Determination 667460
Insurer offer for underpinning, turf, fence and verandah repairs
Summary
A homeowner's first claim for movement damage was declined, and a later underground leak was found. AFCA found the insurer's offer largely fair but ordered payment of additional repair costs, the scope of works with a 15% uplift if cash settled, and $2,000 for non-financial loss.
The insurer failed to discover the cause of damage in the first claim and caused confusion about underpinning, so it must meet the additional repair costs and pay non-financial loss.
Issues
- Claim amount dispute primary · upheld
“In the circumstances, I think it is fair that the insurer pays for these expenses, being turf, boundary fence, neighbour's driveway and concrete verandah.”
- Inadequate claim investigation secondary · upheld
“the insurer failed to discover the cause of the damage claimed in 2015.”
- Poor communication secondary · upheld
“there was confusion about whether the insurer had agreed to pay the complainant for the underpinning.”
Subjects and remedies
home or building damagepay claimpay non financial lossrepair or rectify
Text of the determination
Determination
Case number 667460
Financial firm AAI Limited
Determination | Case number: 667460 Page 2 of 7
Case number: 667460 20 August 2020
1 Determination overview
1.1 Complaint
The complainant held a Building and Contents policy with the financial firm (insurer).
The complainant lodged a claim, in March 2015 for movement damage to his house.
The insurer declined the claim.
In November 2018, the complainant commenced underpinning of the house and
discovered an underground water leak. The insurer accepted the claim for the
damage caused by the leak. The complainant says the insurer led him to believe that
the underpinning would be paid by the insurer. The insurer has paid for the
underpinning and incidental costs. The complainant also claims increase use of
electricity and water but has not provided any information that confirms this.
The case analyst provided the parties with a preliminary view which was substantially
in favour of the insurer. The complainant disputes this and the matter has been
referred for determination.
1.2 Issues and key findings
Is the offer by the insurer reasonable?
On the information provided to me, on balance, I am satisfied that the offer made by
the insurer, together with the amount paid of $20,201.88 is fair and reasonable and
meets the obligations under the policy. However, the insurer is required to pay the
additional costs associated with underpinning.
Is the complainant entitled to non-economic loss?
On the information provided to me, I am satisfied the insurer’s conduct in this matter
was not satisfactory. The insurer has attempted to rectify this by making payments for
repairs which, they say, may not have been necessary.
The insurer should pay the complainant $2,000 for non-financial loss.
1.3 Determination
This determination is partially in favour of the insurer.
If the insurer has not yet done so, it is to:
reimburse the cost to relay turf
reimburse the cost to reinstate the boundary fence
reimburse the cost to reinstate the neighbour’s fence
Determination | Case number: 667460 Page 3 of 7
reinstate the concrete verandah
repair the property pursuant to IL’S scope of works. If the insurer choses to cash
settle the scope of works, it is to add a 15% uplift
pay the complainant $2,000 non-financial loss.
Determination | Case number: 667460 Page 4 of 7
2 Reasons for determination
I have decided this case on what is fair in all the circumstances, having regard to the
relevant legal principles, good industry practice, industry codes of practice and
previous relevant decisions of AFCA and predecessor schemes. I have considered all
the material submitted by the parties, both before and after the preliminary
assessment. I am satisfied the documentation I have relied upon has been provided
to both parties.
2.1 Is the offer by the insurer reasonable?
Onus on complainant
To successfully claim the disputed damage, the complainant must establish, on the
balance of probabilities that they have suffered a loss caused by an event to which
the policy responds. This is known as a prima facie or valid claim.
The complainant held a Home and Contents policy. The policy provided cover for
damage caused by a liquid leaking, overflowing or bursting from drainage and
sewerage systems. The complainant says the leaking pipes caused the damage. I am
satisfied the complainant has established a prima facie claim and the onus now shifts
to the insurer to prove the loss is excluded by the policy or falls outside the cover
provided.
Complainant lodges first claim March 2015
The insurer appointed plumbing investigation by (AL). AL found faults to the
stormwater line. The insurer then appointed engineers (FM). FM did not consider the
movement and damage was caused by faults to the stormwater line. Instead, FM
found the damage due to differential founding soil movement. The insurer declined
the claim on 22 July 2015.
It is noted that there were no leaks found by the insurer’s experts, and the insurer
denied the claim on the basis that the damage was not caused in a manner that the
policy responded.
The complainant having disputed the claim, took the matter no further at that time.
Second claim November 2018
On 12 November 2018, the complainant advised the insurer that a water leak had
been discovered during the excavations of footings of the property. The complainant
lodged a claim. The insurer appointed several experts. An investigation by a plumber
found the sewerage and stormwater pipes were damaged and were leaking.
The insurer then appointed an engineer (IL). IL concluded that the cracking and
movement to the home had been caused by long term defects to the stormwater and
sewer drains, allowing water to saturate the founding soils and causing a loss of
Determination | Case number: 667460 Page 5 of 7
bearing capacity. Importantly, IL said the saturation of the soil existed at the time of
the 2015 claim. It was then recommended that the pipes be repaired and that a period
of 12 months drying stabilisation should occur before repairs were completed.
In the meantime, the complainant had undertaken the underpinning. IL considered the
underpinning should have been the last resort for the damage. IL also stated that
there should have been a geo-technical investigation which in his opinion would have
shown the underpinning was not an appropriate methodology for re mediation of the
movement issues at the property.
On 31 January 2019, the insurer accepted the second claim however, they advised
the complainant that the underpinning was unnecessary.
The plumbing defects, themselves, were not covered by the policy. The complainant
undertook these repairs.
A dispute then arose as to whether the underpinning repairs were necessary.
The complainant maintained as follows:
the insurer had committed to the cost of underpinning
he was entitled electricity and water bills that had increased due to movement
damage and plumbing defect
the insurer had not repaired the damage caused by the plumbing defects.
Subsequently, the insurer agreed to cover the cost of the underpinning works.
The complainant lodged an invoice from the underpinning company in the sum of
$16,000. He also lodged a claim for associated costs including materials, debris
removal, totalling $4,201.88.
The insurer accepted these costs and made a payment of $20,201.88 to the
complainant on 30 October 2019. Initially, the insurer stated it would consider the
costs to relay turf and reinstate the boundary fence.
The insurer was waiting for the complainant to supply the invoices. The insurer
subsequently declined the additional costs including costs for the veranda and the
neighbour’s drivewa y.
In the circumstances, I think it is fair that the insurer pays for these expenses. The
insurer is required to pay the costs to:
relay turf
reinstate the boundary fence
reinstate neighbour’s driveway
reinstate concrete verandah.
Determination | Case number: 667460 Page 6 of 7
The complainant has provided some information in relation to the extra electricity
used, which they say was due to gaps in the windows and doors. The information
provided is insufficient to assess whether there was an increase in electricity usage or
water usage because of the damage.
On 26 November 2019, the insurer’s assessor (SE), building coordinator (CM)
together with A1 assessor and engineer IL attended the site. IL then compiled a
scope of works for the repairs of the damage caused by the plumbing defects. A1
prepared a quotation based on this scope of works. The scope of works amounted to
the sum of $8,108.10.
The complainant says that this scope of works does not cover all the damage that
was caused. He has raised issues with the flooring in the premises.
In response to this, IL has stated that the flooring is normal movement caused by
seasonal variations and not as a result of the damage caused from the leaking pipes.
The complainant has said that they would obtain a report from another party, but they
have not provided this to date. On the information provided to me, I am satisfied, on
balance, that the assessment made by the insurer and the scope of works provided
are an accurate assessment of what is required to meet the terms and conditions of
the policy.
There is nothing provided by the complainant that convinces me that there are other
items that have not yet been assessed or there are repairs that are yet to be
undertaken that were not contained in the scope of works.
If the insurer has not yet done so, it is to:
reimburse the cost to relay turf , boundary fence and neighbour’s driveway
reinstate the concrete verandah
repair the property pursuant to IL’S scope of works .
If the insurer choses to cash settle the scope of works, it is to add a 15% uplift to
cover contingencies and loss of any guarantees.
2.2 Is the complainant entitled to non-economic loss?
The amount AFCA can award for non-financial loss is $5,000 per claim. Assessing an
award for non-financial loss, AFCA will take into account the following:
physical inconvenience.
time taken to resolve a situation.
i nterference with the complainant’s expectation of enjoyment or peace of mind.
AFCA take a conservative approach to assessing compensation for non-financial
loss.
Determination | Case number: 667460 Page 7 of 7
AFCA expects complainants to:
be moderately robust
bear the normal degree of inconvenience experienced when a problem occurs
take reasonable steps to minimise the inconvenience suffered.
In the current circumstances, the insurer failed to discover the cause of the damage
claimed in 2015. The claim was denied, and the complainant went ahead to
undertake underpinning of the property, as he believed that this was the appropriate
process. During the underpinning operations, it was discovered that there was
substantial dampness and upon further investigation by the insurer, the broken pipes
were ascertained.
Had an appropriate assessment been carried out during the first claim, it is likely that
the leaking pipes would have been discovered.
I am satisfied that the complainant has suffered physical inconvenience and
interference with their expectation and enjoyment or peace of mind, particularly given
the time taken to resolve the situation.
I also note that there was confusion about whether the insurer had agreed to pay the
complainant for the underpinning.
The insurer says that underpinning is not the appropriate process in the first instance.
In spite of this, the insurer subsequently agreed to pay for the underpinning and that
has taken place.
I am satisfied that the insurer has endeavoured to rectify these issues, but the
complainant still requires compensation for non-financial loss. In the circumstances, I
find it is appropriate that the insurer pays the sum of $2,000 for non-financial loss.