Determination 663198
Denial of ceiling collapse claim after storm
Summary
The insured's ceiling collapsed during a severe storm, and the insurer denied the claim by attributing it to faulty installation. AFCA found the storm caused the collapse, the defect exclusion did not apply, and ordered the insurer to arrange and commence repairs.
A severe atmospheric disturbance is a storm under the policy, and the defect exclusion requires knowledge of the defect, which the insured did not have, so the unknown-defect cover applies.
Issues
- Claim denial primary · upheld“The insurer is not entitled to refuse payment of the claim.”
Subjects and remedies
home or building damagenatural disasterrepair or rectify
Related
All Suncorp Group determinations · Find similar determinations
Text of the determination
Determination
Case number 663198
Financial firm AAI Limited
Determination | Case number: 663198 Page 2 of 8
Case number: 663198 3 June 2020
1 Determination overview
1.1 Complaint
The complainants hold a home and contents insurance policy with the financial firm
(insurer) and lodged a claim on 13 February 2019 after the ceilings in the home
collapsed following a storm.
The insurer has denied the claim and says:
The damage was not caused by an insured event but was the result of an
incorrect installation of the roof.
This dispute was the subject of a recommendation that was in favour of the insurer.
The complainant has rejected the recommendation.
1.2 Issues and key findings
Has the complainant established a valid claim within the terms of the policy?
I am satisfied that the complainant has established that the insured event, storm, as
defined within the terms of the policy has caused or contributed to the loss or damage
sustained to the home.
Is the insurer entitled to refuse payment of the claim?
The insurer is not entitled to refuse payment of the claim. While I accept that a defect,
structural fault or design fault contributed to the loss or damage, such defect,
structural fault or design fault was not known to the complainant nor could it
reasonably have been known to the complainant.
1.3 Determination
This determination is in favour of the complainants.
Within 14 days of the complainants’ acceptance of this offer the insurer is to arrange ,
in consultation with the complainant, for a further scope of works to be obtained to
repair the damaged property and unless otherwise agreed, attend to the repair of the
damage sustained because of the collapsed ceiling.
Determination | Case number: 663198 Page 3 of 8
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
Following the recommendation both parties have made further submissions and
provided further reports for consideration.
This determination follows consideration of all the available information. It is based on
what is fair in all the circumstances, having regard to the relevant legal principles,
terms of the policy, good industry practice including codes of practice and prior
determinations where applicable.
2.1 Have the complainants established a claim within the terms of the
policy?
Complainants have onus to establish a claim within the terms of the policy
It is established insurance law that an insured person has the onus to establish, on
the balance of probability, that is, more likely than not, that the loss or damage
claimed falls within the terms of the policy. This is commonly called a prima facie
claim.
The complainants’ policy is an in sured events policy that includes cover to the home
for a series of insured events including storm. The policy also includes optional cover
for accidental damage although that had not been selected by the complainants.
Storm under the terms of the policy means ‘ a storm, cyclone or severe atmospheric
disturbance, it can be accompanied by strong winds, rain, lightning, hail, snow or
dust’.
The complainants say the home was damaged following the monsoonal trough and
tropical low that impacted north Queensland as a result of Tropical Cyclone Riley in
late January 2019.
For the complainants to establish a prima facie claim it is necessary to establish that
most likely the ceiling collapsed because of the storm.
Expert reports agree extended period of moisture due to high humidity had
caused ceiling to fail
The insurer’s assessor in a report dated 2 August 2019, although referring to the
faulty ceiling installation which I will deal with later, notes the engineer reported:
During the extended period of high humidity experienced in January 2019, the
ceilings have absorbed moisture. The absorption has resulted in an increase in
weight to the ceiling linings causing the fixings to fail.
Determination | Case number: 663198 Page 4 of 8
The assessor considered that as there was no water ingress into the roof cavity
du ring the storm, the only reason for the increase in weight was the ‘atmospheric
condition of humidity’, a common problem in the tropics. The assessor seems to have
ignored the severity of the storm and conditions in the area at the time.
The engineer (S), in its initial report noted that the residence had been through
multiple high wind events including Cyclone Larry in 2006 without damage. However,
during a period of extended heavy rain in January 2019 the ceilings throughout the
property started to sag and crack.
Whilst S observed that the ceiling had not been correctly installed consistent with
relevant Australian Standard 2589, he concluded that the extended period of the high
humidity experienced in January 2019 caused the ceilings to have absorbed moi sture.
The absorption had resulted in an increase in weight of the ceiling linings causing the
fixings to fail.
In a supplementary report S commented as follows:
Ceiling failure is due to incorrect fittings.
The reference to the absorption of moisture due to high humidity is to explain why
the ceiling has not previously failed. Based on the statements made by the
insured’s representative, the property has been subject to high winds events
without failing, however it had not been subject to an extended period of humidity.
Following rejection of the recommendation the complainant provided a report from
CHP. CHP notes that the property was constructed in 2000 and there had been no
issue with the property until the sudden fail during the storm event. He disputes the
installation of the roof was faulty.
CHP considers that during usual weather patterns the fixing process would not
normally have failed however, given the torrential flood event, the fixing procedure did
fail due to the extra weight it needed to hold. I accept from this that CHP believes the
extra moisture in the plasterboard lining caused the fixture to fail.
Finally, the insurer in response to the latest report from the complainant provided a
further assessment report dated 8 April 2020. That report provides a reasonable
summary of the various reports received. The report adds little to the accumulated
information provided by the earlier reports.
I accept based on the reports provided by both the complainants and the insurer that
the ceiling plasterboard had absorbed an unusually high amount of moisture during
the storm. I accept that both the moisture absorption has contributed to the collapse
of the ceiling in January 2019.
Determination | Case number: 663198 Page 5 of 8
Policy provides cover for storm including a severe atmospheric disturbance
T he insurer’s assessor has referred to general exclusion in the terms of the policy that
references wear, tear, gradual deterioration including atmospheric or climatic
conditions.
I do not propose spelling out the exclusion in this determination but note i n my view,
reference to atmospheric or climatic condition is referenced to normal atmospheric or
climatic conditions. Otherwise this would make a nonsense of the definition of storm
which includes ‘ severe atmospheric disturbance ’ .
There is no dispute that the area in which the complainant lives was subject to the
unusual monsoonal trough. According to information available, the monsoonal trough
and its tropical low extended for the period from 26 January – 30 January 2019 in
tropical cyclone Riley.
The complainant has provided several BOM reports that confirm the severity of the
event. In rejecting the recommendation, the complainant has referred to the BOM
Special Climate Statement 69, ‘ an extended period of heavy rainfall and flooding in
tropical Queensland ’ . Significantly under item 7 of that report there is reference as
follows:
Other phenomena associated with this event
High perceptible water
The atmospheric moisture level associated with this monsoon low were very
much above average over large areas of tropical Queensland. Perceptible water
provides an estimate of the amount of moisture in the atmosphere and was close
to the highest on record for several days both near to the coast and inland.
The insurer has not disputed this report.
I am satisfied in these circumstances that the area was experiencing a severe
atmospheric disturbance associated with the storm.
Storm a proximate cause of the damage
I am satisfied that the severe atmospheric disturbance arising from the monsoonal
trough is a storm within the terms of the policy.
I am also satisfied that the storm has resulted in the high level of moisture absorption
in the ceiling plaster, causing the weight of the plaster to increase. Consistent with the
findings in the relevant expert reports this has most likely led to the collapse of the
ceiling and the failure of the fixings.
Determination | Case number: 663198 Page 6 of 8
In these circumstances I accept that the complainant has established a prima facie
claim within the terms of the policy for loss or damage arising from the insured event,
storm.
2.2 Is the insurer entitled to refuse payment of the claim?
The insurer relies upon exclusions to refuse payment of the claim
The insurer has the onus to establish the application of an exclusion if it is to refuse
payment of the claim. The insurer says that the roof fixings and batons were not
correctly installed and that it was the faulty installation and not an insured event that
has caused the collapse of the ceiling.
Whilst there are competing views as to whether the ceiling was correctly installed or
not, I do not believe it is necessary for me to determine this. The policy excludes
cover for loss or damage caused by a defect, structural fault or design fault that you
knew about (or should reasonably have known about) and didn’t fix before the loss or
damage occurred.
The insurer concedes that the complainants would not have known about the faulty
installation until the damage arose.
Insofar as the insurer’s assessor has referred to the exclusion relating to atmospheric
or climatic conditions, as I have already indicated I believe that only applies with
respect to normal atmospheric or climatic conditions. Its application could not possibly
apply to loss or damage caused by severe atmospheric disturbance within the insured
event of storm.
Insurer is l iable to meet the complainants’ claim
The complainants’ policy provides that if a property suffers damage from an insured
event and an unknown defect was the cause or part of the cause (i.e. the possible
faulty installation), it will pay for the resulting damage and if the unknown defective
part is also damaged by the same incident it will fix this as well.
I accept in these circumstances the policy extends to cover the complainants for the
repair of the damaged ceiling and including the repair of any unknown defect.
Insurer is to repair the complainants’ property
The policy provides the insurer with the discretion whether to repair, replace or cash
settle the complainants’ claim. When exercising this discretion, the insurer must do so
fairly, reasonably and consistently with utmost good faith.
No current quote has been provided for the cost to repair the property. The scope of
works and quote provided by the insurer is close to 12 months old and I do not
believe this should be used to assess a cash settlement. The complainants have
indicated that they are unable to obtain quotes at the current time and would prefer
the insurer to complete any repairs.
Determination | Case number: 663198 Page 7 of 8
In my view it is fair that the insurer should exercise its discretion and repair the
complainants’ property given the difficulty faced by the complainants in employing
suitable trades to complete the repairs.
The insurer should, within 14 days of the complainants’ acceptance of this
determination arrange for a further scope of works to be completed and an actionable
quote obtained. The insurer should then, unless otherwise agreed with the
complainants commence the repairs in a timely manner. If the complainants choose
to cash settle the complaint the Insurer can do so based on the scope of works and
actionable quote obtained.
Determination | Case number: 663198 Page 8 of 8
3 Supporting information
3.1 Extracts from PDS
General exclusions
You are not covered under any section of this policy for damage, loss, cost or
legal liability that is caused by, arises from or involves:
...
Defect, structural fault or design fault
a defect, structural fault or design fault that you knew about (or should reasonably
have known about) and did not fix before the loss or damage occurred (e.g. if
there are signs that a defect previously caused damage, we will not pay a later
claim for further damage from this defect).
Dealing with defects
If a known defect is the cause of the damage
We do not pay for loss or damage caused by a defect, structural fault or design
fault at your home that you knew about (or should reasonably have known about)
and did not fix before the loss or damage occurred.
If an unknown defect is the cause of the damage
If an incident covered by your policy damages your home and an unknown defect
was the cause or part of the cause, we will pay for the resulting damage. If the
unknown defective part of your home is also damaged by the same incident, we
will fix this as well.