Home / Suncorp Group / Determination 661554

Determination 661554

Scope of storm damage repairs and cash settlement amount

FirmSuncorp Group
Decided2020-08-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$120,019
Non-financial loss—
Amount claimed$239,245
SourceAFCA PDF

Summary

Insurer accepted a storm water damage claim but disputed the scope of works, and the complainants sought a cash settlement based on a higher builder quote plus non-financial loss. AFCA ordered the insurer to pay $108,019.22 for building damage and $12,000 temporary accommodation, and refused non-financial loss compensation.

The insurer's builder scope of works was found accurate and fair, with a contingency allowance added to the cash settlement for transfer of risk.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 661554 Financial firm AAI Limited Determination | Case number: 661554 Page 2 of 8 Case number: 661554 26 August 2020 1 Determination overview 1.1 Complaint On 17 December 2018 the complainants lodged a claim under their home and contents insurance policy with the financial firm (insurer), after a storm caused water to enter and damage their property. The insurer accepted the claim. A dispute has arisen as to the scope of works (SOW). The complainants say the SOW does not cover the damage and want a cash settlement based on their own quotation. The insurer says its builder is willing to complete the works for which it has provided a scope, alternatively it offered a cash settlement of $93,929.76 as full and final settlement of the claim. The complainants rejected this offer and want a cash settlement based on their quotations and compensation for non-financial loss. 1.2 Issues and key findings Is the offer of a cash settlement fair in the circumstances? Yes. The Panel is satisfied that it is fair in the circumstances that the claim be cash settled based on the SOW from the insurers builder BB subject to a 15% allowance for the transfer of risk and contingencies. Further an allowance should be made for 12 weeks temporary accommodation of $1000 per week during the repair period. Are the complainants entitled to compensation for non-financial loss? No. While the Panel is satisfied this matter took an unusual time to resolve, this has related largely to the delays in the complainant accepting the SOW . The Panel is not satisfied this was due to the insurers poor handling of the claim. 1.3 Determination This determination is partially in favour of the complainant. The insurer is to pay the complainants $108,019.22 for the claimed building damage plus $12,000 by way of temporary accommodation in settlement of the claim in accordance with the terms and conditions of the policy. Determination | Case number: 661554 Page 3 of 8 2 Reason for determination There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. Due to the complexities involved this dispute has been referred to a Panel for determination. The Panel comprises and ombudsman, a representative with extensive industry experience and a representative with extensive experience as a consumer representative. This determination follows consideration of all relevant information exchanged. It is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice, codes of practice and previous decisions where appropriate. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues which are considered directly relevant to the outcome only. 2.1 Is the offer of a cash settlement fair in the circumstances? Complainants must establish valid claim and policy coverage When lodging an insurance claim, the complainant bears the initial onus to establish a on the balance of probabilities (that is more likely than not) that the claim falls within the terms of the policy. Once established the onus shifts to the insurer to show, on the balance of probabilities that an exclusion applies or it is otherwise entitled to deny the claim. The complainants ’ policy provided cover for a series of insured events including storm. The policy defines storm as a ‘storm, cyclone or severe atmospheric disturbance. It can be accompanied by strong winds, rain, lightning, hail, snow or dust.’ There is no dispute that on 14 December 2018, there was heavy rainfall which caused water to enter the complainants’ property with resultant loss and damage. The insurer accepts the complainant has a valid claim however the dispute is as to the extent of damage. Determination | Case number: 661554 Page 4 of 8 Parties dispute the extent of damage The available information, video and photographs indicate the water entered through the second storey roof ’s box gutter after it became overwhelmed with storm water, allowing water to run through the balcony and through both levels of the property. The insurer first appointed assessor (MK) who says significant damage had been caused almost throughout the entire property. MK noted damage to the ground floor ceilings, architraves and skirtings, timber flooring in the cinema room cupped. MK noted damage to the first-floor ceilings, floor tiles in ensuite, timber flooring on first floor has cupped, internal doors are swollen and the cabinetry in the master bedroom is also affected. The complainants say MK provided the most detailed representation of the damage and the insurer failed to reflect on his report after appointing a different building co - ordinator (RC). The complainants say tiling around the pool has been damaged when rainfall caused the pool to overflow and say various cracks in plaster and render have been caused by the event and provided advice to this effect from their chosen builder PN and representative (ZJ). The insurer made various concessions to resolve the claim and arranged a joint assessment with ZJ to agree upon a scope of works. The complainants remained dissatisfied and still want various aspects of damage to be included in the insurer’s scope of works. The more substantial items include cracking damage to property, first floor timber flooring, painting to the entire property and damage to the pool. A final quotation was provided from the insurer ’ s builder (BB) following the joint assessment for $93,929.76, the insurer says it is prepared to complete the works or cash settle this amount to the complainants. The complainants seek to be s ettled based on their builder PN’s quotation for $239,245.00 and a separate quotation was submitted from (BP) purely for the joinery works at the property for an amount of $122,128. A review of BP’s quotation shows many of the items within the quotation ar e duplicate items from PN’s quote and therefore given the amount it is not considered a reasonable settlement for the joinery items. Flooring and mould remediation quotations were also provided however, they also form part of PN’s quotation . The complainants argue they do not believe their property can be returned to its previous condition, using high end materials and they have not been able to find a builder who will come close to the quotation provided by BB. Determination | Case number: 661554 Page 5 of 8 First level timber flooring not damaged by event The Panel accepts water came into contact with the first-level flooring based on the evidence at hand. However, it does not accept the water has been shown to cause damage to the first-level timber flooring, Following MK’s report the insurer appointed flooring expert (TF), who notably reported the following: It is my opinion the rumpus room on the ground floor has been damaged as a result of a flood event requiring a total replacement. The flooring to the first floor has no visible signs of flood related damage. There is no cupping to the floor surface, no expansion of the flooring resulting in boards tenting or moving, the floor remains flat in appearance. Moisture readings were recorded across the floor producing a corrected reading ranging from 10.2% in the lounge room, 10.7% near the void to the stairwell and 10.7% to the timber leading to the master bedroom where the flood event took place. The floor has minor gaps ranging from 0.7mm – 1.2mm. These gaps appear in the floor at measurements between gaps of 850mm – 2700mm. This issue is consistent with what is called edge bonding. The complainants provided photographs to floor expert (CO) who says based on the images provided from the complainants there is evidence of severe cupping and boards have peaked further down the passage. CO did not inspect the flooring CO has not provided any persuasive evidence to show cupping occurred. The building co-ordinator RC explained in an email to the complaints representative that the subfloor of the first-level floor is made of a material (yellow tongue) which is water resistance, therefore the Panel does not accept it has moved from the claimed event. The P anel is persuaded by TF’s report that the gaps in the flooring occurred most likely due to the installation. The Panel considers the complainants have not established a valid claim for the first-floor timber flooring and the insurer was correct in excluding this from cover. Insufficient information to prove other disputed damage caused by event The Panel is not persuaded that the additional damage to:  a ground floor tile that has lifted requiring replacement of all tiles in the vicinity  the entire property requiring repainting, replacing instead of repairing plaster  pool damage due to overflow of pool and alfresco area doors  entry ceiling and cedar eaves  render and eave staining  security camera system not working, Determination | Case number: 661554 Page 6 of 8  was caused by the insured event. RC was in contact with the complainant’s builder PN and queried a number of the additions within his quotation. RC and PN exchanged their positions on items which were in question for cover. Based on the exchange, the panel is persuaded by RC’s view in relation to coverage of the above items and additional repairs being claimed by the complainants. The claims for cracking and movement damage are not accepted, there is no evidence to show this was caused by the insured event. RC explains there is 10-15 metres between cracking damage claimed and the water entry point, with no evidence of water staining between the water entry point and the claimed damage. The Panel finds this persuasive. The Panel considers this also applies to the entry hallway and alfresco doors movement, as RC has explained there is no water staining in these areas. The complainant has claimed for the entire property to be repainted. The insurance policy is clear, when repairing or replacing building items it will only cover the costs to fix the items damaged. BB’s quotation only covers painting the rooms which were damaged by the event. The Panel does not accept that a single loose tile on the ground floor in the entry hall way justifies replacement of all tiles. The Panel is persuaded that most likely this is a building defect. There is no expert information to explain how the storm damaged this tile. There is insufficient information to show the render staining was caused by a single storm event. Rather the Panel considers it is likely these items which are exposed to the elements have sustained damage in the normal course of events. This also applies to the security cameras; the insurer accepts one camera was possibly affected by the event. However, the complainants say the whole system is now faulty and not working. There is insufficient information to prove the security system was damaged in the storm. There is no information to support a finding that there was pool damage due to the storm. Scope of works provided by BB is fair in the circumstances In the absence of any persuasive evidence form the complainants the Panel finds the insurers quotation from BB and the SOW is an accurate assessment of the damage caused by the storm and the extent of the insurers liability. Determination | Case number: 661554 Page 7 of 8 Cash settlement offer needs to include contingency amount The Panel acknowledges the insurer’s builder is still willing to complete the repairs, however it is likely the complainants will opt for a cash settlement given it seems some of the repairs have already commenced. When considering a fair cash settlement to resolve this claim it is necessary to consider the transfer of risk a nd the likely contingency’s that may arise during the repair process. Adequate allowance needs to be made for the fact that the insurer will not be providing a lifetime guarantee on the works and that the complainant could encounter unforeseen costs to complete the claim-related repairs. The communication between RC and PN shows there is likely to be some slight inclusions and increases in final costs. Considering the insurers willingness to complete the repairs, the Panel considers it fair in the circumstances that a 15% allowance be added to the $93,929.76 to bring the settlement to $108,019.22. Insurer to determine coverage and timeframe for temporary accommodation In addition, the policy provides for the insurer will pay reasonable temporary accommodation costs for the time it will take to repair or rebuild the building to a liveable condition. The Panel has not been provided an estimate of the time it would take to repair the building. However, given the issues involved in this dispute and the nature of the repairs required the panel considers it fair to allow a reasonable repair period would be 12 weeks. The Panel also considers a reasonable weekly rental allowance would be $1000. The insurer must pay the complainants an additional $12,000 by way of temporary accommodation benefits Contents settlement has been fair in the circumstances A part of the initial dispute included the claim for various contents at the property. An email from the insurer shows that the complainants ’ representative at the time came to an agreement on the fair settlement of the contents and paid $59,805 for the non-restorable contents. The insurer confirmed it also previously settled the carpet portion of the claim and a payment of $34,290.90 for the settlement of linen and towels. A review of the inventory list and costs of items claimed, the Panel is satisfied this was a fair settlement in the circumstances and the insurer is not required to make any further contributions towards the contents items. Determination | Case number: 661554 Page 8 of 8 2.2 Is the complainant entitled to compensation? AFCA can award compensation in certain circumstances AFCA’s Rules enable it to aw ard compensation to complainants for non-financial loss outside of the policy terms (capped at $5,000). Compensation for non-financial loss is limited. AFCA may decide an insurer should compensate complainants for such a loss only where there has been:  an unusual amount of physical inconvenience;  time taken to resolve a situation; or  interference with the complainants’ expectation of enjoyment or peace of mind. AFCA takes a conservative approach to compensation for non-financial loss and expects complainants to be moderately robust and bear the usual degree of inconvenience when managing an insurance claim. Complainants seeks compensation for claims handling experience The complainants are dissatisfied with the claims experience. They highlighted the fact that due to the length of time they had to live in the home without heating and the general discomfort of a property in disrepair. The panel accepts the complainants have had some discomfort from the claimed damage, however a review of the claims history shows the insurer acted reasonably and assessed the damage promptly. A large delay in the claim has come from the negotiation and disputing of the accepted damage, which the panel has found for the most part the insurer was correct in its settlement. Ultimately a large part of the dissatisfaction was the damage itself, not the insurers actions. The panel considers the insurers settlement scope of works was the correct outcome and therefore non-financial loss compensation is not warranted in these circumstances.