Home / IAG / Determination 672959

Determination 672959

Cash settlement amount for escape of liquid building repairs and temporary accommodation

FirmIAG
Decided2020-08-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$105,168
Non-financial loss$1,500
Amount claimed$107,171
SourceAFCA PDF

Summary

After an escape of liquid damaged the complainants' home, they disputed the insurer's $42,340.61 repair scope and claimed $71,000 repairs plus $36,171.12 temporary accommodation. AFCA preferred the complainants' repair quote, ordered $68,996.91 repairs with interest, $36,171.12 accommodation and $1,500 non-financial loss, and refused other items.

The complainants' more complete quote better reflects the likely repair cost, and the insurer's delay and temporary accommodation handling caused unusual inconvenience.

Issues

Subjects and remedies

home or building damagepay claimpay interestpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 672959 Financial firm Insurance Manufacturers of Australia Pty Ltd Determination | Case number: 672959 Page 2 of 7 Case number: 672959 1 June 2020 1 Determination overview 1.1 Complaint The complainants lodged a claim for damage to their property following an escape of liquid event with their insurer, the financial firm (insurer). The insurer accepted the claim and undertook repairs. However, the complainants disagree with the scope of works to address the remaining issues and want to be cash settled. The complainants also want compensation for other losses and for their claims experience. 1.2 Issues and key findings What is the extent of the insurer’s liability for the building claim? The insurer should pay the amounts set out in section 2.1 in full and final settlement of the building claim. Is the insurer required to pay compensation for other items? No. There is insufficient basis to award compensation for the other items being claimed. Should the insurer pay non-financial loss? The insurer should pay an additional $1,500 in non-financial loss given the complainants’ claims experience. 1.3 Determination This determination is partially in favour of the complainants. The insurer should pay the amounts set out in section 2.1. The insurer should also pay an additional $1,500 in non-financial loss. These amounts should be paid within 21 days of the insurer receiving notification that the complainants accept this determination. Determination | Case number: 672959 Page 3 of 7 2 Reasons for determination 2.1 What is the extent of the insurer’s liability for repairs? Claim should be cash settled This complaint has been the subject of an AFCA recommendation issued on 16 April 2020. Part of the recommendation was that it was fair for the claim to be cash settled. The insurer accepted the recommendation, which was partially in favour of the complainants. The complainants rejected it for various reasons. However, they did not disagree that the claim should be cash settled. Given this background, it is reasonable to proceed along the lines of a cash settlement. Parties have provided different quotes The complainants are seeking payme nt of their quote from builder 2B. This quote totalled $71,000. The insurer offered to cash settle the outstanding works for $42,340.61. This appears to be based on JL’s scope of works that was attached to the insurer’s email to the complainants dated 14 June 2019. In its submissions to AFCA, the insurer included a document entitled ‘[JL] Final Mould SOW’. This was referred to in the AFCA recommendation. However, this appears to set out the mould remediation necessary and which was presumably done given:  the insurer says the property has been cleared of any contamination  the amount the insurer has offered is more than what this document says is outstanding  the scope of works included in the insurer’s email differed from this document and does not include mould remediation. Therefore, I accept the scope of works relied upon by the insurer is that attached to its email to the complainant. I also accept the amount that would have been charged by JL for those scope of works is $42,340.61. 2B ’s quote includes items that are missing in JL’s scope One aspect of the complainant’s quote that the insurer disagrees with is the requirement for an engineer to assess the property. However, I note the following item in JL’s scope of works: Remove and replace damaged timber frame as required by the engineer This indicates an engineer may be necessary. Determination | Case number: 672959 Page 4 of 7 2B refers to possible concrete cancer. 2B provided photos of the exposed concrete in support. The insurer has not specifically addressed this. I accept this provisional sum should be included as a possible contingency. 2B also refers to a rotten bottom plate loadbearing wall and other aspects. 2B provided photos in support. The insurer does not specifically comment on this. This should be included and lends further support to the engagement of an engineer. 2B ’s scope also differs from JL as it replaces all items in the bathrooms whereas JL reinstates some of the original fixtures. It is not clear if some of the original fixtures could not be reused. It is also not clear if the removal process could damage the original fixtures. 2B does include the engagement of a mould remediation company to identify and organise a safety strategy. It is not clear this is necessary as PN’s latest report does not indicate there should be outstanding items. However, given the absence of any clearance certificate, it is appropriate to include this. The insurer has not highlighted other aspects of 2B’s quote that it disagrees with. Most of the other items are fairly consistent with JL’s scope of works. Repairs should be based on 2B’s quote After carefully considering the available information, I prefer 2B’s quote for the following reasons. 2B’s quote is available to the complainant. Therefore, it more likely reflects the cost the complainants would incur for the damage. 2B includes it ems that are not addressed by JL’s scope of works and appear necessary. I acknowledge 2B’s quote includes other items that may not be necessary, such as concrete cancer or replacing all fixtures and fittings. However, I accept these inclusions account for the possible variances and contingencies that may arise in works. This includes potential damage to fixtures and concrete cancer. According to the insurer’s email to the complainants dated 14 July 2019, a cash settlement for the hallway flooring was issued . This totalled $2,003.09. 2B’s scope of works includes the hallway flooring. This amount should therefore be deducted. The complainant, when rejecting the case analyst’s recommendation, said an additional allowance should be provided for COVID-19 issues. I accept interest should be payable on this quote. This quote was issued on 26 September 2019 and it is likely to be outdated to a certain degree. However, I do not accept further allowances should be made. There is nothing to indicate that building Determination | Case number: 672959 Page 5 of 7 works and timeframes have increased markedly, particularly given the restrictions are continually changing and currently easing. Therefore, the insurer should pay $68,996.91 for the outstanding repairs plus interest pursuant to section 57 of the Insurance Contracts Act 1984. Interest is payable from 26 October 2019, being one month after the quote was issued and would have likely lapsed, until payment is made. Insurer should pay $36,171.12 for temporary accommodation The complainants say 64 days is required for the repairs. This is consistent with 2B’s quote. There is no dispute the property will be uninhabitable due to the repairs as two bathrooms are being substantive repaired. The insurer has allowed six weeks (42 days) for temporary accommodation. However, t his was based on JL’s scope. Given I have preferred 2B’s quote, then it is fair to allow 64 days. The complainants, when rejecting the recommendation, provided a quote for $36,171.12 of temporary accommodation. This was for a period of 64 days and included accommodation for their pets. The insurer has not disputed the rates are reasonable. Therefore, the insurer’s settlement should include $36,171.12 for temporary accommodation. Interest is not payable on this given it is not a cost the complainants have incurred yet. 2.2 Is the insurer required to pay compensation for other items? Insufficient basis to accept other items being claimed The complainants have sought compensation for various other items, including:  cleaning contaminated clothing  replacement of clothing and other items due to contamination  replacement of the gas heating system, evaporative cooling system and split system air-conditioning unit  medical bills The complainants say these costs were incurred due to the poor containment measures undertaken by the insurer. This caused the vents of the various systems to be contaminated as well as their clothing and other items. They also incurred medical costs. There is insufficient information to show the clothing was contaminated. Whilst the complainants provided numerous photos, it is not apparent from them that these Determination | Case number: 672959 Page 6 of 7 items were contaminated, required cleaning or replacement. No other report or expert was obtained to verify that they were contaminated and required additional cleaning or replacement. No information was provided to confirm the heating and cooling systems were actually damaged. 2B’s quote note d possible contamination. However, this has not been verified. Given this, there is insufficient basis to allow this. It is not clear from the medical invoices that these were due to the claim or other factors. Given all this, I am not satisfied there is sufficient basis to award the amounts sought by the complainants. 2.3 Should the insurer pay non-financial loss? Compensation is awarded conservatively Under the AFCA Rules, we may award compensation (capped at $5,000) for non- financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interfere nce with their expectation of enjoyment or peace of mind. We take a conservative approach to compensation for non-financial loss. It is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Insurer should pay an additional $1,500 in non-financial loss I accept there were aspects of the insurer’s claims handling that could have been improved. The repair process has been substantively prolonged. The insurer’s technical assessor noted this was unacceptable in a claim note on 3 June 2019. There were also issues with the temporary accommodation. The complainants were told initially it was short term. However, this became substantively prolonged and caused an unusual degree of inconvenience . The complainant provided evidence of a mould related illness. However, it is not clear this was due to the insurer’s handling of the claim. Whilst the leak had been reported to the insurer on 15 November 2018, it is not clear if it had been occurring before then and may have affected their health during that time. The complainants have raised concerns that the mould containment was insufficient. This was not specifically addressed by the insurer. Given there were mould issues identified several months after the repairs began, then the complainants would have been understandably stressed by this. Determination | Case number: 672959 Page 7 of 7 The insurer has offered to refund the $1,000 excess and to undertake the repairs through another builder. The insurer has also provided temporary accommodation during the dispute. These mitigate the inconveniences suffered to a degree. However, I do not accept they do so fully given the above factors. Therefore, it is fair in all the circumstances the insurer pays a further $1,500 for non- financial loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.