Refusal to draw down or reinstate additional construction funding under home loan
Text of the determination
Determination
Case number 666724
Financial firm Suncorp - Metway Limited
Determination | Case number: 666724 Page 1 of 11
Case number: 666724 10 December 2021
1 Determination overview
1.1 Complaint
This complaint relates to a home loan Mr and Mrs S (the complainants ) obtained from the
financial firm (the bank ) to complete construction of their partially built home.
In June 2003, the complainants first applied for a home loan with a principal sum of $164,000
to fund their purchase of a property ( property M ). The loan was increased and varied four
times between 2003 and 2009. The increases and variations are detailed below:
Date New credit Total loan amount Purpose
2 June 2003 New loan $162,383.3 ( L1 ) Purchase property M
9 August 2004 $405,142 $564,107.48 ( L2 ) Build on property M for $360,000
Pay out personal loan $36,000
Pay out car loan of $6,900
Associated costs and outlays
4 July 2005 $91,332 $648,671.61 ( L3 ) Cash out $44,000
$46,000 for build
Associated costs and fees
7 June 2006 $94,663 $731,391.33 ( L4 ) $94,663 for home improvements
11 February 2009 $256,041 $951,214.54 ( L5 ) $240,000 for build
$14,000 for Lender’s Mortgage
Insuranc e
Associated costs and fees
The complainants say:
the bank offered an inappropriate product when it provided L5 in February 2009
the bank should have permitted them to draw down on L5 in September 2009
they suffered ongoing loss from their inability to complete construction of their home after
the bank did not make funds from L5 available, and
the bank should have reinstated L5 in September 2009 and allowed them to draw down on
L5 after they made a reinstatement request.
1.2 Issues and key findings
Did the bank offer an appropriate product in 2009?
The loan product offered by the bank in February 2009 was appropriate. The bank was not
required to offer a loan with interest only repayments.
Determination | Case number: 666724 Page 2 of 11
Was the bank entitled to prevent further drawdowns from L5 in 2009?
The bank was entitled to prevent further drawdowns under the L5 contract in September 2009
for the following reasons:
the complainants did not meet the special condition in the loan offer, and
the L5 contract entitled the bank to prevent further drawdowns if the complainants did not
fully draw down L5 within three months from February 2009.
Was the bank required to reinstate the additional funding under L5?
The bank was not required to reinstate L5. The decision about whether to reinstate L5 was a
commercial decision, and the bank did not breach its obligations to the complainants when it
declined to reinstate L5 in September 2009.
Did the bank fail to respond to the complainants’ request?
There is insufficient information to conclude that the bank failed to respond to the
complainant’s request to reinstate the additional funding in September 2009.
Have the complainants established their other claims?
The complainants have not established that the bank’s ex -employees misappropriated funds.
Why is the outcome fair?
The events the complainants have described are unfortunate and I understand the
complainants have suffered loss and personal hardship because they have been unable to
obtain funding to complete construction of their home.
However, the bank did not breach its obligations to the complainants when it declined to
provide the additional funding under L5 and declined to reinstate the additional funding on
request.
The bank has not breached any obligation to the complainants, so it would not be fair to
require it to compensate the complainants.
1.3 Determination
This determination is in favour of the bank.
The bank is not required to compensate the complainants or take any further steps.
Determination | Case number: 666724 Page 3 of 11
2 Reasons for determination
2.1 Did the bank offer an appropriate product in 2009?
The loan product offered by the bank in February 2009 was appropriate. The bank was not
required to offer a loan with interest only repayments.
The complainants say the bank offered an inappropriate product in 2009
The complainants say:
during the construction stage of a property, the bank is expected to offer interest-only
repayments but failed to do so
a customer service employee of the bank told them the loan provided was a wrong loan,
and for this reason the bank refused all of their interest rate review requests
the bank tried to hide its internal misconduct by not identifying the loan as a low-doc loan,
and
they were unable to negotiate for a lower interest rate due to the loan being a low-doc
loan.
The low-doc loan offered by the bank in February 2009 was appropriate
On 4 December 2008, the complainants applied for a loan increase of $240,000 to complete
the construction of their home at property M. The application form shows the complainants
established a construction business operating as a partnership in 2007.
As part of the application, the complainants signed a low-doc loan declaration in which they
declared:
total taxable annual income of $100,000 for Mr S
the information disclosed in the application and declaration is true and correct
their acknowledgement that the bank relies on the declaration in considering whether to
approve their loan application.
Because Mr S was relying on his self-employed income to service the loan, it was reasonable
for the bank to process the L5 application as a low-doc loan.
The bank had obligations when assessing the low doc loan to be aware of any red flags that
indicated the information provided on the low-doc loan application was unreliable or incorrect.
I do not consider that there were any red flags on the face of the application or in the
information the bank had about the complainants from their previous applications that would
have caused the bank to reasonably suspect that the information in the L5 application was
not accurate. It was therefore appropriate for the bank to assess the affordability of the L5
loan based on the information in the low-doc declaration and the other information the bank
had about the complainants.
The bank was not required to offer a loan with interest-only repayments
The bank approved L1 in 2003 to fund the complainants’ purchase of property M as vacant
land. The L1 loan application did not request funding for construction on property M.
The complainants originally applied for L2 as an owner builder loan. An owner builder is a
borrower who builds the house themselves with no fixed price contract with a registered
builder. The complainants provided the bank with an owner builder permit dated April 2004
with a scope of works valued at $300,000.
Determination | Case number: 666724 Page 4 of 11
After some negotiations with the bank, the complainants subsequently provided the bank with
a fixed price building contract for $360,000 dated June 2004. The building contract disclosed
the works involved constructing a two-storey dwelling on property M. In August 2004, the
bank approved L2, which provided the complainants a loan increase of $405,142 to fund the
construction under the fixed price building contract and for other costs and expenses.
The bank then approved L3 in July 2005 partly to finalise the build, and partly to pay out the
complainants’ other existing debts. The bank then approved L4 in June 2006 (almost two
years after the funds were provided for the fixed price building contract under L2) to fund
home improvements.
Having reviewed the loan applications and circumstances of the complainants’ construction
program as it was evident to the bank between 2004 and 2009, in my view it was reasonable
for the bank to presume that construction of the home would be completed within 12-18
months from the provision of L2 in August 2004. The date for practical completion on the
original fixed price building contract was 31 November 2004. The application for L3 in July
2005 for funds to complete the building supports a presumption that the dwelling would be
finalised shortly thereafter.
The complainants’ application for L4 in June 2006 for ‘home improvements’ further suggests
that the complainants were residing in, or would shortly be residing in, property M, and that
construction had already been completed.
In fact, the complainants say construction was never completed and they have been residing
in a partially completed portion of the dwelling at property M for over ten years.
There is nothing to suggest the bank was aware of this. In these circumstances, it was
reasonable for the bank to offer loans with principal and interest repayments, particularly once
the complainants were residing at property M and had no other housing costs. This is
because the finalisation of construction woul d not significantly impact on the complainants’
ability to meet principal and interest repayment obligations.
In some circumstances, it may be appropriate for a lender to offer a loan with interest only
repayments – for example, where construction needs to be finished before income can be
earned from the property. However, the complainants did not have other housing costs and
they were not reliant on the finalisation of construction to, for example, generate rental
income to make the required repayments towards the loan.
In my view, the bank offered the complainants appropriate loan products for the disclosed
loan purposes.
2.2 Was the bank entitled to prevent further drawdowns from
L5 in 2009?
The bank was entitled to prevent further drawdowns from L5 in September 2009 because:
it does not appear the complainants met the special condition set out in the L5 contract,
and
the L5 contract entitled the bank to prevent further drawdowns if the complainants did not
fully draw down L5 within 3 months from February 2009.
The complainants were notified of the special condition
In February 2009, the bank approved L5, which included $256,041 in new credit to enable the
complainants to finalise construction of the dwelling at property M. The L5 offer was made on
Determination | Case number: 666724 Page 5 of 11
11 February 2009. Because of the successive funding requests between 2004 and 2009, the
L5 contract required the complainants to provide certain documents before the bank would
release new funding:
The Borrower agrees and acknowledges this offer of finance is conditional upon
the Borrower providing, prior to settlement, the Bank with copies of a fixed price
Building Contract Specifications and Council Approved Plans the terms or
conditions of which are to be satisfactory to the Bank.
The complainants have not provided information to show that they met the special condition
by providing a copy of a fixed price building contract and council approved plans to the bank.
AFCA has requested that the complainants provide information or correspondence to show
that they met this special condition under the L5 contract. The complainants say that the
plans and building contract from 2004 are sufficient to meet the special condition. However, I
d o not agree with the complainants’ contention . In my view, the special condition in the L5
contract requires the provision of an updated fixed price building contract for the works the
complainants say were outstanding in 2009. The bank had already provided funding in
excess of the price of the fixed price building contract from 2004, so that contract was not
sufficient to demonstrate the works that required funding in 2009.
It is therefore my view that the complainants did not meet the special condition in the L5
contract, and the bank was not obliged to provide funding under the L5 contract.
The bank had other rights to decline additional drawdowns
Even if the complainants did meet the requirements of the special condition, the bank had
other rights to decline the complainants ’ request to draw down new funds under the L5
contract.
Relevantly, clause 2 of the L5 contract provides:
the bank reserves the right to withdraw the offer of additional funds if the complainants
have not drawn the additional funds within one month from the date of the L5 contract, and
if the additional funds are not fully drawn within three months of the L5 contract (that is, by
11 May 2009), the bank may reduce the amount of credit to the outstanding balance of the
loan at that time.
The complainants did not submit a funding request to the bank until 28 August 2009. At that
time, more than three months had passed since the contract date and the complainants had
not yet drawn down on the loan, so the bank had the right to decline further drawdowns under
clause 2 of the L5 contract.
On 28 August 2009, the complainants provided a funding request to the bank, requesting a
payment of $156,098.63.
On 9 September 2009, the complainants requested the bank release progress payments of
$157,840. In or around October 2009, seven months after the bank approved L5, the
complainants provided a series of invoices for construction work to the bank. It appears all
invoices were addressed to the complainants and not a third-party builder. Many of the costs
the complainants were claiming related to materials they said they had already purchased
and were storing at the property.
Even if the bank was not entitled to decline the funding request because of clause 2 of the
contract, I am not satisfied that the funding request the complainants made to the bank was in
Determination | Case number: 666724 Page 6 of 11
a reasonably acceptable form. Considering the requirements of the special condition in the
contract, in my view it was unreasonable for the complainants to provide invoices addressed
to them personally without an updated building contract with a registered builder, and without
plans showing the construction work being funded.
The bank was entitled to decline to provide further funding in September and October 2009.
The bank communicated its withdrawal of funding to the complainants
The complainants say the bank failed to provide any advice or explanation for its decision to
decline further funding.
On 28 September 2009, a bank staff member emailed the complainants after a telephone
discussion with one of the complainants. The email confirmed the bank had explained to the
complainants at the time that the approval for additional funding under the L5 facility had
expired and the bank required information from the complainants to consider reinstating the
additional funding under the L5 contract.
I am satisfied that the bank communicated to the complainants the reason for its decision to
decline further funding under L5 was due to the passage of time as contemplated in clause 2
of the L5 contract.
2.3 Was the bank required to reinstate the additional funding
under L5?
The bank was not required to reinstate the additional funding under L5. This decision was a
commercial decision for the bank to make at its discretion. The bank did not breach its
obligations to the complainants when it declined to reinstate the additional funding under L5 in
September 2009.
The complainants applied for L5 offer to be reinstated
On 16 September 2009, the complainants submitted an application to the bank for the bank to
consider their request to reinstate the additional funding under L5.
The complainants say that this application was not a new application, but an application to
reinstate the L5 offer that was approved in February 2009.
As part of the application, the complainants signed a low-doc declaration, similar to the low-
doc declaration they signed in December 2008. Along with their application, the complainants
provided the bank with their income documents.
Amongst other information, the bank required the complainants to provide details of the
project stages, the time that progress draws would be required, the work that was to be
completed and the anticipated completion dates for each project stage. This information was
reasonably required to assist the bank to consider the complainants’ application and to
enable its valuer to complete an updated valuation.
The complainants responded to the bank’s request on 9 November 2009. On 17 November
2009, a bank staff member emailed the complainants confirming the information they supplied
had been forwarded to the bank’s credit analysts for assessment.
Determination | Case number: 666724 Page 7 of 11
The bank was not required to reinstate L5
The bank took steps to reassess the credit risk and the complainants’ request for funding to
complete further construction of the dwelling on property M.
As outlined in section 2.1, the bank had already provided significantly more funding than the
amount required under the 2004 building contract, and the complainants had not provided
detailed information about why they required significant additional funds to finalise the
construction of the dwelling at property M.
When a diligent and prudent bank assesses an application for a construction loan, it conducts
due diligence about the building works that are being financed. The bank’s request for a new
fixed price building contract is in line with good banking practice. The complainants applied in
December 2008 for a further $240,964 for construction of a dwelling which, according to the
information available at the time, ought to have been completed with the funding from L2 in
2004, and which should certainly have been finalised after L4 was provided in 2006 for ‘home
improvements’. Accordingly, it was reasonable for the bank to require a fixed price building
contract as part of its assessment of L5 to reasonably satisfy itself about the outstanding
building works required.
The complainants provided some information to the bank in October and November 2009
about the outstanding works required, but this information was not detailed and included
references to significant costs already incurred and materials already purchased. In any
event, the decision about whether to reinstate the funding under L5 was subject to the bank’s
commercial discretion, and the bank had no obligation to provide the funding.
The bank was not required to reinstate the additional funding under L5 and it did not breach
any obligation to the complainants when it declined their request to reinstate the additional
funding.
2.4 Did the bank fail to respond to the complainants’ request?
There is insufficient information to conclude that the bank failed to respond to the
complainant’s request to reinstate the additional funding under L5 in 2009.
The complainants say the bank failed to respond to their application
The complainants say:
the last response they received from the bank in response to their application in
September 2009 was an email dated 17 November 2009
they received no further response from the bank
they suspect the bank’s credit analysts identified internal misconduct and therefore did not
progress with reinstating L5.
Information about the assessment is not available
On 17 November 2009, a bank staff member emailed the complainants to confirm the further
application information they provided had been forwarded to the bank’s credit analysts for
assessment.
The bank says due to the passage of time, it is unable to provide further records to confirm its
assessment of the complainants’ application to reinstate the funding under L5. However, the
bank says it declined the complainants’ request to reinstate the additional funds under L5.
Determination | Case number: 666724 Page 8 of 11
In some circumstances, AFCA will draw an adverse inference that a party’s failure to provide
information requested does not favour its position. However, where there is a valid reason the
information is unavailable, such as in this case due to the time that has passed (over ten
years), we may not draw an adverse inference. This is because there is no requirement that
the bank retain this information indefinitely, particularly information relating to declined loan
applications.
There is no contemporaneous record to confirm the bank advised the complainants after 17
November 2009 that it required the complainants to lodge a new loan application. Therefore,
it is unclear if the bank provided a final response to the complainants’ request for the
February 2009 offer to be reinstated. However, there is also no contemporaneous record to
show the complainants followed up with the bank between 17 November 2009 and October
2010.
The bank’s file note da ted 5 October 2010 records that the bank advised the complainants in
2009 that their application to reinstate the February 2009 offer did not proceed. The October
2010 file note also indicates the bank discussed paths forward with the complainants and
they were considering submitting a new loan application.
The October 2010 file note confirms that the bank had a discussion with the complainants in
October 2010 and at that time the complainants were aware of the bank’s position. This file
note also refers back to earlier conversations about the 2009 application.
In my view, it is more likely than not the bank made the complainants aware in late 2009 that
it did not intend to reinstate the additional funding under L5.
2.5 Have the complainants established their other claims?
The complainants have not established their other claims about the bank.
The complainants raised other claims about the bank
The complainants say:
during their meeting with the bank on 5 March 2021, an employee of the bank advised
them L5 was approved in September 2008
on 30 March 2021, amongst other invoices, the bank provided AFCA with a copy of an
invoice dated 28 August 2009 unrelated to their construction work
they believe two of the bank’s ex -employees embezzled loan funds from L5, and this is
supported by the unrelated invoice dated 28 August 2009.
There is no information to show L5 was approved in September 2008
A review of the available information confirms L5 was approved in or around February 2009,
as the bank issued the L5 variation contract on 11 February 2009. There is no information to
show that the bank approved L5 in September 2008. In any event, if L5 was approved in
September 2008, that would not alter the outcome of this complaint in any way.
The bank provided an unrelated invoice in error
The complainants say the invoice dated 28 August 2009 was not related to them because:
the invoice was issued by a builder that was not their builder
the invoice was addressed to a different Mr S (with the same surname as Mr S but a
different first name), and
the job address for construction was another property other than property M.
Determination | Case number: 666724 Page 9 of 11
The bank says this particular invoice does not relate to the complainants and was placed on
the file in error.
The bank made an error when it included the unrelated invoice in the information provided to
AFCA. Where a financial firm makes an error, AFCA considers whether the financial firm ’s
error caused the complainants to suffer any loss. However, AFCA cannot impose a fine or
punish a financial firm for its actions.
I do not consider the bank’s error caused the complainants any loss .
The complainants say they believe two of the bank’s ex -employees embezzled loan funds
from L5 in 2009, and the unrelated invoice supports this view.
Having reviewed the available information and the overall circumstances of the bank’s refusal
to reinstate L5 in 2009, I consider the complainants have not established those claims.
It is more likely than not that the bank made an error when responding to AFC A with a series
of construction-related invoices from the complainants. I do not consider the unrelated invoice
supports a view that the bank’s ex -employees misappropriated loan funds.
In its response of 30 March 2021, the bank says it approved L5 in February 2009 and the
additional loan funds of $256,041.75 were placed in the loan account ready for drawdown by
the bank’s progress funding team once the complai nants provided the required documents
including construction invoices. However, the outstanding loan amount did not increase
because the complainants did not draw down on these funds.
The loan account statement for the loan account confirms an amount of $256,041.75 was
made available for drawdown on 23 February 2009, however because the complainants did
not draw down this amount, the outstanding loan balance did not increase.
The bank offered appropriate hardship assistance
The complainants say the bank should have reduced the interest rate on their loan to make
repayments more affordable so they could have a better quality of life and keep up with the
repayments. The bank was not required to reduce the interest rate on the c omplainants’ loan.
The complainants made several hardship applications with the bank between 2013 and 2019,
and the bank provided hardship assistance including reductions in monthly repayments and
capitalisation of arrears.
Hardship assistance is generally intended to address short term financial hardship to enable
borrowers to continue making full repayments at a later date without substantial accumulation
of arrears. The bank was not obliged to provide ongoing long-term reductions in repayments
or interest on the loan. The bank complied with its financial hardship obligations when it
offered to reduce the complainants’ monthly repayments and capitalise arrears in July 2013.
The bank also met its financial hardship obligations when it offered to capitalise $16,118 in
arrears and defer four monthly repayments from November 2013, and capitalise the deferred
payments if the complainants then met their repayment obligations for a further six months.
The bank offered the complainants further short-term repayment reductions in February 2018
and November 2018 when the complainants made further financial hardship requests. When
it assessed each of these applications, the bank was required to balance the complainants’
desire to remain in their home, their temporary financial challenges caused by mental health
difficulties, and their longer-term difficulty in meeting their repayment obligations. In my view,
the bank took appropriate steps to discuss short-term financial hardship assistance with the
complainants and offered appropriate assistance.
Determination | Case number: 666724 Page 10 of 11
The bank is not required to compensate the complainants for other loss
The complainants say they suffered consequential loss and damage including vilification from
neighbours, pain and suffering, physical and psychological damage and loss of income
because of their present living situation in a partially constructed home.
The complainants say they were unable to properly care for their late son who had special
needs whilst he was unwell. I appreciate that these events have caused the complainants
significant personal hardship and I extend my condolences to them about the tragic loss of
their son.
However, AFCA can only require a financial firm to compensate complainants for loss where
a financial firm makes an error. Because the bank did not make an error for the reasons
outlined in this determination, the bank is not required to compensate the complainants.
2.6 Why is the outcome fair?
The events the complainants have described are unfortunate and I understand the
complainants have suffered hardship because they have not been able to obtain funding to
complete construction of their home.
However, the bank did not breach its obligations to the complainants and it would not be fair
to require the bank to compensate the complainants.
Determination | Case number: 666724 Page 11 of 11
3 Supporting information
3.1 The AFCA processes
AFCA’s approach is based on fairness
I have determined this complaint based on what is fair in all the circumstances, having regard
to:
relevant legal principles
applicable industry codes or guidance
good industry practice, and
previous decisions of AFCA or its predecessor schemes (which are not binding).
I have reviewed and considered all information the parties have provided and I am satisfied
all relevant information has been exchanged to both parties
While the parties have raised a number of issues in their submissions, I have restricted
commentary in this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties, and
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
3.2 Loan affordability
The AFCA recommendation issued on 10 December 2020 considered the affordability of the
loans. The complainants did not dispute the recommendation’s assessment of affordability in
their further submissions. The complainants say their complaint is not about affordability of
the loans, but instead about the other issues discussed in this determination. I have not
repeated AFCA’s findings about the affordability of the loans in this determination.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.