Cyclone and escape of liquid claims: cash settlement amount, scope of works and claim handling
Text of the determination
Determination
Case number 678075
Financial firm Westpac General Insurance Limited
Determination | Case number: 678075 Page 1 of 11
Case number: 678075 23 July 2021
1 Determination overview
1.1 Complaint
The complainant has two claims with the financial firm (insurer). The first claim (Claim 1) was
due to damage caused by Cyclone Debbie in 2017. This claim was declined by the insurer,
however, subject to a determination by AFCA’s predecessor scheme, the Financial
Ombudsman Service (FOS), the insurer was required to accept the claim for storm damage.
The second claim (Claim 2) relates to damage to the insured property due to an escape of
liquid event when a sink overflowed in the ensuite. The insurer has accepted the claims. The
complainant says the insurer has failed to fulfil its obligations set out under the policy as well
as those provided in the FOS determination.
The complainant is dissatisfied with the insurer’s management of her claims as well as the
complaint process. The complainant believes under Claim 1, the insurer has failed to act with
the utmost good faith and breached of the General Insurance Code of Practice (GICOP). by
attempting to intentionally withhold information (documentation) from her.
In the interest of brevity, the scope of works relating to the repairs to the insured property
under Claim 1 and Claim2, have been combined for the purpose of the insurer’s assessment
of its liability as well as this determination.
1.2 Issues and key findings
Is the insure r’s assessment of its liability under the claims reasonable?
No. The insurer’s final claim settlement to complainant in the amount of $217,562.15 does not
fulfil its policy obligations under the claims. The insurer is to increase and settle the
complainant ’s claims as discussed and set out within section 2.2 of this determination.
Is the complainant entitled to non-financial loss compensation?
Yes. The insurer accepts the level of service provided to the complaint under the claims was
not the level which is to be expected from a professional organisation. I am satisfied the
insurer’s apology and offer to pay the $10,000 in non-financial loss compensation is fair in all
the circumstances.
1.3 Determination
This determination is significantly in favour the complainant.
The insurer is required to increase its settlement as set out in section 2.2 of this
determination. Further, the insurer is to pay the complainant $10,000 in non-financial loss
compensation within 14 days of the complainant’s acceptance of this determination.
Determination | Case number: 678075 Page 2 of 11
2 Reasons for determination
2.1 The insurer has failed to act with the utmost good faith
The insurer has failed to act with the utmost good faith
Having reviewed the available information, I accept the complainant’s opinion that there are
elements within the insurer’s management of her claim that would, on balance, amount to a
failure to act with the utmost good faith.
The available information shows, the insurer was required to reverse its position regarding a
damaged wall at the insured property caused by Cyclone Debbie line with a FOS
determination dated 28 June 2018, which determined the insurer was to cover this damage. It
is clear prior to FOS’s involvement, the complainant had already expressed concerns
regarding the insurer’s appointed consultants ‘IC’ and their assessment of the damage. IC
had been appointed through the insurer’s consultants ‘CC .
The evidence shows IC, who had been appointed before the FOS determination, were no
longer involved with the claim post FOS determination. In September 2018, the insurer
received a scope of works from its consultants CC, which I note was based on the
recommendations previously put forward by IC and which were one of the reasons for the
complainant complaint lodged with FOS. She had rejected and expressed concerns regarding
IC’s proposed repair proposal.
The evidence shows the insurer despite being awar e of the complainant’s concerns c ontinued
to press for her to accept these proposed works. I note the proposed works were clearly not
in the complainant’s best interest, something the insurer’s assessor recognised and had
acknowledged in conversations with the complainant. The works proposed not to repair the
original damaged wall but to build a new wall behind the original wall within the room in
question.
As previously raised by the complainant and acknowledged by the insurer’s assessor on a
site visit, this was not in the best interest of the complainant seeing it would reduce the
area/dimensions of the room in question. Given the parties could not come to an agreement
on the insurer’s proposed works, the insurer appointed consultants ‘LO to the claim. L O were
tasked to attend the insured property to complete and assessment of the damage as well as
review the scope of works proposed by the insurer.
LO attended the insured property and met with the complainant onsite. The complainant says
LO found IC’s p roposed repairs strange and acknowledged that these repairs may not be in
the best interest of the complainant, given it would result in loss of area. LO provided the
insurer with two communications dated 7 December 2018 and 14 December 2018. In the first
communication, LO accepts IC’s proposed repair method may be a plausible and more cost-
effective repair method.
However, in the separate communication dated 14 December 2018, LO notes IC’s proposed
repair method may not be in the best interest of the complainant and it refers to an alternative
method of repair. It is clear this alternative method of repair included a much more significant
scope of works at a higher cost. The insurer contacted the complainant and in referring to
LO’s earlier communication, sought for the complainant to accept the scope of works put
forward by CC based on IC proposal. The complainant noted this was not consistent with her
conversation with LO and requested to be provided with LO’s report for her review.
Determination | Case number: 678075 Page 3 of 11
After numerous requests and close to a month’s delay the insurer provided the complainant
with information from LO in the end of January 2019. However, the insurer did not provide the
complainant with both communications received from LO and only provided her with the one
date d 7 December 2019, which accepted IC’s proposed method of repair to be plausible. The
complainant again expressed concerns regarding the contents of the report and requested
the insurer provide her with all the information it has received from LO.
Following this, the information shows the complainant would then have to make many
repeated requests to be provided with all the information the insurer had received from LO for
several months. The evidence shows the insurer failed to provide LO’s communication dated
14 December 2018 to the complainant until mid-May 2019. Over this period, the insurer
continued to press for the complainant to accept the scope of works proposed by IC and
quoted by CC.
The available information shows over the extended period of time where the insurer failed to
provide the complainant with the requested information, it actually told the complainant there
was only one report from LO (the first communication dated 7 December 2018). It confirmed it
has already provided her with the information received from LO and has, on balance, sought
to withhold LO’s communication dated 14 December 2018 from the complainant.
The available information also shows, at the time of appointing LO, the instruction the insurer
gave to LO were not discuss its opinions/recommendations with the complainant on its visit to
assess the insured property. It told LO this was not its role and any conversation with the
complainant would be attended to by the claims department. The insurer says the failure to
provide LO’s second report to the complainant was an oversight and on realising this it did
send the report to her.
I accept it is not unreasonable to accept that a party may miss a document during ongoing
exchanges of information. However, I find it highly unlikely that a party can overlook providing
a document that is the subject of numerous, repeated and specific ongoing requests over a
period of months. I note the insurer seems to refer to CC’s failure in this regard, however, CC
was appointed by and acts for the insurer for the purpose of the claim and this complaint.
The facts show , on balance, the insurer did not wish to present the complainant with LO’s
alternative repair method which is obviously more expensive and incorporates a significantly
larger sco pe of works. Also, despite being in possession of this engineer’s report and knowing
IC’s proposed scope of works were not in the best interest of the complainant, the insurer has
continued to seek for the complainant to accept IC’s scope of works.
I find this to be completely unreasonable. I accept, on balance, this establishes that the
insurer has failed to act with the utmost good faith towards the complainant under the claim.
Further, that the actions of the insurer, despite a FOS determination in June 2018, have
further deteriorated the relationship with the complainant in terms of trust and that this is a
significant factor for the continued and ongoing delays resulting the insurer’s failure to bring
this claim to conclusion over three years since it was originally lodged.
2.2 Is the insurer’s assessment of its liability reasonable?
The insurer it to amend/increase its final claim settlement offer under the claim
There is no dispute the complainant has valid claims under the insured events of storm and
escape of liquid, which the insurer has now agreed to cover. The complainant however
Determination | Case number: 678075 Page 4 of 11
disputes the insurer’s assessment and therefore the extent of cover it is offering for the loss
and damage claimed.
The product disclosure statement (PDS) states the insurer can, at its discretion, choose to
repair the building or pay the reasonable cost to repair the property. The insurer has offered
to repair the property or pay a cash settlement to repair the property. The complainant has
expressed a preference to be cash settled under the claims.
I accept, under the policy, the insurer has the option to choose whether to authorise and
manage repairs under a claim or to cash settle the complainant for the reasonable cost of
repairs. However, in this instance and for the reasons considered above, I determine the
insurer is to cash settle the complainant consistent with the complainant’s preference for the
claim to be cash settled
The insurer has offered to cash settle the complainant in the amount of $217,562.15 plus
interest for the combined scope of works under the claims. The insurer says its appointed
consultants ‘CC’ have confirmed they are able to complete the authorised repairs for this
amount and so this represents the reasonable cost of repairs.
I am not satisfied the proposed settlement amount is reasonable in the circumstances and is
to be amended in line with the findings of this determination.
The complainant disputes th e insurer’s final scope of works
The complainant disagrees and says there are items/areas of damage that have not been
included within this settlement offer as well as seeks additional payment of temporary
accommodation as part of the settlement.
The comp lainant, in addition to the insurer’s accepted scope of works is seeking cover for
costs associated with installation of windows, landscaping, project management and the
removal and storage of items. The complainant notes the insurer, in making its final claims
settlement offer, has reduced the cost of repairs that were quoted in the original scope of
works.
The insurer says the original quotes included variances which had been reviewed and
costings confirmed by CC before providing the final scope of works and associated repair
costs. Further, the insurer says it is not obliged to cover the windows as the damage to the
area is pre-existing and the replacement windows sought by the complainant are upgrades
and not a like for like for the original aluminium framed windows.
With respect to the landscaping, the insurer notes the quote provided by the complainant from
‘B’, however, says the quote is excessive and that the project management fees are already
built into the scope of works and quotes relied on to offer settlement under the claims.
The complainant has raised concerns about, and provided supporting documentation
including quotes and invoices, several matters. These will be considered below in line with
the relevant policy provisions provided in section 3.
Insurer is to accept replacement of the windows under the claim
The complainant says the rear windows require replacement due to the storm damage and
has provided quotes for her preferred replacements as well as installation of the windows.
The complainant is seeking a cash settlement in the amount of $24,310 for the replacement
timber framed louvre windows based on a quote from ‘E’ as well as $23,375 for a building
quote from ‘MP, that includes the cost t o install the rear windows.
Determination | Case number: 678075 Page 5 of 11
The insurer accepts the windows will need to be removed as part of the scope of works to
repair the accepted storm damage. However, based on a report from CC, it says it expects to
find the windows to be damaged due to rot and gradual deterioration, which is excluded from
cover under the policy. Also, even if it were to accept to cover the windows, the replacement
sought by the complainant would amount to an ‘upgrade’ and not like for like for the existing
aluminium framed windows.
The complainant disagrees with the insurer’s position and says rot has developed due to the
length of time that has lapsed since the claim was lodged in 2017. Having considered the
available information, I accept it shows the cyclone did cause damage to the timber structure
above the rear windows and which has not been repaired since 2017. Pictures show, on
balance, this damage has worsened developing rot over time. I am of the view, if the windows
are expected to be damaged whilst being removed for the purpose of completing the repairs
to accepted under the claim, then it is fair in all the circumstances that this be covered under
the claim.
I note the insurer’s concerns regarding the quoted provided by the complainant and this this
would result in the windows being upgraded i.e. they will not be a like for like replacement.
However, the insurer in expressing this concern has not made available any evidence in the
form of an alternative quote or costings for a like for like replacement. Given the insurer’s
conduct under the claim and in the interest of bring this matter to conclusion, I determine it is
fair in all the circumstances, that the insurer accept and incorporate the quotes from E and
MP into its final claim cash settlement to the complainant.
Insurer is entitled to limit its liability under the garden and landscaping benefit
The complainant has provided an invoice ($275) from consultant B for its attendance for the
purpose of providing a quote for the damage the complainant expects to occur to the garden
as part of the repairs to the insured building. B has provided a report and quote dated 12
December 2020 for the works in the amount of $22,084.
I accept the insurer is to reimburse the complainant for B’s invoice in the amount of $275, if it
has not already done so, as part of the claim settlement. I acknowledge the insurer’s position
that B’s quote is excessive and includes more works than what will be to repair damage
expected to be done to the garden during repair works. Further, that B’s quote includes costs
associated with providing grown plants, trees and shrubs whilst the policy limits cover to costs
associated with re-establishing the garden.
The insurer has also referred to a maximum policy limit of $10,000 for gardens and
landscaping. The complainant says this policy limit relates to damage caused by an insured
event and that it does not apply in these circumstances because the damage to the garden
will be the result of repair works rather than the storm event. I am not of the same opinion, as
having read the policy wording, I am satisfied it limits the insurer’s liability under the claim to:
the cost of replacing landscaping and garden features of the same or similar variety and of
a size suitable to commence the re-establishment of the garden. It specifically excludes
cover for the grown value of a tree, plant or shrub at the time of the event; and
$10,000, for both instances, that is where trees, plants and shrubs are totally destroyed by
an event or are totally destroyed by the work required to repair the insured building.
I note the insurer’s scope of works and costing do not include costs to replace the timber
fence. The scope of works states that the fence requires removal and replacement however
no allowance has been made in the scope of works.
Determination | Case number: 678075 Page 6 of 11
Accordingly, in line with the evidence and to bring finality to this matter, I determine the
insurer is to amend the claim settlement offer to include payment for the fence in the amount
of $3,360 based on the complainant’s quote. The insurer is to also increase the claim
settlement offer to include $10,000 which its maximum liability under the policy for the garden
and landscaping benefit.
Insurer to cover the complainant for alternative accommodation
The complainant is seeking cover for temporary accommodation for the duration required to
complete the repairs to the property. The policy provides extra cover for emergency
accommodation.
The complainant says the repairs will take 4 weeks and has provided a quote for an
accommodation she believes meets her requirements including her pet in the amount of
$5,447. The insurer says it has confirmed with CC that it will provide temporary access to the
property during the time of repairs and that the home is safe is to live in. Therefore, it does
not believe provision of emergency accommodation is required in the circumstances.
The complainant says she has broken both her legs and therefore has issues with respect to
accessing the property via the steep driveway and that her sister also needs easy access to
the insured property. Further, that the works will require removal/damage to the front access
which has approximately a 6-foot drop and so feels accommodation is necessary in the
circumstances.
I accept the works to be completed to repair the insured property are extensive and will
include damage/removal of existing access points to the property, removal of large trees as
well as significant structural works. For this reason, I accept it is reasonable and fair in all the
circumstances that the insurer covers the complainant for costs associated with emergency
accommodation.
I believe the example of temporary accommodation from Airbnb provided by the complainant
is no longer current and appears excessive in terms of the costs claimed. The insurer has
declined cover for emergency accommodation and as such did not provide any information
regarding the cost of such accommodation.
In the absence of other quotes, I think it is fair to allow the complainant $1,000 per week for
emergency accommodation for a period of six weeks. In reaching this figure I am mindful of
the time this matter has been in dispute and the importance of reaching some finality of the
claim. Further, the allowance of six weeks accounts allows for possible over run in time for
completion of the repairs given the current environment. Interest is not payable on this
amount as part of the claim settlement.
Project management and other costs
I note the complainant has provided information relating to the costs/wages of project
managers. Given, she is seeking for the claim to be cash settled, she expects the insurer to
increase the claim settlement so to include project management costs.
I accept the insurer’s position that these costs are built into the quote and cost of repairs put
forward by CC and that CC is prepared to complete the repairs for the quoted amount.
Therefore, this represents what it will reasonably cost the insurer to complete the repairs. It is
not required to increase its claim settlement in line with the complainant’s expected project
management fees in the circumstances.
Determination | Case number: 678075 Page 7 of 11
Similar is the case for removal and storage of large items as these have also been included in
the costings noted in the insurer’s scope of works.
Insurer is not required to cover the cost to replace undamaged sofa
The insurer has agreed to cover the cost of the damaged sofa due to the escape of liquid
claim. However, the complainant says the damaged sofa was part of a pair and seeks the
insurer to pay the cost for the undamaged sofa.
The policy states the insurer will only pay the reasonable cost to repair or replace the item or
part of it that was damaged, and not for any special value it may have as a pair or set.
I am satisfied the insurer ’s offer to cover the damaged sofa alone is in line with its policy
obligations. The insurer has accepted the complainant’s quote for the damaged sofa and
agreed to pay an additional $1,699 plus interest from 5 June 2019. I consider this fair and
reasonable in the circumstances.
Insurer is to reassess its liability under the claim in line with this determination
Other than the issues noted above, I am satis fied the insurer’s proposed scope of works and
therefore liability under the claim meets its policy obligations. Within 21 days of the
complainant’s acceptance of this determination, the insurer is to source the required
additional information and arrange settlement payment to the complainant in line with this
determination.
As noted above, the insurer is to increase the settlement by 20% to allow for contingencies
and the transfer of risk associated with such cash settlement. Further, subject to any
payments already made, applicable policy deductions and amounts excluded from interest in
this determination, the insurer is to pay interest on the cash settlement amount in line with this
determination in line with section 57 of the Insurance Contracts Act 1984 (the Act).
Interest is payable from the 9 September 2020 for the escape of liquid claim, being the date
of the scope of works from CC until payment is made. For the storm damage claim, interest is
to be paid from 29 September 2018, this being 90 days from the date of the FOS
determination instructing the insurer to accept and repair the storm damage, which is yet to
be completed.
In the interest of completeness, in calculating the final claim settlement amount to be paid
under the claim, the insurer is entitled to remove any costs included in the 9 June scope of
works (based on which its final claim settlement offer is made) that relate to the
landscaping/gardening and the removal of the rear windows. The insurer is to then, in line
with this determination, increase the final claim settlement offer to include:
$10,000 for the landscaping (maximum allowed under the policy)
$3,360 towards the cost to replace a portion of the timber fence
$24,310 for the replacement timber framed louvre windows based on the quote from E as
well as a further $23,375 for a building (installation) quote from MP
$6,000 for emergency accommodation
$1,699 plus interest for the sofa; and
$275 for B’s attendance and report prepared for the complainant.
Determination | Case number: 678075 Page 8 of 11
2.3 Is the complainant entitled to compensation?
The complainant is dissatisfied with the insurer’s handling of the claim
The AFCA Rules (Rule D 3.3) allow for an award of up to $5,000 for non-financial loss
compensation, if the insurer caused the complainant to suffer an unusual degree or extent of
inconvenience, delay or interference. AFCA takes a conservative approach when considering
any award of compensation.
The complainant has expressed dissatisfaction for the way the insurer has handled the
claims. The complainant says:
the insurer intentionally withheld documentation including relevant claim related reports
the insurer has engaged in unconscionable conduct during the claim
the insurer has breached its duty of utmost good faith under the Act
the insurer has not adequately addressed the issues raised by the complainant and has
been dismissive in its responses; and
the insurer has unreasonably delayed the claim.
Insurer has apologised for its handling of the claim
The insurer has responded to the complaina nt’s concerns and accepts that the service was
below standard. Additionally, the insurer accepts that it breached the Code by failing to
provide claim related documentation within 10 business days as required under the Code.
The insurer has apologised to the complainant for the service the complainant received
during the claims.
However, the insurer states that it does not accept that the documentation was intentionally
withheld or that it breached its duty of utmost good faith under the Act.
The insurer has offered to pay the complainant $10,000 in non-financial loss compensation
under the claims given the level of service provided and associated delays experienced.
Insurer’s offer of non-financial loss compensation is reasonable
I acknowledge that the complainant ’s concerns and dissatisfaction with the fact she has had
to dispute several decisions made by the insurer since 2017. I accept the insurer does not
dispute this, other than not accepting it failed to act with the utmost good faith and has offered
to pay the complainant $10,000 in non-financial loss compensation.
The insurer’s actions and poor management of the claims will have caused the complainant
an unusual degree of inconvenience, stress, anxiety and interference with her expectation of
enjoyment or peace of mind. It has led to finalistion of the claims being prolonged for an
unreasonable long period of time.
I consider the insurer’s offer of $10,000 ($5,000 per claim) is fair and reasonable in the
circumstances as well as consistent with the maximum that AFCA can award in the
circumstances.
Determination | Case number: 678075 Page 9 of 11
2.4 Why is the outcome fair?
The outcome is fair because the determination acknowledges and accepts several of the
concerns raised by the complainant resulting in an increase in cover to be provided to her
under the claims. Equally, a fair interpretation of the policy provisions ensures the insurer can
limit its liability under the claims in line with its policy obligations. Further, the determination
acknowledges the concerns raised by the complainant r elating to the insurer’s actions under
the claim and accepts the insurer’s offer to compensat e the complainant for these failings is
fair in all the circumstances.
Determination | Case number: 678075 Page 10 of 11
3 Supporting Information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
Determination to the issues that are relevant to the outcome.
3.2 Relevant policy provisions
Gardens and landscaping
If we agree to pay a claim for loss or damage caused by any of the following
insured events – fire, explosion, lightning, earthquake, malicious acts, riot or civil
commotion, impact or storm (not including rain), we will cover the costs of
replacing landscaping and garden features of the same or similar variety and of a
size suitable to commence the re-establishment of your garden.
We will only pay this benefit if your trees, plants and shrubs:
are totally destroyed by the event or have been totally destroyed by the
work required to repair your home after an event,
were living specimens before the event, and
were not being produced for commercial purposes.
Not covered.
flower, vegetable and herb gardens,
non-permanent trees, plants and shrubs (i.e. those in pots), or
the grown value of the tree, plant or shrub at the time of the event.
Premier care (Policy) Up to $10,000
…
Emergency accommodation
If your home is unliveable, we will cover the cost of similar alternative
accommodation for you and any other insureds.
Determination | Case number: 678075 Page 11 of 11
This expense will only be paid if you actually incur costs for emergency
accommodation, and only while your home remains unliveable.
Premier Care (Policy)
Up to 10% of the sum insured or the cost of accommodation for up to 12 months
from the date of the event, whichever is less
3.3 AFCA Rules
D.3.3 An AFCA Decision Maker may decide that the Financial Firm is to compensate
the Complainant for non-financial loss:
a) for a complaint relating to an individual’s privacy rights - injury has occurred to
the Complainant’s feelings or humiliation has been s uffered by the Complainant;
or
b) for other complaints – an unusual degree or extent of physical inconvenience,
time taken to resolve the situation or interference with the Complainant’s
expectation of enjoyment or peace of mind has occurred.