with the water pooling in the streets. The insurer is otherwise entitled to refuse payment of the balance of the complainant‟s claim on the grounds that the damage was caused as a result of flood. Determination | Case number: 678404 Page 8 of 8 3 Supporting information 3.1 AFCA approach to this dispute We have considered it appropriate to expedite this complaint in accordance with the Operational Guidelines to the AFCA Rules, due to the nature of the complaint. Accordingly, this complaint has not been the subject of a preliminary assessment and has proceeded directly to determi nation. The determination is made by a panel consisting of the Ombudsman together with a consumer representative who has extensive experience in consumer claims and an industry representative who has extensive experience in the insurance industry. The Ombudsman, who has had extensive experience with flood complaints, viewed the general area in November 2019. This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. 3.2 Rainwater that mixes with flood water is flood The Courts have established that once rainwater mixes with flood water, it is all considered flood water. Where rainwater mixes with flood water and causes damage, a flood exclusion will usually apply to defeat the claim. Accordingly, when deciding complaints, consideration has been given to whether there was any rainwater runoff damage before the flood water arrived at the insured property.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.