Refusal of roof collapse claim arising from unapproved building modifications, with rent and expert report costs

FirmStewart Title Limited
Decided2020-04-20
ProductGeneral Insurance · Other general
OutcomeFor the complainant
Amount awarded$1,661
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant's roof collapsed after unapproved structural modifications, and the insurer declined the claim. AFCA found the claim covered and ordered the insurer to meet it with interest and rent, and to reimburse $1,661 in expert report costs.

The policy responds where a local authority forces rectification of a structure modified without building approval, and the workmanship and dilapidation exclusion does not apply to such a claim.

Issues

Subjects and remedies

pay claimpay compensationpay interest

Related

All Stewart Title Limited determinations · Find similar determinations

Text of the determination

Determination Case number 675536 Financial firm Stewart Title Limited Determination | Case number: 675536 Page 2 of 6 Case number: 675536 17 April 2020 1 Determination overview 1.1 Complaint The complainant holds a residential purchaser policy with the financial firm (insurer). The policy was incepted during the purchase of her home in April 2019. In August 2019 a section of the roof began collapsing. The complainant lodged a claim on 1 September 2019 for this. The insurer declined the claim on the basis it does not fall within the relevant coverage under the policy. The complainant disputes this. 1.2 Issues and key findings Is the insurer entitled to refuse payment of the claim? The insurer is not entitled to refuse payment of the claim. This is because the information shows the building order was issued because a part of the existing structure was modified without obtaining building or development approval. This falls within the policy coverage Is the insurer liable for the complainant’s incurred rent costs? Yes. This is because the complainant was unable to live in the house given it is structurally unsound and her circumstances fall within the policy coverage. Is the insurer liable for the cost of the complainant’s expert reports? Yes. This is because the experts assisted her position. 1.3 Determination This determination is in favour of the complainant. The insurer is required to meet the complainant’s claim as set out in sections 2.1 and 2.2. The insurer should also reimburse the costs of the complainant ’s expert reports. Determination | Case number: 675536 Page 3 of 6 2 Reasons for determination There has been a full exchange of material between the parties and each party had the opportunity of addressing the issues that arise from the information exchanged. Given the issues involved, it has been considered appropriate to expedite this complaint to determination in accordance with the operational guidelines to the AFCA Rules. The determination is based on what is fair in all the circumstances having regard to the relevant legal principles, good industry practice (including relevant codes of practice) and prior determinations (where applicable). 2.1 Is the insurer entitled to refuse payment of the claim? Expert reports conclude modifications were carried out to the building The complainant purchased the insured property in April 2019. The roof started to collapse in August 2019. The complainant engaged a structural engineer (S) and a building consultant (H) to inspect the home and provide an opinion as to the likely cause. S provided a report dated 29 August 2019. S compared the floor plans in 2009 and noted that as from at least 2014, several walls were removed. This included walls between the kitchen and new living room. S stated it was clear there was excessive deflection of the roof line over the living/meals area. S also identified that some of the under-purlins, struts and ridge beams were cracked, distorted or deflected in the roof space. S concluded the existing roof structure was not structurally adequate. H provided a report dated 18 September 2019. H also identified that several walls have been removed in the same areas. Further, H identified that undersized single beams have been placed in the ceiling and ceiling joists have been joined poorly. Further, H noted:  there are many areas where the propping has not been adequately replaced  one of the existing props was just sitting loosely on the ceiling plaster  works should have been done with a building permit or structural engineering certification The insurer did not provide any expert opinion regarding the building’s structure or to refute these views. Determination | Case number: 675536 Page 4 of 6 Works have been done without the relevant approvals required On 19 September 2019 a building surveyor from the local council attended the property. The local council found there were building works carried out in breach of the requirements of the Building Act 1993 or Building Regulations 2018. An order was made for rectification works to carried out because: there are visual defects to the existing roof framing from the accessible location which could pose a danger to the occupant of the dwelling The council also confirmed in the preceding 10 years, no permits or certificates had been issued for the property. Claim falls within the policy coverage The insurer’s policy covers various risks. Relevant to this dispute is the following wording under the heading ‘Risks affecting your use of the Land’ : n) … you are forced by a Local Authority to rectify or remove all or par t of the structure(s) on the Land (other than boundary walls or boundary fences) because: … (iii) any portion of the existing structure(s) does not comply with or was built or modified without obtaining building or development approvals from the relevant Local Authority, provided building or development approvals would have been required by the relevant Local Authority at the time of construction of the structure. The insurer says the complainant’s claim does not fall within this risk . The council has not issued the building order because of unapproved modifications to an existing structure which would have required building approval. Instead, the order was issued because of visual defects. I disagree with the insurer’s position. The evidence shows the roof is defective because of works done to the property. The reports from H and S support this finding. The insurer has not provided any evidence to refute their analysis. H also indicated that these works required a building permit. Given the amount of walls removed and how it has compromised the roof’s structure , this is plausible and unrefuted by other evidence. Therefore, the evidence shows the roof is defective because a portion of the existing structure was modified without obtaining a building approval from the council. I am also satisfied that if the works were done with a building permit, it is likely the roof would not be defective at the time of purchase. This is because no certified Determination | Case number: 675536 Page 5 of 6 completion order would have been issued with the amount of defects identified. Instead, the owner would have been required to address these and this would have been done before the property was purchased. The insurer’s submissions rests on the wording of the order issued. However, the policy wording does not say that the order must include this wording. Instead, the policy wording simply says that the policy responds if you are forced by a Local Authority to rectify any part of the structure of the land because any portion of the existing structure was modified without building approval. I am satisfied the evidence demonstrates this. The roof is defective because a portion of the existing structure was modified without building approval. This resulted in the building order being issued. Further, and in the alternative, I consider this to be fair in all the circumstances for similar reasons. Exclusion does not apply The insurer has relied on an exclusion under the heading ‘Workmanship, Infestation and Dilapidation’ in the policy which says: any claims, loss or damage relating to the condition and repair of any structures erected on the land, or the infestation or dilapidation of those structure(s). I do not accept this applies. The claim is not due to the condition or repair of the structure or the infestation or dilapidation of the structure. Instead, the claim is because an order was issued by the council regarding modifications done without approval which the complainant must rectify. Further, if it could be said that this exclusion could apply in these circumstances, then it would negate much of the policy coverage. This is because claims under ‘Risks affecting the Land’ would likely often apply to works that are not compliant with relevant standards and requirements. This is unfair and cannot be consistent with the purpose of the policy coverage for these risks. Therefore, after careful consideration of all the available information, I am satisfied the insurer is required to indemnify the complainant for a claim under this section of the policy. Further, in the event this claim is cash settled, the insurer is to pay interest pursuant to section 57 of the Insurance Contracts Act 1984. Interest is payable from 25 September 2019, being the date it denied the claim, until payment is made. Determination | Case number: 675536 Page 6 of 6 2.2 Is the i nsurer liable for the complainant’s incurred rent costs? Policy responds to rent incurred when claim is accepted The complainant has not been able to live in her residence since September 2019. She has been paying $2,340 per month since this time and has provided proof of the payments made. The policy provides the following cover for ‘Rental accommodation’: If you cannot use the Land as your principal place of residence because of circumstances insured under this Policy and we have agreed to indemnify you under the terms of the Policy, you may rent a reasonably equivalent home. We will reimburse your actual rent until you are able to resume the use of the Land as your principal place of residence or until we settle your claim in accordance with our choices under the Policy (whichever is the earlier), provided that we will only reimburse you in respect of your actual rent which we consider to be necessarily and reasonably incurred by you. Given the house was structurally unsound, I accept the complainant could not use the property. I also accept the policy should respond to her claim. Therefore, the insurer should reimburse her rent in accordance with this policy coverage. The insurer should also pay interest pursuant to section 57 of the Act. Interest is payable from when the complainant paid rent or 25 September 2019, whichever is later, until the insurer issues payment. 2.3 Is the insurer liable for the cost of the complainant’s expert reports? Reports assisted complainant ’s position Under Rule D5, AFCA may decide a financial firm contribute to the professional costs incurred by a complainant in the course of a complaint. This is normally capped at $5,000 unless exceptional circumstances apply. This can be awarded when experts were needed for the complainant to understand or establish their claim. The complainant paid $891 for the H’s report and $770 for S’ s report. These reports materially assisted the complainant to establish her claim. The insurer should therefore reimburse the complainant the cost of these reports.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.