Credit union released progress payment 7 without borrower endorsement while works were incomplete
Text of the determination
Determination
Case number 671721
Financial firm BCU ( a divisi on of Police and Nurses Limited )
Determination | Case number: 671721 Page 2 of 11
Case number: 671721 2 September 2020
1 Determination overview
1.1 Complaint
In July 2017 the complainants ( Mr and Mrs B ) obtained a construction loan from the
financial firm ( credit union ) in an amount of $500,000 ( loan ) to be drawn down
during the construction period. In March 2018, the complainants entered into a fixed
price building contract with a builder for $331,169 ( building contract ). After
construction commenced, several progress payment claims were submitted by the
builder to the complainants, passed on to the credit union by the complainants and
paid by way of the credit union processing drawdowns on the loan.
This complaint is about whether the credit union breached any obligation it owed to
the complainants when it paid progress payment claim 7 dated 8 October 2018 ( PPC
7 ) for an amount of $52,987 ( payment ).
The complainants say:
the valuer who inspected the works the subject of PPC 7 and recommended the
payment be released, did so when the works were incomplete
the credit union should not have released the payment
the builder‟s company ( company ) went into liquidation on 15 October 2018, and
because the works the subject of PPC 7 were incomplete, the complainants
themselves had to pay for those works to be completed.
The complainants are seeking reimbursement of $52,987 plus interest.
On 8 January 2020, the case manager issued a recommendation in this matter which
was in favour of the credit union. A copy of the recommendation is attached to this
determination. The complainants rejected the recommendation and the matter
proceeded to determination.
1.2 Issues and key findings
Were the findings in the recommendation correct?
The findings contained in the recommendation were substantially correct and are
adopted in this determination. Further submissions provided by the complainants
after the recommendation have been considered.
Do the complainants ’ further submissions change the outcome?
I have considered the complainants ‟ further submissions. For the reasons set out in
Section 2.2 below, they do not change the outcome of the complaint.
Determination | Case number: 671721 Page 3 of 11
1.3 Determination
This determination is in favour of the credit union.
The credit union is not required to compensate the complainants or take any other
action.
Determination | Case number: 671721 Page 4 of 11
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
The findings in the recommendation were substantially correct
I have decided this complaint based on what is fair in all the circumstances having
regard to the relevant law, good industry practice, codes or guidance as to p ractice
and previous AFCA decisions. I have considered all material submitted by the parties
and I am satisfied that the material I relied upon in reaching my findings has been
exchanged between the parties or is otherwise in their possession.
I am satisf ied that the case manager‟s recommendation contains an accurate
summary of the complaint, the issues to be determined, any applicable paragraphs of
the Rules and any relevant law.
I am satisfied that the findings in the attached recommendation were substantially
correct, and I adopt them in this determination. In particular, I find that:
the credit union did not breach any obligation owed to the complainants when it
made the payment, and
the credit union is not responsible for the complainants‟ loss .
I make further observations and findings below.
The complainants rejected the recommendation and made further submissions
The complainants rejected the recommendation and made further submissions,
including that the credit union:
breached the terms and conditions of the loan ( terms and conditions ):
> by making the payment without their endorsement
> by making the payment when the contracted works were not completed to 88%
of the contract price
> in accepting an unsigned builder ‟ s invoice
> in failing to confirm all subcontractors had been paid to the date of the invoice,
and
caused them loss as they had to pay twice for the incomplete works that had not
been completed when the payment was made.
2.2 Do the complainants ’ further submissions change the outcome?
Clause 4 does not impose positive obligations on the credit union
The complainants submit that the credit union breached the terms and conditions
when it made the payment. I have reviewed PPC 7 and clause 4 of the terms and
Determination | Case number: 671721 Page 5 of 11
conditions, in particular (sub)clauses 4.3 “Conditions for payment of monies due
under a building contract” , 4.4 “Form of progress payment claim”, 4.5 “Procedure for
payment of a progress payment claim”, and 4.7 “General” . These clauses are
extracted in Section 3.1 below.
The complainants are correct in identifying that the credit union made the payment
when aspects of PPC 7 did not meet the requirements in clauses 4.3 and 4.4 – in
particular, PPC 7 was not signed by the builder and did not confirm that all
subcontractors had been paid to date.
In relation to the question about whether all subcontractors had been paid as at the
date of PPC 7, while the complainants have supplied two unpaid subcontractor
invoices, I am unable to find that these were relevantly overdue as at 8 October 2018.
That is to say, if the credit union had insisted on confirmation from the builder that all
payments to subcontractors were up to date, the existence of these two invoices
would not have prevented the builder from providing that confirmation.
The invoice for bricklaying services was dated 2 October 2018 and does not contain
payment terms. However, it is unlikely that payment terms were less than 7 days -
meaning it would not have been overdue at the time PPC 7 was issued. The second
invoice for plumbing services was dated 15 October 2018 with payment terms of
seven days. It was not overdue until 22 October 2018. There is no other information
to suggest that payments due to subcontractors had not been paid as at 8 October
2018. In any event, for reasons including those set out below, I am not satisfied that
by making the payment in the absence of confirmation about the payment of
subcontractors the credit union breached any obligation it owed to the complainants.
A fair reading of clauses 4.3, 4.4, 4.5 and 4.7 of the terms and conditions indicates,
and I find that:
Clause 4.3 sets out the conditions on which the credit union will “allow” the
complainants to draw down monies under the loan. In other words, it sets out the
conditions which, if not met, give the credit union a right under the loan contract to
refuse a drawdown request.
Clause 4.4 sets out the „form‟ requirements of a progress payment claim, which , if
not met, would entitle the credit union to refuse a drawdown request under clause
4.3(a).
Clauses 4.3 and 4.4 do not operate to impose positive obligations on the credit
union to refuse a drawdown request if any of the requirements set out in those
clauses are not met.
Rather, the credit union may waive compliance with those conditions before
approving the drawdown request - provided it is not on notice of anything which
would make it inappropriate to do so. This interpretation is supported by clause
4.5(b) which states that the credit union “ will ” process the request to drawdown “if
Determination | Case number: 671721 Page 6 of 11
the progress payment request and inspection report are in a form and content
satisfactory to us”.
As discussed further below, there is nothing to suggest that the credit union was on
notice of any concerns about the builder not performing works as required under
the building contract, or that there were any other „red flags‟ that would make it
inappropriate for the credit union to waive requirements under clauses 4.3 or 4.4.
The credit union did obtain an inspection report (valuer‟s report ) from a certified
practising valuer prior to making the payment and it confirmed the works in PPC 7
were completed and recommended PPC 7 be paid.
Clause 4.7(b) makes it clear that it is the complainants, not the credit union, who
must “ensure that the works take place in accordance wi th the building contract”.
This includes ensuring progress payment claims issued by the builder properly
correspond with the work required to be performed under the building contract.
Consequently, I am not satisfied that the credit union breached its obligations to the
complainants when it approved the drawdown request and made the payment in
circumstances where some of the requirements under clauses 4.3 and 4.4 were not
met.
The complainants impliedly endorsed PPC 7
The complainants submit that they did not “ endorse the claim with [their] consent ”
before the credit union made the payment, and consequently, the credit union
breached its obligations to them when it made the payment. For reasons including
the following I do not accept this submission:
In line with my observations above, the requirement for PPC 7 to be “endorsed with
[ the complainants‟] consent” under clause 4.3(h) was a requirement the credit
union was entitled to waive (so long as there was no question that the drawdown
request was being made by the complainants as opposed to a third party - such as
the builder himself). In this instance, by forwarding the progress payment to the
credit union, Mrs B on behalf of the complainants, was clearly requesting to draw
down on the loan.
In any event, the requirement that PPC 7 be “endorsed with your consent” does not
require express endorsement of consent and could fairly be considered as having
been met in circumstances where Mrs B forwarded it to the credit union without
indicating any concerns about its payment in her covering email. This is
particularly so where all previous progress payments were submitted to the credit
union in this manner and were processed without any additional requirements for
express consent.
Finally, it is relevant that the complainants did not object to the payment having
been made for more than five months, and after construction was complete. If the
complainants did not consent to the credit union making the payment at the time,
or had otherwise intended to object to it, one would expect this to have been made
known to the credit union at an earlier point in time.
Determination | Case number: 671721 Page 7 of 11
The valuer’s report was for the credit union’s purposes only
The complainants also submit that the valuer‟s inspection report dated 15 October
2018 ( valuer’s report ) which confirmed the works in PPC 7 had been completed and
construction was 88% complete, was incorrect because the work the subject of PPC 7
was substantially incomplete.
Regardless of whether or not the valuer‟s re port was incorrect, valuations are
obtained for the credit union‟s purposes only. Namely, to ensure that if the
complainants were to default on the loan and a sale of the security property was
required, that the credit union‟s security position was protect ed under the applicable
loan to security value ratios.
If the credit union had obtained a valuation report which, on its face, indicated there
was a problem with the work that was completed or otherwise raised red flags, there
may be an argument that it was required to take further steps to investigate the
matter. However, in these circumstances, there was no such „red flag‟ – rather, the
opposite was the case insofar as the valuer informed the credit union on 10 October
2018 that he had deferred the inspection for a couple of days to allow completion of
the work the subject of PPC 7. The credit union was entitled to rely on the valuer‟s
subsequent report and was not required to make further enquiries to confirm that the
work the subject of PPC 7 had in fact been completed.
I understand that there may have been some confusion on the complainants‟ part
about the role of the valuer in providing valuation or inspection reports. The
complainants say that this arises from the credit unions‟ email to Mrs B dated 5
October 2017 which explains the process if the builder issues an invoice for
incomplete work. While I acknowledge the complainants‟ confusion , having reviewed
that email (which is extracted in Section 3.2 below), I am unable to find the credit
union relevantly caused or contributed to any misunderstanding on the complainants‟
part. Rather, I consider the email was directed at advising the complainants that
should the valuer recommend funds be withheld because works are incomplete, and
a subsequent valuation is required, the cost of that valuation will be passed back to
the complainants. Further, I do not consider that the credit union made any
representations in that email to the effect that the valuation reports were obtained to
protect the com plainants‟ position , or that the complainants could rely on the valuation
reports to ensure the work was being performed as required under the building
contract.
The credit union ‟s role was one of lender. At no sta ge did it assume the responsibility
of project managing the construction or ensuring on behalf of the complainants that
works were completed in accordance with the building contract. It did not owe the
complainants any fiduciary duty to act in their best interests or to ensure they were
fully aware that it was their responsibility to ensure the builder‟s works were
completed in accordance with the building contract. Nor did not owe the
complainants a duty of care to ensure that the construction works paid for by the
Determination | Case number: 671721 Page 8 of 11
complainants under the building contract were complete or completed to a sufficient
standard prior to processing drawdown requests to pay progress payment claims .
While I have sympathy for the position the complainants found themselves in when
the company went into liquidation, particularly because the builder allegedly refused
them access to the construction site to inspect the works, I am not satisfied their
unfortunate position arises because of the credit union‟s actions.
The credit union’s actions did not cause the complainants ’ loss
Regardless of my conclusions about whether the credit union breached an obligation
to the complainants when it made the payment, I am not satisfied that this caused the
complainants‟ loss. Nor am I satisfied that, in the circumstances, fairness would
require the credit union to respond to complainants for that loss. I have reached this
view for reasons including the following:
The loss arising from the builder‟s alleged failure to complete the works for which
he sought payment under PPC 7 was caused by the builder not the credit union.
The complainants‟ claim for compensation should be properly directed against the
builder under the building contract as opposed to the credit union.
The (amended) building contract was between complainants and the builder as
sole trader - not the company which went into liquidation. The complainants were
aware of this because they in fact requested the original contract be amended to
replace the company with the builder himself. This was because they had realised
that the applicable insurance was in the builder‟s name, not the company‟s name.
Accordingly, the complainants could have, and should have, pursued all available
remedies under the building contract against the builder to seek redress or
compensation for the works he charged for under PPC 7 but allegedly did not
complete.
Instead, and without notice to the credit union, the complainants continued to work
with the builder on a different basis, outside the terms of the building contract,
making non-scheduled payments directly to him and subcontractors for remaining
construction works (including completing the alleged incomplete works).
In doing so, the complainants breached clause 4.7 of the terms and conditions
which required them to:
> ensure the construction works take place in accordance with the building
contract,
> promptly pursue all rights and remedies under the building contract, and
> not agree to any variation to the building contract or terminate the building
contract without the credit union‟s prior consent.
This action by the complainants deprived the credit union of the opportunity to work
with the complainants to help them to protect their (and the credit union‟s) interests
and mitigate any losses arising from the company going into liquidation and the
builder having failed to complete works the subject of PPC 7.
Determination | Case number: 671721 Page 9 of 11
Accordingly, in all the circumstances, the credit union‟s actions in making the payment
cannot be considered as having relevantly caused the comp lainants‟ loss and, in any
event, given the complainants‟ breach of clause 4.7, the credit union should not be
held responsible for it.
Determination | Case number: 671721 Page 10 of 11
3 Supporting information
3.1 Clause 4.3- 4.6 of the loan terms and conditions
Determination | Case number: 671721 Page 11 of 11
3.2 Extract from credit union’s email to Mrs B dated 5 October 2017
“Are you able to make [the builder] aware that you are obtaining finance for the build, as [we]
will need to conduct inspections at each progress draw stage.
Generally the to arrange and complete an inspection takes approx. 3 days, with payment then
processed by our head office as soon as they can.
Overall the proc ess from time of receipt of the invoice is around 5 working days.
Under the circumstances I must also make you aware that should [the builder] issue invoices
before work is completed our valuer will recommend we hold funds back to cover the works not
be completed as per the progress draw schedule listed in the building contract. These funds
will be withheld until such time as the works are completed. The valuer will then be requested
to re value the house at a later stage to confirm the works have been completed with the
residual payment then made, with the cost of the valuation will be passed back to yourself and
Tony.”
Recommendation
Case number 671721
Financial firm Bananacoast Community Credit Union Ltd
Recommendation | Case number: 671721 Page 1 of 7
Case number: 671721 8 January 2020
4 Overview
4.1 Complaint
This complaint is about whether the financial firm (credit union) should have released
a progress payment for an amount of $52,987 (the payment) on 15 October 2018.
The complainants (Mr and Mrs B) say:
the valuer who inspected and passed the progress payment claim did so without all
the works being completed
the credit union should not have released the payment
the builder‟s company went into liquidation on 15 October 2018
they had to pay for materials and labour that were already claimed in earlier
progress payments
they had to spend additional money on top of the building contract to complete the
build.
They are seeking reimbursement from the credit union of $52,987 plus interest.
4.2 Issues and key findings
Did the credit union pay the progress payment claim correctly?
The credit union paid the progress payment claim correctly.
The credit union:
obtained a progress payment certificate from a suitably qualified valuer who stated
that all work to date had been completed satisfactorily
paid the progress payment claim in accordance with the amount identified on the
fixed price building contract of $52,987.00 and
made the payment at the complainants‟ request.
Recommendation
This recommendation is in favour of the credit union.
The credit union is not required to pay the complainants compensation.
Recommendation | Case number: 671721 Page 2 of 7
5 Reasons for recommendation
5.1 Did the credit union pay the progress payment claim correctly?
The complainants signed a fixed price building contract
On the 27 March 2018, the complainants entered into a building contract with Mr GBS
(the builder) to build a new home (the CH property). The building contract was in the
standard “NSW Residential Building Contract for New Dwellings” published by the
Housing Industry Association (HIA).
The contract specified that the total cost for the building contract including GST was
$331,169, but the contract included a warning that the fixed price may vary and
provided some examples of when this may occur.
The contract required the builder to be paid in nine stages, also known as progress
payments. The contract identified each of the nine stages and provided a monetary
amount for each. In addition, the contract provided a percentage allocation for each
payment which was aligned to the total building costs. A copy of the schedule can be
found at section 3.1 below.
The complainants signed a loan contract
On 31 July 2017, the complainants signed a loan contract (the loan contract) wit h the
credit union. It specified the loan amount as $500,000.
The loan contract stated that the contract was governed by the credit union‟s general
terms and conditions (the conditions).
The complainants had concerns about the building works
On 8 October 2018, Mr B sent an email to the builder about progress payment claim
7. The complainants raised their concerns with the builder about the missing linings
on the front veranda and the incomplete works on the decking. A second email was
sent, and the builder was placed on notice that the complainants were not willing to
make the payment until the works had been completed.
It does not appear that the complainants shared their concerns with the credit union
or asked it to withhold the progress payment from the builder until the works were
completed to their satisfaction.
On 9 October 2018, Mrs B emailed the builder‟s invoice for progress payment 7 to the
credit union for payment.
The progress payment matched the building contract
On 9 October 2018, the credit union received an email from Mrs B with the builder‟s
invoice for $52,987.00.
Recommendation | Case number: 671721 Page 3 of 7
The credit union‟s general terms and conditions say that the progress payment claim
must have the following noted on the builder‟s invoice
detail the amount of the claim
detail the work completed to date
detail any variations to the building contract or plans including prices
not be of such amount, which, if made, would result in their being insufficient funds
available under the facility at a later to complete the building contract
The invoice, for the “internal linings stage” (progress claim 7) was consistent with the
building contract since it said, “All plasterboard is attached excluding cornice and
internal doors.”
The credit union required the complainants to forward it the invoice for direct payment
to the builder. In forwarding the builder‟s invoice for payment, the complainants
satisfied the credit union‟s requirement of consent.
The credit union instructed a valuer to complete a progress inspection report
The credit union‟s procedures for home loans state that before the progress payment
can be released the following must be satisfied:
the builder is to provide an invoice of work completed to the borrower
the invoice will be provided to a valuer, who will inspect the property and confirm
that all work is council compliant and will estimate the cost to complete
construction
progress payment must match the amount and stage in the building contract
On 9 October 2018, the credit union requested a progress inspection valuation to be
completed on the CH property. The available information shows that the valuer first
visited the CH property on 10 October 2018. On the same day the valuer sent an
email to the credit union stating “The builder has advised that the internal lin ings
stage won‟t be completed until Monday. I‟ll try again then.”
The valuer was given access to the property to complete the progress payment
inspection on 15 October 2018.
The credit union received a progress payment certificate
The valuer (BM) issued the credit union with a Progress Payment Certificate on the
15 October 2018 and certified
that he had completed an inspection of the property.
that 88% of the construction works had been completed
all works to date appear satisfactory and progress payment $52,987 is
recommended.
Recommendation | Case number: 671721 Page 4 of 7
A copy of the valuer‟s correspondence is in section 3.2 of this recommendation.
The credit union drew down the amount of $52,987 from the loan account on the 15
October 2018 and credited the builder‟s bank account.
The builder’s comp any went into liquidation
The builder was a director of a company that was placed into liquidation on the 15
October 2018. This was the same day the credit union released the progress payment
claim. The company had no contract with the complainants.
The building contract was signed by the complainants with the builder operating as a
sole trader. As a result of his company going into liquidation, he informed the
complainants that he could remain on site as the project manager and said that all
future payments under the contract would need to be made directly to the
tradespersons.
The complainants failed to notify the credit union of the increased costs
The credit union contacted Mr & Mrs B around 21 March 2019, to check on the
progress of the build as they had not received a progress payment claim for six
months. It was at this time the credit union first became aware that the builder‟s
company had gone into liquidation. Mr & Mrs B advised the credit union that they had
subsequently engaged other contractors to complete the build and paid them
independently of the loan.
Although the building contract specified a fixed building price of $331,169, the
complainants paid a total of $391,287 to complete the construction of the house. As a
result, they incurred a loss of $37,947 when the house was sold. A calculation of the
loss is set out in section 3.3 below.
The credit union is not responsible for the complainants’ loss
By dealing independently of the credit union to complete the build, Mr & Mrs B
undertook all risks in accepting the additional costs in completing the construction
with the builder. Mr & Mrs B did not complete any independent due diligence of the
additional costs they incurred to see if they were reasonable given the circumstances.
The credit union says it was not afforded the opportunity to work with Mr & Mr B to
ensure that all work was completed prior to the final valuation. No requests were
made to the credit union to release the remaining undrawn funds in the loan.
If the complainants had enforced the building contract against the builder and
required him to complete the construction for the contract amount, the complainants
would not have suffered a loss.
The credit union is not responsible for the complainants‟ loss because:
Recommendation | Case number: 671721 Page 5 of 7
the credit union agreed to lend the complainants $500,000.
the credit union complied with the loan contract in that it paid the builder his
progress payment claims at the complai nants‟ request.
the complainants incurred a loss because they paid the builder $60,118 more than
the building contract specified.
Because the credit union is not responsible for the complainants‟ loss, it is not
required to pay them any compensation.
Recommendation | Case number: 671721 Page 6 of 7
6 Supporting information
6.1 Progress Payment Schedule from Building Contract
Recommendation | Case number: 671721 Page 7 of 7
6.2 Progress Payment Certificate – Internal Linings
6.3 The complainant’s loss
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.