Home / Search / Determination 671721

Determination 671721

Credit union released progress payment 7 without borrower endorsement while works were incomplete

FirmBCU ( a divisi on of Police and Nurses Limited )
Decided2020-09-02
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$52,987
SourceAFCA PDF

Summary

The complainants sought reimbursement of a $52,987 progress payment the credit union released to a builder whose company went into liquidation, alleging incomplete works and no endorsement. AFCA found the credit union was entitled to rely on the valuer's inspection and the complainants' own breaches caused the loss.

A lender's contractual drawdown conditions give it a right, not a positive duty, to refuse payment, and the borrower bears responsibility for works under the building contract.

Issues

Subjects and remedies

home or building damageno remedy

Related

Find similar determinations

Text of the determination

Determination Case number 671721 Financial firm BCU ( a divisi on of Police and Nurses Limited ) Determination | Case number: 671721 Page 2 of 11 Case number: 671721 2 September 2020 1 Determination overview 1.1 Complaint In July 2017 the complainants ( Mr and Mrs B ) obtained a construction loan from the financial firm ( credit union ) in an amount of $500,000 ( loan ) to be drawn down during the construction period. In March 2018, the complainants entered into a fixed price building contract with a builder for $331,169 ( building contract ). After construction commenced, several progress payment claims were submitted by the builder to the complainants, passed on to the credit union by the complainants and paid by way of the credit union processing drawdowns on the loan. This complaint is about whether the credit union breached any obligation it owed to the complainants when it paid progress payment claim 7 dated 8 October 2018 ( PPC 7 ) for an amount of $52,987 ( payment ). The complainants say:  the valuer who inspected the works the subject of PPC 7 and recommended the payment be released, did so when the works were incomplete  the credit union should not have released the payment  the builder‟s company ( company ) went into liquidation on 15 October 2018, and  because the works the subject of PPC 7 were incomplete, the complainants themselves had to pay for those works to be completed. The complainants are seeking reimbursement of $52,987 plus interest. On 8 January 2020, the case manager issued a recommendation in this matter which was in favour of the credit union. A copy of the recommendation is attached to this determination. The complainants rejected the recommendation and the matter proceeded to determination. 1.2 Issues and key findings Were the findings in the recommendation correct? The findings contained in the recommendation were substantially correct and are adopted in this determination. Further submissions provided by the complainants after the recommendation have been considered. Do the complainants ’ further submissions change the outcome? I have considered the complainants ‟ further submissions. For the reasons set out in Section 2.2 below, they do not change the outcome of the complaint. Determination | Case number: 671721 Page 3 of 11 1.3 Determination This determination is in favour of the credit union. The credit union is not required to compensate the complainants or take any other action. Determination | Case number: 671721 Page 4 of 11 2 Reasons for determination 2.1 Were the findings in the recommendation correct? The findings in the recommendation were substantially correct I have decided this complaint based on what is fair in all the circumstances having regard to the relevant law, good industry practice, codes or guidance as to p ractice and previous AFCA decisions. I have considered all material submitted by the parties and I am satisfied that the material I relied upon in reaching my findings has been exchanged between the parties or is otherwise in their possession. I am satisf ied that the case manager‟s recommendation contains an accurate summary of the complaint, the issues to be determined, any applicable paragraphs of the Rules and any relevant law. I am satisfied that the findings in the attached recommendation were substantially correct, and I adopt them in this determination. In particular, I find that:  the credit union did not breach any obligation owed to the complainants when it made the payment, and  the credit union is not responsible for the complainants‟ loss . I make further observations and findings below. The complainants rejected the recommendation and made further submissions The complainants rejected the recommendation and made further submissions, including that the credit union:  breached the terms and conditions of the loan ( terms and conditions ): > by making the payment without their endorsement > by making the payment when the contracted works were not completed to 88% of the contract price > in accepting an unsigned builder ‟ s invoice > in failing to confirm all subcontractors had been paid to the date of the invoice, and  caused them loss as they had to pay twice for the incomplete works that had not been completed when the payment was made. 2.2 Do the complainants ’ further submissions change the outcome? Clause 4 does not impose positive obligations on the credit union The complainants submit that the credit union breached the terms and conditions when it made the payment. I have reviewed PPC 7 and clause 4 of the terms and Determination | Case number: 671721 Page 5 of 11 conditions, in particular (sub)clauses 4.3 “Conditions for payment of monies due under a building contract” , 4.4 “Form of progress payment claim”, 4.5 “Procedure for payment of a progress payment claim”, and 4.7 “General” . These clauses are extracted in Section 3.1 below. The complainants are correct in identifying that the credit union made the payment when aspects of PPC 7 did not meet the requirements in clauses 4.3 and 4.4 – in particular, PPC 7 was not signed by the builder and did not confirm that all subcontractors had been paid to date. In relation to the question about whether all subcontractors had been paid as at the date of PPC 7, while the complainants have supplied two unpaid subcontractor invoices, I am unable to find that these were relevantly overdue as at 8 October 2018. That is to say, if the credit union had insisted on confirmation from the builder that all payments to subcontractors were up to date, the existence of these two invoices would not have prevented the builder from providing that confirmation. The invoice for bricklaying services was dated 2 October 2018 and does not contain payment terms. However, it is unlikely that payment terms were less than 7 days - meaning it would not have been overdue at the time PPC 7 was issued. The second invoice for plumbing services was dated 15 October 2018 with payment terms of seven days. It was not overdue until 22 October 2018. There is no other information to suggest that payments due to subcontractors had not been paid as at 8 October 2018. In any event, for reasons including those set out below, I am not satisfied that by making the payment in the absence of confirmation about the payment of subcontractors the credit union breached any obligation it owed to the complainants. A fair reading of clauses 4.3, 4.4, 4.5 and 4.7 of the terms and conditions indicates, and I find that:  Clause 4.3 sets out the conditions on which the credit union will “allow” the complainants to draw down monies under the loan. In other words, it sets out the conditions which, if not met, give the credit union a right under the loan contract to refuse a drawdown request.  Clause 4.4 sets out the „form‟ requirements of a progress payment claim, which , if not met, would entitle the credit union to refuse a drawdown request under clause 4.3(a).  Clauses 4.3 and 4.4 do not operate to impose positive obligations on the credit union to refuse a drawdown request if any of the requirements set out in those clauses are not met.  Rather, the credit union may waive compliance with those conditions before approving the drawdown request - provided it is not on notice of anything which would make it inappropriate to do so. This interpretation is supported by clause 4.5(b) which states that the credit union “ will ” process the request to drawdown “if Determination | Case number: 671721 Page 6 of 11 the progress payment request and inspection report are in a form and content satisfactory to us”.  As discussed further below, there is nothing to suggest that the credit union was on notice of any concerns about the builder not performing works as required under the building contract, or that there were any other „red flags‟ that would make it inappropriate for the credit union to waive requirements under clauses 4.3 or 4.4. The credit union did obtain an inspection report (valuer‟s report ) from a certified practising valuer prior to making the payment and it confirmed the works in PPC 7 were completed and recommended PPC 7 be paid.  Clause 4.7(b) makes it clear that it is the complainants, not the credit union, who must “ensure that the works take place in accordance wi th the building contract”. This includes ensuring progress payment claims issued by the builder properly correspond with the work required to be performed under the building contract. Consequently, I am not satisfied that the credit union breached its obligations to the complainants when it approved the drawdown request and made the payment in circumstances where some of the requirements under clauses 4.3 and 4.4 were not met. The complainants impliedly endorsed PPC 7 The complainants submit that they did not “ endorse the claim with [their] consent ” before the credit union made the payment, and consequently, the credit union breached its obligations to them when it made the payment. For reasons including the following I do not accept this submission:  In line with my observations above, the requirement for PPC 7 to be “endorsed with [ the complainants‟] consent” under clause 4.3(h) was a requirement the credit union was entitled to waive (so long as there was no question that the drawdown request was being made by the complainants as opposed to a third party - such as the builder himself). In this instance, by forwarding the progress payment to the credit union, Mrs B on behalf of the complainants, was clearly requesting to draw down on the loan.  In any event, the requirement that PPC 7 be “endorsed with your consent” does not require express endorsement of consent and could fairly be considered as having been met in circumstances where Mrs B forwarded it to the credit union without indicating any concerns about its payment in her covering email. This is particularly so where all previous progress payments were submitted to the credit union in this manner and were processed without any additional requirements for express consent.  Finally, it is relevant that the complainants did not object to the payment having been made for more than five months, and after construction was complete. If the complainants did not consent to the credit union making the payment at the time, or had otherwise intended to object to it, one would expect this to have been made known to the credit union at an earlier point in time. Determination | Case number: 671721 Page 7 of 11 The valuer’s report was for the credit union’s purposes only The complainants also submit that the valuer‟s inspection report dated 15 October 2018 ( valuer’s report ) which confirmed the works in PPC 7 had been completed and construction was 88% complete, was incorrect because the work the subject of PPC 7 was substantially incomplete. Regardless of whether or not the valuer‟s re port was incorrect, valuations are obtained for the credit union‟s purposes only. Namely, to ensure that if the complainants were to default on the loan and a sale of the security property was required, that the credit union‟s security position was protect ed under the applicable loan to security value ratios. If the credit union had obtained a valuation report which, on its face, indicated there was a problem with the work that was completed or otherwise raised red flags, there may be an argument that it was required to take further steps to investigate the matter. However, in these circumstances, there was no such „red flag‟ – rather, the opposite was the case insofar as the valuer informed the credit union on 10 October 2018 that he had deferred the inspection for a couple of days to allow completion of the work the subject of PPC 7. The credit union was entitled to rely on the valuer‟s subsequent report and was not required to make further enquiries to confirm that the work the subject of PPC 7 had in fact been completed. I understand that there may have been some confusion on the complainants‟ part about the role of the valuer in providing valuation or inspection reports. The complainants say that this arises from the credit unions‟ email to Mrs B dated 5 October 2017 which explains the process if the builder issues an invoice for incomplete work. While I acknowledge the complainants‟ confusion , having reviewed that email (which is extracted in Section 3.2 below), I am unable to find the credit union relevantly caused or contributed to any misunderstanding on the complainants‟ part. Rather, I consider the email was directed at advising the complainants that should the valuer recommend funds be withheld because works are incomplete, and a subsequent valuation is required, the cost of that valuation will be passed back to the complainants. Further, I do not consider that the credit union made any representations in that email to the effect that the valuation reports were obtained to protect the com plainants‟ position , or that the complainants could rely on the valuation reports to ensure the work was being performed as required under the building contract. The credit union ‟s role was one of lender. At no sta ge did it assume the responsibility of project managing the construction or ensuring on behalf of the complainants that works were completed in accordance with the building contract. It did not owe the complainants any fiduciary duty to act in their best interests or to ensure they were fully aware that it was their responsibility to ensure the builder‟s works were completed in accordance with the building contract. Nor did not owe the complainants a duty of care to ensure that the construction works paid for by the Determination | Case number: 671721 Page 8 of 11 complainants under the building contract were complete or completed to a sufficient standard prior to processing drawdown requests to pay progress payment claims . While I have sympathy for the position the complainants found themselves in when the company went into liquidation, particularly because the builder allegedly refused them access to the construction site to inspect the works, I am not satisfied their unfortunate position arises because of the credit union‟s actions. The credit union’s actions did not cause the complainants ’ loss Regardless of my conclusions about whether the credit union breached an obligation to the complainants when it made the payment, I am not satisfied that this caused the complainants‟ loss. Nor am I satisfied that, in the circumstances, fairness would require the credit union to respond to complainants for that loss. I have reached this view for reasons including the following:  The loss arising from the builder‟s alleged failure to complete the works for which he sought payment under PPC 7 was caused by the builder not the credit union. The complainants‟ claim for compensation should be properly directed against the builder under the building contract as opposed to the credit union.  The (amended) building contract was between complainants and the builder as sole trader - not the company which went into liquidation. The complainants were aware of this because they in fact requested the original contract be amended to replace the company with the builder himself. This was because they had realised that the applicable insurance was in the builder‟s name, not the company‟s name.  Accordingly, the complainants could have, and should have, pursued all available remedies under the building contract against the builder to seek redress or compensation for the works he charged for under PPC 7 but allegedly did not complete.  Instead, and without notice to the credit union, the complainants continued to work with the builder on a different basis, outside the terms of the building contract, making non-scheduled payments directly to him and subcontractors for remaining construction works (including completing the alleged incomplete works).  In doing so, the complainants breached clause 4.7 of the terms and conditions which required them to: > ensure the construction works take place in accordance with the building contract, > promptly pursue all rights and remedies under the building contract, and > not agree to any variation to the building contract or terminate the building contract without the credit union‟s prior consent.  This action by the complainants deprived the credit union of the opportunity to work with the complainants to help them to protect their (and the credit union‟s) interests and mitigate any losses arising from the company going into liquidation and the builder having failed to complete works the subject of PPC 7. Determination | Case number: 671721 Page 9 of 11 Accordingly, in all the circumstances, the credit union‟s actions in making the payment cannot be considered as having relevantly caused the comp lainants‟ loss and, in any event, given the complainants‟ breach of clause 4.7, the credit union should not be held responsible for it. Determination | Case number: 671721 Page 10 of 11 3 Supporting information 3.1 Clause 4.3- 4.6 of the loan terms and conditions Determination | Case number: 671721 Page 11 of 11 3.2 Extract from credit union’s email to Mrs B dated 5 October 2017 “Are you able to make [the builder] aware that you are obtaining finance for the build, as [we] will need to conduct inspections at each progress draw stage. Generally the to arrange and complete an inspection takes approx. 3 days, with payment then processed by our head office as soon as they can. Overall the proc ess from time of receipt of the invoice is around 5 working days. Under the circumstances I must also make you aware that should [the builder] issue invoices before work is completed our valuer will recommend we hold funds back to cover the works not be completed as per the progress draw schedule listed in the building contract. These funds will be withheld until such time as the works are completed. The valuer will then be requested to re value the house at a later stage to confirm the works have been completed with the residual payment then made, with the cost of the valuation will be passed back to yourself and Tony.” Recommendation Case number 671721 Financial firm Bananacoast Community Credit Union Ltd Recommendation | Case number: 671721 Page 1 of 7 Case number: 671721 8 January 2020 4 Overview 4.1 Complaint This complaint is about whether the financial firm (credit union) should have released a progress payment for an amount of $52,987 (the payment) on 15 October 2018. The complainants (Mr and Mrs B) say:  the valuer who inspected and passed the progress payment claim did so without all the works being completed  the credit union should not have released the payment  the builder‟s company went into liquidation on 15 October 2018  they had to pay for materials and labour that were already claimed in earlier progress payments  they had to spend additional money on top of the building contract to complete the build. They are seeking reimbursement from the credit union of $52,987 plus interest. 4.2 Issues and key findings Did the credit union pay the progress payment claim correctly? The credit union paid the progress payment claim correctly. The credit union:  obtained a progress payment certificate from a suitably qualified valuer who stated that all work to date had been completed satisfactorily  paid the progress payment claim in accordance with the amount identified on the fixed price building contract of $52,987.00 and  made the payment at the complainants‟ request. Recommendation This recommendation is in favour of the credit union. The credit union is not required to pay the complainants compensation. Recommendation | Case number: 671721 Page 2 of 7 5 Reasons for recommendation 5.1 Did the credit union pay the progress payment claim correctly? The complainants signed a fixed price building contract On the 27 March 2018, the complainants entered into a building contract with Mr GBS (the builder) to build a new home (the CH property). The building contract was in the standard “NSW Residential Building Contract for New Dwellings” published by the Housing Industry Association (HIA). The contract specified that the total cost for the building contract including GST was $331,169, but the contract included a warning that the fixed price may vary and provided some examples of when this may occur. The contract required the builder to be paid in nine stages, also known as progress payments. The contract identified each of the nine stages and provided a monetary amount for each. In addition, the contract provided a percentage allocation for each payment which was aligned to the total building costs. A copy of the schedule can be found at section 3.1 below. The complainants signed a loan contract On 31 July 2017, the complainants signed a loan contract (the loan contract) wit h the credit union. It specified the loan amount as $500,000. The loan contract stated that the contract was governed by the credit union‟s general terms and conditions (the conditions). The complainants had concerns about the building works On 8 October 2018, Mr B sent an email to the builder about progress payment claim 7. The complainants raised their concerns with the builder about the missing linings on the front veranda and the incomplete works on the decking. A second email was sent, and the builder was placed on notice that the complainants were not willing to make the payment until the works had been completed. It does not appear that the complainants shared their concerns with the credit union or asked it to withhold the progress payment from the builder until the works were completed to their satisfaction. On 9 October 2018, Mrs B emailed the builder‟s invoice for progress payment 7 to the credit union for payment. The progress payment matched the building contract On 9 October 2018, the credit union received an email from Mrs B with the builder‟s invoice for $52,987.00. Recommendation | Case number: 671721 Page 3 of 7 The credit union‟s general terms and conditions say that the progress payment claim must have the following noted on the builder‟s invoice  detail the amount of the claim  detail the work completed to date  detail any variations to the building contract or plans including prices  not be of such amount, which, if made, would result in their being insufficient funds available under the facility at a later to complete the building contract The invoice, for the “internal linings stage” (progress claim 7) was consistent with the building contract since it said, “All plasterboard is attached excluding cornice and internal doors.” The credit union required the complainants to forward it the invoice for direct payment to the builder. In forwarding the builder‟s invoice for payment, the complainants satisfied the credit union‟s requirement of consent. The credit union instructed a valuer to complete a progress inspection report The credit union‟s procedures for home loans state that before the progress payment can be released the following must be satisfied:  the builder is to provide an invoice of work completed to the borrower  the invoice will be provided to a valuer, who will inspect the property and confirm that all work is council compliant and will estimate the cost to complete construction  progress payment must match the amount and stage in the building contract On 9 October 2018, the credit union requested a progress inspection valuation to be completed on the CH property. The available information shows that the valuer first visited the CH property on 10 October 2018. On the same day the valuer sent an email to the credit union stating “The builder has advised that the internal lin ings stage won‟t be completed until Monday. I‟ll try again then.” The valuer was given access to the property to complete the progress payment inspection on 15 October 2018. The credit union received a progress payment certificate The valuer (BM) issued the credit union with a Progress Payment Certificate on the 15 October 2018 and certified  that he had completed an inspection of the property.  that 88% of the construction works had been completed  all works to date appear satisfactory and progress payment $52,987 is recommended. Recommendation | Case number: 671721 Page 4 of 7 A copy of the valuer‟s correspondence is in section 3.2 of this recommendation. The credit union drew down the amount of $52,987 from the loan account on the 15 October 2018 and credited the builder‟s bank account. The builder’s comp any went into liquidation The builder was a director of a company that was placed into liquidation on the 15 October 2018. This was the same day the credit union released the progress payment claim. The company had no contract with the complainants. The building contract was signed by the complainants with the builder operating as a sole trader. As a result of his company going into liquidation, he informed the complainants that he could remain on site as the project manager and said that all future payments under the contract would need to be made directly to the tradespersons. The complainants failed to notify the credit union of the increased costs The credit union contacted Mr & Mrs B around 21 March 2019, to check on the progress of the build as they had not received a progress payment claim for six months. It was at this time the credit union first became aware that the builder‟s company had gone into liquidation. Mr & Mrs B advised the credit union that they had subsequently engaged other contractors to complete the build and paid them independently of the loan. Although the building contract specified a fixed building price of $331,169, the complainants paid a total of $391,287 to complete the construction of the house. As a result, they incurred a loss of $37,947 when the house was sold. A calculation of the loss is set out in section 3.3 below. The credit union is not responsible for the complainants’ loss By dealing independently of the credit union to complete the build, Mr & Mrs B undertook all risks in accepting the additional costs in completing the construction with the builder. Mr & Mrs B did not complete any independent due diligence of the additional costs they incurred to see if they were reasonable given the circumstances. The credit union says it was not afforded the opportunity to work with Mr & Mr B to ensure that all work was completed prior to the final valuation. No requests were made to the credit union to release the remaining undrawn funds in the loan. If the complainants had enforced the building contract against the builder and required him to complete the construction for the contract amount, the complainants would not have suffered a loss. The credit union is not responsible for the complainants‟ loss because: Recommendation | Case number: 671721 Page 5 of 7  the credit union agreed to lend the complainants $500,000.  the credit union complied with the loan contract in that it paid the builder his progress payment claims at the complai nants‟ request.  the complainants incurred a loss because they paid the builder $60,118 more than the building contract specified. Because the credit union is not responsible for the complainants‟ loss, it is not required to pay them any compensation. Recommendation | Case number: 671721 Page 6 of 7 6 Supporting information 6.1 Progress Payment Schedule from Building Contract Recommendation | Case number: 671721 Page 7 of 7 6.2 Progress Payment Certificate – Internal Linings 6.3 The complainant’s loss

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.