Home / Suncorp Group / Determination 663738
Determination 663738
Delay in repairs to kitchen after tenant damage and claim for loss of rent
Summary
The complainant claimed loss of rent and further compensation after repairs to his kitchen, damaged by former tenants, took several months. AFCA accepted there were some delays but found the policy does not cover loss of rent and the $500 already paid was adequate compensation, so no further payment was ordered.
The policy does not cover loss of rent, the complainant did not establish a direct financial loss, and the $500 already paid adequately compensates the inconvenience caused by delay.
Issues
- Delay primary · upheld
“Whilst there were some delays in the repair process, I consider the insurer's payment of $500 is adequate compensation in the circumstances.”
- Claim denial secondary · not upheld
“I accept there is no cover under the policy for loss of rent.”
Subjects and remedies
no remedy
Text of the determination
Determination
Case number 663738
Financial firm AAI Limited
Determination | Case number: 663738 Page 2 of 5
Case number: 663738 14 February 2020
1 Determination overview
1.1 Complaint
The complainant held a home and contents insurance policy with the financial firm
(insurer) and lodged a claim on 23 January 2019 for damage to his kitchen caused by
his previous tenants on or around 24 August 2017. The complainant only became
aware of the full extent of the damages once the tenants vacated the property in
January 2019.
The insurer accepted the claim for the damage and authorised repairs, however the
complainant is dissatisfied with the length of time the repairs took place. The
complainant wants the insurer to pay him for the loss of rent during the repair period.
1.2 Issues and key findings
Is the complainant entitled to any loss of rent?
The complainant is not entitled to any loss of rent, because there is no entitlement
under the policy for the benefit. The complainant has otherwise not established a ny
direct financial loss as a result of the insurer’s actions.
Is the complainant entitled to any compensation?
Whilst there were some delays in the repair process, I consider the insurer’s payment
of $500 is adequate compensation in the circumstances and it is not required to pay
the complainant any further amount.
1.3 Determination
This determination is in favour of the insurer.
The insurer says it has already paid the complainant $500 in compensation. It is not
required to pay the complainant any further amount.
Determination | Case number: 663738 Page 3 of 5
2 Reasons for determination
2.1 Is the complainant entitled to any loss of rent?
Complainant says insurer delayed repairs to his property
The complainant incepted a landlord property and contents insurance policy to be
effective from 6 December 2018, however at the time of the loss, the complainant did
not hold a landlord policy. There is no dispute the complainant’s policy d id not cover
loss of rent, however the complainant says the insurer should pay him for his loss of
rent due to the length of time it took to complete repairs.
The complainant provided a timeline of the repairs completed at the property. He says
he believes the insurer’s builder was at the property for a total of six to eight days,
spread out over a six-month period. The complainant says this was an unreasonable
period of time to complete the repairs required at the property.
Insurer says complainant is not entitled to loss of rent
The insurer says there is no cover for loss of rent under the policy. It also refers to the
general exclusion in the product disclosure statement (PDS) for:
You are not covered under any section of this policy for damage, loss, cost or
legal liability that is caused by, arises from or involves:
…
Consequential loss (financial and non-financial loss) or extra costs following an
incident covered by your policy, such as:
…
• Any costs not covered by your policy
The insurer also says there were no unreasonable delays on the claim. It says the
claim was lodged on 23 January 2019, with the assessment and scope of works
completed on 11 February 2019. It says the repairs commenced on 11 March 2019
and the initial repairs to the kitchen cabinetry were completed by 1 April 2019, which
would have made the property liveable at this stage. The insurer says the vinyl
flooring was damaged when removing asbestos, and these repairs were completed
on 22 May 2019.
The insurer says the complainant raised concerns with cleaning required at the
property, which was completed on 6 June 2019. The insurer also says the fact the
insurer needed to clean the property did not make it unliveable, therefore it is not
liable for any loss of rent at the property. It says it then notified the complainant of the
completed repairs in July 2019.
The insurer says only minor delays occurred due to the cleaning required, as well as
difficulty in confirming completion of repairs due to the complainant going on holidays
from 29 May 2019.
Determination | Case number: 663738 Page 4 of 5
The insurer also says whilst the complainant provided a timeline of occasions when
the repairer attended the property, complexities surrounding building repairs do not
always make it possible for a repairer to attend a property for one continuous period.
It also says there were periods when materials were being sourced, and in April 2019
there was a period in which the insurer was waiting for the complainant to provide
documentation relating to the replacement vinyl flooring.
The insurer says it accepts there were some delays and paid $500 in compensation
for these delays.
Complainant not entitled to any loss of rent
I accept there is no cover under the policy for loss of rent. The complainant held a
home and contents policy at the time of loss, which did not provide this benefit.
Regarding payment of three months’ loss of rent as compensation due to the insurer’s
actions, the complainant has not established he suffered any direct financial loss for
loss of rent, as he has not established he was entitled to any rent whilst the claim was
ongoing. The insurer was therefore entitled to decline cover for any loss of rent.
2.2 Is the complainant entitled to any compensation?
Complainant not entitled to compensation
I have also considered whether the insurer’s actions entitle the complainant to any
non-financial loss compensation.
Under our Rules, the Australian Financial Complaints Authority (AFCA) may award
compensation for non-financial loss (capped at $5,000) where there has been an
unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to compensation and expects a complainant to
bear a normal degree of inconvenience during the course of a claim.
The insurer acknowledges there were some delays on the claim and paid the
complainant $500 in compensation. I have reviewed the claim notes and timeline
provided by the builder. This information shows, on balance, there was a reason for
the time the repairs took to complete, including the nature of the repairs and materials
required.
I do consider there were some delays on the claim, which would have caused some
inconvenience to the complainant. However, I consider the amount of $500 in
compensation already paid is sufficient in the circumstances.
Determination | Case number: 663738 Page 5 of 5
3 Supporting information
3.1 AFCA approach to this complaint
This complaint has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions of AFCA or its predecessor schemes (which are not binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised.
All of the provided material has been reviewed and considered. The parties have
raised numerous issues in their submissions to AFCA. However, commentary in this
determination is restricted only to those issues considered relevant to the outcome.