Lender paid builder on allegedly forged drawdown notices; higher default interest rate applied
Text of the determination
Determination
Case number 671751
Financial firm Balanced Securities Limited
Determination | Case number: 671751 Page 2 of 10
Case number: 671751 5 June 2020
1 Determination overview
1.1 Complaint
The complainants are a company and its director. The company entered into a
contract with a builder on 13 July 2016 for a project for construction of five
townhouses on a block of land in Sydney. It obtained a construction loan ***227 (loan)
from the financial firm (lender) subject to the loan terms in a facility agreement of 19
January 2018 (agreement) and mortgage memorandum (memorandum) under which:
The principal sum borrowed was $2,575,000.
The loan was to be drawn down over a year in a series of progress payments.
The loan is secured by a mortgage over the five townhouses and by personal
guarantees from the director, NC, ZC and MC.
The complainants say the lender:
paid the builders based on four forged drawdown notices (disputed notices)
is charging a higher than usual interest rate
caused them loss as the builders had no incentive to finish work properly because
they were paid direct by the lender regardless, causing completion to be delayed.
An AFCA case manager gave the parties a recommendation in the lender’s favour
dated 24 February 2020. A copy is attached to this determination.
1.2 Issues and key findings
Were the findings of the recommendation correct?
The findings in the recommendation were correct and are adopted in this
determination. I have considered submissions made since the recommendation.
Do the complainants ’ further submissions change the outcome?
The complainants ’ further submissions do not change the outcome for the reasons set
out in section 2.2, below.
1.3 Determination
This determination is in the lender’s favour. It is not required to compensate the
complainant. If the complainant accepts the determination then the lender should give
it three months from the date of its acceptance to repay the outstanding loan balance
or provide an unconditional contract of sale for the security properties and a further 30
days to finalise settlement. If the complainant rejects the determination or fails to pay
Determination | Case number: 671751 Page 3 of 10
the debt in full or sell the properties within the specified time period, the lender can
take enforcement action in accordance with the loan terms.
Determination | Case number: 671751 Page 4 of 10
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
The recommendation was correct
I have decided this case on its merits, having regard to the relevant law, good industry
practice, codes of practice and previous AFCA decisions. I have considered all the
material submitted by the parties, both before and after the recommendation. I am
satisfied that the documents I have relied on have been provided to both parties.
I am satisfied the case manager’s recommendation contains an accurate summary of
the complaint, the issues to be determined, any applicable paragraphs of the Rules
and any relevant law.
The complainant rejected the recommendation
The complainant rejected the recommendation and says:
the lender controlled when the builders were paid
the lender did not act diligently by failing to detect the forged drawdown notices
and breached a duty of care owed to them
if they had known the lender was paying the builder based on forged drawdown
notices, they would have cancelled their contract with the builder and found new
builders
the builder’s costs were paid before they had completed set building tasks
their contract with the lender and the clauses referred to in the recommendation
are unfair and unreasonable
Clause 189 of the memorandum specifies the conditions on which the lender would
pay the builder. The lender has breached this clause by accepting the forged
drawdown notices
the recommendation was wrong to say that if the builder had not been paid, there
would have been building delays
the lender has failed to meet its anti-money laundering (AML) obligations
the lender did not act in accordance with regulatory guidance issued by the
Australian Securities and Investments Commission (ASIC), in particular:
> Regulatory Guide (RG) 104, and
> RG259.
Overdue interest rates were charged due to the predicament the lender put them
in. By paying the builder without their consent, the builder did not have incentive to
complete the work to an acceptable standard on time. The lender is looking to gain
from its own compliance failure through default interest for the period. The reason
the complainants cannot sell the t ownhouses is based on the builder’s indifference
Determination | Case number: 671751 Page 5 of 10
to complete the works and provide an occupancy certificate (OC). Had a sizeable
portion of the drawdown advances been withheld until OC, the builder would have
finished the project on a timely basis.
2.2 Do the complainants ’ further submissions change the outcome?
The lender was entitled to control when the builder was paid
The complainants say the lender, not them, controlled the borrowed funds and when
the builder was paid. They say this is unfair because the complainants should have
had the final say about when to pay the builder.
With construction loans, lenders will often provide loans over a relatively short time
period. This means that it is very important that construction finishes on time, so that
the new properties can be sold, and the loans repaid on time. It is not uncommon for
lenders, when providing loans for the construction of property to give themselves (in
the loan contract,) broad rights to control the funds being lent.
The agreement provided at clause 3.8:
The advance shall be made available to the Borrower by the Lender in such instalments as
the Lender may in its absolute discretion from time to time determine…and any such
instalment may be paid to the Builder or Contractor employed in construction.
The memorandum at clause 205 provided:
Payments may be made directly to the builder or contractor involved in the
Construction by the Lender and:
a) such payments will form part of the Debt;
b) the Lender is under no obligation to ensure that the Construction or any part thereof
has been completed adequately or in accordance with the building contract before
making any such payment;
c) the Debtor hereby indemnifies and holds harmless the Lender in respect of any such
payments; and
d) no rights will accrue to the Debtor because of such payments and the Debtor releases
and forever makes the Lender safe from any such claim.
It is therefore apparent that under the contract:
the lender had absolute discretion over when to pay instalments
the lender was entitled to make payments direct to the builder
the lender did not require the complainants ’ consent to pay the builder direct
the lender was not required to ensure any part of construction had been
adequately finalised before making a payment to the builder
Determination | Case number: 671751 Page 6 of 10
the complainants did not have the right to control when payments were made to
the builder
the complainants did not have the right to require the lender to withhold payments
until any part of the construction had been completed adequately or in accordance
with the building contract.
While I accept the complainants feel the contract terms are unfair, the information
shows that they:
were given a copy of the agreement and memorandum
accepted the terms and conditions disclosed in these documents
obtained independent legal advice before entering into the contract and guarantee.
This was a business to business loan, not a consumer loan. Therefore, the unfair
contract term provisions of the Australian Consumer Law and the National Consumer
Credit Protection Act (NCCP) do not apply to it.
There is no information to show these terms were unfair in the context of this
complaint, or that the complainants were misled about who had control of how and
when payments were made under the loan contract.
If the disputed notices were forged, this does not change the outcome
The complainant says the lender did not act diligently because it did not detect that
the disputed notices were forged and that it is not in accordance with good industry
practice to make payments based on forged drawdown notices. They say if they had
known the lender was paying the builder based on forged drawdown notices, they
would have cancelled their contract with the builder and found new builders
The contract defines a drawdown notice as:
A notice in writing from the Borrower to the Lender…detailing the purpose for which the
Advance is requested and monies applied to the Project
Clearly therefore, a purported drawdown notice which is not actually from the
borrower (complainant company), does not qualify as a drawdown notice under the
contract. If any of the disputed notices were not actually signed by the borrower, the
effect would be that the borrower never gave instructions to the lender to draw down
those funds.
I agree with the complainants that it is not good industry practice to make payments
based on forged signatures. If the borrower did not sign the drawdown notices, it did
not instruct the lender to pay the builder. If the contract had required the borrower to
approve payment to the builder before the lender could advance funds to the builder,
by acting on forged signatures, the lender would have breached its mandate and
would effectively have paid away its own funds.
Determination | Case number: 671751 Page 7 of 10
However:
Whilst the condition precedent in clause 8.1 of the contract provides that the lender
does not have to make a payment under the contract until the borrower gives it a
drawdown notice, clause 8.4 makes it clear that the conditions precedent are “for
the benefit of the Lender, which may, in its absolute discretion, waive compliance
with any one or more of them”. Therefore, the lender was not required to obtain a
drawdown notice from the borrower before making payments under the loan.
Whilst clause 189 of the memorandum requires that requests from the borrower for
progress payments must be made in writing and specifies what information the
lender requires for those requests; it has to be read in conjunction with clause 205
and the relevant clauses of the agreement, which provide the lender can pay the
builder direct and can make payments at its absolute discretion.
The contract did not require the borrower to approve payments to the builder
before the lender could pay them (see above). It was entitled to pay instalments
directly to the builder at its absolute discretion. Therefore, even if the lender had
realised the drawdown notices were forged and had refused to act on the
instructions in them, it would still have been entitled to pay the builder without the
borrower’s consent.
This is because it was important for the lender that the builder finished work on time,
so that the loan would then also be paid out on time. The borrower was not entitled to
withhold payments from the builder or to have instalments paid to it – it was upto the
lender when it paid instalments and whether it paid them direct to the builder or not.
The complainants say if they had known the lender was paying the builder based on
forged drawdown notices, they would have cancelled their contract with the builder
and found new builders. However, the facility agreement made it clear the lender
agreed to the advance of funds for the project subject to the specific builder and
specific building contract detailed in the agreement. Therefore, the company was not
free to unilaterally change the builder it was using – it would have been in breach of
the agreement if it had replaced the builder without the lender’s consent , which it was
not obliged to give.
The lender did not have a fiduciary duty
In general, a financial services provider, such as a lender or credit provider, does not
have a “fiduciary‟ duty or responsibility to put a customer’s interests before its own .
This means that it is not obliged to conduct due d iligence on a customer’ s proposed
investment or project.
The relationship between the lender and the complainant company is a commercial
one, based on the law of contract. In this case, neither the loan contract, nor any
industry code incorporated into the contract, or good industry practice, committed the
lender to such a duty. No such duty exists generally at law.
Determination | Case number: 671751 Page 8 of 10
A fiduciary responsibili ty arises only where the lender’ s role is seen to extend beyond
that of finance provider and into the area of advice, or where the lender agrees to
provide a dedicated exercise of its judgment for the customer ’ s interests alone and
not in any way for its own benefit. There is no information to show this was the case in
the circumstances of this complaint.
The complainant has not shown it suffered loss from any error by the lender
The complainant says by processing the payments based on forged signatures on the
drawdown requests, the lender caused completion of construction to be significantly
delayed. This was because the builder had no incentive to complete works to the
required standard, as it was receiving payment regardless.
If the complainants had received the payments, they could have withheld them from
the builder until it completed each part of the construction to the required standard. By
paying the builder direct without the borrower’s consent, the lender removed any
negotiating power the complainants had with the builder during the project. The
complainants say they had to fund finalisation of some works which the builder had
not done properly, themselves.
Even though I appreciate this would have been frustrating for the complainants and I
accept the lender made an error if it accepted forged signatures to process the
disputed notices, the complainants have not shown they suffered any loss as a result
because:
the lender was entitled to pay the builder direct without the complainants ’ consent
and without requiring that any part of the construction be finished to an acceptable
standard first
the funds drawn down were paid to the builder for the purpose of construction of
the townhouses and were not used for some other purpose. The complainants
have benefitted from the builder’s work funded by the payments (even if it was not
to the standard they wished) and I understand are earning rent from the
townhouses
even if I were to accept that the lender should not have paid the funds direct to the
builder (even though it was entitled to under the contract), to determine whether
the payments based on the disputed notices were the cause of completion being
delayed, would require evidence from the builder. AFCA does not have the powers
of a court to require third parties to give evidence and test that evidence under oath
the lender was entitled to include any payment to the builder in the debt owed by
the borrower
the lender was entitled to charge the higher interest rate in accordance with the
loan terms. The loan was first drawn down on 22 August 2017. The lender’s
account statements show that it has applied the higher rate of interest since 22
August 2018. This is the date on which the loan matured and was to be repaid by
the company. The loan was not repaid, which constituted an event of default under
Determination | Case number: 671751 Page 9 of 10
the agreement. Accordingly, the higher rate of interest applies until the loan is
repaid in full.
The complainants are not entitled to any compensation from the lender
The complainants have not shown the lender made errors causing them loss
warranting compensation. AFCA does not award compensation to punish a lender for
making an error.
The complainants are liable for the full outstanding loan balance.
AFCA cannot consider the builder’s actions. The complainants are free to pursue
action against the builder.
Determination | Case number: 671751 Page 10 of 10
3 Supporting Information
3.1 Other issues raised by the complainant
The complainant raised the following issues, but it is not necessary to deal with them
in detail, as they do not change the outcome:
The complainant says the lender did not comply with its AML obligations.
Australian Transaction Reports and Analysis Centre (AUSTRAC) regulates AML
compliance by reporting enti ties. AFCA is a dispute resolution scheme for financial
services but does not regulate the financial services industry. Our role is to
consider specific types of complaints about errors made by our members and we
can award compensation for loss or damage c aused by those errors. I cannot
consider whether the lender complied with its AUSTRAC obligations , but the
complainant is free to raise such issues with AUSTRAC.
https://www.austrac.gov.au/contact-us
AFCA does not have jurisdiction to review the lender’s compliance or fraud
detection procedures and policies. This is because such a policy or procedure is a
commercial one for the lender to make taking into account its risk appetite.
RG104 is more broadly about financial firms having systems in place to ensure
they are effectively complying with their legal obligations within Australia. RG104 is
silent on the issue of construction loans and forged drawdown notices.
RG259 does not support the complainant’s pos ition. RG259 considers how a
financial firm implements risk management systems on a more broader level. The
complainant says the lender had inadequate risk management systems in place to
detect forged drawdown notices. Whether or not the disputed notices were forged
does not change the outcome . Any issues about the lender’s risk management
systems compliance with RG259 is an issue of practice and policy and is not
something I can review. However, the complainant is free to raise any regulatory
compliance issues with ASIC https://asic.gov.au/about-asic/contact-us/
Recommendation
Case number 671751
Financial firm Balanced Securities Limited
Recommendation | Case number: 671751 Page 2 of 7
Case number: 671751 24 February 2020
1 Overview
1.1 Complaint
The complainant is a company (the company) created for constructing five
townhouses on a block of land in Sydney. The company obtained a construction loan
***227 (the loan) with the financial firm (the lender).
The loan was to be drawn down over a period of a year in a series of progress
payments made to the builders.
The complainant says the lender:
paid the builders based on four forged drawdown notices (disputed notices), and
is charging a higher than usual interest rate.
The loan is secured by a mortgage over the five townhouses and by personal
guarantees from RC, NC, ZC and MC. The loan contract comprises a Facility
Agreement (the agreement) and a Mortgage Memorandum (the memo).
The principal sum borrowed is $2,575,000. The balance of the loan account was
$3,415,191 on 23 December 2019.
1.2 Issues and key findings
Was the lender entitled to rely on the disputed notices?
The lender was entitled to rely on the disputed notices. The agreement between the
parties confirms the “conditions precedent” for th e payment of the drawdown notices
are for the lender’s benefit which it can waive.
Is the lender entitled to charge the higher rate of interest?
The lender is entitled to charge the higher rate of interest because the loan is in
default.
1.3 Recommendation
This recommendation is in favour of the lender. It is not required to pay the
complainant compensation or provide any other remedy. If accepted by the parties,
the following should occur within 14 days of the acceptance:
the lender should provide the complainant with a period of three months to repay
the loans, and
Recommendation | Case number: 671751 Page 3 of 7
if the complainant is unable to repay the loans within three months, the lender will
be entitled to enforce its rights under the terms of the loan contract.
Recommendation | Case number: 671751 Page 4 of 7
2 Reasons for recommendation
2.1 Was the lender entitled to rely on the disputed notices?
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test evidence on
oath, or to require third parties to give evidence. When we assess complaints, we
consider available documents, the recollections of the parties, and all relevant
circumstances. We give more weight to contemporaneous documentary information.
The complainants say the disputed notices were forged
Section 3.1 below lists the disputed notices. The complainants say:
the signatures on the disputed notices were forged
the lender should have declined to pay the builders the amounts claimed in those
notices
because they did not authorise the disputed notices, the lender has made an error
and is now liable to compensate them. They say:
under the terms of the loan, the Lender requires the signature of the Borrowers
or its authorised representative before payments to the builder are made or
drawdowns are affected.
A drawdown notice was a condition precedent to a progress payment
The relationship between the parties is contractual in nature, so where the
complainants say the lender has made an error, it is necessary to investigate the
terms of the agreement that governs their relationship.
Clause 8.1 of the ag reement lists the “ Conditions Precedent to Drawdowns for the
Project ”. They list the conditions which must be met before the lender is obliged to
make a progress payment to the builder.
The relevant provision is clause 8.1(k) which says the lender is not obliged to make a
progress payment until “the Borrower has given the Lender a Drawdown Notice”.
A “Drawdown Notice” is defined in the agreement as a notice “from the Borrower”.
Since the disputed notices were forged, they were not “provided by the Borrower ”.
The complainants say that for that reason the lender should not have made payment
to the builder based on those notices.
The lender was entitled to make the progress payments
It would appear from clause 8.1 of the agreement that if the company had not
provided the disputed notices, the lender should not have paid the builder the sums it
Recommendation | Case number: 671751 Page 5 of 7
claimed. On that basis, it would seem appropriate that the company, and therefore the
complainant, are not liable to repay the lender the sums it paid to the builder.
However, clause 8.4 of the agreement makes it clear that the lender was entitled to
make payments to the builder even if it had not received valid drawdown notices. It
says:
Each of the conditions precedent in Clauses 8.1, 8.2 and 8.3 is for the benefit of th e
Lender, which may, in its absolute discretion, waive compliance with any one or more
of them
The lender effectively waived the requirement for valid drawdown notices when it paid
the builder on the basis of the disputed notices.
The lender had a contractual obligation to pay for the construction of five townhouses.
Its obligation to do so was subject to the terms of the agreement.
The complainant is not entitled to compensation
For a claim to succeed, a complainant must establish that the lender made an error or
breached an obligation owed to the complainant, and that the error or breach caused
them actual loss which was not too remote.
As long as:
the money it paid was paid to the builder for the purpose of construction of the
townhouses, and was not used for some other purpose, and
the lender acted in accordance with the terms of the contract,
the money it paid out became a debt owing by the company to the lender.
For the reasons set out above, the lender paid the builder on the disputed notices in
accordance with its rights under the agreement.
If the builder forged the disputed notices, and if the company suffered loss as a result,
that is an issue between the company and the builder. The forgery does not affect the
lender’s entitlement to pay the b uilders and ensure construction completed on
schedule.
In this case, the complainant has not established the lender made an error by paying
the builders for the construction of the townhouses.
The whole of the money paid by the lender to the builder is owing by the company
and the guarantors.
Recommendation | Case number: 671751 Page 6 of 7
The building delay is a matter for the complainant and the builders
The complainant’s solicitors also say:
Furthermore, our client argues that this lack of checks and balances that he could
have carried out if he had controlled the timing and amounts of the payments to
the builder has resulted in the project being delayed (so that the project took 18
months to completion instead of 12 months).
It is not clear what is meant by “checks and balances”. It seems to mean that the
company would not have signed the disputed notices if the builder had asked it to. If
so, this might have resulted in the construction taking longer than it did. In any event,
the lender is not responsible for the failure of the company and the builder to agree on
what work had been done.
2.2 Is the lender entitled to charge the higher rate of interest?
The higher rate applied from 22 August 2018 when the loan went into default
The loan was first drawn down on 22 August 2017. The lender’s account statements
show that it has applied the higher rate of interest since 22 August 2018. This is the
date on which the loan matured and was to be repaid by the company.
The loan was not repaid and accordingly, the higher rate of interest applies until the
loan is repaid in full. The complainant signed the loan contracts with the lender and
was accordingly on notice of the pending higher interest rate. The lender is not liable
to compensate the complainant for the building delays.
Recommendation | Case number: 671751 Page 7 of 7
3 Supporting information
3.1 Disputed drawdown notices
Date Amount
21 - Jun - 18 $ 66,191
21 - Jun - 18 $ 142,005
21 - Jun - 18 $ 243,583
19 - Jul - 18 $ 340,085
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.