Determination 666724

Refusal to draw down or reinstate additional construction funding under home loan

FirmSuncorp Group
Decided2021-12-10
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainants sought reinstatement of and drawdown on a 2009 construction loan increase and related compensation after the bank declined to release the funds. AFCA decided the bank was entitled to decline drawdowns and was not required to reinstate the funding, so no compensation was ordered.

The bank was entitled to prevent drawdowns under the L5 special condition and the three-month clause, and reinstatement was a commercial discretion not an obligation.

Issues

Subjects and remedies

deceased estatefinancial hardshiphealth or medicalmental healthno remedy

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 666724 Financial firm Suncorp - Metway Limited Determination | Case number: 666724 Page 1 of 11 Case number: 666724 10 December 2021 1 Determination overview 1.1 Complaint This complaint relates to a home loan Mr and Mrs S (the complainants ) obtained from the financial firm (the bank ) to complete construction of their partially built home. In June 2003, the complainants first applied for a home loan with a principal sum of $164,000 to fund their purchase of a property ( property M ). The loan was increased and varied four times between 2003 and 2009. The increases and variations are detailed below: Date New credit Total loan amount Purpose 2 June 2003 New loan $162,383.3 ( L1 ) Purchase property M 9 August 2004 $405,142 $564,107.48 ( L2 )  Build on property M for $360,000  Pay out personal loan $36,000  Pay out car loan of $6,900  Associated costs and outlays 4 July 2005 $91,332 $648,671.61 ( L3 )  Cash out $44,000  $46,000 for build  Associated costs and fees 7 June 2006 $94,663 $731,391.33 ( L4 )  $94,663 for home improvements 11 February 2009 $256,041 $951,214.54 ( L5 )  $240,000 for build  $14,000 for Lender’s Mortgage Insuranc e  Associated costs and fees The complainants say:  the bank offered an inappropriate product when it provided L5 in February 2009  the bank should have permitted them to draw down on L5 in September 2009  they suffered ongoing loss from their inability to complete construction of their home after the bank did not make funds from L5 available, and  the bank should have reinstated L5 in September 2009 and allowed them to draw down on L5 after they made a reinstatement request. 1.2 Issues and key findings Did the bank offer an appropriate product in 2009? The loan product offered by the bank in February 2009 was appropriate. The bank was not required to offer a loan with interest only repayments. Determination | Case number: 666724 Page 2 of 11 Was the bank entitled to prevent further drawdowns from L5 in 2009? The bank was entitled to prevent further drawdowns under the L5 contract in September 2009 for the following reasons:  the complainants did not meet the special condition in the loan offer, and  the L5 contract entitled the bank to prevent further drawdowns if the complainants did not fully draw down L5 within three months from February 2009. Was the bank required to reinstate the additional funding under L5? The bank was not required to reinstate L5. The decision about whether to reinstate L5 was a commercial decision, and the bank did not breach its obligations to the complainants when it declined to reinstate L5 in September 2009. Did the bank fail to respond to the complainants’ request? There is insufficient information to conclude that the bank failed to respond to the complainant’s request to reinstate the additional funding in September 2009. Have the complainants established their other claims? The complainants have not established that the bank’s ex -employees misappropriated funds. Why is the outcome fair? The events the complainants have described are unfortunate and I understand the complainants have suffered loss and personal hardship because they have been unable to obtain funding to complete construction of their home. However, the bank did not breach its obligations to the complainants when it declined to provide the additional funding under L5 and declined to reinstate the additional funding on request. The bank has not breached any obligation to the complainants, so it would not be fair to require it to compensate the complainants. 1.3 Determination This determination is in favour of the bank. The bank is not required to compensate the complainants or take any further steps. Determination | Case number: 666724 Page 3 of 11 2 Reasons for determination 2.1 Did the bank offer an appropriate product in 2009? The loan product offered by the bank in February 2009 was appropriate. The bank was not required to offer a loan with interest only repayments. The complainants say the bank offered an inappropriate product in 2009 The complainants say:  during the construction stage of a property, the bank is expected to offer interest-only repayments but failed to do so  a customer service employee of the bank told them the loan provided was a wrong loan, and for this reason the bank refused all of their interest rate review requests  the bank tried to hide its internal misconduct by not identifying the loan as a low-doc loan, and  they were unable to negotiate for a lower interest rate due to the loan being a low-doc loan. The low-doc loan offered by the bank in February 2009 was appropriate On 4 December 2008, the complainants applied for a loan increase of $240,000 to complete the construction of their home at property M. The application form shows the complainants established a construction business operating as a partnership in 2007. As part of the application, the complainants signed a low-doc loan declaration in which they declared:  total taxable annual income of $100,000 for Mr S  the information disclosed in the application and declaration is true and correct  their acknowledgement that the bank relies on the declaration in considering whether to approve their loan application. Because Mr S was relying on his self-employed income to service the loan, it was reasonable for the bank to process the L5 application as a low-doc loan. The bank had obligations when assessing the low doc loan to be aware of any red flags that indicated the information provided on the low-doc loan application was unreliable or incorrect. I do not consider that there were any red flags on the face of the application or in the information the bank had about the complainants from their previous applications that would have caused the bank to reasonably suspect that the information in the L5 application was not accurate. It was therefore appropriate for the bank to assess the affordability of the L5 loan based on the information in the low-doc declaration and the other information the bank had about the complainants. The bank was not required to offer a loan with interest-only repayments The bank approved L1 in 2003 to fund the complainants’ purchase of property M as vacant land. The L1 loan application did not request funding for construction on property M. The complainants originally applied for L2 as an owner builder loan. An owner builder is a borrower who builds the house themselves with no fixed price contract with a registered builder. The complainants provided the bank with an owner builder permit dated April 2004 with a scope of works valued at $300,000. Determination | Case number: 666724 Page 4 of 11 After some negotiations with the bank, the complainants subsequently provided the bank with a fixed price building contract for $360,000 dated June 2004. The building contract disclosed the works involved constructing a two-storey dwelling on property M. In August 2004, the bank approved L2, which provided the complainants a loan increase of $405,142 to fund the construction under the fixed price building contract and for other costs and expenses. The bank then approved L3 in July 2005 partly to finalise the build, and partly to pay out the complainants’ other existing debts. The bank then approved L4 in June 2006 (almost two years after the funds were provided for the fixed price building contract under L2) to fund home improvements. Having reviewed the loan applications and circumstances of the complainants’ construction program as it was evident to the bank between 2004 and 2009, in my view it was reasonable for the bank to presume that construction of the home would be completed within 12-18 months from the provision of L2 in August 2004. The date for practical completion on the original fixed price building contract was 31 November 2004. The application for L3 in July 2005 for funds to complete the building supports a presumption that the dwelling would be finalised shortly thereafter. The complainants’ application for L4 in June 2006 for ‘home improvements’ further suggests that the complainants were residing in, or would shortly be residing in, property M, and that construction had already been completed. In fact, the complainants say construction was never completed and they have been residing in a partially completed portion of the dwelling at property M for over ten years. There is nothing to suggest the bank was aware of this. In these circumstances, it was reasonable for the bank to offer loans with principal and interest repayments, particularly once the complainants were residing at property M and had no other housing costs. This is because the finalisation of construction woul d not significantly impact on the complainants’ ability to meet principal and interest repayment obligations. In some circumstances, it may be appropriate for a lender to offer a loan with interest only repayments – for example, where construction needs to be finished before income can be earned from the property. However, the complainants did not have other housing costs and they were not reliant on the finalisation of construction to, for example, generate rental income to make the required repayments towards the loan. In my view, the bank offered the complainants appropriate loan products for the disclosed loan purposes. 2.2 Was the bank entitled to prevent further drawdowns from L5 in 2009? The bank was entitled to prevent further drawdowns from L5 in September 2009 because:  it does not appear the complainants met the special condition set out in the L5 contract, and  the L5 contract entitled the bank to prevent further drawdowns if the complainants did not fully draw down L5 within 3 months from February 2009. The complainants were notified of the special condition In February 2009, the bank approved L5, which included $256,041 in new credit to enable the complainants to finalise construction of the dwelling at property M. The L5 offer was made on Determination | Case number: 666724 Page 5 of 11 11 February 2009. Because of the successive funding requests between 2004 and 2009, the L5 contract required the complainants to provide certain documents before the bank would release new funding: The Borrower agrees and acknowledges this offer of finance is conditional upon the Borrower providing, prior to settlement, the Bank with copies of a fixed price Building Contract Specifications and Council Approved Plans the terms or conditions of which are to be satisfactory to the Bank. The complainants have not provided information to show that they met the special condition by providing a copy of a fixed price building contract and council approved plans to the bank. AFCA has requested that the complainants provide information or correspondence to show that they met this special condition under the L5 contract. The complainants say that the plans and building contract from 2004 are sufficient to meet the special condition. However, I d o not agree with the complainants’ contention . In my view, the special condition in the L5 contract requires the provision of an updated fixed price building contract for the works the complainants say were outstanding in 2009. The bank had already provided funding in excess of the price of the fixed price building contract from 2004, so that contract was not sufficient to demonstrate the works that required funding in 2009. It is therefore my view that the complainants did not meet the special condition in the L5 contract, and the bank was not obliged to provide funding under the L5 contract. The bank had other rights to decline additional drawdowns Even if the complainants did meet the requirements of the special condition, the bank had other rights to decline the complainants ’ request to draw down new funds under the L5 contract. Relevantly, clause 2 of the L5 contract provides:  the bank reserves the right to withdraw the offer of additional funds if the complainants have not drawn the additional funds within one month from the date of the L5 contract, and  if the additional funds are not fully drawn within three months of the L5 contract (that is, by 11 May 2009), the bank may reduce the amount of credit to the outstanding balance of the loan at that time. The complainants did not submit a funding request to the bank until 28 August 2009. At that time, more than three months had passed since the contract date and the complainants had not yet drawn down on the loan, so the bank had the right to decline further drawdowns under clause 2 of the L5 contract. On 28 August 2009, the complainants provided a funding request to the bank, requesting a payment of $156,098.63. On 9 September 2009, the complainants requested the bank release progress payments of $157,840. In or around October 2009, seven months after the bank approved L5, the complainants provided a series of invoices for construction work to the bank. It appears all invoices were addressed to the complainants and not a third-party builder. Many of the costs the complainants were claiming related to materials they said they had already purchased and were storing at the property. Even if the bank was not entitled to decline the funding request because of clause 2 of the contract, I am not satisfied that the funding request the complainants made to the bank was in Determination | Case number: 666724 Page 6 of 11 a reasonably acceptable form. Considering the requirements of the special condition in the contract, in my view it was unreasonable for the complainants to provide invoices addressed to them personally without an updated building contract with a registered builder, and without plans showing the construction work being funded. The bank was entitled to decline to provide further funding in September and October 2009. The bank communicated its withdrawal of funding to the complainants The complainants say the bank failed to provide any advice or explanation for its decision to decline further funding. On 28 September 2009, a bank staff member emailed the complainants after a telephone discussion with one of the complainants. The email confirmed the bank had explained to the complainants at the time that the approval for additional funding under the L5 facility had expired and the bank required information from the complainants to consider reinstating the additional funding under the L5 contract. I am satisfied that the bank communicated to the complainants the reason for its decision to decline further funding under L5 was due to the passage of time as contemplated in clause 2 of the L5 contract. 2.3 Was the bank required to reinstate the additional funding under L5? The bank was not required to reinstate the additional funding under L5. This decision was a commercial decision for the bank to make at its discretion. The bank did not breach its obligations to the complainants when it declined to reinstate the additional funding under L5 in September 2009. The complainants applied for L5 offer to be reinstated On 16 September 2009, the complainants submitted an application to the bank for the bank to consider their request to reinstate the additional funding under L5. The complainants say that this application was not a new application, but an application to reinstate the L5 offer that was approved in February 2009. As part of the application, the complainants signed a low-doc declaration, similar to the low- doc declaration they signed in December 2008. Along with their application, the complainants provided the bank with their income documents. Amongst other information, the bank required the complainants to provide details of the project stages, the time that progress draws would be required, the work that was to be completed and the anticipated completion dates for each project stage. This information was reasonably required to assist the bank to consider the complainants’ application and to enable its valuer to complete an updated valuation. The complainants responded to the bank’s request on 9 November 2009. On 17 November 2009, a bank staff member emailed the complainants confirming the information they supplied had been forwarded to the bank’s credit analysts for assessment. Determination | Case number: 666724 Page 7 of 11 The bank was not required to reinstate L5 The bank took steps to reassess the credit risk and the complainants’ request for funding to complete further construction of the dwelling on property M. As outlined in section 2.1, the bank had already provided significantly more funding than the amount required under the 2004 building contract, and the complainants had not provided detailed information about why they required significant additional funds to finalise the construction of the dwelling at property M. When a diligent and prudent bank assesses an application for a construction loan, it conducts due diligence about the building works that are being financed. The bank’s request for a new fixed price building contract is in line with good banking practice. The complainants applied in December 2008 for a further $240,964 for construction of a dwelling which, according to the information available at the time, ought to have been completed with the funding from L2 in 2004, and which should certainly have been finalised after L4 was provided in 2006 for ‘home improvements’. Accordingly, it was reasonable for the bank to require a fixed price building contract as part of its assessment of L5 to reasonably satisfy itself about the outstanding building works required. The complainants provided some information to the bank in October and November 2009 about the outstanding works required, but this information was not detailed and included references to significant costs already incurred and materials already purchased. In any event, the decision about whether to reinstate the funding under L5 was subject to the bank’s commercial discretion, and the bank had no obligation to provide the funding. The bank was not required to reinstate the additional funding under L5 and it did not breach any obligation to the complainants when it declined their request to reinstate the additional funding. 2.4 Did the bank fail to respond to the complainants’ request? There is insufficient information to conclude that the bank failed to respond to the complainant’s request to reinstate the additional funding under L5 in 2009. The complainants say the bank failed to respond to their application The complainants say:  the last response they received from the bank in response to their application in September 2009 was an email dated 17 November 2009  they received no further response from the bank  they suspect the bank’s credit analysts identified internal misconduct and therefore did not progress with reinstating L5. Information about the assessment is not available On 17 November 2009, a bank staff member emailed the complainants to confirm the further application information they provided had been forwarded to the bank’s credit analysts for assessment. The bank says due to the passage of time, it is unable to provide further records to confirm its assessment of the complainants’ application to reinstate the funding under L5. However, the bank says it declined the complainants’ request to reinstate the additional funds under L5. Determination | Case number: 666724 Page 8 of 11 In some circumstances, AFCA will draw an adverse inference that a party’s failure to provide information requested does not favour its position. However, where there is a valid reason the information is unavailable, such as in this case due to the time that has passed (over ten years), we may not draw an adverse inference. This is because there is no requirement that the bank retain this information indefinitely, particularly information relating to declined loan applications. There is no contemporaneous record to confirm the bank advised the complainants after 17 November 2009 that it required the complainants to lodge a new loan application. Therefore, it is unclear if the bank provided a final response to the complainants’ request for the February 2009 offer to be reinstated. However, there is also no contemporaneous record to show the complainants followed up with the bank between 17 November 2009 and October 2010. The bank’s file note da ted 5 October 2010 records that the bank advised the complainants in 2009 that their application to reinstate the February 2009 offer did not proceed. The October 2010 file note also indicates the bank discussed paths forward with the complainants and they were considering submitting a new loan application. The October 2010 file note confirms that the bank had a discussion with the complainants in October 2010 and at that time the complainants were aware of the bank’s position. This file note also refers back to earlier conversations about the 2009 application. In my view, it is more likely than not the bank made the complainants aware in late 2009 that it did not intend to reinstate the additional funding under L5. 2.5 Have the complainants established their other claims? The complainants have not established their other claims about the bank. The complainants raised other claims about the bank The complainants say:  during their meeting with the bank on 5 March 2021, an employee of the bank advised them L5 was approved in September 2008  on 30 March 2021, amongst other invoices, the bank provided AFCA with a copy of an invoice dated 28 August 2009 unrelated to their construction work  they believe two of the bank’s ex -employees embezzled loan funds from L5, and this is supported by the unrelated invoice dated 28 August 2009. There is no information to show L5 was approved in September 2008 A review of the available information confirms L5 was approved in or around February 2009, as the bank issued the L5 variation contract on 11 February 2009. There is no information to show that the bank approved L5 in September 2008. In any event, if L5 was approved in September 2008, that would not alter the outcome of this complaint in any way. The bank provided an unrelated invoice in error The complainants say the invoice dated 28 August 2009 was not related to them because:  the invoice was issued by a builder that was not their builder  the invoice was addressed to a different Mr S (with the same surname as Mr S but a different first name), and  the job address for construction was another property other than property M. Determination | Case number: 666724 Page 9 of 11 The bank says this particular invoice does not relate to the complainants and was placed on the file in error. The bank made an error when it included the unrelated invoice in the information provided to AFCA. Where a financial firm makes an error, AFCA considers whether the financial firm ’s error caused the complainants to suffer any loss. However, AFCA cannot impose a fine or punish a financial firm for its actions. I do not consider the bank’s error caused the complainants any loss . The complainants say they believe two of the bank’s ex -employees embezzled loan funds from L5 in 2009, and the unrelated invoice supports this view. Having reviewed the available information and the overall circumstances of the bank’s refusal to reinstate L5 in 2009, I consider the complainants have not established those claims. It is more likely than not that the bank made an error when responding to AFC A with a series of construction-related invoices from the complainants. I do not consider the unrelated invoice supports a view that the bank’s ex -employees misappropriated loan funds. In its response of 30 March 2021, the bank says it approved L5 in February 2009 and the additional loan funds of $256,041.75 were placed in the loan account ready for drawdown by the bank’s progress funding team once the complai nants provided the required documents including construction invoices. However, the outstanding loan amount did not increase because the complainants did not draw down on these funds. The loan account statement for the loan account confirms an amount of $256,041.75 was made available for drawdown on 23 February 2009, however because the complainants did not draw down this amount, the outstanding loan balance did not increase. The bank offered appropriate hardship assistance The complainants say the bank should have reduced the interest rate on their loan to make repayments more affordable so they could have a better quality of life and keep up with the repayments. The bank was not required to reduce the interest rate on the c omplainants’ loan. The complainants made several hardship applications with the bank between 2013 and 2019, and the bank provided hardship assistance including reductions in monthly repayments and capitalisation of arrears. Hardship assistance is generally intended to address short term financial hardship to enable borrowers to continue making full repayments at a later date without substantial accumulation of arrears. The bank was not obliged to provide ongoing long-term reductions in repayments or interest on the loan. The bank complied with its financial hardship obligations when it offered to reduce the complainants’ monthly repayments and capitalise arrears in July 2013. The bank also met its financial hardship obligations when it offered to capitalise $16,118 in arrears and defer four monthly repayments from November 2013, and capitalise the deferred payments if the complainants then met their repayment obligations for a further six months. The bank offered the complainants further short-term repayment reductions in February 2018 and November 2018 when the complainants made further financial hardship requests. When it assessed each of these applications, the bank was required to balance the complainants’ desire to remain in their home, their temporary financial challenges caused by mental health difficulties, and their longer-term difficulty in meeting their repayment obligations. In my view, the bank took appropriate steps to discuss short-term financial hardship assistance with the complainants and offered appropriate assistance. Determination | Case number: 666724 Page 10 of 11 The bank is not required to compensate the complainants for other loss The complainants say they suffered consequential loss and damage including vilification from neighbours, pain and suffering, physical and psychological damage and loss of income because of their present living situation in a partially constructed home. The complainants say they were unable to properly care for their late son who had special needs whilst he was unwell. I appreciate that these events have caused the complainants significant personal hardship and I extend my condolences to them about the tragic loss of their son. However, AFCA can only require a financial firm to compensate complainants for loss where a financial firm makes an error. Because the bank did not make an error for the reasons outlined in this determination, the bank is not required to compensate the complainants. 2.6 Why is the outcome fair? The events the complainants have described are unfortunate and I understand the complainants have suffered hardship because they have not been able to obtain funding to complete construction of their home. However, the bank did not breach its obligations to the complainants and it would not be fair to require the bank to compensate the complainants. Determination | Case number: 666724 Page 11 of 11 3 Supporting information 3.1 The AFCA processes AFCA’s approach is based on fairness I have determined this complaint based on what is fair in all the circumstances, having regard to:  relevant legal principles  applicable industry codes or guidance  good industry practice, and  previous decisions of AFCA or its predecessor schemes (which are not binding). I have reviewed and considered all information the parties have provided and I am satisfied all relevant information has been exchanged to both parties While the parties have raised a number of issues in their submissions, I have restricted commentary in this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties, and  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. 3.2 Loan affordability The AFCA recommendation issued on 10 December 2020 considered the affordability of the loans. The complainants did not dispute the recommendation’s assessment of affordability in their further submissions. The complainants say their complaint is not about affordability of the loans, but instead about the other issues discussed in this determination. I have not repeated AFCA’s findings about the affordability of the loans in this determination.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.